Preface To The Joint Aashto-Agc-Artba Guide Specification For Shotcrete Repair of Highway Bridges 1.0 Background

This document provides guidelines for shotcrete repair of highway bridges. It is based on previous research and recommendations from an expert task force. The guidelines include specifications for both dry-mix and wet-mix shotcrete repair processes. It also provides commentary and considerations to help specifiers select the appropriate repair method and ensure durable, long-lasting repairs. Key goals are to protect repaired areas from future damage by deicing chemicals and moisture in order to avoid compromising the repairs over time.

Uploaded by

filipe
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
78 views87 pages

Preface To The Joint Aashto-Agc-Artba Guide Specification For Shotcrete Repair of Highway Bridges 1.0 Background

This document provides guidelines for shotcrete repair of highway bridges. It is based on previous research and recommendations from an expert task force. The guidelines include specifications for both dry-mix and wet-mix shotcrete repair processes. It also provides commentary and considerations to help specifiers select the appropriate repair method and ensure durable, long-lasting repairs. Key goals are to protect repaired areas from future damage by deicing chemicals and moisture in order to avoid compromising the repairs over time.

Uploaded by

filipe
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 87

1

PREFACE TO THE JOINT AASHTO-AGC-ARTBA GUIDE


SPECIFICATION FOR SHOTCRETE REPAIR OF HIGHWAY BRIDGES

1.0 BACKGROUND

This Guide Specification was based heavily on the Recommended Practice for Shotcrete
Repair of Highway Bridges which was prepared by Dr. D.R. Morgan, P.Eng. of HBT
AGRA Limited, Vancouver, B.C., Canada, under the auspices of the Canadian Strategic
Highway Research Program (C-SHRP) study titled: “Durability of Shotcrete
Rehabilitation Treatments of Bridges”. That original document was revised and adapted
for use in the U.S. by Joint Task Force 37, Shotcrete Repair of Highway Bridges:

Jim Asher, Fibermesh Co., San Antonio, TX 78250


Ken Boedecker, W.R. Grace and Co., Charleston, SC
Jim Dikeou, ACI, Detroit, MI
Mahmoud Elnahal, Virginia DOT, Richmond, VA
Steven H. Gebler, Construction Technology Laboratories, Inc., Skokie, IL
George Yoggy, Master Builders Technologies, Cleveland, OH
Leon Glassgold, Masonry Resurfacing and Construction Co., Balt., MD
Frank Nelson, Oregon DOT, Salem, OR
Christy Philipp and Dan Thomas, California DOT, Sacramento, CA
John Simmons, Pneumatic Concrete Inc., Burmingham, AL
Peter C. Tatnall, Bekaert Corp., Marietta, GA
Larry Totten, Johnson Western Gunite Co., San Leandro, CA
Curt White, Coastal Gunite Construction Co., Cambridge, MD
Gerald White, Chairman, North Carolina DOT, Raleigh, NC
Bruce Johnson, Secretary, Federal Highway Administration, Salem, OR

This document represents the best current practice for the durable shotcrete repair of
bridges and is based on the professional experience of the prime author, Dr. D.R.
Morgan, and persons acknowledged above in the implementation of many shotcrete
bridge repair projects. It is believed that if remedial works are conducted rigorously in
accordance with the procedures outlined in this Guide Specification, the Owner will be
provided with durable shotcrete repairs, and greater service life than the surrounding
non-repaired concrete.

2.0 SPECIFIER’S GUIDE

This document has been prepared in a three-part format:

(a) Guide Specifications for Dry-Mix Shotcrete Repair of Highway Bridges


(b) Guide Specifications for Wet-Mix Shotcrete Repair of Highway Bridges
(c) Commentary on Guide Specifications for Shotcrete Repair of Highway Bridges

There is a considerable amount of repetition of content between the Dry-Mix and Wet-
Mix Specifications, but it was considered that there were sufficient differences between
2

the dry-mix and wet-mix shotcrete processes, that they warranted separate treatment.
The Guide Specifications are followed by a Commentary, which applies to both the dry
and wet-mix shotcrete processes. This Commentary draws distinctions between the two
processes, and provides the Specifier with guidance to assist in selection of the
appropriate shotcrete process for a given project. The Commentary also provides
additional guidance to the Specifier and Contractor regarding the practical repair of
bridges with shotcrete.

The Joint Task Force recognized that a National Specification cannot be written which
would be directly applicable to each State or even each region of the country.
Nevertheless, the Specifier should be able to readily adopt material from the document in
preparation of project-specific specifications, including combining the two Guide
Specifications to allow the contractor to select the most efficient process for a given
project.

The Specifier will be required to make certain design selections and choices in preparing
a specification. The Commentary section of the document must be used in conjunction
with the Guide Specifications section to aid the Specifier in preparation of contract
documents. The same numbering system has been used in the Guide Specifications and
Commentary section of the document, to aid the Specifier in this process. As a further
aid to the specifier, a CHECKLIST is provided in Section 5 of this Preface. This
CHECKLIST summarizes items requiring action by the Engineer.

The Payment section was based on a consensus of the Joint Task Force. Nevertheless it
is recognized that agencies may change to other methods of measurement and payment
depending on local preferences. These documents concentrate on technical requirements
for the remedial work.

Pertinent American Concrete Institute (ACI) and American Society for Testing and
Materials (ASTM), documents are invaluable for providing background and details of
common practice when making decisions about a specific project. However, they are not
normally referenced in Specification documents since they are not written in
specification format. Of these documents, the most useful is the ACI 506R-90, "Guide to
Shotcrete". While this document does not specifically address the use of shotcrete for
repair of bridges, it contains much useful information, which will be of assistance to the
Specifier in preparing contract documents. The Guide Specifications cite specific
chapters in ACI 506R with the intent that the specifier, using the Commentary, will
choose the requirements which apply to their project and insert those requirements in the
project specifications using appropriate imperative language.

3.0 DEFINITIONS
3

The following definitions refer to words and terms used in this specification. For
definitions not covered in this document, refer to ACI 506R and ACI 506.2.

3.1 Acceptable, approved or permitted: Acceptable to, approved or permitted by the


Engineer.

3.2 Bench gunning: The practice of shooting thick members of full section by building
from the bottom up.

3.3 Blowpipe: Air jet operated by nozzlemen’s helper in shotcrete gunning to assist in
keeping rebound and overspray out of the work.

3.4 Contractor: The person, firm or corporation with whom the Owner enters into
agreement for construction of the work.

3.5 Dry-Mix Shotcrete: Shotcrete in which most of the mix water is added at the nozzle.

3.6 Engineer: The accepting authority responsible for issuing the project specifications and
administering work under the contract documents.

3.7 Ground Wire (also called screed wire or shooting wire): Small gauge, high strength
wire used to establish line and grade to guide shotcrete work.

3.8 Gunning (also called shooting): The act of applying shotcrete.

3.9 Nozzleman: Worker on the shotcrete crew who manipulates the nozzle, controls air or
water addition at the nozzle and controls final deposition of the material.

3.10 Overspray: Shotcrete material deposited away from the intended receiving surface.

3.11 Predampener (also known as a premoisturizer): An apparatus used to predampen dry-


mix shotcrete materials prior to discharge into the shotcrete gun.

3.12 Rebound: Shotcrete material leaner than the original mixture which ricochets off the
receiving surface and falls to accumulate on the ground or other surfaces.

3.13 Rod: Sharp-edged cutting screed used to trim shotcrete to forms or ground wires.

3.14 Shotcrete: Mortar or concrete pneumatically projected at high velocity onto a receiving
surface.

3.15 Sloughing (also called sagging): Subsistence of shotcrete, due generally to excessive
water in the mix or placing too great a thickness of shotcrete in a single pass.

3.16 Specifier: The authority issuing the project specifications; normally the Engineer.
4

3:17 Wet-Mix Shotcrete: Shotcrete in which all the shotcrete ingredients, including mix
water, are mixed prior to introduction into the shotcrete delivery system, and compressed
air is introduced to the material flow at the nozzle.

4.0 DESIGN CONSIDERATIONS

4.1 Review of the performance of some 60 shotcrete repaired bridges in Canada (Ref. 1,
Commentary), has revealed that there are certain basic considerations which should be
applied in the design of shotcrete repairs for bridges in order to provide durable, long
service-life repairs.

4.2 Most deterioration in bridge structures, which has given rise to the need for shotcrete
repair, has resulted from the combined actions of deicing chemicals and frost action on
saturated concrete. In the remedial design, every attempt should be made, wherever
possible, to protect the existing concrete and new shotcrete repairs from continuing
exposure to deicing chemicals and saturation. Such measures may include sealing, repair
or replacement of bridge decks and/or expansion joints; redesign of deck and abutment
drainage systems; re-profiling substructure elements such as pier caps and abutments, to
prevent ponding and facilitate drainage. If this is not done, the original concrete can
continue to deteriorate around the shotcrete repair, ultimately compromising the repair.

4.3 In many bridges it may be necessary to maintain either full or partial traffic on the bridge
deck during the period of shotcrete remedial work. It should be noted that it may be
difficult to affect quality repairs on elements which are subjected to continuous vibration
or deflections from traffic during shotcreting operations. Careful consideration should be
given at the design stage as to whether traffic control measures or restrictions need to be
placed on the bridge during the repair program. Questions which need to be considered
include:

• Will live loads be allowed on the bridge during repairs?


• Will temporary shoring or strengthening of the structure be
required?
• How long must the repairs be allowed to cure before the bridge is
returned to full service?

4.4 Some shotcrete repair of bridges has been required because of general deterioration of
the concrete matrix, attributable to alkali-aggregate reactivity, or the use of inherently
non-freeze/thaw durable, non-air entrained concrete in the original construction. In
shotcrete repair of such structures, reliance should not be placed solely on the quality of
bond of the shotcrete to the original concrete for long-term performance of the repair.
Concrete could continue to deteriorate behind the shotcrete repair and thus it becomes
important to tie back the repair shotcrete into the existing concrete, using appropriately
designed anchors or the existing reinforcement. If this is not done, there is a danger of
long term “slabbing” failure of the repair; the failure being initiated in the original
concrete with the shotcrete still adhered to it.
5

4.5 Corrosion of embedded reinforcing steel and subsequent spalling in the original concrete
has been the cause of the need for shotcrete repair of many bridges. In many instances,
corrosion has resulted from a lack of adequate cover to reinforcing steel (sometimes
caused by cage movement during original construction). In such repair it is important
that all spalled, deteriorated and delaminated concrete be removed. Also, concrete
should be removed and replaced in areas displaying high reinforcing steel corrosion
activity as indicated by half-cell potential measurements or other suitable procedures. In
such repairs concrete should be removed from around corroded reinforcing steel to
provide a minimum of 20 mm clearance behind the steel, to facilitate full encapsulation
with shotcrete. Tests have shown (Ref. 2, Commentary) that only partial removal of
concrete, to the front face of the reinforcing steel, will compromise the longevity of the
repair, particularly in elements subjected to repetitive dynamic loading. Reinforcing bars
should be bent back or surface contours adjusted to provide adequate cover.

4.6 In many severely corroded bridge elements it may be necessary to remove and replace, or
supplement existing reinforcing steel with additional reinforcement. Some older bridges
may be inadequately reinforced by current design standards. Additional reinforcement
can be included as part of the designed repair. Fiber reinforcement can be effectively
used in some structures, in lieu of reinforcing mesh, but not in lieu of primary reinforcing
steel. Fiber reinforcement can be very effective in minimizing thermal and shrinkage
induced cracking in the shotcrete repair. It also provides increased toughness and impact
resistance to the shotcrete repair.

4.7 In repair of deteriorated load-bearing elements it may be necessary to carry out the repair
work in a sequential manner, with partial concrete removal, preparation and shotcreting
being completed in repair of a bridge component, prior to removal of more material.
This is particularly important in repair of pier caps and abutments in areas adjacent to
bearings. Careful consideration should be given by the Engineer and Contractor to the
needs for shoring and sequential repair in order to not compromise the safety of the
structure.

4.8 The design should prohibit “featheredging” of shotcrete repairs, or the application of
“skim-coats” of shotcrete to unprepared original concrete surface. Such types of repairs
have a high occurrence of failure in the field. The perimeter of all prepared areas for
shotcrete repairs should be chipped on a 45 degree angle (to facilitate escape of rebound)
except that the outer edges of prepared repair areas should be saw cut to a square edge, to
a minimum of depth of 15 mm, to neatly define the extremity of the repair and eliminate
shotcrete “featheredging”.

4.9 Where considerable thicknesses of shotcrete are required to be applied (particularly in


overhead applications) considerations should be given to the use of dry-mix silica fume
shotcrete. Wherever possible, shotcrete should be applied in a single lift, rather than in
multiple layer construction; dry-mix silica fume shotcrete is better suited to single lift
construction than any of the other shotcrete types.
6

4.10 In repair of structural elements such as piers, abutments and parapets, the designer should
attempt to completely cap the element with repair shotcrete. If the shotcrete repair does
not cap the element, there is a potential for the shotcrete to act as a “dam” and promote
the saturation of the original concrete with water and salt solution. This can accelerate
deterioration of the original concrete. Caps should be designed with a minimum 3
percent grade to facilitate drainage.

4.11 Superstructure elements, such as deck soffits, girders, beams and arches, should be
designed with grooves or drip strips, to prevent wetting and staining of the soffits of such
elements with water and salts.

4.12 Finally, the designer should consider the aesthetic requirements for the shotcrete repairs.
The particular type of shotcrete used, and type of finish selected, will affect aesthetics.
The most economical finish is the as-shot, gun finish. This may suffice for many
structures with low visibility or on secondary highways, but may not be satisfactory for
bridges in city areas, or on primary highways, where visual aesthetics and public
perception are important. In such structures the requirements for finishing of shotcrete
repairs and possibly even the application of pigmented coatings should be considered at
the design stage.

5.0 CHECKLIST

This CHECKLIST summarizes items requiring action by the Engineer. The reference
numbers in the checklist refer to numbers in the clauses in the Guide Specifications
which follow.

1.2 QUALIFICATIONS

1.2.1 Specify contractor and nozzlemen qualifications.

1.3 REQUIREMENTS

1.3.1 Provide details in the contract documents and in the field regarding areas of
spalled, deteriorated and damaged concrete requiring removal.

1.3.1 Provide details regarding replacement of excessively corroded reinforcing steel.

1.3.1 Provide details for all new reinforcing steel, mesh and anchors.

1.3.2 Provide criteria and guidelines or details for temporary support of portions of the
bridge, if needed.

2.0 Review submittal and approve contractor qualification test reports, mix design,
preconstruction trial results, quality control program, curing details, and
temporary support.
7

4.0 MATERIALS

4.1.1 Specify required cement type.

4.2.1 Specify which supplementary cementing materials (if any) to be used.

4.4.1 Specify nominal maximum aggregate size and gradation.

4.5.1 Specify whether air entraining admixture is required and the amount or rate of
addition at the nozzle, if appropriate.

4.5.2 Specify which chemical admixtures are required or allowed.

4.6.2 Provide details for all replacement reinforcing steel.

4.6.4 Specify whether fiber is to be used, and if so, type, length, diameter, if
appropriate, and addition rate (kg/m3).

5.0 SHOTCRETE PROPORTIONING

5.1.1 Review and approve shotcrete mixture proportions proposed for use by
Contractor.

5.1.4 Review shotcrete mix performance test data from previous experience, if
available.

5.2.1 Specify silica fume content, if appropriate.

5.3 PERFORMANCE REQUIREMENTS

5.3.1 Specify shotcrete performance requirements (Note: make any project specific
changes to Table 1 that may be required).

5.3.2 (Optional) Establish maximum permissible rapid chloride permeability coulomb


limits for shotcrete which does not contain silica fume.

6.0 SUPPLY AND EQUIPMENT

6.1.1 Provide written approval for site batching using either the volume or mass
batching method.

6.1.5 Specify frequency for mass batch checks on volumetrically proportioned


shotcrete mixtures.

7.0 PREPARATION FOR SHOTCRETING


8

7.1.1 Provide direction for removal of unsound concrete and for removal depths greater
than 150 mm, if appropriate.

7.1.7 Specify whether requirement for abrasive blast cleaning of prepared surfaces may
be waived (e.g., in case of surface preparation with high pressure water blasting).

7.1.8 Approve the method of disposal of debris.

7.2 REINFORCEMENT

7.2.2 Direct Contractor as to which corroded reinforcing steel to remove and replace.
Specify the percent of loss of cross section for which bars must be augmented or
replaced.

7.2.4 Specify the minimum lap length for replacement reinforcement.

7.2.6 Specify whether welding of replacement reinforcement is permitted.

7.2.11 Specify whether fiber reinforcement is permitted as an alternative to mesh


reinforcement; provide details for anchor and tie-back systems.

7.3.1 Specify anchor spacing.

7.3.2 Specify anchor type.

7.3.3 Specify minimum pull-out force required for anchors; specify frequency of
anchor testing to verify pull-out force.

7.4 ALIGNMENT CONTROL AND COVER

7.4.2 Review and approve Contractor’s proposed means of alignment and cover
control.

7.4.7 Specify required tolerances on finished work.

8.0 QUALITY ASSURANCE AND QUALITY CONTROL TESTING

8.1.1 Administer quality assurance program, as detailed in Section 8.1.1.

8.2.1 Specify the hardened shotcrete properties to be tested in the contractor’s quality
control program and the frequency of the tests.

8.3.1 Evaluate Contractor performance in preconstruction trial.


9

8.3.3 Direct the contractor to core preconstruction trial panels at reinforcement


intersections and in unreinforced areas.

8.3.7 Evaluate quality of cores extracted from prequalification test panel.

10.0 SHOTCRETE APPLICATION AND FINISHING

10.1.1 Review and approve prepared areas prior to application of shotcrete.

10.1.6 Specify whether use of curing compound is permitted in multiple layer shotcrete
construction.

10.1.8 Approve areas not requiring temporary support.

10.1.9 Verify whether sufficient lighting and ventilation is being provided to enable safe
application of quality shotcrete.

10.1.12 Specify the tolerance for line and grade of shotcrete repair surfaces.

10.2.1 Specify type of finish required.

11.0 CURING AND PROTECTION

11.1.1 Specify whether use of curing compound permitted.

11.1.3 Specify minimum period of moist curing.

11.2.3 Review and approve Contractor’s proposed hot weather shotcreting procedures.

11.2.5 Review and approve Contractor’s proposed heating procedures for cold-weather
shotcreting.

12.0 SHOTCRETE ACCEPTANCE AND REPAIR

12.1.1 Reject shotcrete work which does not conform to the project specifications.

12.1.4 Examine the completed shotcrete work for any deficiencies.

12.1.5 Implement a program of testing for in-place shotcrete if compliance testing on


shotcrete test panels, or assessment of plastic or hardened shotcrete indicates non-
conformance with project specifications; provide details for locations of cores to
evaluate in-place shotcrete. Specify core hole patching details.

12.2.3 Inspect and approve prepared repair areas prior to application of repair shotcrete.
10

JOINT AASHTO-AGC-ARTBA GUIDE SPECIFICATION FOR


DRY-MIX SHOTCRETE REPAIR OF HIGHWAY BRIDGES

1.0 GENERAL DESCRIPTION AND REQUIREMENTS

1.1 SCOPE

1.1.1 This document provides a guide specification for the repair of highway bridges using the
dry-mix shotcrete process. It provides guide specifications for: selection of materials;
shotcrete mixture proportioning; selection of shotcrete equipment; preparation for
shotcreting; quality assurance and quality control testing; safety measures; shotcrete
application, finishing and curing procedures; and shotcrete acceptance. If incorporated
into the Contract Documents, this document shall become a part of the Contract
Documents and the Contractor shall comply with all provisions in this document unless
otherwise specified by the Contract Documents or modified in writing by the Engineer.

1.2 QUALIFICATIONS

1.2.1 The shotcrete contractor’s crew foreman and nozzlemen shall meet the following
requirements unless otherwise specified in the contract documents:

(a) Furnish proof that the shotcrete crew foreman has at least 5 years experience in
Shotcrete repair work on projects of similar size and character along with 5
references who were responsible for supervision of similar projects. Include
name, address, and telephone number of references who will testify to the
sucessful completion of these projects by the shotcrete crew foreman.

(b) Furnish proof that the nozzlemen have sucessfully completed 3 projects of similar
size and character along with 3 references of those responsible for supervision of
these projects. The nozzlemen shall also pass a test demonstrating their
competence described in Section 8.3.

1.3 REQUIREMENTS

1.3.1 The Contractor shall furnish all labor, materials and equipment for:

(a) Removal of all spalled, deteriorated and damaged concrete as detailed in the
Contract Documents and directed by the Engineer;

(b) Cleaning corrosion product from corroded in-place reinforcing steel and where
specified removing and replacing excessively corroded reinforcing steel with new
reinforcement;

(c) Preparing concrete surfaces to receive shotcrete by either high pressure water
blasting or abrasive grit blasting;
11

(d) Installing all new reinforcing steel, mesh and anchors as detailed in the Contract
Documents;

(e) Supply, application, finishing, curing and protection of shotcrete; and

(f) Provision of a quality control program to ensure compliance of completed


shotcrete remedial work with contract documents.

1.3.2 The Contractor shall implement a safety program which shall include but not necessarily
be limited to:

(a) Ensuring that the structural integrity of all bridge elements is protected during the
repairs by shoring or other suitable means as specified in the Contract
Documents;

(b) Protecting all personnel and the traveling public from falling debris, blasting grits
and high pressure water jets, during concrete removal processes;

(c) Protecting all personnel and the traveling public from pneumatically applied
shotcrete and rebound materials during the shotcrete application process;

(d) Ensuring that all employees have training for materials being handled on site and
that Material Safety Data Sheets for all materials being used are available on site
for inspection and use; and

(e) Ensuring compliance with all state and Federal OSHA regulations.

2.0 SUBMITTALS

The Contractor shall submit to the Engineer 10 working days before the commencement
of production shotcreting work written documentation which provides:

2.1 The qualifications of the work crew, including the supervisor, shotcrete nozzlemen,
gunmen and blowpipe operators, and the references for the supervisor and nozzlemen
required in 1.2.1 (b) & (c).

