Spm1500 Manual
Spm1500 Manual
English Units
Document Revision 6
SPM-1500 Manual Operator
Front Matter
World
Wide Web www.simtronics.com
Process Description
Process Flow Warning: Real fired heaters are very dangerous to operate. Explosions, fires and
damaged tubing along with severe injury or even death to personnel can occur
despite following approved operating procedures. Some heaters have minimal trip
logic while others are highly instrumented to protect the heater from damage. In
either case, experience has shown it is still possible to damage a heater from normal
operations. The simulator will not necessarily replicate these scenarios because they
highly depend on the type of heater and the particular fuel type, combustion air
supply system, controls and interlocks. Therefore, operations practiced on the
simulator should not be considered absolutely safe just because there were no
dangerous conditions experienced. The simulator is intended to familiarize the
operator with the basic principles of heat transfer by the combustion of fuel.
Additional safety training on fired heaters is highly recommended in order to master
the principles of safe operation.
Economizer
Steam Drum
Preheated boiler feedwater from the Economizer enters the Steam Drum situated
atop the boiler’s structure. The Steam Drum is a long horizontal vessel and supplies
water to the Downcomers. The Steam Drum also serves to separate the water and
steam entering the vessel from the Risers. Arrays of specially engineered moisture
separators separate saturated steam from the boiler water. The separated steam is
saturated and is routed to the Superheater.
Downcomers
The Downcomers are a string of tubes that pass outside the firebox to supply water
to the Mud Drum by gravity. The water from the Downcomers collects in the Mud
Drum.
Mud Drum
The Mud Drum is a long horizontal vessel that sits at the base of the boiler firebox
and collects water and a small amount of steam from the Downcomers. The Mud
Drum supplies the Risers with water. The Mud Drum also serves to collect, as its
name implies, solids formed in the boiler system. These solids (sediment) will settle
at the bottom of the Mud Drum. Regular purging of water from the Mud Drum
(known as blowdown) helps keep these solids from accumulating. Blowdown also
helps prevent accumulation of undesirable dissolved chemicals that can increase
scaling and corrosion of the boiler’s tubes.
Risers
The Risers are also a string of tubes that pass through the main volume of the
firebox to produce steam from pickup of heat from hot combustion gases. The string
of tubes is commonly referred to as a waterwall.
The upward flow of fluid in the Risers is induced from a physical phenomenon
commonly referred to as the Thermosiphon Effect or the Bernoulli Effect. This effect
is that lower density fluids will rise in a gravitational field compared to higher density
fluids (e.g. a hot air balloon in cool air). As steam is produced from heat pickup in
the Risers, it lowers the net density of the fluid in the Risers. As the fluid rises higher
in the Risers, it picks up even more heat and more vaporization occurs. This
decreases the fluid’s density even more, resulting in a vigorous upward flow from
the Mud Drum back to the Steam Drum. Thus, the Thermosiphon Effect will cause
the Risers to pull water (and steam) from the Mud Drum which, in turn, receives
water by gravity from the Steam Drum via the Downcomers.
Superheater
Saturated steam is generated in the Risers of the boiler. Saturated steam readily
forms condensate in piping as the steam cools. Therefore, saturated steam needs to
be heated well above its dew point (superheating) to avoid excessive condensation
in the utility piping network the Boiler serves. Superheating also improves the
performance of equipment such as steam turbines.
Before going to the Steam Header, the saturated steam leaves the Steam Drum and
passes through the Superheater where it reenters the firebox of the boiler and is
superheated.
Attemperator
The final temperature of the superheated steam from the boiler is controlled by
injecting a small flow of boiler feedwater into the steam line. A special mixer known
as an Attemperator is used for injecting the boiler water. The boiler water normally
vaporizes completely. This system prevents excessively superheated steam from
reaching the Steam Header. High steam temperatures can damage piping and
equipment that the Steam Header serves.
