CH - 3 Embankment Dam PDF
CH - 3 Embankment Dam PDF
CH - 3 Embankment Dam PDF
1 2019/2018A.Y
3. Types of Embankment Dams
3.1. Introduction
ICOLD defined an embankment dam as, "any dam constructed of excavated materials
placed without addition of binding materials other than those inherent in the natural
material. The materials are usually obtained at or near the dam site“
An embankment dam is a non-rigid dam, which resists the forces exerted upon it mainly
by its shear strength. For the construction of embankment dams the entire range of
soils from clays to boulders or quarried stones are used.
These dams usually provide the most economical and most satisfactory solution for
sites at which suitable foundation at reasonable depth may not be available for a dam of
concrete or masonry.
2
Characteristics
General Remarks
mostly separated into supporting and sealing part of the damming construction.
3
Advantages:
Construction on loose rock is possible;
requirements);
4
Disadvantages:
Sensitive to wave wash (also if backwater level is lowered);
Not overflowable (operating set-ups and spillway must be clearly separated from
Surface erosion at the downstream slope due to rain (counter measure: berms);
However, composite earth and rock fill type of embankment dams are also being widely used.
Earth dams: can be constructed on almost all types of foundations, provided suitable measures are
taken. Earth dams are usually cheaper than gravity dams if the soil in abundant quantity is available
near the site. Modern developments in earthmoving equipment have resulted in decreased cost for
earth dams.
Rockfill dams: require somewhat stronger foundations as compared to earth dams, but the
foundation need not be as strong as those for gravity dams.
Rockfill dams are more economical than gravity dams if Rockfill is easily available at the site.
6
4.2. Earth (fill) Dams
The design of earth dam involves both hydraulic and structural considerations.
Hydraulic analysis primarily involves a determination of the seepage patterns and magnitudes, as well
as the internal hydrostatic forces resulting from seepage, both for the dam body and foundation of
particular importance is piping.
Structural analysis involves a study of the embankment stability under the given conditions of seepage
and other forces. Settlement and stability studies of the foundation are also important.
Rolled-fill dams are most commonly used in practice. These dams are constructed by placing materials in thin
7 layers, about 15 to 45 cm thick, and compacting each layer to the required dry density with heavy rollers.
Cont’d…
In hydraulic-fill earth dams water is used for transporting and placing the materials.
The main advantages are
8
Cont’d…
The main disadvantages of the hydraulic fill dam are that the fill is saturated
when placed and a very high pore-water pressure develops in the core
material.
The embankment should be safe under the pore-pressure developed during the
9
Cont’d…
In semi-hydraulic fill dams, the coarse material is dumped from trucks into the
required position to form shells. The core is, however, constructed by hydraulic-fill
method. The fines are sluiced into a core.
Out of these three types of dams rolled fill dams are most commonly adopted.
This is so because in the case of the other two types of dams lack of control in
placing the material may result in the failure of the dam.
The inclined drain serves to prevent the downstream slope from becoming saturated and
susceptible to piping and/or slope failure and to intercept and prevent piping through any
horizontal cracks traversing the width of the embankment.
In this type of dam, the slope must be relatively flat for stability.
11
Cont’d…
Basic properties required in the material for an homogeneous embankment or for the core of a
It must be sufficiently impervious to prevent excessive loss of water through the dam, the
acceptable loss being determined by the safety of the structure and the value of the lost water;
It must be capable of being placed and consolidated to give a practically homogeneous mass,
free from potential paths of percolation, either through the fill or along its contact with the
foundation;
The soil should develop a maximum practical shear strength under compaction and maintain
12
2. Zoned Earth Dams: Composed of more than one type of soil
A zoned earth dam usually consists of a central impervious core flanked by shells of
pervious materials on the upstream and downstream sides.
A transition filter is usually required between the core and the shell to prevent piping.
The central core checks seepage through the dam. It is constructed of clay, silt, silty clay
or clayey silt.
The pervious shell gives stability to the dam and it consists of sand, gravel, or a mixture of
these materials.