2.2 Test records, showing source and proof of conformance to project specifications of all
shotcrete materials, including:
(a) Portland cement.
(b) Supplementary cementing materials (silica fume, fly ash, ground blast furnace
slag).
(c) Aggregates.
(d) Mix water.
(e) Chemical admixtures.
(f) Reinforcement, including welded wire mesh fabric, reinforcing steel, fibers.
12

2.3 Details of proposed shotcrete mixture(s) including shotcrete proportions and means of
shotcrete supply.

2.4 Results of the preconstruction testing program and a description of the proposed
construction quality control testing program, including the frequency of specific tests.

2.5 Proposed curing procedures and protection to be provided to shotcrete.

2.6 Proposed scaffolding or other temporary support system for workers and inspectors.

2.7 Proposed falsework or temporary support system for all bridge elements which undergo
loss of strength or support during concrete removal operations. Design criteria for
falsework or temporary structural suppport systems shall be as listed in the contract
documents.

3.0 REFERENCE DOCUMENTS

3.1 The documents referenced below form a part of this document only to the extent
referenced. In case of conflicts between the referenced portions of these documents and
this specification, the requirements of this specification takes precedence.

3.1.1 American Concrete Institute (ACI)

ACI 506R, Guide to Shotcrete


ACI 506R.3, Guide to Certification of Shotcrete Nozzlemen
ACI 506.2, Specifications for Materials Proportioning and Application
of Shotcrete

3.1.2 American Society for Testing and Materials (ASTM)

ASTM A185, Specification for Steel Welded Wire Fabric, Plain, for Concrete
Reinforcement
ASTM A385, Practice for Providing High-Quality Zinc Coating (Hot Dip)
ASTM A615, Specification for Deformed an Plain Billet-Steel Bars for Concrete
Reinforcement
ASTM A641, Specification for Zinc-Coated (Galvanized) Carbon Steel Wire
ASTM A706, Specification for Low-Alloy Steel Deformed Bars for Concrete
Reinforcement
ASTM A767, Specification for Zinc-Coated (Galvanized) Steel Bars for
Concrete Reinforcement
ASTM A775, Specification for Epoxy-Coated Reinforcing Steel Bars
ASTM A820, Specification for Steel Fibers for Fiber Reinforced
Concrete
ASTM C33, Specification for Concrete Aggregates
ASTM C39, Test Method for Compressive Strength of Cylindrical
Concrete Specimens
13

ASTM C42, Test Method for Obtaining and Testing Drilled Cores and
Sawed Beams of Concrete
ASTM C150, Specification for Portland Cement
ASTM C260, Specification for Air-Entraining Admixtures for Concrete
ASTM C387, Standard Specification for Packaged, Dry, Combined
Materials for Mortar and Concrete
ASTM C494, Specification for Chemical Admixtures for Concrete
ASTM C595M, Specification for Blended Hydraulic Cements
ASTM C618, Specification for Coal Fly Ash and Raw or Calcined
Natural Pozzolan for Use as a Mineral Admixture in Portland
Cement Concrete
ASTM C642, Standard Test Method for Specific Gravity, Absorption and
Voids in Hardened Concrete
ASTM C685, Standard Specification for Concrete Made by Volumetric
Batching and Continuous Mixing
ASTM C989, Specification for Ground Granulated Blast-Furnace Slag
for Use in Concrete and Mortars
ASTM C1116, Standard Specification for Fiber Reinforced Concrete and
Shotcrete
ASTM C1017, Specification for Chemical Admixtures for Use in Producing
Flowing Concrete
ASTM C1140, Standard Practice for Preparing and Testing Specimens from
Shotcrete Test Panels
ASTM C1202, Test Method for Electrical Indication of Concrete’s Ability to
Resist Chloride Ion Penetration
ASTM C1240 Specification for Silica Fume for Use in Hydraulic-Cement
Concrete and Mortar

3.1.3 American Association of State Highway Transportation Officials (AASHTO)

AASHTO M6, Standard Specification for Fine Aggregate for Portland Cement
Concrete
AASHTO M80, Standard Specification for Coarse Aggregate for Portland Cement
Concrete
AASHTO M157, Ready-Mixed Concrete

4.4.0 MATERIALS

4.1 CEMENT

4.1.1 Cement shall conform to the requirements of ASTM C150, or C595M. Engineer shall
select appropriate cement type.

4.2 SUPPLEMENTARY CEMENTING MATERIALS


14

4.2.1 Engineer shall specify which supplementary cementing materials, if any, are permitted or
required for use on project.

4.2.2 Fly ash shall conform to the requirements of ASTM C618.

4.2.3 Granulated slag shall conform to the requirements of ASTM C989, Grade 100 or 120,
ground granulated blast furnace slag.

4.2.4 Silica fume shall conform to the requirements of ASTM C1240.

4.3 WATER

4.3.1 All water used in shotcrete production, including water added in premoisturizer and at
the shotcrete nozzle shall be of drinking water standard and free of oil and chemical or
organic impurities.

4.3.2 Similarly all water used for high pressure water blasting, predampening of concrete
surfaces prior to application of shotcrete, in blowpipes for removal of rebound and
overspray, and for shotcrete curing, shall be of drinking water standards and free of oil
and chemical or organic impurities.

4.4 AGGREGATES

4.4.1 Aggregates shall be normal weight aggregates conforming to the requirements of


AASHTO M6 for fine aggregate and AASHTO M80 for coarse aggregate. Gradation of
aggregates shall be as required in the Contract Documents or as approved by the
Engineer.

4.5 ADMIXTURES

4.5.1 Air entraining admixtures shall be added to the mix water if specified in the Contract
Documents. Air entraining admixtures shall conform to the requirements of ASTM
C260.

4.5.2 No admixtures shall be added to the shotcrete without approval of the Engineer. In
particular any admixtures containing chlorides shall not be used. Shotcrete accelerators
shall not be used without written authorization by the Engineer.

44.76 REINFORCEMENT

4.6.1 Welded wire mesh fabric shall be welded galvanized steel of dimensions and mass
specified in drawings and shall conform to ASTM A185.

4.6.2 New or replacement reinforcing bars shall be installed as detailed in the Contract
Documents. Reinforcing bars shall conform to ASTM A615, A706, A767, or A775.
15

4.6.3 Inserts for attachment of welded wire mesh fabric to existing concrete shall be galvanized
in accordance with ASTM A385 and A641, and be of adequate length and strength to
resist a 10 kN pull-out force.

4.6.4 Fibers shall conform to the requirements of ASTM C1116. Fiber type, length and
addition rate shall be as specified in the contract documents.

4.7 MATERIALS HANDLING AND STORAGE

4.7.1 Portland cement and supplementary cementing materials shall be stored so as to be


protected from exposure to moisture and temperatures below 5 degrees C and above 30
degrees C.

4.7.2 All admixtures shall be maintained at temperatures above 5 degrees C and below 30
degree C at all times.

4.7.3 Aggregates used in site batching of shotcrete shall be stockpiled and handled so as to
prevent segregation, and shall be maintained in a 3 to 7 percent moisture content range.
Shelters or tarpaulins shall be used to protect the aggregate stockpiles during periods of
wet weather.

4.7.4 Fiber shall be stored in dry, sealed containers until ready for batching and shall be free
from corrosion, oil, grease or other contaminants.

5.0 SHOTCRETE PROPORTIONING

5.1 MIXTURE DESIGN

5.1.1 The Contractor shall be responsible for shotcrete mixture proportioning and shall submit
the proposed shotcrete mixture proportions to the Engineer for review and approval 10
working days prior to application of production shotcrete. As a minimum, for each
shotcrete mixture design the following information shall be submitted:

(a) An easily identifiable mix designation, number or code.

(b) Batch quantities of fine aggregate, coarse aggregate, cement, supplementary


cementing material, expected water demand (to include all water from moisture in
aggregates, and water added in premoisturizer and at nozzle) and all other
3
shotcrete ingredients, in kg/m , based on saturated surface dry aggregates.

(c) Aggregate source, gradation, relative bulk density (specific gravity) and
absorption.

5.1.2 Allowance shall be made for the shooting orientation and rebound in shotcrete mixture
proportioning.
16

5.1.3 Shotcrete shall be proportioned to meet the performance requirements detailed in the
project drawings and Section 5.3.

5.1.4 The Contractor shall submit performance test data from previous experience, if available,
along with the shotcrete mixture proportions for review by the Engineer.

5.1.5 In the absence of suitable shotcrete mixture proportioning experience, the Contractor
shall use the nominal trial mixture proportions detailed in Section 5 of the Commentary
section of this GuideSpecification. Adoption of these nominal trial mixture proportions
shall not relieve the Contractor of responsibility for meeting the performance
requirements detailed in the Contract Documents.

5.2 SILICA FUME SHOTCRETE

5.2.1 The silica fume content of silica fume shotcrete shall be between 5 and 15 percent by
mass of cement content or as specified in the Contract Documents.

5.2.2 Silica fume shall be supplied and added to the mixture in either a slurry; loose,
uncompacted; or partially compacted form. Densely compacted silica fume shall not be
used.

5.3 PERFORMANCE REQUIREMENTS

5.3.1 Shotcrete shall conform to the performance requirements in Table 1.


17

TABLE 1
Dry-Mix Shotcrete Performance Requirements

Test Description Test Method Age Specified


(Days) Requirement
Min. Compressive Strength, MPa (f’ c) ASTM C39 7 28
ASTM C42 28 35
Max. Boiled Absorption, % ASTM C642 7 8
Max. Vol. of Permeable Voids, % 7 17
Max. Rapid Chloride Permeability, Silica- ASTMC1202 7 1500
Fume Shotcrete, Coulombs

5.3.2 For dry-mix shotcretes other than silica-fume shotcrete, the Contract Documents shall
establish maximum permissible rapid chloride permeability coulomb limits.

6.0 SUPPLY AND EQUIPMENT

6.1 BATCHING, MIXING AND SUPPLY

6.1.1 Dry-mix shotcrete shall be batched, mixed and supplied by one of the following methods:

(a) Dry-bagged premix material supplied in either small bags (30 kg typical) or large
synthetic cloth bulk bin bags (1600 kg typical).

(b) Site batching, using either volume or mass batching subject to written approval
by the Engineer of the proposed batching equipment.

6.1.2 The use of mobile volumetric batcher units shall be permitted, provided such units are
properly calibrated in accordance with ASTM C685.

6.1.3 The use of central or transit mix batched, and transit mix supplied dry-mix shotcrete,
shall not be permitted, unless the Contractor can demonstrate satisfactory conformance to
all the project performance requirements.

6.1.4 All dry-mix shotcrete shall be shot within 45 minutes of the time of moisture (either from
damp sand, or the premoisturizer) coming into contact with the cementitious materials.

6.1.5 When using volume batching, proportions shall be verified at the frequency specified in
the Contract Documents, using a mass batching check. The minimum checking
frequency shall be at the beginning of the work and at least once a week thereafter.

6.1.6 Dry-bagged premixed shotcrete materials shall be produced in conformance with the
pertinent requirements of ASTM C387. In particular, all aggregates shall be dried to a
moisture content of less than 0.1% by mass, based on oven drying at 105 to 110 degrees
C.
18

6.1.7 Dry-bagged premixed shotcrete materials shall be protected from moisture during
handling, transport and storage. Any bags which display lumps of pre-hydrated shotcrete
shall not be used on the project.

6.1.8 Dry-bagged premixed shotcrete materials shall be maintained in a temperature range of 5


to 30 degrees C during storage and application. Frozen material shall not be used.

6.2 SHOTCRETE PLACING EQUIPMENT

6.2.1 Shotcrete batching, mixing and supply equipment shall be capable of combining the dry-
mix shotcrete materials into a uniform mixture and discharging it without segregation.

6.2.2 Dry-bagged premixed shotcrete materials shall be predampened to provide a consistent


moisture content in the range of 3 to 5 percent by mass in a predampener, prior to
discharge into the shotcrete gun. Discharge of completely dry materials into the
shotcrete gun shall not be permitted, unless satisfactory performance is demonstrated in
the test panel.

6.2.3 Similarly, for site mixed materials, if the moisture content in the sand is too low to
provide a moisture content of the mixed shotcrete materials in the range of 3 to 5 percent,
then the shotcrete shall be predampened in a predampener, prior to discharge into the
shotcrete gun.

6.2.4 The mixing and predampening units shall be capable of producing a shotcrete mixture
with a uniform moisture content, such that the nozzleman is not required to repeatedly
adjust the water content at the nozzle water ring.

6.2.5 The delivery equipment (gun) shall be capable of discharging a continuous, smooth
stream of uniformly mixed material into the delivery hose.

6.2.6 The discharge nozzle shall be equipped with a manually-operated water injection system
(water ring) for directing an even distribution of water through the mixture. The water
valve shall be capable of ready adjustment to vary the quantity of water and shall be
convenient to the nozzleman.

6.2.7 The water pressure at the discharge nozzle shall be sufficiently greater than the operating
air pressure so that the water is intimately mixed with the predampened shotcrete
materials. If the line water pressure is inadequate, a water booster pump shall be
introduced into the water line to provide a steady, non-pulsating water pressure. Water
heaters shall be provided during cold weather if required to produce shotcrete at a
suitable temperature.

6.2.8 The water ring shall be carefully monitored for any signs of blockage of individual water
spray holes. If non-uniform wetting of discharged shotcrete becomes apparent, shooting
shall be stopped, and the water ring cleaned or other appropriate corrective actions taken.
19

6.2.9 The delivery equipment shall be thoroughly cleaned at the end of each shift. Any build-
up of coatings in the delivery hose and nozzle liner shall be removed. The water ring and
nozzle shall be regularly inspected and replaced as required.

6.3 AUXILIARY SHOTCRETE EQUIPMENT

6.3.1 The Contractor shall supply a clean, dry air supply, capable of maintaining sufficient
nozzle velocity for all parts of the work and simultaneous operation of a blow pipe and,
if pneumatically operated, the predampener.

6.3.2 The air supply system shall contain a moisture and oil trap to prevent contamination of
the shotcrete.

6.3.3 Auxiliary shotcrete equipment such as delivery hose, water hose, water booster pumps,
blowpipes, couplings, admixture dispensers and fiber feeders shall conform to the
recommendations in ACI 506R, Section 3.8.

7.0 PREPARATION FOR SHOTCRETING

7.1 CONCRETE REMOVAL AND PREPARATION

7.1.1 The Contractor, at the direction of the Engineer shall locate and remove all loose,
spalled, deteriorated and delaminated concrete. Sounding shall be used to locate
delaminated areas. Care shall be exercised not to damage areas of sound concrete or
reinforcing steel during concrete removal operations. Unless specificaly directed by the
Engineer, depth of removal shall not exceed 150 mm. Concrete removal shall be in
accordance with a sequence approved by the Engineer.

7.1.2 Concrete removal shall be accomplished using one or more of the following methods:

a) Chipping with hand picks, chisels or light duty pneumatic or electric chipping
hammers (not to exceed 7 kg mass);

b) Scarifiers, scabblers or other suitable mechanical means;

c) High pressure (100 to 275 MPa) water jetting.

7.1.3 If sound concrete is encountered before existing reinforcing steel is exposed, the surface
shall be prepared and repaired without further removal of the concrete. When corroded
reinforcing steel is exposed, concrete removal shall continue until there is a minimum 20
mm clearance around the exposed, corroded reinforcing bar. Care shall be taken to not
damage bond to adjacent non-exposed reinforcing steel during concrete removal
processes.
20

7.1.4 The perimeter of all areas where concrete is removed shall be tapered at an
approximately 45° angle, except that the outer edges of all chipped areas shall be sawcut
to minimum depth of 15 mm to prevent featheredging unless otherwise approved by the
Engineer.

7.1.5 After all deteriorated concrete has been removed, the repair surface to receive shotcrete
shall be prepared by abrasive blast cleaning or high pressure (100 to 275 MPa) water
jetting. The repair surface shall have an adequate surface roughness determined as three
peak to valley measurements of 5mm within 150 mm.

7.1.6 Abrasive blast cleaning or high pressure water jetting shall remove all fractured surface
concrete and all traces of any unsound material or contaminants such as oil, grease, dirt,
slurry, or any materials which could interfere with the bond of freshly placed shotcrete.
Cleaned areas shall have shotcrete applied within 48 hours, or shall be reblasted.

7.1.7 The requirement for abrasive blast cleaning or high pressure water jetting may be waived
by the Engineer where concrete removal has been performed with high pressure water
blasting and the prepared surface is free of any residual slurry or other material
detrimental to adequate shotcrete bond.

7.1.8 Unless otherwise specified in the contract documents, all material removed shall become
the property of the Contractor and shall be disposed of as approved by the Engineer.

7.2 REINFORCEMENT

7.2.1 All corroded reinforcing steel exposed during concrete removal shall have corrosion
products removed by abrasive grit blasting. The exposed reinforcing steel surface that is
facing away from the sandblast nozzle shall be cleaned to remove all dust and loose
particles.

7.2.2 Reinforcing steel displaying deep pitting or loss of more than 20 percent of cross-
sectional area, or as specified in the Contract Documents shall be removed and replaced
or augmented with additional reinforcement, as detailed in the Contract Documents.

7.2.3 In cases of isolated pitting, the existing reinforcing steel need not be cut, but shall be
reinforced by addition of appropriately placed reinforcing bar of suitable length as
detailed in the Contract Documents.

7.2.4 The minimum lap splice length of all replacement and new reinforcing steel shall be as
detailed in the Contract Documents. Such bars shall be placed in accordance with the
recommendations of ACI 506R, Sections 5.4 and 5.5. In particular, bars shall not be
bundled in lapped splices, but shall be placed such that the minimum spacing around
each bar is three times the maximum aggregate size or 20 mm, which ever is larger to
allow for proper encapsulation with shotcrete.
21

7.2.5 Intersecting reinforcing bars shall be tightly secured to each other using 1.6 mm or
heavier gauge tie wire, and adequately supported to minimize vibration during shotcrete
placement.

7.2.6 As an alternative to lapped splices, replacement reinforcing steel shall be welded to


existing reinforcing, subject to verification of weldability of both existing and new
reinforcing steel and as specified in the Contract Documents.

7.2.7 Welded wire mesh fabric reinforcement shall conform to the requirements of ASTM
A185 and shall be galvanized.

7.2.8 Welded wire mesh fabric shall be provided as detailed in the Contract Documents and at
each repair area larger than 0.1 square meter if the depth of the repair exceeds 70 mm
from the original dimension of the repaired member. Sheets of adjoining mesh shall be
lapped by at least one and one-half spaces at all intersections, in both directions, and be
securely fastened. Welded wire mesh fabric shall have a minimum shotcrete cover of 50
mm.

7.2.9 Mesh shall be fastened to preset anchors or existing reinforcing using 1.6 mm or heavier
gauge tie wire, on a grid not more than 300 mm square. Large knots of tie wire which
could result in sand pockets and voids during shotcreting shall be avoided.

7.2.10 The minimum clearance between installed reinforcing steel or mesh and existing concrete
shall be 20 mm.

7.2.11 As an alternative to welded wire mesh fabric, steel or synthetic fiber reinforced shotcrete
may be used, as specified in the Contract Documents. Fiber reinforced shotcrete shall
only be used in conjunction with appropriate anchor and tie-back systems, as specified by
the Contract documents.
22

7.3 ANCHORS

7.3.1 Anchors shall be positioned at the spacing detailed in the Contract Documents. Any
given area shall have a minimum of four anchors. The reinforcing shall not vibrate or
deform excessively during shotcreting. Unless otherwise specified the maximum anchor
spacing shall not exceed 600 mm on a grid pattern over the entire repair area.

7.3.2 Anchors shall be of the type specified in the Contract Documents and shall be either
mechanically set or grouted, as specified.

7.3.3 Anchors shall develop the minimum pull-out force specified by the Contract documents.
Anchors shall be randomly tested at a frequency specified by the Contract documents, to
verify pull-out force. In no case shall the pull-out force be less than 10kN. If any
anchors fail to meet the minimum acceptable pull-out value, corrective measures shall be
taken.

7.4 ALIGNMENT CONTROL AND COVER

7.4.1 Alignment control shall be implemented to establish control over line and grade and
ensure that the minimum specified shotcrete thickness and cover to reinforcing steel are
maintained.

7.4.2 Alignment control shall be accomplished by means of shooting wires, guide strips, depth
gauges or forms. The proposed means of alignment control shall be submitted to the
Engineer for review and approval.

7.4.3 When shooting wires (also called ground wires) are used, they shall consist of a high
strength steel wire (piano wire) kept taut during shotcreting. Shooting wires shall be
removed after completion of shotcreting and screeding operations.

7.4.4 Guide strips and forms shall be of such dimensions and installation configuration that
they do not impede the ability of the nozzleman to produce uniform, dense, properly
consolidated shotcrete. In particular, installations which are conducive to the formation
of sand-pockets and voids shall not be used.

7.4.5 When depth gauges are used for alignment control, they shall be installed at a spacing not
exceeding 1200 mm on a grid pattern. Metal depth gauges shall be cut back to 5 mm
below the finished surface, to prevent corrosion staining on the surface.

7.4.6 All repaired members shall be restored as close as practicable to their original
dimensions, including chamfered, if detailed. A minimum of 50 mm shotcrete cover
shall be provided over reinforcing steel exposed during repair.
23

8.0 QUALITY ASSURANCE AND QUALITY CONTROL TESTING

8.1 QUALITY ASSURANCE

8.1.1 The owner shall implement a quality assurance program for the work. Such a program
will normally be administered by the Engineer and shall include:

(a) Review of Contractor Submittals;

(b) Review and approval of Contractor's proposed materials, supply, equipment and
crew. In particular, all shotcrete nozzlemen proposed for use on the project shall
be evaluated in the preconstruction testing program; only nozzlemen approved in
writing by the Engineer shall be used on the project.

(c) Examination and approval of all areas prepared for shotcreting, including
installation of anchors, reinforcement, and devices to control line and grade, prior
to application of any shotcrete;

(d) Provision of inspectors to monitor shotcrete installation, with the authority to


require removal and replacement of defective shotcrete while still plastic;

(e) Regular monitoring of the results of the Contractor's quality control testing;

(f) Implementation of a program for in-place evaluation and acceptance or rejection,


where test results indicate shotcrete non-conforming to the project specifications;

(g) Implementation of a program of remedial works by the contractor, where


indicated as being necessary from the results of the quality assurance program.