Steam Header
In addition to the steam produced by the Boiler, two other boilers of similar design
and capacity as the main boiler provide superheated steam to the steam header.
These other boilers are not simulated in detail. Steam users then draw the
superheated steam from the Steam Header.
Fuel Firing
Fuel and air enter the firebox of the boiler where they are ignited and burned. The
superheater, the downcomers, and risers are heated both by radiant and convective
heat transfer. The hot combustion gases then preheat the boiler feedwater in the
economizer before passing out the stack. The rate of steam generated will depend
on the rate of fuel fired.
Product Three boilers provide approximately 250 KPPH (500 GPM of BFW) of superheated
Specifications steam each to the steam header. The pressure in the steam drum is 735 PSIG. The
saturated steam is then superheated to 761 DEG F. The pressure in the steam
header is maintained at 700 PSIG.
Each boiler requires approximately 12,675 PPH of fuel to accomplish this task. 3,815
MSCFH of air is required to maintain a 25 % excess of air in the boiler, whereby the
stack O2 is maintained at 4.25 VOL %. The stack gases leave the boiler at
approximately 300 DEG F.
Equipment The boiler consists of a firebox where the fuel and air mixture is burned, a radiant
Specifications heat transfer section, and convective heat transfer section, superheater,
downcomers, risers, steam drum, mud drum, economizer, and stack. The boiler
consumes a total of approximately 96 MW of energy. Each boiler operates at
approximately 60% to 75% of its maximum capacity.
In the event of a flame out, and during startup, there is burner logic that requires
that the furnace is purged with air for 60 seconds before the flame can be ignited.
Superheated
Steam Boiler
Burner Logic
Instrumentation
Boiler feed water to the Steam Drum is controlled by flow controller FIC-101. Boiler
feedwater temperature is indicated by TI-101. Boiler feedwater temperature
entering the Steam Drum is indicated by TI-102. Blowdown from the Mud Drum is
controlled by flow controller FIC-103.
Fuel rate to the Boiler is indicated by FI-301 and air to the Boiler is controlled by
FIC-201. The switch “BURNER” acts as both an ignitor and a flame indicator. Fuel
and air temperature are indicated by TI-301 and TI-201 respectively. Stack
temperature is indicated by TI-202 and stack O2 is indicated by AIC-201.
Steam Header pressure is controlled by PIC-501. The steam generated by the other
2 boilers is indicated by FI-401. The percentage of steam generated by the boilers
is indicated by HIC-301 and HIC-401. Steam demand is controlled by FIC-601.
The boiler master control consists of the steam header pressure controller (PIC-501)
and the firing bias controllers (HIC-301 and HIC-401). The output of the pressure
controller (PIC-501) is multiplied by the setpoint of the bias controllers (HIC-301 and
HIC-401). This signal is the output of the bias controllers (HIC-301 and HIC-401)
which in turn adjusts the fuel valves.
To get maximum firing from the boilers, the setpoints of the bias controllers (HIC-
301 and HIC-401) should be 100%. To change the ratio of firing amongst the
boilers the setpoints of the bias controllers should be changed. To increase the
amount of steam generated by the main boiler, the setpoint of the bias controller for
the other two boilers (HIC-401) should be decreased. To increase the amount of
steam generated by the other two boilers, the setpoint of the main boiler's bias
control (HIC-301) should be decreased. The bias controllers (HIC-301 and HIC-401)
indicate the percentage of total steam that each boiler generates.
Please keep in mind that when you are manipulating the bias controller for the other
two boilers (HIC-401), you are in fact changing the bias for those two boilers
simultaneously. Since all three boilers are of similar design, the ratio of steam
generated by each boiler should be approximately one-third each. However, keep in
mind that under loads vastly different from design, the setpoints of the bias
controllers (HIC-301 and HIC-401) may have to be trimmed to maintain a steam
generation rate of one-third each.