13
Cont’d…
The upstream pervious zone provides free drainage during sudden
drawdown. The downstream pervious zone acts as a drain to control the
phreatic line.
The pervious zones give stability to the core and also distribute the load
over a large area of foundation.
The transition filter prevents the migration of the core material into the
pores of the shell material.
The downstream transition filter is useful during the steady seepage
conditions and the upstream filter is useful during the sudden drawdown
conditions.
14
3. Diaphragm-type Earth Dams:
Consists of a thin impervious core, called diaphragm, surrounded by pervious shells.
It is also called thin core earth dam. The difference between zoned earth dam and
diaphragm-type earth dam is only in the thickness of the core.
If the thickness of the core at any elevation is less than the height of the embankment
above the elevation or 10 m, the dam is generally considered to be of diaphragm type.
Diaphragm-type earth dams are not common. These are constructed only when there is
shortage of impervious material for the construction of a zoned earth dam.
15
Embankment Dam with Core
Description
Core within the embankment cross section,
16
Advantages:
Seepage control of layer is in a protected position;
Possibility of ponding from both sides in the function of a low weir upstream of a
reservoir (Forebay).
Disadvantages:
Only indirect control is possible;
No possibility of repair;
Merging of construction stages (core and supporting shell at the same time).
17
(a) Thick core (clay, loam, silt)
Flexible core, made of natural or prepared cohesive soils; vertical
placement between filter layers.
18
Cont’d…
Advantages:
Little sensitivity to unregular settling (sealing in the direction of the settlings);
Disadvantages:
The downstream shell of the core only acts as supporting body
against water pressure;
Installation of filters before and behind the core is necessary;
possibly slightly inclined in the upper part towards the downstream side. Favorably used
20
Cont’d…
Advantages:
Simple construction;
Disadvantage:
Water pressure acts horizontally, thus minimizing stability.
21
Cont’d…
The minimum thickness of core is dependent on a number of factors:
the type of material chosen for the core and shoulders of the dam;
22
Cont’d…
Advantages of vertical cores:
One advantage of the vertical core is that higher pressures will exist on the
contact between the core and the foundation, and will provide more protection
against the possibility of leakage along the contact.
The vertical core tends to be slightly thicker for a given quantity of impervious soil
23
Sloping Impervious Core Earthfill Dams
Natural impervious materials (loam, clay) or prepared sealing materials
(clay concrete, hydrated clay); position upstream under the surface
between filter layers.
24
Advantages:
Greater part of the embankment acts as supporting shell;
Filling of the supporting shell independent from dam sealing and underground sealing;
Disadvantage:
Sensitive to deformations.
It may be difficult to locate the grout curtain in the desired position relative to the core
contact area.
If it is anticipated that additional grouting is required through the embankment after the
dam is completed then a central core design is preferred, because the work can be done
25 from the crest of the dam without lowering the reservoir.
3.3. Foundation Requirements of earth dams
Earth dam can be constructed on almost all types of foundations provided that
sub-surface strata have been thoroughly investigated and the design has been
adopted to suit the foundation.
The foundation of earth dam should provide a stable support for the dam under
all conditions of saturation and loading. Moreover, it should provide sufficient
resistance to seepage to prevent piping failure and excessive loss of
water.
Foundations may be classified into the following three types:
Rock foundations
The shear stresses in the foundation due to earth dams are usually low and
well within the bearing capacity of the rock.
If there are fissures, joints, fault planes or permeable seams in the
foundation rock, grouting is done to check the excessive erosive leakage and
loss of water.
Shale foundations may, however, cause difficulties, especially if they contain
joints, faults, weak layers and seams filled with soft materials.
While designing the dam, excess pore pressure and the overall strength should
be considered.
27
(b) Pervious soil foundations
Sometimes the earth dam foundations consist of recent alluvial soil overlying
For such foundations, adequate measures are required to check seepage and
piping.