8.2 QUALITY CONTROL TESTING

8.2.1 The Contractor shall establish and maintain a quality control program for the shotcrete
work, to assure compliance with the contract requirements. Such a program shall
include, but not be limited to:

(a) Maintenance of test records for all quality control operations;

(b) For site-batched materials, regular monitoring of aggregate gradation and


moisture content; one moisture content check shall be made at the start-up of each
shotcreting operation and with any changes in aggregate moisture content.

(c) For dry-bagged premix materials, wash-out testing at the frequency specified by
the Contract Documents, to check cementitious content, aggregate gradation, and
fiber content of fiber reinforced shotcretes.
24

(d) For volume-batched shotcrete mass batch checks of moisture proportions and
mixture proportions at the frequency specified by the Contract Documents;

(e) Physical testing for the hardened shotcrete performance parameters specified in
the contract documents, at the frequency specified by the Contract Documents.

8.3 PRECONSTRUCTION TRIALS

8.3.1 The Contractor shall implement a preconstruction trial to enable the Engineer to evaluate
conformance of the proposed materials, shotcrete mixture, equipment and crew to the
project specifications. Acceptance of the preconstruction trial results by the Engineer is
required prior to performance of any work detailed in the Contract Documents.

8.3.2 The preconstruction trial shall be used to prequalify the nozzlemen proposed for use on
the project. Nozzlemen who have not been prequalified shall not be permitted to apply
shotcrete on the project.

8.3.3 The preconstruction trial shall approximate actual working conditions, configuration,
reinforcement, and shooting position as near as possible. The trial shall involve a
workmanship demonstration in accordance with Section 2.5 of ACI 506.3R, "Guide to
Certification of Shotcrete Nozzlemen". The trial shall be evaluated by core grading in
accordance with ACI 506.2. Cores for grading shall be taken at locations of intersecting
reinforcement, as directed by the Engineer. Cores from any one panel shall have a mean
grade of 2.0 or less. Panels are unacceptable if any of the cores have a grade of 4 or 5 as
described in Section 8.3.4.

8.3.4 CORE GRADING

8.3.4.1 Grade 1: Shotcrete specimens are solid; there are no laminations, sandy areas or voids.
Small air voids with a maximum diameter of 3 mm and maximum length of 6 mm are
normal and acceptable. Sand pockets or voids behind continuous reinforcing steel are
unacceptable. The surface against the form or bond plane shall be sound, without a
sandy texture or voids.

8.3.4.2 Grade 2: Shotcrete specimens shall have no more than two laminations or sandy areas
with dimensions not to exceed 3 mm thick by 25 mm long. The height, width and depth
of voids shall not exceed 10 mm. Porous areas behind reinforcing steel shall not exceed
13 mm in any direction except along the length of the reinforcing steel. The surface
against the form or bond plane shall be sound with full paste, without a sandy texture or
voids.

8.3.4.3 Grade 3: Shotcrete specimens shall have no more than two laminations or sandy areas
with dimensions exceeding 5 mm thick by 32 mm long, or one major void, sand pocket,
or lamination containing loosely bonded sand not to exceed 16 mm thick and 32 mm in
width. The surface against the form or bond plane may be sandy with voids containing
overspray to a depth of 2 mm.
25

8.3.4.4 Grade 4 core: The core shall meet in general the requirements of Grade 3 cores, but may
have two major flaws such as described for Grade 3 or may have one flaw with a
maximum dimension of 25 mm perpendicular to the face of the core with a maximum
width of 38 mm. The end of the core that was shot against the form may be sandy with
voids containing overspray to a depth of 3 mm.

8.3.4.5 Grade 5 core: A core that does not meet the criteria of core grade 1 through 4, by being
of poorer quality, shall be classified as Grade 5.

8.3.5 Preconstruction test panels shall be prepared, cured, and tested in accordance with ACI
506.3R.

8.3.6 Three test specimens shall be extracted at each test age from the non-reinforced
shotcrete, for testing for the performance parameters specified in Section 5.3, Table 1,
except for Rapid Chloride Permeability test, if required, where two specimens shall
suffice.

8.3.7 The Engineer shall evaluate the quality of the extracted cores and test panel. When a
prequalification test panel is rejected, the nozzleman shall be permitted to shoot two
additional test panels. If either of the additional test panels is also rejected, the
nozzleman shall not be permitted to shoot on the project until he has successfully
completed an appropriate training program and passed a preconstruction trial test.

8.3.8 If the preconstruction test specimens fail to meet the project performance requirements,
then the Contractor shall make the necessary adjustments in shotcrete materials, mixture
design or application, and re-shoot test panels. No work shall commence on the project
until the preconstruction performance testing requirements have been met.

8.4 CONSTRUCTION TESTING

8.4.1 One construction test panel shall be shot by each nozzleman for each 20 cubic meters of
shotcrete production, but not more than once per day, and at least once per week. The
panel shall be shot in the same position as the repair work being done.

8.4.2 Test panels shall be produced in accordance with the requirements of ASTM C1140, but
shall have minimum dimensions of 450 x 450 mm x 100 mm deep. They shall be
constructed of wood and sealed plywood, with 45 degree sloped edge forms, to permit
escape of rebound. Construction test panels shall contain no reinforcement or
embedments (other than fiber reinforcement). The panels shall be cored or cut to provide
three compression test specimens as described below.

8.4.3 Construction test panels shall be stored, handled and cured in the same manner prescribed
for preconstruction test panels. Similarly, test specimens shall be prepared in the same
manner prescribed for preconstruction test specimens.
26

8.4.4 Compressive strength test specimens shall be either:

(a) 75 mm diameter cores with length/diameter ratios preferably 2:1 and not less than
1:1, or

(b) 75 mm cubes.

Compressive strength tests shall be conducted in accordance with ASTM C42. Measured
compressive strengths shall be corrected to equivalent 2:1 (length:diameter) cores, using
the core correction factors given in ASTM C42.

8.4.5 The mean compressive strength for a set of three cores shall equal or exceed f'c (where
f'c = specified strength). The mean of a set of three cubes shall equal or exceed 1.15 f'c.

8.4.6 Specimens for boiled absorption and permeable voids testing to ASTM C642, shall be 75
mm cubes, or extracted 75 mm diameter cores at least 100 mm long. Three specimens
shall be tested at age 7 days after shooting.

9.0 SAFETY AND CLEANUP

9.1 PREPARATION

9.1.1 The contractor shall implement a safety program during preparation for shotcreting to
ensure that:

(a) The structural integrity of all bridge elements is protected during concrete and
reinforcing steel removal operations by shoring or other suitable means;

(b) All personnel are protected from falling debris, blasting grits and high pressure
water jets during concrete removal processes.

9.1.2 The Contractor shall dispose of all debris, blasting grits, hydrodemolition and water
jetting slurry, in accordance with all local, state, and Federal laws, rules, and regulations.

9.2 SHOTCRETE APPLICATION SAFETY

9.2.1 The Contractor shall implement a safety program to protect all personnel and
surrounding property from pneumatically applied shotcrete overspray and rebound
materials during the shotcrete application process, using shrouds, screens or other
appropriate measures.

9.2.2 Personnel working near the shotcreting operation, including nozzleman, nozzleman's
helpers, supervisor and inspectors, shall wear appropriate protective equipment. Such
equipment shall include, but not be limited to: safety helmet, safety boots, gloves,
appropriate clothing, safety eye glasses with side enclosures and dust masks.
27

9.2.3 Nozzleman's helper shall keep a supply of water, cloth or towel and back-up safety
glasses available for nozzleman, so satisfactory vision can be maintained at all times
during shooting operations. Sufficient lighting shall be provided to enable the nozzleman
to have a clear view of the work.

9.2.4 Eyebaths and wash facilities shall be readily available in the immediate vicinity of the
shotcrete application. Shotcrete crew shall apply appropriate skin protection and adopt
work hygiene to protect against cement or accelerator alkali burn.

10.0 SHOTCRETE APPLICATION AND FINISHING

10.1 SHOTCRETE APPLICATION

10.1.1 All areas prepared for shotcrete repair shall be reviewed and approved by the Engineer
prior to application of any shotcrete.

10.1.2 Shotcrete shall be applied in accordance with good practice as detailed in Chapter 8 of
ACI 506R. Application requirements of Section 8.5 of ACI 506R apply, except that with
silica-fume modified shotcrete it will usually be possible to apply the full thickness of
shotcrete in a single pass, without the need for multiple layer construction. Wherever
possible, shotcrete shall be applied to the full thickness in a single layer.

10.1.3 The concrete substrate shall be saturated the day before shotcreting and then re-wetted
prior to shooting. At least one hour prior to application of shotcrete, all surfaces to be
shotcreted shall be flushed with water of drinking quality standard. Wetted surfaces shall
be allowed to dry back to a saturated-surface-dry condition prior to application of
shotcrete. If necessary, a blowpipe shall be used to facilitate removal of surface water.
Only oil-free compressed air shall be used in the blowpipe. In the event a work stoppage
longer than two hours takes place on any shotcrete layer prior to the time it has been built
up to required thickness, the surface shall be re-wetted prior to continuing. No shotcrete
shall be applied to a dry surface or to a surface with free surface water.

10.1.4 The minimum number of layers required to build up the full thickness of shotcrete
without sagging, separation or sloughing, shall be used.

10.1.5 When using multiple layer shotcrete construction, the first layer shall be prepared before
application of a subsequent layer, by either:

(a) Brooming the stiffening layer with a stiff bristle broom to remove all loose
material, rebound, overspray or glaze, prior to the shotcrete attaining initial set: or

(b) If the shotcrete has set, surface preparation shall be delayed at least 24 hours, at
which time the surface shall be prepared by sandblasting or high pressure water
blasting, to remove all loose material, rebound, hardened overspray, glaze, or
28

other material that prevents adequate bond as specified in the Contract


Documents.

10.1.6 When successive layers of shotcrete are required to build up the full shotcrete thickness,
the first layer shall be prevented from drying out by fogging or wetting. The use of
curing compound shall not be permitted between layers, except with the approval of the
Engineer in writing. If a curing compound is used, it shall be removed by abrasive blast
cleaning or high pressure water blasting, prior to application of the next layer of
shotcrete. The first layer of shotcrete shall be free of surface water and in a saturated-
surface-dry condition at the time of application of the next shotcrete layer.

10.1.7 Care shall be exercised to protect adjacent surfaces from build-up of rebound and
overspray. Rebound shall not be permitted in the completed work. Hardened rebound
and hardened overspray shall be removed prior to application of additional shotcrete,
using abrasive blast cleaning, chipping hammers, high pressure water blasting or other
suitable techniques.

10.1.8 The Contractor shall provide scaffolding or other temporary support system (eg. manlifts,
suspended work platform, etc.) at each repair location unless otherwise approved by the
Engineer. Plans for the proposed temporary support system shall be provided to the
Engineer for review and approval prior to its installation. No holes shall be drilled into
the superstructure to accomodate the support system unless approved in writing by the
Engineer. All anchorages placed in the substructure shall be removed when the platform
is removed and the substructure repaired at no additional cost.

10.1.9 Sufficient lighting and ventilation shall be installed to provide the nozzleman and helpers
with a clear, unhindered, view of the shooting area. Work shall be terminated and
corrective measures adopted if, in the opinion of the Engineer, visibility is unsuitable for
the safe application of quality shotcrete.

10.1.10 Shotcrete nozzling shall follow acceptable shooting practice, as detailed in ACI 506R. In
particular;

(a) The nozzle shall be generally operated at a distance of one half to one and one half
meters from the receiving surface and shall be oriented at right angles to the receiving
surface, except as required to fill corners, cove edges and encase large diameter
reinforcing steel;

(b) The combination of air pressure at the nozzle, moisture content of the shotcrete
and distance of the nozzle from the receiving surface shall be optimized to
achieve maximum compaction of the shotcrete;

(c) Care shall be taken while encasing reinforcing steel and mesh to keep the front
face of the reinforcement clean during shooting operations, so that shotcrete
builds up from behind, to encase the reinforcement and voids and sand pockets
are prevented from forming;
29

(d) Accumulations of rebound and overspray shall be continuously removed by the


blowpipe operator in advance of the deposition of new shotcrete. Rebound
material shall not be reused.

10.1.11 Shotcrete shall not be applied during periods of rain, or high wind which could
interfere with the shotcrete stream, unless suitable protective covers, enclosures or wind
breaks are installed.

10.1.12 Shotcrete shall be applied to the required line and grade and tolerance detailed in the
Contract Drawings, using shooting wires, depth gauges, guide strips, forms or other
suitable devices that do not entrap rebound. Shotcrete shall be applied to provide the
minimum cover to reinforcing detailed in the drawings. A positive means of checking
the total thickness of the applied shotcrete shall be provided by the use of shooting wires
which shall be removed prior to the final finish coat.

10.1.13 The application of a 5 to 20 mm thick final layer of plain 5 mm maximum size aggregate
flash coat of shotcrete shall be permitted over the top of 10 mm maximum aggregate size
shotcrete or steel fiber reinforced shotcrete.

10.2 SHOTCRETE FINISHING

10.2.1 Unless finishing is specifically required in the Contract Documents, the surface of the
shotcrete shall be built up slightly and trimmed to the final surface by cutting with the
leading edge of a sharp trowel. Any imperfections shall be floated using a rubber float.
Work done to the finished surface shall be limited to correcting imperfections caused by
cutting with the trowel.

10.2.2 Where finishing is required, shotcrete shall be cut back to line and grade using trowels
cutting rods, screeds or other suitable devices. The shotcrete shall be allowed to stiffen
sufficiently, before cutting and trimming, so as to prevent the formation of tears, cracks
and delaminations. Shooting wires shall be removed on completion of cutting and
trimming.

10.2.3 One or more of the following optional finishes may be applied, as specified in the
Contract Documents'

(a) Wood float finish; either as a preliminary finish for other surface treatments, or as
a granular texture finish;

(b) Rubber float finish; applied to either a flash coat, or wood float finish, to produce
a finer textured granular finish;
30

(c) Brush finish; a fine hairbrush float finish, leaving a finely textured, sandy finish.

10.2.4 All shotcrete and overspray shall be trimmed back from adjacent non-prepared
concrete surfaces. The edges of all shotcrete repairs shall have a minimum square
saw-cut edge 15 mm deep and shotcrete shall be finished up to this edge.
Featheredging of shotcrete (including flash coats) shall be prohibited.

11.0 CURING AND PROTECTION

11.1 CURING

11.1.1 On completion of finishing, shotcrete shall immediately be prevented from drying out by
fogging, wetting or where permitted by the Contract documents, by application of a
curing compound.

11.1.2 Curing compounds, if permitted by the Contract Documents, shall be removed prior to
application of subsequent paints, coatings or additional layers of shotcrete.

11.1.3 Once shotcrete has attained final set, it shall be kept continuously moist for a minimum
period of 7 days, unless the Contract documents permits a shorter curing period, or the
use of a curing compound. Moist curing shall be accomplished using one or more of the
following procedures:

(a) Wrapping the elements in wet burlap which has been presoaked in water for 24
hours prior to installation; wrapping the wet burlap in plastic sheet is useful for
retarding the rate of drying of the burlap.

(b) Installation of sprinklers, soaker hoses or other devices which keep the shotcrete
repairs continuously wet. The use of intermittent wetting procedures which allow
the shotcrete to undergo wetting and drying during the curing period shall be
prohibited.

11.2 HOT AND COLD WEATHER PROTECTION

11.2.1 The general requirements for hot and cold weather concreting detailed in ACI 305R and
ACI 306R, shall also apply to shotcrete remedial work except the maximum temperature
of the shotcrete shall not exceed 35 degrees C.

11.2.2 If the prevailing ambient conditions (relative humidity, wind speed, air temperature and
direct exposure to sunlight) are such that the shotcrete develops plastic shrinkage and/or
early drying shrinkage cracking, shotcrete application shall be terminated. The
Contractor shall:

(a) Reschedule the work to a time when more favorable ambient conditions prevail;
and/or
31

(b) Adopt corrective measures, such as installation of sun-screens, wind breaks,


surface evaporation retardants or fogging devices, to protect the work.

11.2.3 Shotcrete application shall be terminated if the ambient temperature rises above 30
degrees C, unless the Contractor adopts special hot-weather shotcreting procedures,
which are approved by the Engineer.

11.2.4 During periods of cold weather, shotcreting may only proceed if the concrete substrate to
which the shotcrete is applied is free of frost and the air temperature in contact with the
repair surfaces is above 5 degrees C.

11.2.5 The air temperature in contact with repaired surfaces shall be maintained at 5 degrees C
or greater for at least 3 days after application of shotcrete. The means of maintaining the
air temperature shall be approved by the Engineer. The use of unvented heaters, which
give rise to carbonation, shall be prohibited.

11.2.6 The temperature of applied shotcrete shall be preferably in the range of 10 to 20 degrees
C but not outside the range of 5 to 35 degrees C. Cooler mix temperatures are preferred
during hot weather shotcreting operations and warmer mix temperatures during cold
weather shotcreting.

12.0 SHOTCRETE ACCEPTANCE AND REPAIR

12.1 SHOTCRETE ACCEPTANCE

12.1.1 The Engineer shall have authority to accept or reject the shotcrete work. Shotcrete
which does not conform to the project specifications may be rejected either during the
shotcrete application process, or on the basis of tests on the test panels or completed
work.

12.1.2 Deficiencies observed during the shotcrete application process, such as, but not limited
to:

(a) failure to properly control and remove build-up of overspray and rebound;
(b) incomplete encasement of or incomplete consolidation around reinforcing steel,
mesh or anchors;
(c) incorporation of sand lenses, excessive voids, delaminations, sags, rebound, and
sloughing; or
(d) failure to apply shotcrete to the required line and grade and tolerance;

shall constitute cause for rejection of the plastic shotcrete. If plastic shotcrete is rejected
the contractor shall stop the work and take all measures necessary to correct deficiencies.

12.1.3 The Contractor shall, whenever possible, perform remedial work to correct deficiencies
while the shotcrete is still plastic.
32

12.1.4 The Engineer shall examine the completed shotcrete work. The hardened shotcrete shall
be examined for any evidence of cracking, tears, featheredging, sloughs or other
deficiencies. Sounding or other non-destructive evaluation (NDE) methods shall be used
to check for delaminations at 28 days, or less when approved by the Engineer in writing.
Non-conforming shotcrete is any that lacks uniformity; exhibits segregation,
honeycombing, or delaminations; has suffered excessive cracking; was not prepared or
applied in compliance with these specifications; fails to meet the specified requirements
in Table 1; or fails to meet the core grading requirements.

12.1.5 If the results of compliance tests from shotcrete construction test panels, or assessment of
the plastic and hardened shotcrete indicate non-conformance of the shotcrete to the
project specifications, the contractor shall drill at least three cores from the repaired
member. The cores shall penetrate into the existing concrete a minimum of 50 mm. The
number and location of the cores shall be at the discretion of the Engineer. These cores
shall be core graded in accordance with ACI 506.2 and tested for compressive strength,
boiled absorption, volume of permeable voids, and, if required, rapid chloride
permeability. The shotcrete shall be accepted if the mean core grade is 2.0 and the test
results meet the specified requirements for Boiled Absorption, Volume of Permeable
Voids, and Rapid Chloride Permeability in Table 1, and the following compressive
strength criteria. The mean compressive strength of a set of three cores shall equal or
exceed 0.85 f'c with no individual core less than 0.75 f'c. The mean of a set of three
cubes shall equal or exceed f'c with no individual cube less than 0.88 f'c. All core holes
shall be patched as detailed in the Contract Documents.

12.1.6 Shotcrete which is determined by the Engineer to be defective or non-conforming


to the project specifications based on evaluation of cores from the finished shotcrete shall
be repaired or removed and replaced by the contractor at no cost to the Owner. Repairs
of non-conforming shotcrete are subject to the same testing, evaluation, and acceptance
criteria as the original repair shotcrete.

12.2 SHOTCRETE REPAIR

12.2.1 Shotcrete which is identified as being non-conforming while still plastic shall be
removed using spades, scrapers or other suitable mechanical devices. High pressure
water jetting may be used, subject to acceptable disposal of the removed shotcrete and
slurry.

12.2.2 Hardened shotcrete which is identified as being non-conforming shall be removed using
the same basic procedures used for removal of deteriorated concrete. Care shall be taken
to avoid damage to reinforcing steel, mesh or anchors. Any embedments damaged
during the shotcrete removal process shall be replaced at no cost to the Owner.
33

12.2.3 All prepared repair areas shall be inspected and approved by the Engineer prior to the
placement of any repair shotcrete. Repair shotcrete shall be placed, finished, cured and
protected in the same manner specified for shotcrete work.

12.2.4 The contractor shall bear the costs for all repair and tests for non-conforming shotcrete.

13.0 MEASUREMENT

13.1 Shotcrete shall be measured by the in-place volume in cubic meters of applied shotcrete.
The depth shall be measured from the original outside concrete face. The Contractor and
Engineer shall measure repair quantities after removal of unsound concrete and before
application of shotcrete.

13.2 Payment shall be full compensation for furnishing materials, equipment, labor, tools and
incidentals required to accomplish temporary work access, preparation of surfaces,
application of shotcrete, waste shotcrete and rebound, coring of test samples, testing,
replacement of defective shotcrete as specified, clean-up of the area and disposal of waste
water, wasted shotcrete and rebound, and all other work and overhead costs necessary to
complete the designated pay items.

Pay Item Unit of Measurement

Shotcrete Cubic Meter


34

JOINT AASHTO-AGC-ARTBA GUIDE SPECIFICATION


FOR WET-MIX SHOTCRETE REPAIR OF HIGHWAY BRIDGES

1.0 GENERAL DESCRIPTION AND REQUIREMENTS

1.1 SCOPE

1.1.1 This document provides a guide specification for the repair of Highway bridges using the
wet-mix shotcrete process. It provides guide specifications for: selection of materials;
shotcrete mixture proportioning; selection of shotcrete equipment; preparation for
shotcreting; quality assurance and quality control testing; safety measures; shotcrete
application, finishing and curing procedures; and shotcrete acceptance. If incorporated
into the Contract Documents, this document shall become a part of the Contract
Documents and the Contractor shall comply with all the provisions in this document
unless specified in the Contract Documents or modified in writing by the Engineer.

