Stage-1 Implementation Schedule Implementation Schedule For Akaki-Sewerage Project (Lot-1, Lot-2, Lot-3 & Lot-4)

The document outlines the implementation schedule for a sewerage project consisting of 4 lots over 44 months. Lot 1 involves the construction of sewers for the Chefe sub-catchment. Lot 2 involves construction of sewers for the Akaki sub-catchment. Lot 3 is the construction of the Chefe wastewater treatment plant, while Lot 4 is the construction of the Akaki wastewater treatment plant. Construction supervision will include monthly, quarterly, and yearly reports.

Uploaded by

Mesfin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
70 views1 page

Stage-1 Implementation Schedule Implementation Schedule For Akaki-Sewerage Project (Lot-1, Lot-2, Lot-3 & Lot-4)

The document outlines the implementation schedule for a sewerage project consisting of 4 lots over 44 months. Lot 1 involves the construction of sewers for the Chefe sub-catchment. Lot 2 involves construction of sewers for the Akaki sub-catchment. Lot 3 is the construction of the Chefe wastewater treatment plant, while Lot 4 is the construction of the Akaki wastewater treatment plant. Construction supervision will include monthly, quarterly, and yearly reports.

Uploaded by

Mesfin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

Stage-1 Implementation Schedule

Implementation Schedule for Akaki-Sewerage Project (Lot-1, Lot-2, Lot-3 & Lot-4)

IMPLEMENTATION TIME IN MONTHS


…… iii ii ii 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44

Activity name Description of activities


Fund securing
Tendering and awaerd process
(no definite time is set)

FUND SECURING
Task-1
Fund securing from donors and/or local government budget allocation

TENDERING AND AWARDING PROCESS

Task-2 Advertize the lots simeltaneously, open the tender, evaluate, award and
site hand over

CONSTRUCTION OF SEWERS FOR CHEFE SUB-CATCHMENT

Mobilization
Construction and supervision
Lot-1
Site clearing ups
Commisioning
Demobilization

CONSTRUCTION OF SEWERS FOR AKAKI SUB-CATCHMENT


Mobilization
Construction and supervision
Lot-2
Site clearing ups
Commisioning
Demobilization

CONSTRUCTION OF CHEFE WWTP


Mobilization
Construction and supervision
Lot-3
Site clearing ups
Commisioning
Demobilization

CONSTRUCTION OF AKAKI WWTP


Mobilization
Construction and supervision
Lot-4
Site clearing ups
Commisioning
Demobilization
CONSTRUCTION SUPERVISION REPORTS
Monthly reports
TASK-3 Quarterly reports

Yearly reports