28
Cont’d…
Coarse sand and gravel:
These have high shear strength and pose no problem from the
under the loads of the dam, and the shear strength increases
almost simultaneously with the construction of the dam.
The main problem with such foundations is the under seepage.
29
Cont’d…
Loose fine sand or coarse silt:
This presents difficult foundation problems. Such soils have low shear strength and
high compressibility, which cause problems.
If such soils are subject to sudden shear stresses because of earthquakes or any
other such source, they may liquefy and a phenomenon known as liquefaction
occurs.
The soil loses all its shear strength and flows like a liquid. Such a behaviour is
exhibited by uniform sands, which are very fine and consist of rounded grains.
If unavoidable as a foundation, they should be compacted by pile driving or other
methods so that they become quite dense before the construction of the dam.
30
(c) Impervious soil foundations:
Foundations of fine silt and clay are impervious and have very low shear strength.
Shear failures may occur in such foundations. Moreover, there are problems of
excessive pore water pressure, large deformations and settlements.
Such foundations have low permeability and their consolidation takes a very long time.
Because of the very low rate of consolidation, the shear strength develops very
gradually.
The shear stresses induced in the foundation by the earth dam should not exceed the
shear strength of the soil to avoid failure of the foundation by shear.
The earth dam design in such cases should consider likely strains in the foundation. It
usually becomes necessary to provide flatter slopes or berms to spread the load over a
31 large area to reduce the deformation and shear stresses.
3.3.1. Design of earth dam to suit the available material
In the interest of economy the design of earth dam should be adapted to the utilization of
the material available at or near the site.
Thus, if near the site there is nothing available but sand, then the adopted design should
utilize this sand for the bulk of the dam, limiting the imported material of concrete, clay, or
silt for providing an impervious member to the minimum required.
In Figure 1.2 is shown a suitable design for a site where there is nothing available except
sand gravel.
32
Cont’d…
The nearest impervious material is a sandy clay, which is located far away. Due to
excavation and transportation costs the sandy clay material has to be kept at a
minimum.
Figure 1.3 shows a design suitable for a site where both clayey silt and coarse
pervious sand are available in adequate quantities in borrow pits near the site.
Furthermore, both drainage and stability conditions are favourable. The
pervious stratum has adequate shear strength.
33
Cont’d…
The design in figure 1.4 is suitable for a site where both clayey silt and coarse sand are
In figure 1.5 is shown a suitable design for a site where both sand gravel and clayey silt are
available and where the foundation is highly pervious to a great depth. A blanket of clayey silt,
which is very impervious as compared with the sand gravel of the foundation, is carried from
the impervious core upstream under the upstream shell and extended for a distance frequently
10 or more times the head upstream from the heel of the dam.
34
Cont’d…
Such blankets cut down the seepage materially by forcing the
35
Cont’d…
In figure 1.6 is shown an earth dam design, which is suitable for a site where the only
material available is silty clay and where the foundation consists of silty clay, which is
highly unconsolidated.
In this case, the upstream slope is flattened to take care of rapid drawdown, and also in
many cases the flatness of both slopes is determined by the requirements for spreading the
load.
So that the maximum unit stress induced in the foundation will be less than the shear
strength of the plastic material in the foundation with a fair factor of safety.
36
3.4. Causes of failures of earth dams
Earth dam failures are mainly caused by improper design, lack of thorough
The various causes of failures can be grouped into three categories as,
37
Cont’d…
Hydraulic failures: may be occur
38
Cont’d…
following causes:
Piping through the dam
Piping through the foundation
Conduit leakage
Sloughing of downstream toe
40
Cont’d…
Structural failures in earth dams are generally shear failures leading to
Foundation slides
Liquefaction slides
42
3.5. Criteria for safe design of earth dams
The earth dam should be designed such that the failure of the dam or its foundation
does not occur.
The dam should be safe and stable during construction and throughout its life. For the
safe design of earth dam, the following basic criteria should be satisfied.