1.2 QUALIFICATIONS

1.2.1 The shotcrete contractor’s crew foreman and nozzlemen shall meet the following
requirements unless otherwise specified in the contract documents:

(a) Furnish proof that the shotcrete crew foreman has at least 5 years experience in
Shotcrete repair work on projects of similar size and character along with 5
references who were responsible for supervision of similar projects. Include
name, address, and telephone number of references who will testify to the
sucessful completion of these projects by the shotcrete crew foreman.

(b) Furnish proof that the nozzlemen have sucessfully completed 3 projects of similar
size and character along with 3 references of those responsible for supervision of
these projects. The nozzlemen shall also pass a test demonstrating their
competence described in Section 8.3.

1.3 REQUIREMENTS

1.3.1 The Contractor shall furnish all labor, materials and equipment for:

(a) Removal of all spalled, deteriorated and damaged concrete as detailed in the
Contract Documents and directed by the Engineer;

(b) Cleaning corrosion product from corroded in-place reinforcing steel and where
specified removing and replacing excessively corroded reinforcing steel with new
reinforcement;

(c) Preparing concrete surfaces to receive shotcrete by either high pressure water
blasting or abrasive grit blasting;
35

(d) Installing all new reinforcing steel, mesh and anchors as detailed in the Contract
Documents;

(e) Supply, application, finishing, curing and protection of shotcrete;

(f) Provision of a quality control program to ensure compliance of completed


shotcrete remedial work with contract documents.

1.3.2 The Contractor shall implement a safety program which shall include but not necessarily
be limited to:

(a) Ensuring that the structural integrity of all bridge elements is protected during the
repairs by shoring or other suitable means as specified in the Contract
Documents;

(b) Protecting all personnel and the traveling public from falling debris, blasting grits
and high pressure water jets, during concrete removal processes;

(c) Protecting all personnel and the traveling public from pneumatically applied
shotcrete and rebound materials during the shotcrete application process;

(d) Ensuring compliance with all state and Federal OSHA regulations.

2.0 SUBMITTALS

The Contractor shall submit to the Engineer 10 working days before commencement of
production shotcreting work written documentation which provides:

2.1 The qualifications of the work crew, including the supervisor, shotcrete nozzlemen,
pump operator and shotcrete blowpipe operators, and the references for the supervisor
and nozlemen required in 1.2.1 (b) & (c).

2.2 Test records, showing source and proof of conformance to project specifications of all
shotcrete materials, including:
(a) Portland cement.
(b) Supplementary cementing materials (silica fume, fly ash, blast furnace slag).
(c) Aggregates.
(d) Mix water.
(e) Chemical admixtures.
(f) Reinforcement, including welded wire mesh fabric, reinforcing steel,
fibers.

2.3 Details of proposed shotcrete mixture(s) including shotcrete proportions and means of
shotcrete supply.
36

2.4 Results of the preconstruction testing program and a description of the proposed
construction quality control testing program, including the frequency of specific tests.

2.5 Proposed curing procedures and protection to be provided to shotcrete.

2.6 Proposed scaffolding or other temporary support system for workers and inspectors.

2.7 Proposed falsework or temporary support system for all bridge elements which undergo
loss of strength or support during concrete removal operations. Design criteria for
temporary structural support systems shall be as listed in the contract documents.

3.0 REFERENCE DOCUMENTS

3.1 The documents referenced below form a part of this document only to the extent
referenced. In the case of conflicts between the referenced portion of these documents
and this specification, the requirements of this specification shall take precedence.

3.1.1 American Concrete Institute (ACI)

ACI 506R, Guide to Shotcrete


ACI 506R.3, Guide to Certification of Shotcrete Nozzlemen
ACI 506.2, Specifications for Materials Proportioning and Application of
Shotcrete

3.1.2 American Society for Testing and Materials (ASTM)

ASTM A185, Specification for Steel Welded Wire Fabric, Plain, for Concrete
Reinforcement
ASTM A385, Practice for Providing High-Quality Zinc Coating (Hot Dip)
ASTM A615, Specification for Deformed an Plain Billet-Steel Bars for Concrete
Reinforcement
ASTM A641, Specification for Zinc-Coated (Galvanized) Carbon Steel Wire
ASTM A706, Specification for Low-Alloy Steel Deformed Bars for Concrete
Reinforcement
ASTM A767, Specification for Zinc-Coated (Galvanized) Steel Bars for
Concrete Reinforcement
ASTM A775, Specification for Epoxy-Coated Reinforcing Steel Bars
ASTM A820, Specification for Steel Fibers for Fiber Reinforced Concrete
ASTM C33, Specification for Concrete Aggregates
ASTM C39, Test Method for Compressive Strength of Cylindrical Concrete
Specimens
ASTM C 42, Test Method for Obtaining and Testing Drilled Cores and Sawed
Beams of Concrete
ASTM C150, Specification for Portland Cement
ASTM C260, Specification for Air-Entraining Admixtures for Concrete
37

ASTM C387, Standard Specification for Packaged, Dry, Combined Materials for
Mortar and Concrete
ASTM C494, Specification for Chemical Admixtures for Concrete
ASTM C595M, Specification for Blended Hydraulic Cements
ASTM C618, Specification for Coal Fly Ash and Raw or Calcined Natural
Pozzolan for Use as a Mineral Admixture in Portland Cement
Concrete
ASTM C642, Standard Test Method for Specific Gravity, Absorption and Voids
in Hardened Concrete
ASTM C685, Standard Specification for Concrete Made by Volumetric Batching
and Continuous Mixing
ASTM C989, Specification for Ground Granulated Blast-Furnace Slag for Use in
Concrete and Mortars
ASTM C1116, Standard Specification for Fiber Reinforced Concrete and
Shotcrete
ASTM C1017, Specification for Chemical Admixtures for Use in Producing
Flowing Concrete
ASTM C1140, Standard Practice for Preparing and Testing Specimens from
Shotcrete Test Panels
ASTM C1202, Test Method for Electrical Indication of Concrete’s Ability to
Resist Chloride Ion Penetration
ASTM C1240, Specification for Silica Fume for Use in Hydraulic-Cement
Concrete and Mortar

3.1.3 American Association of State Highway Transportation Officials (AASHTO)

AASHTO M6, Standard Specification for Fine Aggregate for Portland Cement
Concrete
AASHTO M80, Standard Specification for Coarse Aggregate for Portland Cement
Concrete
AASHTO M157, Ready-Mixed Concrete

4.0 MATERIALS

4.1 CEMENT

4.1.1 Cement shall conform to the requirements of ASTM C150, or C595. Engineer shall
select appropriate cement type.

4.2 SUPPLEMENTARY CEMENTING MATERIALS

4.2.1 Engineer shall specify which supplementary cementing materials, if any, are permitted or
required for use on project.

4.2.2 Fly ash pozzolan shall conform to the requirements of ASTM 618.
38

4.2.3 Granulated slag shall conform to the requirements of ASTM C989, Grade 100 or 120,
ground granulated blast furnace slag.

4.2.4 Silica fume shall conform to the requirements of ASTM C1240ASTM ???? C

4.3 WATER

4.3.1 All water used in shotcrete production shall be of drinking water standard and free of oil
and chemical or organic impurities.

4.3.2 Similarly all water used for high pressure water blasting, predampening of concrete
surfaces prior to application of shotcrete, in blowpipes for removal of rebound and
overspray, and for shotcrete curing, shall be of drinking water standards and free of oil
and chemical or organic impurities.

4.4 AGGREGATES

4.4.1 Aggregates shall be normal weight aggregates conforming to the requirements of


AASHTO M6 for fine aggregate and AASHTO M80 for coarse aggregate. Gradation of
aggregates shall be as required in the Contract Documents or as approved by the
Engineer.

4.5 ADMIXTURES

4.5.1 No admixtures shall be added to the shotcrete without approval of the Engineer. In
particular any admixtures containing chlorides shall not be used. Shotcrete accelerators
shall not be used without written authorization by the Engineer.

4.5.2 Air entraining admixtures shall be added to the mix water if specified in the Contract
Documents. Air entraining admixtures shall conform to the requirements of ASTM
C260.

4.5.3 Chemical admixtures, if used, such as water reducing and set-retarding admixtures, shall
conform to the requirements of ASTM C494. Superplasticizing Admixtures, if used,
shall conform to the requirements of ASTM C1017.

4Engineer.6 REINFORCEMENT

4.6.1 Welded wire mesh fabric shall be welded galvanized steel of dimensions and mass
specified in drawings and shall conform to ASTM A185.

4.6.2 New or replacement reinforcing bars shall be installed as detailed in the Contract
Documents. Reinforcing bars shall conform to ASTM A615, A706, A767, or A775.
39

4.6.3 Inserts for attachment of welded wire mesh fabric to existing concrete shall be galvanized
in accordance with ASTM A385 and A641, and be of adequate length and strength to
resist a 10 kN pull-out force.

4.6.4 Fibers shall conform to the requirements of ASTM C1116. Fiber type, length and
addition rate shall be as specified in the contract documents.

4.7 MATERIALS HANDLING AND STORAGE

4.7.1 Portland cement and supplementary cementing materials shall be stored so as to be


protected from exposure to moisture and temperatures below 5 degrees C and above 30
degrees C.

4.7.2 All admixtures shall be maintained at temperatures above 5 degrees C and below 30
degree C at all times.

4.7.3 Aggregates used in site batching of shotcrete shall be stockpiled and handled so as to
prevent segregation, and shall be tested to determine percent moisture for use in mix
design and calculation of water-cement ratio. Shelters or tarpaulins shall be used to
protect the aggregate stockpiles during periods of wet weather.

4.7.4 Fiber shall be stored in dry, sealed containers until ready for batching and shall be free
from corrosion, oil, grease or other contaminants.

5.0 SHOTCRETE PROPORTIONING

5.1 MIXTURE DESIGN

5.1.1 The Contractor shall be responsible for shotcrete mixture proportioning and shall submit
the proposed shotcrete mixture proportions to the Engineer for review and approval 10
working days prior to application of production shotcrete. As a minimum, for each
shotcrete mixture design the following information shall be submitted:

(a) An easily identifiable mix designation, number or code.

(b) Batch quantities of fine aggregate, coarse aggregate, cement, supplementary


cementing material, expected water demand (to include all water from moisture in
aggregates, and water added at the batch site and on site) and all other shotcrete
ingredients, in kg/m3, based on saturated surface dry aggregates.

(c) Aggregate source, gradation, relative bulk density (specific gravity) and
absorption.

5.1.2 Allowance shall be made for the shooting orientation and rebound in shotcrete mixture
proportioning.
40

5.1.3 Shotcrete shall be proportioned to meet the performance requirements detailed in the
project drawings and Section 5.3.

5.1.4 The Contractor shall submit performance test data from previous experience, if available,
along with the shotcrete mixture proportions for review by the Engineer.

5.1.5 In the absence of suitable shotcrete mixture proportioning experience, the Contractor
shall use the nominal trial mixture proportions detailed in Section 5 of the Commentary
section of this Guide Specifications. Adoption of these nominal trial mixture proportions
shall not relieve the Contractor of responsibility for meeting the performance
requirements detailed in the Contract Documents.

5.2 SILICA FUME SHOTCRETE

5.2.1 The silica fume content of silica fume shotcrete shall be between 5 and 15 percent by
mass of cement content or as specified in the Contract Documents.

5.2.2 Silica fume shall be supplied and added to the mixture in either a slurry; loose,
uncompacted; or partially compacted form. Densely compacted silica fume shall not be
used.

5.2.3 Silica fume shall be used in conjunction with the addition of sufficient superplasticizing
and water reducing admixture to control water demand of the mixture. The water
demand of wet-mix silica fume shotcrete shall not exceed the water demand of a
comparable Portland cement shotcrete mixture without silica fume.

5.3 PERFORMANCE REQUIREMENTS

5.3.1 Shotcrete shall conform to the performance requirements in Table 1.


41

TABLE 1
Wet-Mix Shotcrete Performance Requirements

Test Description Test Method Specified


Age Requirement
(Days)
Max. Water-Cementitious Materials Ratio - 0.42
Air Content - As Shot, % ASTM C231 - 5+/- 1½
Slump at Discharge into Pump, mm ASTM C143 - 60 +/- 20
Min. Compressive Strength, MPa (f’c) ASTM C39 7 28
ASTM C42 28)7 35
28
Max. Boiled Absorption, % ASTM C642 7 8
Max. Vol. of Permeable Voids, % 7 17
Max. Rapid Chloride Permeability, Silica- ASTM C1202 7 1500
Fume Shotcrete, Coulombs

5.3.2 For wet-mix shotcrete other than silica-fume shotcrete, the Contract Documents shall
establish maximum permissible rapid chloride permeability coulomb limits.

5.3.3 The air content shall be determined on shotcrete shot into an air pressure meter base.

6.0 SUPPLY AND EQUIPMENT

6.1 BATCHING, MIXING AND SUPPLY

6.1.1 Wet-mix shotcrete shall be batched, mixed and supplied by one of the following
methods:

(a) Central mixing with transit mix delivery.


(b) Transit mixing and delivery.
(c) Volumetric batching, mobile mixer unit.
(d) Dry-bagged premix materials with water added at site.

6.1.2 Central Mixing and Supply:

(a) Aggregate, cement and silica fume shall be mass batched in a central mix plant and
delivered in a transit mixer in accordance with the requirements of AASHTO
M157. Water and chemical admixtures shall be volumetrically batched.
Weighing equipment shall be capable of batching to the accuracy specified in
ASTM C685.
42

(b) Shotcrete materials shall be added in any sequence which provides uniform mixing and
dispersion, except that all water reducing admixtures and superplasticizers shall
be in the mixer at the time of addition of silica fume powder.

(c) Transit mixers shall be free of excessive accumulations of hardened shotcrete or concrete
in the drum or on the blades. Blades shall be free of excessive wear. Transit
delivery shall conform to the requirements of AASHTO M157, Section 10.

(d) One retempering with superplasticizer added directly to the transit mixture during the
period of discharge shall be permitted in order to maintain workability (slump) of
shotcrete within the specified range of 60 +/- 20 mm. Mixing shall continue for a
minimum period of five minutes at rated mixing speed after all additions of
superplasticizer to the transit mixer.

(e) All shotcrete shall be shot within 90 minutes after addition of mix water to the batch.
Shotcrete loads shall be of such batch size that this requirement is met.

6.1.3 Transit Mixing and Supply

(a) The same requirements shall apply as for Central Mixing except that all ingredients shall
be added directly to the transit mixer, instead of the central mixer. Transit mixers
shall be charged to not more than 70 percent of their rated capacity, to enable
efficient mixing action.

6.1.4 Volumetric Site Batching:

(a) The mobile mixer unit for volumetric batching shall conform to the requirements of
ASTM C685. The equipment shall proportion materials to the tolerances
specified in ASTM C685.

(b) The equipment shall be capable of thoroughly mixing materials in sufficient


quantity to maintain shotcreting continuity.

(c) The equipment shall be calibrated in accordance with the requirement of ASTM C685 at
the start of every shift or every 30 cubic meters of shotcrete batched, whichever is
more frequent, using a mass batch check of the volumetric proportioning.

(d) Feed systems for all materials (cement, silica fume, aggregates, admixtures) shall be
interconnected, such that if one feed stops, they all stop.

(e) The equipment shall be cleaned thoroughly at least once per shift to prevent
accumulation of aged material.

(f) All wet-mix shotcrete shall be applied within 90 minutes of mixing. Aged material shall
be discarded and not applied in the work.
43

6.1.5 Dry-Bagged Premix Supply:

(a) The use of dry-bagged premix supply with water addition at the site, shall be permitted,
provided the Contractor can demonstrate uniform mixing of the shotcrete and
satisfactory conformance to all the proper performance requirements.

6.2 SHOTCRETE PLACING EQUIPMENT

6.2.1 The shotcrete delivery equipment shall conform to the requirements of Sections 3.3, 3.6,
and 3.7 of ACI 506R and shall be capable of delivering a steady stream of uniformly
mixed material to the discharge nozzle at the proper velocity and rate of discharge.

6.2.2 The use of positive displacement pumps equipped with hydraulic or mechanically
powered pistons (e.g., similar to conventional concrete piston pumps), with compressed
air added at the discharge nozzle is the preferred type of wet-mix shotcrete delivery
system. Pneumatic feed guns, rotary type feed guns (similar to dry-mix guns) and
peristaltic squeeze-type pumps shall only be used if the Contractor can demonstrate that
they produce shotcrete meeting all the performance requirements in this document.

6.2.3 The air-ring at the nozzle shall be carefully monitored for any signs of blockage of
individual air holes. If non-uniform discharge of shotcrete becomes apparent, shooting
shall be stopped, and the air ring cleaned or other appropriate corrective actions taken.

6.2.4 The delivery equipment shall be thoroughly cleaned at the end of each shift. Any build-
up of coatings in the delivery hose and nozzle liner shall be removed. The air ring and
nozzle shall be regularly inspected and replaced as required.

6.3 AUXILIARY SHOTCRETE EQUIPMENT

6.3.1 The Contractor shall supply a clean, dry air supply, capable of maintaining sufficient
nozzle velocity for all parts of the work and simultaneous operation of a blow pipe.

6.3.2 The air supply system shall contain a moisture and oil trap to prevent contamination of
the shotcrete.

6.3.3 Auxiliary shotcrete equipment such as delivery hose, water hose, water booster pumps,
blowpipes, couplings, admixture dispensers and fiber feeders shall conform to the
recommendations in Section 3.8 of ACI 506R.

7.0 PREPARATION FOR SHOTCRETING

7.1 CONCRETE REMOVAL AND PREPARATION

7.1.1 The Contractor, at the direction of the Engineer shall locate and remove all loose,
spalled, deteriorated and delaminated concrete. Sounding shall be used to locate
44

delaminated areas. Care shall be exercised not to damage areas of sound concrete or
reinforcing steel during concrete removal operations. Unless specifically directed by the
Engineer, depth of removal shall not exceed 150 mm. Concrete removal shall be in
accordance with a sequence approved by the Engineer.

7.1.2 Concrete removal shall be accomplished using one or more of the following methods:

a) Chipping with hand picks, chisels or light duty pneumatic or electric chipping
hammers (not to exceed 7 kg mass);

b) Scarifiers, scabblers or other suitable mechanical means;

c) High pressure (100 to 275 MPa) water jetting.

7.1.3 If sound concrete is encountered before existing reinforcing steel is exposed, the surface
shall be prepared and repaired without further removal of the concrete. When corroded
reinforcing steel is exposed, concrete removal shall continue until there is a minimum 20
mm clearance around the exposed, corroded reinforcing bar. Care shall be taken to not
damage bond to adjacent non-exposed reinforcing steel during concrete removal
processes.

7.1.4 The perimeter of all areas where concrete is removed shall be tapered at an
approximately 45 degree angle, except that the outer edges of all chipped areas shall be
sawcut to minimum depth of 15 mm to prevent featheredging unless otherwise approved
by the Engineer.

7.1.5 After all deteriorated concrete has been removed, the repair surface to receive shotcrete
shall be prepared by abrasive blast cleaning or high pressure (100 to 275 MPa) water
jetting. The repair surface shall have an adequate surface roughness determined as three
peak to valley measurements of 5 mm5mmthin 150 mm.

7.1.6 Abrasive blast cleaning or high pressure water jetting shall remove all fractured surface
concrete and all traces of any unsound material or contaminants such as oil, grease, dirt,
slurry, or any materials which could interfere with the bond of freshly placed shotcrete.
Cleaned areas shall have shotcrete applied within 48 hours, or shall be reblasted.

7.1.7 The requirement for abrasive blast cleaning or high pressure water jetting may be waived
by the Engineer where concrete removal has been performed with high pressure water
blasting and the prepared surface is free of any residual slurry or other material
detrimental to adequate shotcrete bond.

7.1.8 Unless otherwise specified in the contract documents, all material removed shall become
the property of the Contractor and shall be disposed of as approved by the Engineer.

7.2 REINFORCEMENT
45

7.2.1 All corroded reinforcing steel exposed during concrete removal shall have corrosion
products removed by abrasive grit blasting. The exposed reinforcing steel surface that is
facing away from the sandblast nozzle shall be cleaned to remove all dust and loose
particles.

7.2.2 Reinforcing steel displaying deep pitting or loss of more than 20 percent of cross-
sectional area shall be removed and replaced, as detailed in the Contract Documents.

7.2.3 In cases of isolated pitting, the existing reinforcing steel need not be cut, but shall be
reinforced by addition of appropriately placed reinforcing bar of suitable length as
detailed in the Contract Documents.

7.2.4 The minimum lap splice length of all replacement and new reinforcing steel shall be as
detailed in the Contract Documents. Such bars shall be placed in accordance with the
recommendations of ACI 506R, Sections 5.4 and 5.5. In particular, bars shall not be
bundled in lapped splices, but shall be placed such that the minimum spacing around
each bar is three times the maximum aggregate size or 20 mm, which ever is larger to
allow for proper encapsulation with shotcrete.

7.2.5 Intersecting reinforcing bars shall be tightly secured to each other using 1.6 mm or
heavier gauge tie wire, and adequately supported to minimize vibration during shotcrete
placement.

7.2.6 As an alternative to lapped splices, replacement reinforcing steel shall be welded to


existing reinforcing, subject to verification of weldability of both existing and new
reinforcing steel and as specified in the Contract Documents.

7.2.7 Welded wire mesh fabric reinforcement shall conform to the requirements of ASTM
A185 and shall be galvanized.

7.2.8 Welded wire mesh fabric shall be provided as detailed in the Contract Documents and at
each repair area larger than 0.1 square meter if the depth of the repair exceeds 70 mm
from the original dimension of the repaired member. Sheets of adjoining mesh shall be
lapped by at least one and one-half spaces at all intersections, in both directions, and be
securely fastened. Welded wire mesh fabric shall have a minimum shotcrete cover of 50
mm.

7.2.9 Mesh shall be fastened to preset anchors or existing reinforcing using 1.6 mm or heavier
gauge tie wire, on a grid not more than 300 mm square. Large knots of tie wire which
could result in sand pockets and voids during shotcreting shall be avoided.

7.2.10 The minimum clearance between installed reinforcing steel or mesh and existing concrete
shall be 20 mm.

7.2.11 As an alternative to welded wire mesh fabric, steel or synthetic fiber reinforced shotcrete
may be used, as specified in the Contract Documents. Fiber reinforced shotcrete shall
46

only be used in conjunction with appropriate anchor and tie-back systems, as specified by
the Contract documents.

