Assignment CM Final PDF
Assignment CM Final PDF
1) You are given the following information about a project consisting of six activities:
A 5 months
B 1 months
C B 2 months
D A,C 4 months
E A 6 months
F D,E 3 months
(b) Find the earliest times, latest times, and slack for each activity. Which of the paths is
a critical path?
(c) If all other activities take the estimated amount of time, what is the maximum
Solution
Assignment- 2
CONSTRUCTION MANAGEMENT Ceng 5204
Step 1: E(0) = 0
Step 2:
❑ Thus, the minimum time required to complete the project is 14months since E(5) =
14months. In this case, each event had at most two predecessors.
Step 2:
❑ In this project, E(0) = L(0), E(1) = L(1),E(4) = L(4),and E(5) = L(5). As a result nodes are
in the critical path. Activities on the critical path include A (0,1), E (1,4) and F (4,5).
FF(i.j) = E(j)-E(i)-Dij
Assignment- 2
CONSTRUCTION MANAGEMENT Ceng 5204
0
IF(i.j) =
E(j) - L(i) - Dij
A : IF (0,1) = 5 - 0 - 5 = 0
B : IF(0, 2) = 1 - 0 - 1 = 0
C : IF (2,3) = 5 - 5 - 2 = 0
D : IF (3,4) = 11 - 7 - 4 = 0
E : IF(1,4) = 11 - 5 - 6 = 0
F : IF(4,5) = 14 - 11 - 3 = 0
A: L(1)-E(0)-D01= 5-0-5 = 0
B: L(2)-E(0)-D02= 5-0-1 = 4
C: L(3)-E(2)-D23= 7-1-2 = 4
D: L(4)-E(3)-D34= 11-5-4 = 2
E: L(4)-E(1)-D14= 11-5-6 = 0
F: L(5)-E(4)-D45= 14-11-3 = 0
Assignment- 2
CONSTRUCTION MANAGEMENT Ceng 5204
The maximum amount of time that you can delay an activity D ad still finish the project in
shortest time possible is 2months. Delaying an activity D more than 2months will delay
entire projects.
building project. Bill has determined that five tasks would need to be performed to carry
out the project. Using the PERT three-estimate approach, Abera has obtained the
estimates in the next table for how long these tasks will take. Also shown are the
Time Required
There is a penalty of Birr 500,000 if the project is not completed in 11 weeks. Therefore,
Abera is very interested in how likely it is that his company could finish the project in
time.
(b) Find the estimate of the mean and variance of the duration of each activity.
(d) Find the approximate probability of completing the project within 11 weeks.
(e) Abera has concluded that the bid he would need to make to have a realistic
chance of winning the contract would earn AKcon. Construction a profit of about birr
Assignment- 2
CONSTRUCTION MANAGEMENT Ceng 5204
250,000 if the project is completed within 11 weeks. However, because of the penalty for
missing this deadline, his company would lose about birr 250,000 if the project takes more
than 11 weeks. Therefore, he wants to place the bid only if he has at least a 50 percent
to 4tm tp
te
6
Standard deviation (te)
tp to
te
6
Variance ()
te 2
Time Required
Average
Immediate Optimistic Most Likely Pessimistic
Task duration Variance(2)
Predecessors Estimate Estimate Estimate
time(Te)
(Week) (Week) (Week)
A 3 4 5 4 0.111
B A 2 2 2 2 0
C B 3 5 6 4.83 0.25
D A 1 3 5 3 0.444
Assignment- 2
CONSTRUCTION MANAGEMENT Ceng 5204
Step 1: E(0) = 0
Step 2:
❑ Thus, the minimum time required to complete the project is 10.83 weeks since E(4) =
10.83 weeks. In this case, each event had at most two predecessors.
Step 2:
j = 2 : L(2) = Min { L(3) - D23, L(4) - D24 } = Min {7.66 - 0, 10.83 - 4.83} = 6
Assignment- 2
CONSTRUCTION MANAGEMENT Ceng 5204
From calculated earliest time E(ij) and latest time L(ij) for all activities critical
path is A-B-C with a project duration of 10.83 weeks
Where,
The probability of completing project within 11 weeks is given by, P(Z< Zo)
To find Zo
TS TE
Zo
11 10.83
Zo 0.283
0.6008
P=61.31%
Since probability of project completion on 11 weeks is more than 50%; Ato Abera ,
president of AK con Construction Company, should submit a bid contract to earn 250,000
birr profit.
Assignment- 2
CONSTRUCTION MANAGEMENT Ceng 5204
Z scores
0.0 0.50
Assignment- 2