(a) No overtopping: The dam should be safe against overtopping during occurrence of
the worst floods,
An adequate free board should be provided so that the dam is not overtopped due to
the wave action,
A suitable allowance in the height of the dam should be made to account for
settlement.
43
Cont’d…
(b) No seepage failure:
The phreatic line (or the seepage line) should remain well within the
44
Cont’d…
(c) No structural failure:
The slopes (u/s & d/s) should be safe during and immediately after construction,
45
Cont’d…
(d) Proper slope protection:
U/s slope should be protected against erosion by waves,
D/s slope and the crest should be protected against erosion due to rain and
wind.
(e) Proper drainage: The portion of the dam downstream of the impervious core
should be properly drained.
(f) Economic section: As far as possible, the materials available near the dam
site should be used to reduce the cost.
All the above criteria are kept in mind while selecting the preliminary section of
the earth dam.
46
3.5.1. Seepage through earth dams
For any dam of homogeneous material seepage will pass through the dam and
appear at the downstream face regardless of the tightness of the material.
The line of saturation, i.e., the upper boundary of the flow line below, which the
flow is under hydrostatic pressure, is called the phreatic line.
If this line of saturation is allowed to intersect the downstream slope above
the toe, a serious sloughing will always occur unless prevented by
construction of toe drains of filters or rock fill toe.
Location of the position of the phreatic line is desirable for determination of
the amount of seepage and for construction of the flow nets as it represents
one flow boundary.
47
Cont’d…
In order to define the flow and pressure distribution within the embankment and
total flow through the embankment the first step is determination of the upper
flow line (which is the line of seepage boundary) and the length of the seepage
exit face on the downstream slope of the earth dam.
The two dimensional flow of fluid through porous soil can be expressed by
Laplace’s equation
48
Cont’d…
Graphically, the equation can be represented by two sets of curves that
49
Cont’d…
The two unknown boundaries, BC and CD, figure 1.7, are a combination of an
A parabola, shown by the dashed line, is the basic geometric member used to
embankments while others (Harr 1962, Cedergren 1977, and others) added to and
refined the basic methods.
50
Cont’d…
Figure 1.8 provides the nomenclature and formulas for drawing the line of
seepage and exit face and determining the quantity of seepage per unit length
of embankment, q.
values for h, m and α which allow location of points A and B and determination of
51
Cont’d…
(1) α < 30º Schaffernak-Van Iterson: The two formulas for this method given in figure 1.8
assume gradient equals dy/dx and allow direct determination of a and q.
Construction of basic parabola shown in figure 1.9 is the first step in determining the
upper line of seepage (Casagrande 1937).
From embankment geometry and headwater height, point A is located. d and yo are
determined by scribing an arc, with radius DA through point E. Then the point of vertical
tangency of the basic parabola, F, is determined.
Line AG, parallel to the embankment base and horizontal axis of the parabola, is drawn
and divided into an equal number of segments (6 in the case in figure 1.9).
Line GF, the vertical tangent to the parabola, located at yo/2 from the downstream toe of
52the embankment is divided into the same number of equal segments as line AG.
Cont’d…
The points dividing line AG into segments are connected with point F. The intersection of these
lines with their counterpart lines drawn from the points on line GF define the parabola.
Thus the basic parabola, dashed line A-F, is defined. The upstream portion of the line of seepage,
dotted line BH, is drawn by starting at point B perpendicular to the upstream slope (since the
upstream slope is an equipotential line and the line of seepage is a flow line) and continuing
downstream to make line BH tangent to the basic parabola at point H which is selected based on
judgment.
The central portion of the line of seepage is along the basic parabola while the downstream
portion is a smooth transition from the basic parabola to tangency with the downstream slope at
point C.
Point C is located a distance a. from the downstream toe as determined by the equation for
Schaffernak-Van Iterson shown in figure 1.8.
53
Cont’d…
2) α < 90° L. Casagrande: The gradient assumption for this method is i = dy/ds
where s is the distance along the line of seepage, and allows greater accuracy than
Schaffernak-Van Iterson method for steeper downstream slopes.