Instrumentation, continued
Air Control
The air rate to the boiler is controlled by FIC-201. This controller gets its setpoint
from the fuel rate indicator process variable (FI-301). This process variable is
multiplied by a ratio parameter to maintain a 25% excess of air. This ratio is valid
only for a particular fuel. When the stack oxygen controller is in automatic mode, it
adjusts the ratio of FIC-201 to obtain the desired oxygen content in case the fuel
characteristics change. Note that output and setpoint of AIC-201 are initialized in
manual mode so that the controller does not bump the ratio of FIC-201 when AIC-
201 is placed in automatic mode.
When steam vapor is generated in the risers of the boiler, some of the volume in the
tubes is displaced by steam bubbles. These steam bubbles have a smaller density
than the boiler feed water. The density of these steam bubbles is also a function of
temperature and pressure. As more and more of these steam bubbles are
generated, the level indicator does not give a true indication of the inventory of
boiler feed water in the system. As steam demand is increased, this effect becomes
increasingly more pronounced, and the level in the steam drum rises rather than
decreases, as one would expect.
Instrumentation, continued
The Logic system trips off the burners if any of the following conditions occur:
FIC-201 air flow rate is zero
FI-301 fuel flow rate is zero
LIC-101 steam drum level is below its low alarm limit
Similarly, the Logic system allows the burners to start only if all of the following
conditions are met:
FIC-201 air flow rate is greater than zero
FIC-201 air purging exceeds 60 seconds
FI-301 fuel flow rate is greater than zero
LIC-101 steam drum level exceeds its low alarm limit
Note that fuel cannot be introduced until the air purge is completed. The air purge
timer starts when the fuel flow FI-301 is zero and the air rate FIC-201 is greater
than zero.
Normal Operations
Normal Design The following table is a list of the normal design conditions (initial condition 1) for
Conditions the SPM-1500 Superheated Steam Boiler Simulation as provided by Simtronics.
Design Output
Tag ID Description Eng Units
Value Percent
AI-301 FUEL GAS GRAVITY 0.556 SP GR
AIC-201 STACK OXYGEN 4.25 WT%O2
BURNER IGNITOR SWITCH FLAME N/A
FI-102 STEAM TO HEADER 249 KPPH
FI-301 FUEL TO BURNER 12,675 PPH
FI-401 STEAM TO HEADER 500 KPPH
FIC-101 BFW FLOW 498 GPM 49.8 %
FIC-103 BLOWDOWN FLOW 0 GPM 0.0 %
FIC-201 AIR TO BURNER 3,815 MSCFH 43.8 %
FIC-601 STEAM DEMAND 750 KPPH 50.0 %
HIC-102 STM FLOW TO HEADR 50.0 % VLV 50.0 %
HIC-103 STEAM VENT VALVE 0.0 % VLV 0.0 %
HIC-301 MAIN BOILER 33.3 %BIAS 50.0 %
HIC-401 OTHER BOILERS 66.7 %BIAS 50.0 %
LI-101 MUD DRUM LEVEL 100.0 % LVL
LIC-101 STEAM DRUM LEVEL 50.0 % LVL 50.0 %
MEGAWATT MAIN BOILER 96.3 MWATT
PI-101 STM DRUM PRESSURE 735 PSIG
PIC-501 HEADER PRESSURE 700 PSIG 50.0 %
TI-101 BFW SUPPLY 220.0 DEG F
TI-102 BFW TO DRUM 400.0 DEG F
TI-103 SUPERHEATED STEAM 761 DEG F
TI-201 AMBIENT AIR TEMP 68.0 DEG F
TI-202 STACK TEMP 300 DEG F
TI-301 FUEL SUPPLY 68.0 DEG F
TIC-104 STEAM ATEMPRATR 750 DEG F 22.4%
Tag ID Description
AIC-201 STACK O2
BURNER FLAME INDICATOR
FI-102 STEAM FLOW
FI-301 FUEL FLOW
FI-401 STEAM FLOW
FIC-101 BFW FLOW
FIC-201 AIR FLOW
FIC-601 STEAM DEMAND
LIC-101 STEAM DRUM LEVEL
PIC-501 STEAM HEADER PRESSURE
Adjusting To smoothly increase or decrease overall steam production, the steam users' flow
Production controller (FIC-601) setpoint should be gradually adjusted.