7.3 ANCHORS

7.3.1 Anchors shall be positioned at the spacing detailed in the Contract Documents. Any
given area shall have a minimum of four anchors. The reinforcing shall not vibrate or
deform excessively during shotcreting. Unless otherwise specified the maximum anchor
spacing shall not exceed 600 mm on a grid pattern over the entire repair area.

7.3.2 Anchors shall be of the type specified in the Contract Documents and shall be either
mechanically set or grouted, as specified.

7.3.3 Anchors shall develop the minimum pull-out force specified by the Contract documents.
Anchors shall be randomly tested at a frequency specified by the Contract documents, to
verify pull-out force. In no case shall the pull-out force be less than 10 kN. If any
anchors fail to meet the minimum acceptable pull-out value, corrective measures shall be
taken.

7.4 ALIGNMENT CONTROL AND COVER

7.4.1 Alignment control shall be implemented to establish control over line and grade and
ensure that the minimum specified shotcrete thickness and cover to reinforcing steel are
maintained.

7.4.2 Alignment control shall be accomplished by means of shooting wires, guide strips, depth
gauges or forms. The proposed means of alignment control shall be submitted to the
Engineer for review and approval.

7.4.3 When shooting wires (also called ground wires) are used, they shall consist of a high
strength steel wire (piano wire) kept taut during shotcreting. Shooting wires shall be
removed after completion of shotcreting and screeding operations.

7.4.4 Guide strips and forms shall be of such dimensions and installation configuration that
they do not impede the ability of the nozzleman to produce uniform, dense, properly
consolidated shotcrete. In particular, installations which are conducive to the formation
of sand-pockets and voids shall not be used.

7.4.5 When depth gauges are used for alignment control, they shall be installed at a spacing not
exceeding 1200 mm on a grid pattern. Metal depth gauges shall be cut back to 5 mm
below the finished surface, to prevent corrosion staining on the surface.

7.4.6 All repaired members shall be restored as close as practicable to their original
dimensions, including chamfered, if detailed. A minimum of 50 mm shotcrete cover
shall be provided over reinforcing steel exposed during repair.
47

8.0 QUALITY ASSURANCE AND QUALITY CONTROL TESTING

8.1 QUALITY ASSURANCE

8.1.1 The owner shall implement a quality assurance program for the work. Such a program
will normally be administered by the Engineer and shall include:

(a) Review of Contractor Submittals;

(b) Review and approval of Contractor's proposed materials, supply, equipment and
crew. In particular, all shotcrete nozzlemen proposed for use on the project shall
be evaluated in the preconstruction testing program; only nozzlemen approved in
writing by the Engineer shall be used on the project.

(c) Examination and approval of all areas prepared for shotcreting, including
installation of anchors, reinforcement, and devices to control line and grade, prior
to application of any shotcrete;

(d) Provision of inspectors to monitor shotcrete installation, with the authority to


require removal and replacement of defective shotcrete while still plastic;

(e) Regular monitoring of the results of the Contractor's quality control testing;

(f) Implementation of a program for in-place evaluation and acceptance or rejection,


where test results indicate shotcrete non-conforming to the project specifications;

(g) Implementation of a program of remedial works by the contractor, where


indicated as being necessary from the results of the quality assurance program.

8.2 QUALITY CONTROL TESTING

8.2.1 The Contractor shall establish and maintain a quality control program for the shotcrete
work, to assure compliance with the contract requirements. Such a program shall
include, but not be limited to:

(a) Maintenance of test records for all quality control operations;

(b) For site-batched materials, regular monitoring of aggregate gradation and


moisture content; one moisture content check shall be made at the start-up of each
shotcreting operation and with any changes in aggregate moisture content.

(c) For dry-bagged premix materials, wash-out testing at the frequency specified by
the Contract Documents, to check cementitious content, aggregate gradation, and
fiber content of fiber reinforced shotcrete.
48

(d) For volume-batched shotcrete mass batch checks of moisture content of


aggregates and mixture proportions at the frequency specified in the Contract
Documents;

(e) Physical testing for the hardened shotcrete performance parameters at the
frequency specified by the Contract Documents.

8.3 PRECONSTRUCTION TRIALS

8.3.1 The Contractor shall implement a preconstruction trial to enable the Engineer to evaluate
conformance of the proposed materials, shotcrete mixture, equipment and crew to the
project specifications. Acceptance of the preconstruction trial results by the Engineer is
required prior to performance of any work detailed in the Contract Documents.

8.3.2 The preconstruction trial shall be used to prequalify the nozzlemen proposed for use on
the project. Nozzlemen who have not been prequalified shall not be permitted to apply
shotcrete on the project.

8.3.3 The preconstruction trial shall approximate actual working conditions, configuration,
reinforcement, and shooting position as near as possible. The trial shall involve a
workmanship demonstration in accordance with Section 2.5 of ACI 506.3R, "Guide to
Certification of Shotcrete Nozzlemen". The trial shall be evaluated by core grading in
accordance with ACI 506.2. Cores shall be taken at locations of intersecting
reinforcement, as directed by the Engineer. Cores from any one panel shall have a mean
grade of 2.0 or less. The panel is unacceptable if any of the cores have a grade of 4 or 5
as described in Section 8.3.4.

8.3.4 CORE GRADING

8.3.4.1 Grade 1: Shotcrete specimens are solid; there are no laminations, sandy areas or voids.
Small air voids with a maximum diameter of 3 mm and maximum length of 6 mm are
normal and acceptable. Sand pockets or voids behind continuous reinforcing steel are
unacceptable. The surface against the form or bond plane shall be sound, without a
sandy texture or voids.

8.3.4.2 Grade 2: Shotcrete specimens shall have no more than two laminations or sandy areas
with dimensions not to exceed 3 mm thick by 25 mm long. The height, width and depth
of voids shall not exceed 10 mm. Porous areas behind reinforcing steel shall not exceed
13 mm in any direction except along the length of the reinforcing steel. The surface
against the form or bond plane shall be sound with full paste, without a sandy texture or
voids.

8.3.4.3 Grade 3: Shotcrete specimens shall have no more than two laminations or sandy areas
with dimensions exceeding 5 mm thick by 32 mm long, or one major void, sand pocket,
or lamination containing loosely bonded sand not to exceed 16 mm thick and 32 mm in
49

width. The surface against the form or bond plane may be sandy with voids containing
overspray to a depth of 2 mm.

8.3.4.4 Grade 4 core: The core shall meet in general the requirements of Grade 3 cores, but may
have two major flaws such as described for Grade 3 or may have one flaw with a
maximum dimension of 25 mm perpendicular to the face of the core with a maximum
width of 38 mm. The end of the core that was shot against the form may be sandy with
voids containing overspray to a depth of 3 mm.

8.3.4.5 Grade 5 core: A core that does not meet the criteria of core grades 1 through 4, by being
of poorer quality, shall be classified as Grade 5.

8.3.5 Preconstruction test panels shall be prepared, cured, and tested in accordance with ACI
506.3R.

8.3.6 Three test specimens shall be extracted at each test age from the non-reinforced
shotcrete, for testing for the performance parameters specified in Section 5.3, Table 1,
except for Rapid Chloride Permeability test, if required, where two specimens shall
suffice.

8.3.7 The Engineer shall evaluate the quality of the extracted cores and test panel. When a
prequalification test panel is rejected, the nozzleman shall be permitted to shoot two
additional test panels. If either of the additional test panels is also rejected, the
nozzleman shall not be permitted to shoot on the project until he has successfully
completed an appropriate training program and passed a preconstruction trial test.

8.3.8 If the preconstruction test specimens fail to meet the project performance requirements,
then the Contractor shall make the necessary adjustments in shotcrete materials, mixture
design or application, and re-shoot test panels. No work shall commence on the project
until the preconstruction performance testing requirements have been met.

8.4 CONSTRUCTION TESTING

8.4.1 One construction test panel shall be shot by each nozzleman for each 20 cubic meters of
shotcrete production, but not more than once per day, and at least once per week. The
panel shall be shot in the same position as the repair work being done.

8.4.2 Test panels shall be produced in accordance with the requirements of ASTM C1140, but
shall have minimum dimensions of 450 x 450 mm x 100 mm deep. They shall be
constructed of wood and sealed plywood, with 45 degree sloped edge forms, to permit
escape of rebound. Construction test panels shall contain no reinforcement or
embedments (other than fiber reinforcement). The panels shall be cored or cut to provide
three compression test specimens as described below.
50

8.4.3 Construction test panels shall be stored, handled and cured in the same manner prescribed
for preconstruction test panels. Similarly, test specimens shall be prepared in the same
manner prescribed for preconstruction test specimens.

8.4.4 Compressive strength test specimens shall be either:

(a) 75 mm diameter cores with length/diameter ratios preferably 2:1 and not less than
1:1, or

(b) 75 mm cubes.

Compressive strength tests shall be conducted in accordance with ASTM C42. Measured
compressive strengths shall be corrected to equivalent 2:1 length:diameter cores, using
the core correction factors given in ASTM C42. CS

8.4.5 The mean compressive strength for a set of three cores shall equal or exceed f’c (where
f’c = specified strength). The mean of a set of three cubes shall equal or exceed 1.15 f’c..

8.4.6 Specimens for boiled absorption and permeable voids testing to ASTM C642, shall be 75
mm cubes, or extracted 75 mm diameter cores at least 100 mm long. Three specimens
shall be tested at age 7 days after shooting.

9.0 SAFETY AND CLEANUP

9.1 PREPARATION

9.1.1 The contractor shall implement a safety program during preparation for shotcreting to
ensure that:

(a) The structural integrity of all bridge elements is protected during concrete and
reinforcing steel removal operations by shoring or other suitable means;

(b) All personnel are protected form falling debris, blasting grits and high pressure
water jets during concrete removal processes.

9.1.2 The Contractor shall dispose of all debris, blasting grits, hydrodemolition and water
jetting slurry, in accordance with all local, state, and Federal laws, rules, and regulations.

9.2 SHOTCRETE APPLICATION

9.2.1 The Contractor shall implement a safety program to protect all personnel and
surrounding property from pneumatically applied shotcrete overspray and rebound
materials during the shotcrete application process, using shrouds, screens or other
appropriate measures.
51

9.2.2 Personnel working near the shotcreting operation, including nozzleman, nozzleman's
helpers, supervisor and inspectors, shall wear appropriate protective equipment. Such
equipment shall include, but not be limited to: safety helmet, safety boots, gloves,
appropriate clothing, safety eye glasses with side enclosures and dust masks.

9.2.3 Nozzleman's helper shall keep a supply of water, cloth or towel and back-up safety
glasses available for nozzleman, so satisfactory vision can be maintained at all times
during shooting operations. Sufficient lighting shall be provided to enable the nozzleman
to have a clear view of the work.

9.2.4 Eyebaths and wash facilities shall be readily available in the immediate vicinity of the
shotcrete application. Shotcrete crew shall apply appropriate skin protection and adopt
work hygiene to protect against cement or accelerator alkali burn.

10.0 SHOTCRETE APPLICATION AND FINISHING

10.1 SHOTCRETE APPLICATION

10.1.1 All areas prepared for shotcrete repair shall be reviewed and approved by the Engineer
prior to application of any shotcrete.

10.1.2 Shotcrete shall be applied in accordance with good practice as detailed in Chapter 8 of
ACI 506R. Application requirements of Section 8.5 of ACI 506R apply, except that with
silica-fume modified shotcrete it will usually be possible to apply the full thickness of
shotcrete in a single pass, without the need for multiple layer construction. Wherever
possible, shotcrete shall be applied to the full thickness in a single layer.

10.1.3 The concrete substrate shall be saturated the day before shotcreting and then re-wetted
prior to shooting, as above. At least one hour prior to application of shotcrete, all
surfaces to be shotcreted shall be flushed with water of drinking quality standard.
Wetted surfaces shall be allowed to dry back to a saturated-surface-dry condition prior to
application of shotcrete. If necessary, a blowpipe shall be used to facilitate removal of
surface water. Only oil-free compressed air shall be used in the blowpipe. The concrete
substrate shall be saturated thehours takes place on any shotcrete layer priorprioe to the
time it has been built up to req thickness, the surface shall be re-wetted prior to
continuing. No shotcrete shallshal be applied to a dry surface or to a surfwith free
surface water.

10.1.4 The minimum number of layers required to build up the full thickness of shotcrete
without sagging, separation or sloughing, shall be used.

10.1.5 When using multiple layer shotcrete construction, the first layer shall be prepared before
application of a subsequent layer, by either:

(a) Brooming the stiffening layer with a stiff bristle broom to remove all loose
material, rebound, overspray or glaze, prior to the shotcrete attaining initial set: or
52

(b) If the shotcrete has set, surface preparation shall be delayed at least 24 hours, at
which time the surface shall be prepared by sandblasting or high pressure water
blasting, to remove all loose material, rebound, hardened overspray, glaze, or
other material that prevents adequate bondbond as specified in the
ContrDocuments.

10.1.6 When successive layers of shotcrete are required to build up the full shotcrete thickness,
the first layer shall be prevented from drying out by fogging or wetting. The use of
curing compound shall not be permitted between layers, except with the approval of the
Engineer in writing. If a curing compound is used, it shall be removed by abrasive blast
cleaning or high pressure water blasting, prior to application of the next layer of
shotcrete. The first layer of shotcrete shall be free of surface water and in a saturated-
surface-dry condition at the time of application of the next shotcrete layer.

10.1.7 Care shall be exercised to protect adjacent surfaces from build-up of rebound and
overspray. Rebound shall not be permitted in the completed work. Rebound and
overspray shall be removed from surfaces to receive shotcrete; this is best accomplisrete,
using abrasive blast cleaning, chipping hammers, high pressure water blasting or other
suitable techniques.

10.1.8 The Contractor shall provide scaffolding or other temporary support system (e.g.
manlifts, suspended work platform, etc.) at each repair location unless otherwise
approved by the Engineer. Plans for the proposed temporary support system shall be
provided to the Engineer for review and approval prior to its installation. No holes shall
be drilled into the superstructure to accommodate the support system unless approved in
writing by the Engineer. All anchorage’s placed in the substructure shall be removed
when the platform is removed and the substructure repaired at no additional cost.

10.1.9 Sufficient lighting and ventilation shall be installed to provide the nozzleman and helpers
with a clear, unhindered, view of the shooting area. Work shall be terminated and
corrective measures adopted if, in the opinion of the Engineer, visibility is unsuitable for
the safe application of quality shotcrete.

10.1.10 Shotcrete nozzling shall follow acceptable shooting practice, as detailed in Section 8.5 of
ACI 506R. In particular:

(a) The nozzle shall be generally operated at a distance of one half to one and one
half meters from the receiving surface and shall be oriented at right angles to the
receiving surface, except as required to fill corners, cove edges and encase large
diameter reinforcing steel;

(b) The combination of air pressure at the nozzle, moisture content of the shotcrete
and distance of the nozzle from the receiving surface shall be optimized to
achieve maximum compaction of the shotcrete;
53

(c) Care shall be taken while encasing reinforcing steel and mesh to keep the front
face of the reinforcement clean during shooting operations, so that shotcrete
builds up from behind, to encase the reinforcement and voids and sand pockets
are prevented from forming;

(d) Accumulations of rebound and overspray shall be continuously removed by the


nozzleman's helper in advance of the deposition of new shotcrete. Rebound
material shall not be reused.

10.1.11 Shotcrete shall not be applied during periods of rain, or high wind which could
interfere with the shotcrete stream, unless suitable protective covers, enclosures or wind
breaks are installed.

10.1.12 Shotcrete shall be applied to the required line and grade and tolerance detailed in the
Contract Drawings, using shooting wires, depth gauges, guide strips, forms or other
suitable devices that do not entrap rebound. Shotcrete shall be applied to provide the
minimum cover to reinforcing detailed in the drawings. A positive means of checking
the total thickness of the applied shotcrete shall be provided by the use of shooting wires
which shall be removed prior to the final finish coat.

10.1.13 The application of a 5 to 20 mm thick final layer of plain 5 mm maximum size aggregate
flash coat of shotcrete shall be permitted with 10 mm maximum aggregate size shotcrete, or steel
fiber reinforced shotcrete.

10.2 SHOTCRETE FINISHING

10.2.1 Unless finishing is specifically required in the Contract Documents, the surface of the
shotcrete shall be built up slightly and trimmed to the final surface by cutting with the
leading edge of a sharp trowel. Any imperfections shall be floated using a rubber float.
Work done to the finished surface shall be limited to correcting imperfections caused by
cutting with the trowel.

10.2.2 Where finishing is required, shotcrete shall be cut back to line and grade using trowels,
cutting rods, screeds or other suitable devices. The shotcrete shall be allowed to stiffen
sufficiently, before cutting and trimming, so as to prevent the formation of tears, cracks
and delaminations. Shooting wires shall be removed on completion of cutting and
trimming.

10.2.3 One or more of the following optional finishes may be applied, as specified in the
Contract Documents:

(a) Wood float finish; either a s a preliminary finish for other surface treatments, or
as a granular texture finish;

(b) Rubber float finish; applied to either a flash coat, or wood float finish, to produce
a finer textured granular finish;
54

(c) Brush finish; a fine hairbrush float finish, leaving a finely textured, sandy finish.

10.2.4 All shotcrete and overspray shall be trimmed back from adjacent non-prepared concrete
surfaces. The edges of all shotcrete repairs shall have a minimum square saw-cut edge
15 mm deep and shotcrete shall be finished up to this edge. Featheredging of shotcrete
(including flash coats) shall be prohibited.

11.0 CURING AND PROTECTION

11.1 CURING

11.1.1 On completion of finishing, shotcrete shall immediately be prevented from drying out by
fogging, wetting or where permitted by the Contract documents, by application of a
curing compound.

11.1.2 Curing compounds, if permitted by the Contract Documents, shall be removed prior to
application of subsequent paints, coatings or additional layers of shotcrete.

11.1.3 Once shotcrete has attained final set, it shall be kept continuously moist for a minimum
period of 7 days, unless the Contract Documents permits a shorter curing period, or the
use of a curing compound. Moist curing shall be accomplished using one or more of the
following procedures:

(a) Wrapping the elements in wet burlap which has been presoaked in water for 24
hours prior to installation; wrapping the wet burlap in plastic sheet is useful for
retarding the rate of drying of the burlap.

(b) Installation of sprinklers, soaker hoses or other devices which keep the shotcrete
repairs continuously wet. The use of intermittent wetting procedures which allow
the shotcrete to undergo wetting and drying during the curing period shall be
prohibited.

11.2 HOT AND COLD WEATHER PROTECTION

11.2.1 The general requirements for hot and cold weather concreting detailed in ACI 305R and
ACI 306R, shall also apply to shotcrete remedial work except the maximum temperature
of the shotcrete shall not exceed 35 degrees C.

11.2.2 If the prevailing ambient conditions (relative humidity, wind speed, air temperature and
direct exposure to sunlight) are such that the shotcrete develops plastic shrinkage and/or
early drying shrinkage cracking, shotcrete application shall be terminated. The
Contractor shall:

(a) Reschedule the work to a time when more favorable ambient conditions prevail;
and/or
55

(b) Adopt corrective measures, such as installation of sun-screens, wind breaks,


surface evaporation retardants or fogging devices, to protect the work.

11.2.3 Shotcrete application shall be terminated if the ambient temperature rises above 30
degrees C, unless the Contractor adopts special hot-weather shotcreting procedures,
which are approved by the Engineer.

11.2.4 During periods of cold weather, shotcreting may only proceed if the concrete substrate to
which the shotcrete is applied is free of frost and the air temperature in contact with the
repair surfaces is above 5 degrees C.

11.2.5 The air temperature in contact with repaired surfaces shall be maintained at 5 degrees C
or greater for at least 3 days after application of shotcrete. The means of maintaining the
air temperature shall be approved by the Engineer. The use of unvented heaters, which
give rise to carbonation, shall be prohibited.

11.2.6 The temperature of applied shotcrete shall be preferably in the range of 10 to 20 degrees
C but not outside the range of 5 to 35 degrees C. Cooler mix temperatures are preferred
during hot weather shotcreting operations and warmer mix temperatures during cold
weather shotcreting.

12.0 SHOTCRETE ACCEPTANCE AND REPAIR

12.1 SHOTCRETE ACCEPTANCE

12.1.1 The Engineer shall have authority to accept or reject the shotcrete work. Shotcrete which
does not conform to the project specifications may be rejected either during the shotcrete
application process, or on the basis of tests on the test panels or completed work.

12.1.2 Deficiencies observed during the shotcrete application process, such as, but not limited
to:

(a) failure to properly control and remove build-up of overspray and rebound;
(b) incomplete encasement around or incomplete consolidation of reinforcing steel,
mesh or anchors;shotcrete rebound, or fibre
(c) incorporation of sand lenses, excessive voids, delaminations, sags, rebound, and
sloughing;
(d) failure to apply shotcrete to the required line and grade and tolerance;
56

shall constitute cause for rejection of the plastic shotcrete. If plastic shotcrete is rejected
the contractor shall stop the work and take all measures necessary to correct deficiencies.

12.1.3 The Contractor shall, whenever possible, perform remedial work to correct deficiencies
while the shotcrete is still plastic.

12.1.4 The Engineer shall examine the completed shotcrete work. The hardened shotcrete shall
be examined for any evidence ofplastic or drying shrinkage cracking, tearr other
deficiencies. Sounding or other non-destructive evaluation (NDE) methods shall be used
to check for delaminations at 28 days, or less if approved by the Engineer in
writing(Steve Gebler-when?). Non-conforming shotrete is any that in the opinion cks
uniformitombing, or delaminations; has suffered excessive cracking; was not prepared
or applied in strict compliance with these specifications; o to meet the specifiedg
requirements in Table 1; or fails to meet the core grading requirements2.

12.1.5 If the results of compliance tests from shotcrete construction test panels, or assessment of
the plastic and hardened shotcrete indicate non-conformance of the shotcrete to the
project specifications, the contractor shall drill at least three cores from the repaired
member. The cores shall penetrate into the existing concrete a minimum of 50 mm. The
number and location of the cores shall be at the discretion of the Engineer. These cores
shall be core graded in accordance with ACI 506.2 and tested for compressive strength,
boiled absorption, volume of permeable voids, and rapid chloride permeability, if
applicable. The shotcrete shall be accepted if the minimum mean core grade is 2 or leo
individual core grade is 4 or 5, and the test results meet the specified requirements for
Boiled Absorption, Volume of Permeable Voids, and Rapid Chloride Permeability, if
applicable, in Table 12 and the following compressive stength criteria. The mean
compressive strength of a set of three cores shall equal or exceed 0.85 f’c with no
individual core less than 0.75 f’c. The mean of a set of three cubes shall equal or exceed
f’c with no individual cube less than 0.88 f’c. All core holes shall be patched as detailed
in the Contract Documents.