Use of the equations in figure 1.8 and the same general procedures used for the
Schaffernak-Van Iterson method apply for α´s up to 60º. For 60° < α < 90°, since a
and s are interdependent, the location of point C (or distance a) must be estimated to
determine the value of then distance a calculated.
This procedure is repeated until there is satisfactory agreement between the
portion of the distance so as measured and a as calculated. Thus the seepage
boundaries are established allowing flow net construction.
54
Cont’d…
(3) α = 180° Kozeny: For this special case Kozeny described a solution adapted by
parabola.
For this case the seepage face is the distance a0 and the correction ∆a is not
used. Again with boundary definition, the flow net can be drawn.
55
Cont’d…
(4) 30° < α < 180° A. Casagrande: After study of model experiments and
Construction of the basic parabola is the first step in this procedure. The point,
Co, as shown in figure 1.8, where the basic parabola intercepts the downstream
slope is determined and distance a + ∆a is measured. Knowing α, C can be found in
figure 1.11 and ∆a calculated.
Information is then sufficient to draw the line of seepage and discharge face,
Pavlovsky analyzed the embankment by dividing it into three zones, writing an equation for q
in each of the zones and, by assuming continuity of flow, equating the three equations for q.
Figure 1.12 provides the nomenclature for Pavlovsky's solution. The embankment is divided as
shown with
Zone I between the upstream slope and a vertical line at the intersection of the crest and
since qI = qII = qIII = q (continuity of flow, steady state conditions) only a0, h1, and q
are unknown. This analysis provides three equations, (i), (ii), and (iii), or (iv), and
three unknowns.
The equations may be solved in a number of ways. One method for ho= 0 is to
equate (i) and (iv) and solve for a then equate (ii) and (iv) and solve for a0:
59
Quantity of Seepage
Consider earth embankment of homogeneous material given in fig. 4. Flow net
through the dam section has been drawn by trial and error method.
If h is the total hydraulic head and Nd is the number of potential drops (9 in fig.4)
deltah = h/Nd.
Consider a field of length l, the field being an approximate square its width is also
63
Cont’d…
The type of core is selected depending on the availability of materials, topography of the
Depending on the inclination of the axis of the core, there are two types of cores.
(1) Vertical core, and
(2) Inclined core
A vertical core provides a high pressure at the contact plane between the core and the
foundation. Hence, it is more effective in reducing seepage. However, an inclined core
has the advantage that the d/s portion of the dam can be constructed first and the core
can be placed later.
The minimum thickness of the core depends on
(1) Permissible seepage through the dam,
(2) Type of the material available for the core,
64 (3) Minimum practical thickness required for construction.
3.5.3. Control of seepage through foundations
If the foundation of an earth dam consists of an impervious stratum, generally
no specific measures are required to reduce the seepage. However, in rock
foundations, grouting and some surface treatment may be required.
65
Cont’d…
(i) Grouting and grout curtain
(ii) Cut-off trenches
foundation strata act as binder and fill the voids, thus reducing the permeability
and increasing its stability.
foundation.
The number of lines and spacing of holes depend upon the nature of foundation
and width of grout curtain which is usually 1/3 to 1/5 the water head.
67
Cont’d…
Cut-off trenches: The cut-off trenches with sides sloping or vertical are excavated
below the dams and filled with well-compacted impervious material.
The trench should be provided up to bedrock or other impervious strata. For moderate
pervious foundations positive cut-off up to hard stratum is provided. The cut-off may
be:
(i) sheet pile
(ii) cement bound curtain
(iii) concrete diaphragm.
68
Cont’d…
Partial cut-off trench: is effective in stratified foundations by intersecting more
A cut-off going to 80% of the total depth of pervious strata reduces the seepage
discharge by only 50%. Thus, wit a partial cut-off, the reliance is primarily on the
length of the seepage path.
possible to provide a positive cut-off, partial cut-off along with upstream blanket
is provided to reduce the discharge and seepage pressure.