To smoothly change steam header pressure, the steam header pressure controller
(PIC-501) setpoint should be gradually adjusted.
To smoothly change the biasing of the three boilers, the setpoints of the bias
controllers (HIC-301 and HIC-401) should be gradually adjusted.
Note that there is a significant lag time between a change in fuel output and a
change in steam production. Therefore, regulation of the Steam Header pressure
(PIC-501) cannot be tightly controlled to its setpoint by adjusting the fuel rate (FI-
301). If large changes in steam demand are made quickly, it may be necessary to
manually adjust the fuel firing by placing PIC-501 and changing its output faster
than the controller would in automatic mode. If manual adjustments to the firing
rate are made, monitor the boiler conditions closely, especially the stack oxygen
content. Do not make fuel rate changes - especially increases - faster than the air-
to-fuel ratio controller FIC-201 will permit so as to keep the oxygen content in a safe
range.
Responding to An instrument in alarm indicates that there is an upset condition in the process. A
Alarms swift response to an alarm can prevent a dangerous condition from occurring.
Responding directly to a key process variable that is in alarm may not always be the
best corrective action. Understanding and observing the relationships of all process
variables can help you troubleshoot the problem and take proper corrective action to
return the process to design conditions.
For example, in the Superheated Steam Boiler, a stack O2 alarm might not
necessarily indicate a problem with the air system, but rather a change in the fuel.
Pre-Startup
Pre-Startup Pre-startup procedures must be performed before any startup may begin.
Procedure
Normal Pre- All Simtronics process simulations assume that the following normal procedures have
Startup already been completed. However, trainees should be made aware of these
Procedure procedures and any other procedures particular to your process plant.
Cold Start Pre- The cold start initial condition provided by Simtronics ensures that the following
Startup procedures have already been completed. However, trainees should be required to
Procedure perform these procedures as a matter of course. You may change the cold start
initial condition provided by Simtronics, to ensure that trainees do in fact perform
these procedures.
Startup
Normal The following is a startup procedure recommended by Simtronics. You may modify
Startup this procedure to more closely reflect your particular process plant startup
Procedure procedures. Refer to Exercise 2 for the expert solution to the startup procedure.
The entire startup should take approximately 2 hours.
Warning: Real fired heaters are very dangerous to operate. Explosions, fires and
damaged tubing along with severe injury or even death to personnel can occur
despite following approved operating procedures. Some heaters have minimal trip
logic while others are highly instrumented to protect the heater from damage. In
either case, experience has shown it is still possible to damage a heater from normal
operations. The simulator will not necessarily replicate these scenarios because they
highly depend on the type of heater and the particular fuel type, combustion air
supply system, controls and interlocks. Therefore, operations practiced on the
simulator should not be considered absolutely safe just because there were no
dangerous conditions experienced. The simulator is intended to familiarize the
operator with the basic principles of heat transfer by the combustion of fuel.
Additional safety training on fired heaters is highly recommended in order to master
the principles of safe operation.
Overview
The following basic steps are used to start up the Superheated Steam Boiler:
Pre-Startup, continued
Shutdown
Overview
The following basic steps are used to perform a normal shutdown of the
Superheated Steam Boiler:
Reduce steam demand and fuel firing to take the other boilers out of service
Reduce steam demand and fuel firing on the main boiler
Put firing into manual control and switch lineup from steam header to
atmospheric vent
Stop firing, cool and drain unit
Emergency Operations
Emergency All emergencies should be handled quickly. The particular steps taken in an
Operation emergency are specific to the problem at hand. As always, your trainees should
Procedure follow the emergency procedures particular to your process plant. If an emergency
cannot be handled quickly, then an emergency shutdown should be performed.
Overview