12.1.6 Shotcrete which is determined to be defective or non-conforming to the project


specifications by the Engineer based on evaluation of cores from the finished shotcrete
shall be repaired or removed and replaced by the contractor at no cost to the Owner.
Repairs of non-conforming shotcrete are subject to the same testing, evaluation, and
acceptance criteria as the original repair shotcrete.

12.2 SHOTCRETE REPAIR

12.2.1 Shotcrete which is identified as being non-conforming while still plastic shall be
removed using spades, scrapers or other suitable mechanical devices. High pressure
water jetting may be used, subject to acceptable disposal of the removed shotcrete and
slurry.
57

12.2.2 Hardened shotcrete which is identified as being non-conforming shall be removed using
the same basic procedures used for removal of deteriorated concrete. Care shall be taken
to avoid damage to reinforcing steel, mesh or anchors. Any embedments damaged
during the shotcrete removal process shall be replaced at no cost to the Owner.

12.2.3 All prepared repair areas shall be inspected and approved by the Engineer prior to the
placement of any repair shotcrete. Repair shotcrete shall be placed, finished, cured and
protected in the same manner specified for shotcrete work.

12.2.4 The contractor shall bear the costs for all repair and tests for non-conforming shotcrete.

13.0 MEASUREMENT

13.1 Shotcrete shall be measured by the in-place volume in cubic meters of applied shotcrete.
The depth shawill be measuredmeasusred from a place at t original outsete face. The
Contractor and Engineer shawill measure repair quantities after removaof unsound
concrete and before application of shotcrete.

13.2 Payment shall be full compensation for furnishing materials, equipment, labor, tools and
incidentals required to accomplish temporary work access, preparation of surfaces,
application of shotcrete, waste shotcrete and rebound, coring of test samples, testing,
replacement of defective shotcrete as specified, clean-up of the area and disposal of waste
water, wasted shotcrete and rebound, and all other work and overhead costs necessary to
complete the designated pay items.

Pay Item Unit of Measurement


Shotcrete Cubic Meter
58

COMMENTARY ON GUIDE SPECIFICATIONS


FOR SHOTCRETE REPAIR OF HIGHWAY BRIDGES

1.0 GENERAL DESCRIPTION AND REQUIREMENTS

1.1 SCOPE

This Commentary should be read in conjunction with the Joint AASHTO-AGC-ARTBA


Guide Specifications for Dry-Mix (or Wet-Mix) Shotcrete Repair of Highway Bridges.
The same numbering system has been used in the Commentary and Guide specifications
to aid the reader in this process. This Commentary is designed to provide the reader with
further amplification and guidance on the shotcrete repair of bridges. Both the wet-mix
and dry-mix processes have been used for shotcrete repair of bridges. This Commentary
provides information about both dry mix and wet mix shotcrete to assist the Specifier in
selection of the appropriate process for a specific project. Similarly, this Commentary
provides guidance on the relative merits and limitations of conventional, silica fume, and
fiber reinforced shotcretes.

The vast majority of shotcrete repair work on bridges is carried out on elements such as
girders, stringers, slab soffits, diaphragms, arches, abutments, piers, etc. Shotcrete
typically provides a more economical remedial solution for repair of the general thin
(surficial) damage encountered in deteriorated bridges, compared to remedial work
performed with formed and cast-in-place repair concretes, or hand-applied repair
materials.

Occasionally, shotcrete is also used for repair of superstructure elements, such as median
barriers, curb and gutter, parapets, and towers. Conceptually there is no reason why
shotcrete cannot be used for repair of superstructure elements. It should, however, be
noted that the shotcrete process is best suited to the repair of overhead, vertical, or
steeply sloping surfaces. Gradually sloping or horizontal surfaces are generally more
favorably repaired with cast-in-place procedures.

Shotcrete repair of bridge substructures is often done in conjunction with repair of


superstructure elements, such as the bridge deck, expansion joints and curb and gutter.
The C-SHRP study on the "Durability of Shotcrete Rehabilitation Treatments of
Highway Bridges" (Ref. 1) demonstrated that the greatest service life of shotcrete repairs
of bridge substructure elements is achieved when the cause of the original bridge
deterioration is properly addressed. In many cases examined, the prime cause of original
bridge deterioration was water and deicing chemical solutions leaking through deck
joints and deck draining systems onto substructure elements, resulting in scaling and
corrosion induced deterioration in the reinforced concrete elements. If such sources of
moisture and salt were not eliminated in the remedial design, the C-SHRP study (Ref. 1)
found that, while the shotcrete repairs generally performed well, the surrounding non-
repaired original concrete often continued to deteriorate. Thus, the best service life will
be achieved in repairs which take into account the original cause of deterioration and
incorporated mitigative measures in the remedial design.
59

1.2 REQUIREMENTS

The requirements section of the Guide Specifications outlines the services typically
required to be provided by the Contractor in a shotcrete repair of bridges project. If
remedial work and/or mitigative measures are required for the deck and superstructure
elements, the Requirements section of the Guide Specifications will have to be expanded.

Emphasis has been placed on the need for the Contractor to implement an appropriate
safety program. In the repair of deteriorated bridge elements there is often a need for
removal of significant quantities of deteriorated concrete, and sometimes corroded
reinforcing steel. It is important that the Contractor provide suitable shoring and support
to maintain the structural integrity of the bridge during the concrete removal processes.
In some cases this will require sequential concrete removal and shotcrete reconstruction
in order to maintain structural integrity; e.g., in removal of deteriorated concrete adjacent
to major bearings on pier or abutments. Frequent on-site communication with the
Engineer will normally be required in such circumstances.

Emphasis is also placed on other safety aspects of the concrete preparation and shotcrete
application processes. These processes, typically require the use of blasting grits and/or
high pressure water jets, and the high velocity, pneumatic conveyance of shotcrete
materials. The Contractor should implement a safety program which satisfies the
requirements of the authorities having jurisdiction over the operation of such equipment.

2.0 SUBMITTALS

Shotcrete rehabilitation of bridges is a specialist trade, which requires the use of


appropriate equipment and a knowledgeable work crew, experienced in this specific type
of work if the Owner is to obtain a satisfactory end product. In particular, it is important
that the shotcrete nozzlemen used on the project have suitable prior experience in this
type of work. Thus it is recommended that the Contractor, at the bid stage, submit proof
of qualification of the proposed work crew to perform the required work. It should,
however, be recognized that the Contractor may not be able to identify all specific
individuals proposed for the work at bid stage.

Some specifications require the nozzleman to be certified in accordance with the ACI
506R.3, "Guide to Certification of Shotcrete Nozzleman". Very few nozzlemen are,
however, likely to have been "certified" in accordance with ACI 506R.3, unless it was
done by an independent lab or agency, or unless the contractor has set up a certification
program which has been reviewed and accepted by the owner of the project. Thus proof
of past pertinent experience, including a list of previously completed projects (in
conjunction with preconstruction testing), is the best means of evaluating the capability
of the crew supervisor and nozzlemen to perform the work.

Other submittals should include the normal materials test records showing proof of
conformance of proposed materials to the project specifications. In addition, the
60

Contractor should submit details of the proposed shotcrete mixture design(s), and
shotcrete batching, mixing, supply and application equipment. The Contractor should
also submit details of the proposed quality control testing procedures, and curing and
protection to be provided to the shotcrete. The Engineer should review the conformance
of all submittals to the project specifications.

3.0 REFERENCE DOCUMENTS

Pertinent American Concrete Institute (ACI) and American Society for Testing and
Materials (ASTM) documents are invaluable for providing background and details of
common practice when making decisions about a specific project. However, they are not
normally referenced in Specification documents since they are not written in
specification format. Of these documents, the most useful is the ACI 506R, "Guide to
Shotcrete". While this document does not specifically address the use of shotcrete for
repair of bridges, it contains much useful information, which will be of assistance to the
Specifier in preparing contract documents. The Guide Specifications cite specific
chapters in ACI 506R with the intent that the specifier, using the Commentary, will
choose the requirements which apply to their project and insert those requirements in the
project specifications using appropriate imperative language.

Additional useful information with respect to the dry-mix shotcrete process, particularly
with respect to encasement of reinforcing steel, is provided in Reference 2. Other useful
referral documents are listed in the references at the end of this Commentary.

4.0 MATERIALS

4.1 CEMENT

Most shotcrete repair of bridges is carried out with ASTM Type I or II Portland cement.
Where there is a requirement for high early strength development (e.g., in bridges
carrying traffic during construction) a Type III cement may be specified. For
substructure elements, such as abutments, piers and wingwalls in sulfate soil or
groundwater conditions it may be necessary to specify the use of a Type V cement. It
should, however, be remembered that Type V cements (with low C3A contents) are less
suited to inhibition of chloride ion penetration than Type I, II or III cements. (See
Reference 3)

4.2 SUPPLEMENTARY CEMENTING MATERIALS

Pozzolans, such as fly ash, have been used in wet-mix shotcrete repair projects. They are
used for many of the same reasons they are used in concrete (Ref. 4):

• to provide additional fines to enhance pumpability and adhesion and cohesion of


the shotcrete mix, particularly if the sand tends to be coarse;
61

• to provide enhanced long-term durability; through the pozzolanic reactions which


reduce permeability and enhance resistance to chloride ion penetration;
reduced heat of hydration in thick-section repairs.

There is very limited experience in the use and performance of blast-furnace slag
modified shotcretes. Prototype field tests are thus recommended for such shotcrete
before using it for repair of bridges.

By far the most widely used supplementary cementing material in shotcrete is silica
fume. Silica fume has been used in shotcretes in Scandinavian countries since the 1970's
and found its first use in shotcrete repair of structures in North America in the early
1980's (Ref. 5). Silica fume is used in both wet and dry-mix shotcrete for the benefits it
imparts to both the plastic and hardened shotcrete. These benefits are detailed in Section
5.2 of this Commentary.

Silica fume shotcrete, particularly applied by the dry-mix shotcrete process, is now
finding widespread use for bridge repair in some areas.

4.3 WATER

It is important that all mix water used in shotcrete preparation and production processes
be of drinking water quality. In particular, water which is muddy, or contains sulfate or
chloride salts or other contaminants, should not be used. Wash-down with muddy water
could leave a fine clay residue on the prepared surface and interfere with shotcrete bond.
Water used in preparation of concrete surfaces should be free of oil or other
contaminants. Similarly, compressors used for adding air at the air-ring at the nozzle in
the wet-mix shotcrete process, or pneumatically conveying material in the dry-mix
shotcrete process, should have oil and water traps added to prevent contamination of the
shotcrete. While it may be acceptable to use water meeting ASTM C94 requirements as
mix water for the shotcrete, it is not acceptable to use water meeting that specification for
blast cleaning or wash down, since it may contain sufficient contaminates to affect the
bond of the shotcrete to the substrate.

4.4 AGGREGATES

Only good quality, hard, dense aggregates conforming to all the requirements of
AASHTO M6 for fine aggregate and AASHTO M80 for coarse aggregate, should be
allowed in shotcrete used to repair bridges. In particular, the use of frost-susceptible or
alkali-reactive aggregates should be avoided, in view of the aggressive exposure
conditions to which most shotcrete bridge repairs are subjected.

Recommended shotcrete aggregate gradation limits for nominal 10 mm and 5 mm


maximum size aggregate gradations are given below. These gradation limits correspond
62

to the ACI 506R, Table 2.1 Gradation No. 2 and No. 1 limits respectively. There tend to
be regional preferences regarding whether to use nominal 10 mm or 5 mm maximum size
aggregate (MSA) gradation shotcrete for bridge repair. One of these gradations should
be specified in the Contract Documents. For the 10 mm nominal maximum aggregate
size the 10 to 2.5 mm coarse aggregate fraction should be stockpiled and added
separately from the fine aggregate (nominal 5 mm maximum size) during mixing
operations.

TABLE 1:
Gradation Limits for Nominal 10 mm and 5 mm Maximum Size Aggregate Shotcretes

Metric Sieve Size Total Passing Each Sieve, % by Mass


Nominal Maximum Aggregate Size 5 mm 10 mm
14 mm 100 100
10 mm 100 90 - 100
5 mm 95 - 100 70 - 85
2.5 mm 80 - 100 50 - 75
1.25 mm 50 - 90 35 - 55
630 mm 25 - 65 20 - 35
315 mm 10 - 35 8 - 20
160 mm 2 - 10 2 - 10

The following tabulation provides an indication of the relative advantages and


disadvantages of the different aggregate gradations.
63

10 mm Nominal Maximum Aggregate Size


Advantages Disadvantages
• More "concrete-like" mixture, with • Greater rebound of coarse aggregate,
coarse aggregate component, giving rise to particularly during encapsulation of reinforcing
lower water demand and hence reduced steel using the dry-mix shotcrete process.
shrinkage and cracking potential compared to 5
mm MSA shotcrete. • Leaves a rough "pock-marked" as-shot
finish, which may be less aesthetically acceptable
• Larger maximum size aggregate than a 5 mm MSA as-shot finish.
provides better "cleaning" of the shotcrete lines
and nozzle in the dry-mix shotcrete process. • Requires more finishing effort compared
to 5 mm MSA shotcrete.
• Greater momentum of larger aggregate
particles helps keep the front face of reinforcing • May require application of a 5 mm MSA
steel "clean" during shooting and facilitates the shotcrete finish coat.
shotcrete compaction process.
5 mm Nominal Maximum Aggregate Size
Advantages Disadvantages
• Lower rebound than 10 mm MSA • Being a mortar, rather than a more
shotcrete, particularly when encasing concrete-like mixture, has a higher water demand
reinforcing steel or mesh. than 10 mm MSA shotcrete.

• More easily finished than 10 mm MSA • Requires higher cementitious content than
shotcrete, usually does not require a finish coat. 10 mm MSA shotcrete to produce a given
strength.

• Has a higher shrinkage capacity and


hence greater cracking potential than 10 mm
MSA shotcrete.

• More prone to the formation of "sand


lenses" or "sand pockets" when encapsulating
reinforcing steel or mesh, using the dry-mix
shotcrete process.

As a general rule, 10 mm MSA shotcrete is more suited to thicker-section shotcrete repairs and
where shotcrete finishing is not required. By contrast, 5 mm MSA shotcrete might be preferred
for thin-section repairs and where finished surfaces are required.

4.5 ADMIXTURES
64

The use of admixtures is generally not required in dry-mix shotcrete, with the possible
exception of the addition of air entraining admixture. Extensive research (Ref. 6, 18) has
shown that freeze/thaw durable dry-mix shotcrete can be produced without the addition
of air-entraining admixtures, provided the shotcrete is properly proportioned, applied and
cured. Recent work at Laval University (Ref. 7) has, however, shown that the addition of
air-entraining admixture to the mix water added at the nozzle in the dry-mix shotcrete
process results in enhanced deicing chemical scaling resistance. This procedure is being
used for shotcrete repair of bridges in Quebec at an addition rate of 15 ml/l of water.
More recently an air-entraining powder has been developed to be mixed with the dry
ingredients so that water alone can be added at the nozzle. Air-entraining admixture is
not considered necessary for properly applied, well compacted dry-mix shotcrete in
normal applications since it has been shown to contain appropriate air-void parameters
resulting from the application process which protect it from freeze-thaw damage.

In wet-mix shotcrete, the use of air entraining admixtures is considered mandatory for
shotcrete exposed to freezing and thawing (Ref. 6). It should be noted that
approximately half the air content in the mixture is lost during the shotcrete application
process; thus the air content in the as-batched shotcrete should be adjusted accordingly.
The use of water-reducing admixtures is generally recommended for wet-mix shotcrete,
as they reduce the water demand of the shotcrete, thus helping reduce shrinkage. In
warm weather the use of set-retarding admixtures may be beneficial. For silica fume
modified wet-mix shotcretes the use of superplasticizing admixture is strongly
recommended, in order to control water demand and hence strength and shrinkage of the
mixture.

The addition of "concrete-type" set-accelerating admixtures may be appropriate for wet-


mix shotcrete work conducted in cold weather conditions. Such accelerators should,
however, be chloride free. The use of “shotcrete accelerators" (such as typically used in
support of underground openings) is, however, not recommended for shotcrete repair of
bridges. Such accelerators typically result in substantial increases in drying shrinkage
and hence shrinkage cracking potential. They reduce compressive and flexural strength
and markedly increase permeability and susceptibility to chloride ion intrusion (Ref. 5,
18). They also reduce frost-resistance and increase the potential for deterioration from
deicing chemicals (Ref. 7).

4.6 REINFORCEMENT

Good general guidance regarding the selection, location and fixing of reinforcement for
shotcrete applications is provided in the ACI 506R, "Guide to Shotcrete". In shotcrete
repair of bridges it is sometimes necessary to replace existing corroded reinforcing, or
add additional reinforcing steel to strengthen the structure (e.g., in seismic retrofit).
Good shotcrete practice dictates that small bar sizes be used wherever possible, with 15
M bars being the preferred maximum size. Bars as large as 25 M have been used, but
they require special skills on the part of the nozzlemen, to achieve full encapsulation with
shotcrete.
65

Placement of reinforcing steel for shotcrete applications differs from conventional


concrete reinforcing steel installation requirements in that the bars should always be
spaced and arranged to facilitate shotcrete placement and the avoidance of the formation
of sand pockets and voids. In particular, direct contact of reinforcing splices should be
avoided; lapped bars should be spaced apart at least three times the diameter of the
largest bar at the splice. Where double layers of reinforcing are required, the spacing of
bars should be offset, to permit clear, unobstructed access for shooting to the interior
reinforcement. All bars should be securely tied to intersecting bars and anchors, to
minimize vibration and prevent movement during shooting, which could interfere with
bond.

Welded wire mesh fabric is commonly used in shotcrete repair of bridges. It serves two
major purposes:

• to mechanically tie back the shotcrete repair to fixed anchors, or existing


reinforcing steel, so that the longevity of the repair is not totally dependent on
bond to the substrate concrete (or the continuing integrity of the substrate
concrete);

• to enhance the resistance of the shotcrete to thermal and drying shrinkage induced
cracking.

Commonly used welded wire mesh fabric sizes are tabulated below:

Metric Designation
50 mm x 50 mm MW 5.6 x MW 5.6
102 mm x 102 mm MW 9.1 x MW 9.1
102 mm x 102 mm MW 13.3 x MW 13.3
152 mm x 152 mm MW 18.7 x MW 18.7

The Engineer should select the appropriate mesh size for the specific repair application.
The smaller diameter, more closely spaced meshes are generally preferred in small patch-
type repairs. In larger and deeper repairs, particularly where there is a danger of the
mesh vibrating excessively during shotcrete applications, the larger diameter, stiffer
meshes are preferred. The use of chain-link mesh, or "chicken-mesh" should not be
permitted as they are not conducive to full encapsulation with shotcrete, without the
formation of sand pockets and voids.

Fiber reinforcement can be used in lieu of mesh reinforcement, but it should be properly
mechanically anchored to the existing concrete, using anchors with appropriate shear
connectors. Anchoring along the perimeter of the repair is particularly recommended.
The use of steel fiber reinforced shotcrete is advantageous, compared to mesh
reinforcement, in that it eliminates the requirement for fixing mesh and the difficulties
which can sometimes be encountered in fully encasing mesh.
66

Steel fiber has typically been added to the shotcrete at addition rates varying between 40
and 60 kg/m3. The exact amount of fiber used depends on the particular type of fiber
used and bridge element being repaired. Where fibers are being used primarily for
shrinkage crack control 40 kg/m3 fiber content may suffice. Where "toughness"
enhancing characteristics of the fiber are important (e.g., in strengthening load-bearing
precast or cast-in-place deck support elements), the use of 60 kg/m 3 of steel fiber would
be more appropriate.

It should be remembered that different levels of performance will be provided by


different fiber types. As general guidance, for steel fibers the higher aspect ratio
(length/equivalent diameter) deformed types of fiber provide the best performance (Ref.
15, 16). Also, it should be remembered that a higher proportion of steel fibers will
rebound in dry-mix, compared to wet-mix shotcretes. It should also be noted that
exposed steel fibers in the shotcrete surface may create rust stains. If this undesirable,
stains can be prevented by application of a non-fiber surface coat.

Polypropylene fiber has also been used in shotcrete repair of bridges. While high
addition rates (up to 0.6 percent by volume) have been used in some bridge repair (Ref.
5), polypropylene fiber has generally been added to shotcrete at low addition rates of 0.1
percent by volume (1 kg/m3). At these addition rates the polypropylene fiber may
provide some resistance to plastic shrinkage cracking. Reference 15 contains additional
information about the effect of various addition rates of polypropylene fibers on both
crack resistance and toughness.

Polypropylene fiber has been used in both the wet-mix and dry-mix shotcrete processes
(Ref. 17). However, in the dry-mix shotcrete process it may be difficult to incorporate
any significant quantities of some specific types of fiber (say more than 0.1% by volume)
in the completed work. A significant quantity of the fiber added tends to be carried away
in the "return air stream" during the shotcreting process. If more than 0.1% of
polypropylene fibers are required in the final in-place shotcrete, washout tests should be
performed to select the specific fiber types which can achieve a higher percentage for the
application intended.

Anchors for fixing mesh or mechanically anchoring steel fiber reinforced shotcrete
should be carefully designed. If the substrate concrete is of questionable quality, or
likely to continue to deteriorate in behind the shotcrete repairs because of continuing
alkali-aggregate reactivity, or frost action, the anchors should be sufficiently deep seated
that the repair shotcrete does not simply slab off, with the substrate concrete still adhered
to it (Ref. 1).

4.7 MATERIALS HANDLING AND STORAGE

Difficulties can be encountered in shotcrete repair of bridges if the temperature of the


shotcrete making materials is allowed to get excessively low or high. At temperatures
below 5°C shotcrete rebound can increase markedly and the shotcrete can be very slow in
67

setting, hardening and gaining early strength. This can result in excessive shut-down
periods for bridges under repair, or damage to bond in operating bridges. During cold
weather, shotcrete making materials should be stored in warm enclosures whenever
possible, until the time of use. Warm water should be used if necessary to increase the
temperature of the in-place shotcrete. Temperatures in excess of 30°C can result in
excessively rapid loss of workability in wet-mix shotcretes, limiting time from batching
to completion of discharge of shotcrete. High temperatures or low temperatures with low
relative humidity can also increase the potential for plastic and early drying shrinkage
cracking.