69
Cont’d…
Sheet piling cut-off: Steel sheet piling cut-off can be used in silty, sandy and fine
gravel foundations.
If the foundation strata contain boulders the sheet piles will not easily penetrate.
70
Cont’d…
Upstream blanket: Impervious clay placed upstream of a dam and connected to the
impervious section is a convenient way of effecting moderate reduction in the amount of
seepage.
The quantity of seepage is somewhat less than inversely proportional to the total length of
impervious material (Figure 1.16).
71
Cont’d…
72
Cont’d…
73
Cont’d…
Relief wells: Their main purpose is to reduce artesian pressures which otherwise
Relief wells should be designed to penetrate into the principal pervious strata to
(i) Positive cut-off is generally the most suitable measure if the depth of pervious stratum is
moderate.
(ii) When the pervious stratum is quite deep and extensive and its permeability is between 10-3
to 10-5 m/s, an upstream blanket combined with downstream relief wells and drainage
trenches have been found to be quite effective.
(iii) When the permeability of the pervious stratum is quite high, of the order of 10-3 m/s or
higher, and the stratum is quite deep, grout curtains and diaphragms are generally
economical.
75
3.5.4. Drainage of earth dams
Some water always seeps through the dam and foundation even after adopting several
The water, which has seeped through should be suitably drained away from the downstream
Drainage in earth dams is usually provided to bring the phreatic line well within the
downstream face.
A proper drainage system also helps in avoiding heaving and piping, by arresting the soil
The drainage system also reduces the pore water pressure in the downstream portion of the
The blanket extends from the downstream toe for a distance of about three times
the height of the dam or about one-third of the base width of the dam. However, it
should not be longer than two-thirds of the base width of the dam. In the case of a
zoned section, it extends up to the core.
The blanket must be very pervious to drain off the water effectively and its design
should fulfill the usual filter criteria in order to prevent the movement of particles
of the foundation or embankment by seepage discharge.
78
Cont’d…
The main disadvantage of a horizontal blanket is that it is not effective if the
In such a case, the seepage water may flow horizontally towards the downstream
79
Cont’d…
Rock toe: is provided at the d/s toe of an earth dam and it forms a part of the dam
(Figure 1.18).
It consists of stones of size varying from 15 to 20 cm. The upstream face of the
rock toe may be vertical or inclined, but d/s slope is always inclined and it is in the
continuation of the d/s slope of the dam.
A graded filter is provided between the rock toe and the soil mass in the dam to
prevent piping.
The graded filter is also provided between the rock toe and the foundation if it is
pervious.
80
Cont’d…
The height of the rock toe is generally between H/3 and H/4, where H is the
While fixing the height of the rock toe, it should be ensured that there is at least a
minimum cover of 1 m between the phreatic line and the downstream face.
81
Cont’d…
Chimney drains: is a vertical or nearly vertical drain, which is located inside the dam so
that it intercepts all layers of the dam in the seepage zone (Figure 1.19).
Thus the chimney drain prevents the emergence of the seepage water on the d/s face of
the dam even when the embankment has stratifications and some layers of high
permeability.
A chimney drain thus renders the d/s portion of the dam free from seeping water and
it increases the stability of the d/s slope. From the chimney drain, the water is carried
to the d/s toe of the dam through a horizontal drainage blanket.
82
Cont’d…
Toe drain and drainage trenches: They are used to collect the seepage from the horizontal
drainage blanket which discharge into the spillway-stilling basin or into the river channel below
the dam (Figure 1.20).
Drainage trenches can be used to control seepage where the top stratum is thin and the
pervious foundation is shallow so that the trench can be built to penetrate the aquifer
substantially. The filter comprising the drainage layers should be designed in accordance with the
filter criteria.
83
Cont’d…
Relief wells: As mentioned above, they are used for the drainage of foundation if
Relief wells are provided at or near the d/s toe of the dam to collect water
seeping through the foundation and to reduce the pore pressure in the
foundation.