Wide ranges in moisture contents in shotcrete making aggregates should be avoided.


This may require storage of aggregates in sheltered enclosures or under tarpaulins,
particularly for volumetrically site-batched shotcrete. Excessive moisture contents can
result in aggregate "bridging" over gates in hoppers and erratic aggregate feed, with
resultant variable shotcrete mixture proportions.

5.0 SHOTCRETE PROPORTIONING

5.1 MIXTURE DESIGN

The burden for shotcrete mixture design should be placed on the Contractor, as per the
Guide Specifications. Most experienced shotcrete contractors will be able to readily
submit suitable mixture designs, together with appropriate performance documentation,
based on previous bridge or other infrastructure repair experience. In the absence of such
experience, the Contractor may select one or more of the following "starting mix"
designs, depending on the shotcrete type and performance requirements detailed in the
Specifications. Selection of these "starting mix" proportions does, however, not relieve
the Contractor of responsibility to meet the performance requirements of the
specification.
68

Typical Remedial Shotcrete Mix Designs, Proportions at the Nozzle in kg/m 3


Mix Description (Exiting the nozzle - not in-place)
Material
Wet-Mix Dry-Mix
Plain Silica-Fume Plain Silica-Fume
Portland Cement 400 350 425 375
Silica Fume - 47 - 50
10 mm Coarse Aggregate* 460 485 495 490
Concrete Sand* 1260 1215 1215 1205
Water 170 177 165 165
Water Reducing Admixture Yes Yes - -
Superplasticizer - Yes - -
Air Entraining Admixture Yes Yes - -
TOTAL: 2290 2274 2300 2285
*Proportions based on Saturated Surface Dry (SSD) Aggregate

These proportions are based on nominal 10 mm MSA (Maximum Size Aggregate)


aggregate. For nominal 5 mm MSA aggregate mixtures similar mixture proportions
could be used, but it may be necessary to increase the cement content slightly, because of
the increased water demand (and hence increased water/cement ratio and reduced
strength) for the finer aggregate mixture. Also, it should be noted that these are nominal
mixture proportions based on combined aggregates with relative bulk density (specific
gravity) of about 2.72. The Contractor should design the as-batched mixture to yield
correctly. The yield will, of course, be influenced by the actual water demand and air
content of the mixture. Mixture design and yield analysis calculations should only be
done on the basis of saturated surface dry (SSD) aggregates.

An example of a shotcrete mixture design, and yield analysis for a typical wet-mix, steel
fiber reinforced, silica fume shotcrete follows:
69

Typical Wet-Mix Shotcrete Proportions and Yield Analysis


Material Mass Bulk Density Volume
(kg) (kg/m3) (m3)
Cement (Type I or II) 350 3150 0.1111
Silica Fume 47 2200 0.0214
Coarse Aggregate (SSD) 485 2730 0.1777
10 x 2.5 mm
Sand (SSD) 1215 2710 0.4484
Water (Estimate) 177 1000 0.1770
Water Reducing Admixture 2000 ml 1100 0.0018
Superplasticizer 5800 ml 1100 0.0053
Steel Fiber 60 7860 0.0076
Air Entraining Admixture As required
for
Air Content (As Shot into air pot) 5 + 1.5% 0.0500
TOTALS: 2342 1.0003
Slump = 60 mm + 20 mm
Approximate W/(Cement + Silica Fume) = 0.40

In wet-mix shotcretes the in-place shotcrete mixture proportions will be very similar to
the as-batched proportions, since there is normally very little rebound in the wet-mix
shotcrete process (usually less than 5 percent rebound on vertical surfaces and less than
10 percent rebound on overhead surfaces). By contrast, in dry-mix shotcrete, significant
rebound is a normal aspect of the shotcrete process. The amount of rebound will depend
on many factors, including shotcrete orientation (vertical or overhead surfaces), shotcrete
thickness, the presence of reinforcing steel, and whether silica fume is used. For dry-mix
silica fume shotcrete rebound of 20 percent on vertical surfaces and 25 percent on
overhead surfaces is not unusual (Ref. 8). Substantially higher rebound can be expected
in conventional dry-mix shotcrete.

Rebound materials characteristically contain less cementitious material than the as-
batched shotcrete. Thus in-place dry mix shotcrete characteristically has a higher
cementitious content than the as-batched material. This aspect should be taken into
consideration during design of dry-mix shotcrete mixtures. It should, however, be
remembered that attempts to produce excessively lean (low cementitious material
content) dry-mix shotcrete mixtures can be counterproductive. Rebound increases
markedly in lean dry-mix shotcrete mixtures. As-batched cementitious contents of less
than 350 kg/m3 are not recommended for any dry-mix repair shotcrete.
70

5.2 SILICA FUME SHOTCRETE

Silica fume is finding increasing use in shotcrete for repair of bridges because of the
benefits it imparts to both the plastic and hardened shotcrete. In the plastic shotcrete it
results in improved adhesion (to the substrate surfaces) and cohesion (adhesion to itself).
This enables the build-up of greater thicknesses of shotcrete in a single pass and reduces
or eliminates the need for use of shotcrete accelerators. In many repair applications it
becomes possible to build up the entire thickness of shotcrete in a single pass, thus
eliminating the need for multiple layer shotcrete construction. This is particularly true of
the dry-mix shotcrete process, where thicknesses of 500 mm or more on vertical surfaces
and 200 mm or more on overhead surfaces have been built up in a single pass. Silica
fume additions also enables substantial reductions in rebound in the dry-mix shotcrete
process (Ref. 8).

Improvements in the hardened shotcrete resulting from the use of silica fume include:

• increases in compressive and flexural strength (particularly evident in wet-mix


shotcrete);
• reduced permeability and enhanced resistance to chloride ion penetration (Ref. 9);
• improved resistance to deicer salt scaling (Ref. 7).

Silica fume is typically incorporated in shotcrete at addition rates of between 5 and 15


percent by mass of cement. Addition rates of 8 percent will often suffice for repair of
predominantly vertical or sloping surfaces. Addition rates of about 12 percent are
generally preferred for predominantly overhead repairs. In operating bridges, subjected
to vibration, or repair in wet areas, such as intertidal zones on piers and caissons, it may
be necessary to increase the silica fume content to as much as 15 percent by mass of
cement in order to prevent loss of freshly placed shotcrete. This has been done with
considerable success in repair of marine structures subjected to wave action (Ref. 5).

In dry-mix shotcrete the use of superplasticizing admixtures is not required. In wet-mix


shotcrete the use of superplasticizers, to control the water demand of the mixture is
strongly recommended.

5.3 PERFORMANCE REQUIREMENTS

Recommended performance requirements for bridge repair shotcretes are given in the
Guide Specification, Table 1. Shotcretes batched to the proportions given in Section 5.1
of this Commentary will normally readily meet these performance requirements,
provided the shotcrete is batched, mixed, applied and cured in conformance with the
requirements detailed in the Guide Specification.

A maximum water-cementitious materials ratio of 0.42 will usually suffice for most
strength and exposure conditions. Precise determination of the water-cementitious ratio
for dry-mix shotcrete is not easily done, and is thus seldom used as a routine quality
control item. More typically, the water-cementitious materials ratio for the proposed
71

mixture is determined during the preconstruction phase of the project, using a materials
balance approach; i.e., recording the mass of shotcrete materials and water consumed
over a set shooting period. For wet-mix shotcrete the precise water-cementitious ratio
can, if required, be readily determined by a yield analysis check at the batch plant.

Higher compressive strengths than the 28 MPa at 7 days and 35 MPa at 28 days given in
the Guide Specification, Table 1, can be specified, if required for structural reasons.
There is, however, no benefit in specifying lower compressive strengths. Good quality
shotcrete, which displays satisfactory adhesion, cohesion, thickness of build-up and
acceptable rebound, requires total cementitious contents which should be more than
adequate to meet the 28 MPa at 7 days and 35 MPa at 28 strength requirements. The use
of a 7 day strength specification is recommended, since in shotcrete repair of bridges, the
entire repair may be completed at 28 days after application of the first shotcrete, in which
case it is too late to find out if there is a problem with strength. Even earlier age strength
limits could be specified if considered necessary (as is often done in shotcrete support of
underground openings).

Specification of maximum limits on the permissible values of boiled absorption and


volume of permeable voids, as determined by the ASTM C642 test has proven useful as a
measure of shotcrete quality (Ref. 5). It provides a measure not only of the quality of the
shotcrete mixture, but also of the nozzlemanship and adequacy of consolidation of the
shotcrete. Defects attributed to causes such as sand pockets, voids of incomplete
consolidation, entrapment of rebound or hardened overspray, will be quantified in this
test.

The ASTM C1202, Rapid Chloride Permeability Test has been adopted by some highway
agencies as a quality control measure for bridge repair shotcrete. It provides an
indication of the chloride ion intrusion inhibiting characteristics of the shotcrete. It
should be noted that conventional shotcrete (no silica fume) will typically display
coulomb values which may be as much as an order of magnitude greater than in
shotcretes made with silica fume (Ref. 9). The limit recommended in the Guide
Specification, Table 1, of 1500 coulombs at 7 days for silica fume shotcrete can normally
be readily achieved in the field. Limits for other types of shotcrete should be established
by the Engineer during preconstruction testing; i.e., values attained in approved
preconstruction test panels should be used to set the standard for the work. Rapid
Chloride permeability testing is not suitable for use with steel fiber reinforced shotcrete.

6. SUPPLY AND EQUIPMENT

WET-MIX VS. DRY-MIX SHOTCRETE

The first decision to be made in any shotcrete bridge repair project is whether to use the
dry-mix or wet mix shotcrete process. The dry-mix shotcrete process is best suited to
smaller volume repair projects particularly where there is a considerable starting and
stopping, or a need to frequently relocate during shooting operations. By contrast the
wet-mix shotcrete process is better suited to larger volume (say 5 m3/hr. or more)
72

continuous shooting operations, with few interruptions. The dry-mix shotcrete process,
compared to the wet-mix process, also tends to be better suited to predominantly
overhead repair work, because of the greater thicknesses of build-up attainable in a single
pass. In some projects the decision as to which process to use may not be clear and in
such circumstances it may be appropriate to allow both the dry-mix and wet-mix process
to be used and let the successful low bidder select the application process.

The following is a brief tabulation of the relative advantages and disadvantages of the
dry-mix and wet-mix shotcrete processes for bridge repair work.
73

DRY-MIX SHOTCRETE
Advantages Disadvantages
• Suitable for small volume start/stop type • Substantially greater rebound compared
repair operations. to wet-mix shotcrete.
• With the exception of the air compressor, • Highly dependent on the skill of the
requires relatively small, highly mobile nozzleman for wetting the shotcrete to the
equipment. appropriate consistency.
• Convenient to frequent relocations • More onerous for removing over-spray
during shooting. and rebound, particularly when encasing
• Allows thicker build-up on vertical and reinforcing steel or mesh.
overhead surfaces, particularly when silica fume • Greater potential for formation of sand
is used. pockets and lenses and entrapment of rebound.
• Equipment is more easily cleaned at • More rebound to dispose of at
completion of daily shotcrete operations. completion of shotcreting.
WET-MIX SHOTCRETE
Advantages Disadvantages
• Suitable for larger volume, continuous • Not suited to frequent start-stop type
shooting operations. operations; shotcrete has finite "pot-life".
• Much greater productivity (m3/hr.) • Limited in thickness achievable on
• Nozzleman not concerned with overhead surfaces, particularly with
controlling water addition; only has to control conventional shotcrete.
air addition at the nozzle and shooting technique. • Requires larger, more costly equipment
• Markedly less rebound than in dry-mix than for dry-mix process; e.g., transit mixers,
shotcrete and hence less rebound clean-up pumps, etc.
required. • Clean-up of pumps and hoses and
disposal of waste material at end of day more
onerous.

6.1 BATCHING, MIXING AND SUPPLY

Site-batching of dry-mix shotcrete, using either volumetric or mass batching equipment


can be used for shotcrete bridge repair. The volume of shotcrete materials required for
most bridge repair contracts is such that it is normally not expedient to establish
stockpiles of shotcrete making materials and batching facilities on site. Most dry-mix
shotcrete repair of bridges is performed using either dry-bagged premix materials, or
mobile, volumetric site batching. These are the preferred supply systems, as they
produce fresh shotcrete on an as-needed basis, with minimal wastage. Dry-bagged
premix materials are typically supplied in either small (30 kg) paper bags, or large (1600
kg) synthetic cloth bulk bin-bags.
74

The use of rotary drum, transit-mix batched and supplied dry-mix shotcrete is not
recommended for bridge repair. There is a tendency for "balls" or "pellets" of non-
homogeneous material to develop in the transit mixer. This negatively impacts the
quality of the resultant shotcrete particularly during warm weather or extended discharge
periods. Negative influences include marked increases in rebound, reduced application
thickness and non-homogeneous in-place shotcrete.

When volumetric site batching is used, quality control checks should be implemented to
verify that the batched proportions meet the design mixture proportions. Mass batch
checks should be used at an appropriate frequency. For dry-bagged premix materials
quality control checks should include wash-out and gradation analyses to verify the as-
batched proportions. Such tests should be conducted at the frequency specified by the
Engineer.

Wet-mix shotcrete is essentially similar to conventional concrete in terms of batching,


mixing and supply. The most common systems are either central mix batched and transit
mix supplied shotcrete, or transit mix batched and supplied shotcrete. Volumetric site
batching, using fixed or mobile batching units can, however, also be used, subject to
satisfactory calibration. Another system which has been used for bridge repair,
particularly in remote areas, is dry-bagged premixed shotcrete materials which are
discharged into a transit or other suitable mixer, with water added at the site. With this
system the shotcrete should be given adequate "soak time" to enable absorption of water
by the "bone-dry" materials, prior to discharge into the shotcrete pump; otherwise
pumping and shotcrete finishing difficulties may be encountered.

6.2 SHOTCRETE PLACING EQUIPMENT

There is a wide variety of shotcrete placing equipment which can be used for application
of dry-mix and wet-mix shotcrete. ACI 506R, "Guide to Shotcrete" provides details of
some of the different types of equipment available. Equipment manufacturer's are
continually upgrading and improving upon their shotcrete application systems and thus it
is not appropriate in this document to recommend specific types of equipment.

In the wet-mix system there are two basic different types of shotcrete application
systems; the conventional or "thick-stream" method and the "thin-stream" method. The
"thick-stream" method is most commonly used and typically utilizes conventional
concrete-type pumps with air addition at the nozzle at the end of the delivery hose. The
delivery hose typically has a 50 or 63.5 mm internal diameter. Hose diameters any larger
than this become too heavy for the nozzleman to effectively operate.

The "thin-stream" method normally involves the use of a pressurized chamber to


pneumatically convey the shotcrete down the hose to the receiving surface. The "thin-
stream" method normally utilizes a hose with an internal diameter of 40 mm or less. It is
most suited to the application of mortar-like mixtures (nominal 5 mm MSA aggregates)
and has low productivity rates. It is thus best suited to small, shallow, patch-type repairs.
The "thin-stream" method may not provide suitable impacting velocity to properly encase
75

larger diameter reinforcing steel and should be carefully evaluated before being permitted
for use in such an application. The Wet-Mix Guide Specifications do not apply to the
“thin-stream” method.

There are a wide variety of dry-mix shotcrete "guns" for shotcrete application, including
guns that operate on a rotating barrel-feed system and pressurized chamber type guns.
Large capacity air compressors are required to pneumatically convey the shotcrete
materials down the line to the nozzle. Water is added partially through the use of damp
aggregates, (or in the case of dry-bagged premix materials, in a predampening auger)
with the remainder of the required mix water being added at a water ring at the nozzle.
The application of dry-bagged premix materials, without the use of a predampening
auger, should not be permitted. Such practice results in excessive dust, poor shooting
visibility, increased rebound and an increased potential for the formation of sand pockets
and dry lenses in the in-place shotcrete.

"Housekeeping", in terms of keeping clean shotcreting equipment, lines and hoses, and
particularly the air-ring in wet-mix shotcrete, or water-ring in dry-mix shotcrete, is
important. Work should be stopped and appropriate corrective action taken if non-
uniform discharge of shotcrete becomes apparent.

7.0 PREPARATION FOR SHOTCRETING

7.1 CONCRETE REMOVAL AND PREPARATION

One of the most important aspects of shotcrete repair of bridges is proper preparation of
the substrate, prior to shotcrete application. All areas of loose, spalled, delaminated or
deteriorated concrete should be removed prior to application of repair concrete. In repair
of deteriorated load bearing elements, it may be necessary to provide shoring and/or
carry out the repair work in a sequential manner, with partial concrete removal of more
material. In some very old structures the depth of deterioration may be so great (from
influences such as freeze/thaw or alkali-aggregate reactivity induced damage) that it may
not be possible to remove all deteriorated concrete. In such circumstances shotcrete
"jacketing" is sometimes used to upgrade the structure. Such jacketing should be
carefully designed to include suitable reinforcing and deep anchors, such that the
integrity of the repair is not solely dependent on bond to the substrate concrete. If this is
not done, slabbing failure of the repair can occur with the shotcrete still adhered to the
substrate concrete, but failure occurring within the substrate concrete (Ref. 1).

If inadequate surface preparation is suspected, bond testing may be performed by drilling


cores through the shotcrete repair layer. The recommended minimum bond is 1.0 MPa,
at the shotcrete-substrate interface. If lower test values are obtained when the failure
surface extends down into the substrate, the interface bond cannot be determined. The
Engineer must then evaluate whether the failure resulted from undetected delaminations,
new or growing delaminations, or poor quality concrete to decide if further repair is
necessary under contract bid items or by extra work.
76

Concrete removal can be accomplished using a wide variety of mechanical tools,


including chipping hammers, scarifiers, scabblers, etc. The use of heavy duty equipment,
which could damage sound concrete beneath the prepared surface should, however, be
avoided. Most mechanical preparation procedures (particularly scabblers and scarifiers)
will cause some micro fracturing of aggregate (sometimes called "bruising") in the
prepared surface. Abrasive blast cleaning using sand-blasting wet-grit blasting or closed-
loop steel shot blasting, should be used to prepare the surface and remove any "bruised"
concrete, unsound material, or contaminants such as oil, grease, slurry or any materials
which could interfere with the bond of freshly placed shotcrete.

As an alternative to mechanical concrete removal and final surface preparation, high


pressure water jetting (usually 100 to 250 MPa hydrodemolition equipment can be used).
There is a wide variety of such equipment available for hydrodemolition, but care should
be taken to ensure that the system used creates a suitable prepared surface profile.
Excessive undercutting of exposed aggregate may create a prepared surface which is not
conducive to good shotcrete bond, and should be avoided. Low volume water jetting
systems which create lesser volumes of demolition water and slurry are preferred. Proper
procedures for containing and disposing of hydrodemolition slurry should be
implemented. This is particularly important over water-ways.

Similarly, the Contractor should implement appropriate measures for collecting and
disposing of removed concrete and blasting grits. The requirements of the authorities
having jurisdiction should be followed. Also, it should be recognized that high pressure
water jetting and abrasive grit blasting are potentially dangerous procedures. A rigorous
safety program to protect personnel from injury and adjacent property from damage
should be implemented by the Contractor when using such equipment.

When corroded reinforcing steel is exposed, concrete removal should continue until there
is at least a 20 mm clearance around all exposed reinforcing steel. Research conducted in
Sweden (Ref. 10) has shown that the interface between old concrete and shotcrete should
not coincide with the reinforcement plane. There is a potential for bond failure at this
plane, particularly under conditions conducive to repeated dynamic cycling (e.g., bridge
deck soffits and support elements). Removing concrete behind existing reinforcing steel
also facilitates the removal of any corrosion product on the reinforcement, and provides
mechanical anchorage for the repair shotcrete.

Proper preparation of the perimeters of all patch-type shotcrete repairs is also an


important consideration. Featheredging should be avoided, as the C-SHRP study (Ref. 1)
showed that this was a major cause of edge delamination in shotcrete repairs. The
recommended procedure is to square cut the edge of the repair to about a 15 mm depth
using an appropriate saw, and then chip the remainder of the perimeter of the repair on
about a 45° angle. Deeper square cut edges should be avoided, as they are conducive to
entrapment of rebound and overspray during shotcrete application. The square cut edge
provides a well defined boundary for shotcrete finishing operations. It provides a
convenient edge to ensure featheredging does not occur and results in a more aesthetic
77

completed repair. If used for aesthetics only, saw cutting can be eliminated if inspection
is conducted to assure featheredging does not occur.

7.2 REINFORCEMENT

Reinforcement requirements in shotcrete repairs can include:

• replacement of existing corroded reinforcing steel;


• addition of new reinforcing steel to upgrade or strengthen the structure;
• provision of shrinkage and temperature crack control reinforcement;
• reinforcement to tie-back the shotcrete repair to the existing concrete.

Judiciously designed reinforcement will serve more than one, if not all, of the above
functions.

For corroded reinforcing steel, bars which display deep pits, or have lost more than 20
percent of their cross-sectional area, should be removed and replaced, or supplemented
with additional reinforcement. (In some highly stressed structures, Engineers may
impose more stringent limits on the allowable loss of cross-sectional area). Placement of
replacement or supplemental bars, however, differs from conventional reinforced
concrete construction, in that bars should not be bundled in lapped splices. The general
recommendation is that the minimum spacing around each bar should be three times the
maximum aggregate size, to allow for proper encapsulation with shotcrete. As an
alternative to lapped splice, replacement reinforcing steel may be welded to existing
reinforcement, but only subject to verification of the weldability of both new and existing
reinforcing steel.

When placing double mats of reinforcing steel, bar spacing should as far as possible be
offset, such that the interior layer of reinforcement is clearly visible to the nozzleman
during shooting. Shooting through more than two layers of reinforcement should be
prohibited. Intersecting bars should be tightly secured to each other at appropriate
spacing, using 1.6 mm or heavier gauge or wire. Large knots of tie wire, which could
interfere with shotcrete placement, should be avoided. Use should be made of suitable
reinforcing chairs, or anchors, to support reinforcing steel and mesh, to minimize
vibration and "flapping" during shotcrete placement. The minimum clearance behind all
reinforcing bars or mesh should be 20 mm. It is difficult to properly encapsulate
reinforcing fixed tightly against existing concrete.