Vertical sand drains (Figure1.21): These drains consist of vertical holes drilled in
in the drainage of the foundation. These also accelerate the consolidation of the
foundation soil by providing drainage.
Vertical sand drains are quite effective for the drainage of soft clay foundation,
85
3.6. Preliminary section of earth dam
It is usual practice to select a preliminary section of the earth dam and check
whether the section satisfies all the criteria mentioned in the preceding section.
86
Cont’d…
After the consideration of the above factors, a preliminary section of the earth dam is
selected.
If it does not satisfy the safety criteria, it is modified and again checked. In the preliminary
USBR (1987) provides the following formula for the determination of crest width of small dams:
The free board should be adequate against the wave action and the wind set-up.
It is assumed that the highest possible waves occur when the reservoir is full. The
free board for the wave action is generally taken as 1.5 hw where hw is the height
of the wave.
89
Cont’d…
Upstream and downstream slopes of a dam: These depend upon the type of
gained with similar dams elsewhere and to check the stability of selected slopes.
If the adopted slopes are not safe or economical, they are suitably modified.
The u/s slopes of most earth dams vary from 2.5:1 to 4:1, and d/s slopes are
steep as possible. However, from the stability considerations, the slopes should
90 not be excessively steep. Therefore, a compromise is made.
Cont’d…
Settlement allowance: Earth dams are constructed to a somewhat greater height than the
The extra height of the dam is provided in the form of a longitudinal camber over the top of
the dam.
The camber varies from zero at the abutments to a maximum value at the center of the
valley where the height of the dam is the maximum and the settlement is the largest.
91
Cont’d…
Cutoff in foundation: To reduce seepage through the foundation and to avoid piping failure,
Protection of slopes: Usual type of surface protection for the upstream slope is stone
riprap either dry dumped or hand placed. When a thin layer is used, hand riprap may be
more economical than dumped riprap.
There are several empirical methods to find out the thickness of the riprap. These methods
take into account the wave height, embankment slope, weight of average size stone and its
specific gravity.
The size of stones used for hand placed riprap may be determined with the following
formula.
92
Cont’d…
93
Cont’d…
The design of slopes of earth fill embankments depends on the nature of the
materials of construction and the type of dam (i.e., zone, homogeneous &
diaphragm).
It depends on the nature of the material used for the core and the shells and, in
94
3.7. Stability of Earth Dams
3.7.1. Stability of Slopes
The side slopes of an earth dam should be safe against shear failure. The soil mass
in an earth dam, because of its slope, is subjected to actuating (or driving) forces
which tend to cause movement (or sliding) of the soil mass.
This movement is resisted by the stabilizing (or resisting) forces, which develop at
the potential sliding surface because of the shear strength of the soil.
The side slopes of the earth dam will remain stable if the sum of the resisting
forces on every possible surface of failure (or surface of slippage) is greater than
the sum of the actuating forces.
95
Cont’d…
The Swedish circle method is one of the various methods of stability analysis of
The factor of safety is defined as the ratio of the resisting moments to the
It is also equal to the ratio of the resisting forces to the actuating forces. Thus, the
factor of safety,
96
Cont’d…
Procedure for analysis of slope stability: Consider the stability of
slopes of the earth dam shown in Figure 2.1a. To check the stability of
the slope, a trial slip surface AB is considered.
The soil mass in the trial wedge above the assumed slip surface is
(2) Cohesive force C4 acting along the curved surface, in the direction opposite
(3) Reaction R4 at the base of the slice, acting along a line inclined at an angle Φ
to the normal, where angle Φ is the angle of shearing resistance of the soil. It is
assumed that the slippage is imminent and the full shear strength of the soil has
been mobilized. Therefore, the inclination of the reaction with the normal is equal
to Φ.
98
Cont’d…
(4) The soil reactions ER and EL acting on the vertical sides of the slice exerted by
the adjacent slices on the right and left sides, respectively.
(5) The forces due to pore water pressure UL, UR and UB acting on the left face,
right face and at the base of the slice, respectively.
The force UB acts in the normal direction. In the conventional Swedish circle
method, it is assumed that the reactions ER and EL are equal and opposite and
cancel each other and do not affect the equilibrium.
Thus there are only four forces considered, viz. W4, C4, R4 and UB.
99
Cont’d…
From Figure 2.1 b,
after resolving W into its
normal and tangential
components,
N = W cos θ --------(1)
T = W sin θ ---------(2)
100
Cont’d…
Where θ is the angle, which the normal makes with the vertical.
N – UB = R cos Φ --------------------------------(3)
T – C = R sin Φ ------------------------------------(4)
101
T = (N – UB) tan Φ + c∆L -----------------------------------(5)
Cont’d…
Equation (5) indicates that the tangential component T of the weight is just balanced
by the frictional resistance (N - UB) tan Φ and the cohesion resistance c∆L.
The tangential component is the actuating force, and the frictional and cohesion
resistance are resisting forces. When the forces just balance, the failure is imminent.
For a margin of safety, the mobilization of the resisting forces should be less than
that given by R.H.S. of equation (5), which gives the maximum possible resistance.
For a margin of safety, the soil reaction R would be inclined to the normal at an angle
less than Φ. As soon as the reaction becomes inclined at an angle Φ, the maximum
resistance is developed and the failure is imminent.
102
Cont’d…
On any trial surface, the factor of safety, which is the ratio of the maximum
Forces are computed for all the slices above the assumed slip surface and the
104
Cont’d…
3.7. 2. Location of the most critical slip circle
For location of the most critical slip circle, a number of trial slip surfaces are
The circle, which gives the minimum factor of safety, is the most critical circle.
To reduce the number of trials, the Fellenius line is usually drawn (Figure 2.2).
Fellenius has shown that for a homogeneous slope, the center of most critical
105
Cont’d…
The center of most critical circle may lie anywhere on the line AB or its extension. However, its
exact position can be obtained only after conducting the stability analysis for different slip
surfaces.
The centers of the trial circles are marked as O1, O2, etc. on the line AB. The corresponding factors
of safety F1, F2, etc. are plotted at the corresponding centers as perpendicular ordinates on the line
AB.
The curve of factor of safety is obtained by joining the ends of these ordinates. The center O
corresponding to the minimum factor of safety is the center of the most critical circle.
106
Cont’d…
The above construction is for a C-Φ soil. For a purely cohesive soil (Φ = 0),
the point A itself represents the center of the most critical circle.
The Swedish circle method is used for checking the stability of the earth dam
for the following critical conditions.
(1) Stability of d/s slope during steady seepage condition
(2) Stability of u/s slope during sudden drawdown condition
(3) Stability of both slopes during construction.
107
3.7.3. Stability of downstream slope during steady seepage condition
For the d/s slope of an earth dam, the most critical condition occurs when the reservoir
is full and the steady seepage conditions have established.
A well-defined phreatic line is formed at that stage. The soil below the phreatic line is
saturated and is subjected to the pore water pressure, which reduces the effective
stresses in the soil and consequently the shear strength is also reduced
In Figure 2.3, for the computation of the weight of the soil in the strips, the moist unit
weight is taken for the soil mass above the phreatic line and the saturated unit weight
below the phreatic line.
For convenience, sometimes an average value of the unit weight is taken for the whole
slice.
For the determination of the forces ∑U due to the pore water pressure acting on the
base of the slices, the pore water pressure diagram (shown hatched) is drawn from the
flow net..
108
Cont’d…
Figure (2.3 c) shows an enlarged view of the
water pressure develops in the air as well as water voids due to compaction
carried out during construction and also because of the weight of the soil.
The pore pressures depend upon the placement water content, method of
compaction, weight of overlying layers of the soil, the rate of dissipation of the
pore pressure during construction and the rate of construction.
The slopes may fail during or just after construction if the pore pressures are
quite high. Therefore, the stability of slopes should be checked taking into account
the pore pressure developed.
111
113
114
115
116
117
118
119
120
121