As an alternative to welded wire mesh fabric, fiber reinforced shotcrete may be used.
Fiber reinforcement has the benefit of dispensing with the need to fix reinforcing mesh.
It is also more easily applied and less conducive to the formation of sand pockets and
voids (nozzleman does not have to be concerned with proper encapsulation of mesh).
The fiber reinforced shotcrete should, however, still be properly mechanically anchored
to the substrate concrete, particularly at the perimeter of large repair areas.

7.3 ANCHORS
78

It is generally recommended that the maximum anchor spacing for reinforcing steel
should not exceed 600 mm. In smaller dimension elements such as beams, girders,
columns, etc., it may be necessary to use closer anchor spacing. Anchor spacing should
be such that the reinforcing does not vibrate or deform excessively during shotcreting.
Small areas should contain at least four anchors.

Anchors may be mechanically set or grouted, depending on the exposure conditions


(grouted anchors are preferred in wet conditions) and the purpose of the anchors.
Designed anchors are included on the Contract Drawings when the designer anticipates
they will be needed to ensure the integrity and stability of thick shotcrete repair sections.
Non-designed anchors are used by the contractor to hold reinforcement in place during
the shotcrete application process. A general recommendation is that designed anchors
should develop a minimum pull-out force of 10 kN. Larger pull-out force resistance may
be required in large diameter, deep set designed anchors, used in jacketed repairs of
lower quality concretes. Sufficient testing should be conducted to verify pull-out
resistance of designed anchors.

7.4 ALIGNMENT CONTROL AND COVER

Proper alignment control is required to ensure that the specified tolerance requirements
and cover to reinforcing steel are satisfied. Alignment control is normally achieved by
means of shooting wires, guide strips or depth gauges. In some cases forms or other
types of devices are used. Edge forms can be particularly beneficial when strict
tolerances on the shape and lines of the structure are required for aesthetic reason (e.g.,
arches). Careful form design and shotcreting technique is, however, required to prevent
entrapment of rebound and overspray. When shooting wires are used, they should
consist of a high strength steel wire (piano wire) at constant tension during the shooting
operation. The simple use of fencing wire is not recommended, as it tends to detension
and sag during the shooting operation.

Depth gauges, such as double headed nails are used, but they should be appropriately
spaced. Spacing on a grid pattern not exceeding 1200 mm is often specified. On
completion of shooting such depth gauges should be cut back a minimum of 10 mm
below the finished surface, in order to prevent corrosion staining. General cover to
reinforcing steel should be prescribed on the contract plans. In no case should cover to
reinforcing be less than 30 mm. With steel fiber reinforced shotcrete it may be desirable
for aesthetic reasons, to apply a "flash-coat" of plain (nominal 5 mm MSA) shotcrete, to
prevent corrosion staining of the finished surface.

In encapsulating elements such as pier caps, buttresses, parapets, etc., it is important that
the shotcrete be designed to completely cap the elements. The C-SHRP study (Ref. 1)
found that there was a danger of the shotcrete repair acting as a "dam" to promote
saturation of the original concrete with water and salts, if the shotcrete repair did not
completely cap the element. The original concrete then became vulnerable to freeze-
79

thaw and deicing salt scaling deterioration. All caps should be designed with a minimum
3 percent slope, to prevent ponding and facilitate drainage.

Careful consideration should also be given at the design stage to incorporation of drip
grooves and reveals on the soffits of elements such as decks, beams and arches, which are
exposed to rain and/or deck run-off water and salt solutions. Such details should be
designed to prevent water and salts from seeping to the underside of the elements.

8.0 QUALITY ASSURANCE AND QUALITY CONTROL TESTING

8.1 QUALITY ASSURANCE

As in any engineering project, the Owner should implement a suitable quality assurance
program to achieve a satisfactory end product. Shotcrete rehabilitation projects tend to
differ from most cast-in-place concrete repair type contracts, in that it is often necessary
to implement a preconstruction evaluation and testing program to establish that the
Contractor's proposed materials, supply, equipment and crew are capable of producing
the required end product.

It should also be noted that engineering inspection costs may be higher on a shotcrete
rehabilitation contract than in new concrete construction. On many structural repairs the
Engineer is required to make judgment calls relating to strength and safety which require
a frequent site presence.

8.2 QUALITY CONTROL TESTING

The Contractor should implement a rigorous program of quality control testing to assure
compliance with the contract requirements. The recommended details for such a
program are given in the Guide Specification. Any deficiencies noted during shooting
operations (e.g., sand pockets, dry lenses, shadowing, voids, etc.) are best corrected while
the shotcrete is still plastic. Repair of such defects becomes much more costly if the
shotcrete is allowed to harden.

8.3 PRECONSTRUCTION TRIALS

It is important that the nozzlemen used on the project demonstrate suitable skills. This is
normally done by the Engineer evaluating the performance of the nozzlemen in a
preconstruction "shoot". Such an evaluation should require the nozzlemen to do
preconstruction trials as required in the Guide Specifications. The test panels should be
oriented to be representative of the project work. (Different skills are for example,
required in bench-gunning thick vertical surface, compared to overhead applications). A
minimum of three 100 mm diameter cores should be extracted from locations of
intersecting reinforcing steel and mesh to check the adequacy of consolidation of
shotcrete around reinforcement. At least one core should be taken at the location of an
anchor. Preconstruction test panels should be field cured in the wooden forms in the
80

same manner as the proposed shotcrete work for a minimum of 24 hours, prior to
transport to the test laboratory. Test panels should be transported in their wooden forms
taking care not to crack or damage the shotcrete.

The shotcrete nozzleman should be required to demonstrate his ability to correctly and
successfully apply the type of shotcrete specified for the project. Effective nozzling is a
skill learned from experience and is physically demanding. Only persons who are
physically able and experienced should be allowed to work on the project.

A test panel or test area, simulating a surface on the project, should be shot using the
equipment, materials, mix proportions, and reinforcement specified for the project. The
test panel should be a minimum of 1 m square to allow the nozzleman to adequately
demonstrate his ability. Provision may be made to accumulate and measure rebound
from the panel or test area. Performance requirements may vary from project to project.
The contractor should use the proper type of shooting surface for the test panel or area,
the proper thickness of the shotcrete application to correlate with acceptable core or cube
dimensions, mix proportions for dry-mix or concrete proportions for wet-mix, and
similar reinforcement requirements as called for in the project.

The test panel or area should be checked by the Engineer to verify that the forms are
adequately braced, reinforcing steel bar laps are spaced 2-1/2 bar diameters apart, mesh is
lapped 1-1/2 squares, reinforcement is properly spaced and rigidly tied and secured to
avoid movement during the shotcrete operation, and shooting surfaces and reinforcement
are clean and properly prepared to receive the shotcrete application.

The surface to be shot against, anchorages, reinforcement, panel orientation (vertical,


horizontal, and overhead), total sample thickness, material, and mix shall duplicate job
requirements as nearly as practical.

The Engineer may refer to ACI 506R, Chapter 2, Materials, as a guide for quality
requirements for shotcrete materials. The Engineer should consult with the shotcrete
applicator to establish the materials and the mix proportions for the test.

If sufficient data are available from previous tests of the materials, shotcrete mixture
proportions may be selected from such data to produce a given compressive strength.

If insufficient or no previous data are available, at least three shotcrete control test panels
with a minimum thickness of 75 mm should be shot by an experienced nozzleman using
different proportions. Cores or cubes taken from the test control panels shall be removed
and tested in accordance with ASTM C42.

Based on the compressive strength achieved by the cores or cubes taken from the test
control panels, a mixture proportion should be selected for the test which should produce
shotcrete with a 28-day compressive strength of at least 35 MPa. Core strengths should
be corrected to an L/D of less than 2 in accordance with ASTM C42. Where quick-
setting additives or cements are used, compressive strength and setting time may be
81

adjusted to test for initial set time and initial strength in addition to 28-day compressive
strength.

The test should be conducted using equipment of a design and size normally used for the
specified type of shotcrete. The Engineer may refer to ACI 506R, Chapter 4, Equipment
Requirements, as a guide for recommended equipment requirements for either the dry-
mix process or the wet-mix process.

A competent crew, including an experienced gunman or pump operator, blowpipe


operator, and possibly a finisher, should be provided to assist the nozzleman in shooting
the test panel or area.

The Engineer should carefully observe the shooting of the test panel or area, and note if
the nozzleman:

1. Cleans shooting surface with air and water prior to shooting.

2. Applies bonding coat on shooting surface ahead of heavier shotcrete applications.

3. Directs shotcrete application around reinforcement in a manner which prevents


buildup on the face of the reinforcement and allows shotcrete to flow and compact tightly
around the back and remainder of the reinforcement.

4. If applicable, directs finisher or blowpipe operator to cut out any sags or sand pockets.

5. If applicable, and where necessary, directs the finisher or blowpipe operator to broom
the shotcrete surface prior to application of additional layers of shotcrete. Notes,
photographs, or other documentation made by the Engineer during gunning of the test
panel or area will be helpful later in testing and analyzing the test panel or area.

The test panel or area should be properly cured in accordance with ACI 506R, Chapter 6
paragraph 6.4, Curing and Cold Weather Protection, and ACI 506.2, paragraph 3.7.

Tests and observations of the test panel or area will be used to evaluate workmanship. A
minimum of six cores or cubes should be cut from the test panel or area. Three cores or
cubes cut through the unreinforced sections of the test panel or area should be subjected
to compressive strength tests. Test results will be compared with the compressive
strength requirement established for the tests. At least three cores or cubes should be cut
through the reinforcement for analysis of quality and extent of shotcrete encasement, and
subjected to the core grading requirements of the Guide Specification or ACI 506.2,
paragraph 1.7, Shotcrete Core Grades. All cores or cubes should be examined for
evidence of sand pockets, voids, or sags. A copy of the core grade photos published with
the 1995 version of ACI 506.2 is included at the end of this commentary.

Where applicable, the Engineer should also examine the stripped side of the panel for
evidence of sags, sand pockets, and lack of a bonding coat. Corners and other sections of
82

the panels or areas should be cut or broken open for observation by the Engineer of
laminations, sand lenses, or other defects.

The Engineer may waive the preconstruction evaluation program, if satisfied from
previous experience that the Contractor and nozzleman have demonstrated the ability to
satisfactorily perform the work. The contract documents should specify the conditions
under which this will occur. In such circumstances the Engineer should particularly
closely monitor the Contractor's performance at the start of the repair work.

8.4 CONSTRUCTION TESTING

Construction testing is required to assess the compliance of the shotcrete to the project
specifications. Detailed requirements for construction testing are given in the Guide
Specification. Shotcrete testing differs from testing of cast-in-place concrete in that the
test specimens are typically diamond drilled or saw cut cores or prisms, extracted from
either test panels or the in-place shotcrete, rather than cast specimens. When cores are
extracted from cast-in-place concrete the:

Concrete represented by the core tests shall be considered structurally adequate:

(a) if the average strength of each set of three cores from the portion of the
structure in question is equal to at least 85% of the specified strength;

(b) if no single core is less than 75% of the specified strength.

There is a considerable debate in the shotcrete community as to whether these same


criteria should be applied to interpretation of the results of quality control tests on
shotcrete cores. The existing ACI 506.2, "Specifications for Materials, Proportioning
and Application of Shotcrete", Clause 1.6.3.3 does apply these same criteria to shotcrete.
Some authorities require the average compressive strength for a set of three shotcrete
cores to meet or exceed the specified strength. The Joint Task Force Guide Specification
requires using the full specified compressive strength for acceptance of preconstruction
test panel cores and for construction test panel cores. They are normally shot under good
conditions and should be expected to meet the specified compressive strength. The
Guide Specification recommends applying the ACI criteria shown above in italics for
acceptance of cores taken from the in-place production shotcrete, if it is necessary to take
cores in an area of suspect quality. It should be made very clear to the Contractor in the
Contract Documents which criteria apply.

9.0 SAFETY AND CLEAN-UP

During concrete removal processes safety measures should be implemented to protect


personnel from injury and equipment and adjacent property from damage.

10.0 SHOTCRETE APPLICATION AND FINISHING


83

General guidance for both dry and wet-mix shotcrete application is provided in the ACI
506R, Guide to Shotcrete. The publication by Crom (Ref. 2), provides excellent
guidance on proper dry-mix shotcrete nozzling procedures. These documents do not,
however, deal in any depth with the more recent innovations in shotcrete repair, such as
the use of silica fume or steel fiber reinforcement. More detail concerning the latter
types of shotcrete systems in repair applications are given in References 1, 5, 11, 12, 13
and 14.

Shotcrete should be applied in accordance with the general requirements detailed in ACI
506R and Crom publication (Ref. 2), except that with silica fume shotcrete it is often
possible to build up the full thickness of the repair in a single layer, even on overhead
surfaces. This particularly applies to silica fume shotcrete applied by the dry-mix
shotcrete process. It is technically desirable to build up the full thickness in a single
layer, provided rebound and overspray are properly dealt with and the shotcrete does not
lose adhesion and slough, sag or delaminate. Rebound should be removed from surfaces
to receive shotcrete; this is best done while the material is still plastic using blow pipes,
scrapers, wire brushes, or other suitable tools. Single layer construction eliminates the
requirement for preparing each layer of shotcrete to receive a subsequent layer, and
enhances productivity. With conventional shotcrete the layer thickness on overhead
surfaces will generally be limited to 50 mm or less. Thickness of 200 mm or more in a
single pass on overhead surfaces have been achieved in certain dry-mix silica fume
shotcrete repair projects. Thicknesses of 600 mm or more have been achieved in repair
of vertical surfaces, using steel fiber reinforced, dry-mix silica fume shotcrete (Ref. 14).

General recommendations for shotcrete application in bridge repair projects is provided


in the Guide Specification. Items which are important to the provision of quality
shotcrete are emphasized, such as:

• provision of suitable scaffolding or elevating devices to provide the nozzleman


with good access for proper nozzle orientation to the receiving surface;

• sufficient ventilation and lighting to provide clear, unhindered view of the


shooting area;

• use of predampeners in applying dry-bagged premix shotcrete, to minimize dust


formation and enhance homogeneity of the in-place shotcrete.

Excess shotcrete or overspray should be removed from non-prepared concrete surfaces


adjacent to repair edges. Thin skim coats should not be applied to non-prepared concrete
surfaces to “even-out" the appearance between shotcrete patches. Such material is highly
vulnerable to delamination and peeling.

11.0 CURING AND PROTECTION

Proper curing is one of the most important requirements for a successful repair. Most
shotcrete displays very little bleeding, particularly silica fume shotcrete. Such shotcrete
84

is vulnerable to plastic shrinkage and early age drying shrinkage cracking, unless
appropriate protection and curing measures are taken.

On warm, windy days, with high evaporation rates, on cold days with low relative
humidity, and on surfaces exposed to direct sunlight during shotcreting it may be
necessary to use special shades, wind breaks, fogging equipment, or surface evaporation
retardants, or a combination of these. Alternatively, the shotcrete work may have to be
rescheduled to night shifts, or more favorable ambient conditions. Shotcrete applied
under the above conditions is very vulnerable to cracking especially when applied to
surfaces in direct sunlight and a breeze, at temperatures above about 25°C. In severe
conditions good results have been obtained by applying a finishing compound made
specifically to reduce moisture loss, as an interim measure before wet curing can be
applied.

The best means of curing is to keep the shotcrete continuously saturated with water for a
minimum period of 7 days. This enables the shotcrete to gain strength before being
subjected to pronounced drying shrinkage stresses. Means of accomplishing this are
given in the Guide Specification. In some circumstances the use of moist curing is
impractical, and curing compounds must be removed by grit blasting or high pressure
water blasting if subsequent shotcrete layers, paints or coating are to be applied to the
shotcrete. Under favorable conditions of wind, humidity and temperature the wet curing
time may be reduced to a minimum of 4 days based on a local history of acceptable
performance.

The normal requirements for hot and cold weather concreting also apply to shotcrete. In
cold weather shotcreting operations it is recommended that shotcrete not be applied if the
substrate concrete temperature is below 5°C. The air temperature in contact with the
shotcrete should be above 10°C. Otherwise the shotcrete can be very slow in setting and
hardening, and bond to the substrate could be damaged, particularly on overhead surfaces
(such as soffits of bridge decks) subjected to vibration from traffic.

12.0 SHOTCRETE ACCEPTANCE AND REPAIR

It is highly desirable that the Engineer provide a knowledgeable inspector to monitor the
shotcrete repair work. This is particularly important at start-up of the project, so that any
observed deficiencies can be corrected before the work progresses too far. The Engineer,
or his designated inspector should review and approve all prepared shotcrete surfaces,
anchors and fixed reinforcing steel or mesh, prior to the placement of any shotcrete.
Shotcrete application should be carefully monitored and any deficiencies observed during
the shotcrete application process should be immediately addressed. Any defective
shotcrete should be preferably removed while the shotcrete is still plastic, as it becomes
much more costly to remove once hardened.

When shotcrete test panels, or examination and sounding of the hardened shotcrete
provide indications of non-compliance with the project specifications, a program should
be implemented to evaluate the quality of the in-place shotcrete. Such a program will
85

usually involve diamond core drilling, sometimes in conjunction with other non-
destructive test procedures. The ACI 506 Shotcrete Committee has adopted a "Core
Grade System" to quantify the quality of in-place shotcrete. This system is new, however
it is the best available rational criteria to be used for shotcrete acceptance/rejection and is
highly recommended.

When shotcrete is required to be removed and repaired, the same basic procedures
specified for original concrete repair should be followed. In most contracts the
Contractor is required to bear all cost accrued for testing and repairing defecting
shotcrete.
86

REFERENCES

1. Morgan, D. R. and Neill J., "Durability of Shotcrete Rehabilitation Treatments of


Highway Bridges in Canada", Transportation Association of Canada Annual Conference,
Winnipeg, Manitoba, September 17, 1991, pp. 36.

2. Crom, T. R., "Dry Mix Shotcrete Nozzling", The Crom Corporation, Gainesville, Florida
32607, U.S.A., 1985, pp. 39.

3. Rasheeduzzafar, F. D. and Mukarram, K., "Influence of Cement Composition and


Content on the Corrosion Behavior of Reinforcing Steel in Concrete", ACI SP-100,
Vol. 2, 1987, pp. 1477-1502.

4. Morgan, D.R., "Use of Supplementary Cementing Materials in Shotcrete", Proceedings,


International Workshop on the Use of Fly Ash, Slag, Silica Fume and other Siliceous
Materials in Concrete", Editor W. G. Ryan, Concrete Institute of Australia, Sydney,
Australia, July 4 - 6, 1988, pp. 403-432.

5. Morgan, D.R., "New Developments in Shotcrete for Repairs and Rehabilitation",


CANMET International Conference on Advances in Concrete Technology,
Editor V. M. Malhotra, Athens, Greece, May 1992, pp. 669-740.

6. Morgan, D. R., "Freeze-Thaw Durability of Shotcrete", Concrete International, Vol. 11,


No. 8, August 1989, pp. 86-93.

7. Beaupré, D., Pigeon, M., Talbot, C. and Gendreau, M., "Deicer Salt Scaling Resistance
of Dry- and Wet-Process Shotcrete”, ACI Materials Journal, Sept.-Oct., 1994, pp. 487-
494.8. Morgan D. R., Neill, J., McAskill, N. and Duke, N., "Evaluation of Silica Fume
Shotcrete", CANMET/CSCE International Workshop on Silica Fume in Concrete,
Montreal, Quebec, May 4 - 5, 1987, 34 pp.

9. Morgan, D. R. and Wolsiefer, J., "Wet-Mix Silica Fume Shotcrete: Effect of Silica
Fume Form", American Concrete Institute, SP-132, Vol. II, 1992, pp. 1251-1271.

10. Silfwerbrand, J., "Concrete Repair with Shotcrete", Bulletin No. 153, Department of
Structural Mechanics and Engineering. The Royal Institute of Technology, Stockholm,
Sweden, 1988.

11. Gilbride, P., Morgan, D.R. and Bremmern, T.W., “Deterioration and Rehabilitation of
Berth Faces in Tidal Zones at the Port of Saint John”, American Concrete Institute SP-
109, Detroit, 1988, pp. 199-225.

12. Carter, P., “Bridge Repairs with Steel Fibre Shotcrete”, Alberta Transportation report
presented at American Concrete Institute, 1985 Fall Convention, Seminar on Concrete
Rehabilitation with Shotcrete, Chicago, 1985, 16 pp.
87

13. Morgan, D.R., “Dry-Mix Silica Fume Shotcrete in Western Canada”, Concrete
International, Vol. 10, No. 1., January 1988, pp. 24-26.

14 Anderaon, B.C., “Shotcrete Repairs to Skeena River Crossing Tower Pier Foundations”,
Canadian Electrical Association Meeting, Vancouver, B.C., March 1987, 17 pp.

15. Grzybowski, M., “Determination of Crack Arresting Properties of Fiber Reinforced


Cementitious Composites”, Publication TRITA-BRO-8908, ISSN 1100-648X,
Department of Structural Engineering, Royal Institute of Technology, Stockholm,
Sweden, June 1989, 190 pp.

16. Morgan, D.R. and Mowat, D.N., “A Comparative Evaluation of Plain, Mesh, and Steel
Fibre Reinforced Shotcrete”, American Concrete Institute, SP-81, 1984, pp. 307-324.

17. Morgan, D.R., McAskill, N., Richardson, B.W., and Zellers, R.C., “A Comparative
Evaluation of Plain, Polypropylene Fibre, Steel Fibre, and Wire Mesh Reinforced
Shotcrete”, Transportation Research Record 1226, Washington, D.C., 1989, pp. 78-87.

18. Gebler, S.H., Litvin, A., McLean, W.J., and Schutz, R., “Durability of Dry-Mix
Shotcrete Containing Accelerators”, ACI Materials Journal, Vol. 89, No. 3, May-June,
1992, pp. 259-262.

19. Austin S. and Robins, P., “Sprayed Concrete: Properties, Design, and Application”,
Whittles Publishing, Caithness, Scotland, 1995, pp. 382.