Introduction of A New Metric "Project Health Index" (PHI) To Successfully Manage IT Projects
Introduction of A New Metric "Project Health Index" (PHI) To Successfully Manage IT Projects
www.emeraldinsight.com/0953-4814.htm
Project Health
Introduction of a new metric Index
“Project Health Index” (PHI) to
successfully manage IT projects
Jayaraman Rajagopalan 385
Department of Operations and Supply Chain Management,
Received 24 December 2016
SP Jain Institute of Management and Research, Mumbai, India, and Revised 29 April 2017
Praveen Kumar Srivastava 30 May 2017
13 July 2017
SP Jain Institute of Management and Research, Mumbai, India Accepted 13 September 2017
Abstract
Purpose – The purpose of this paper is to develop a new comprehensive metric to successfully plan and
execute IT projects. The development will be based on a study of all the variables that go into making a
successful IT project.
Design/methodology/approach – A questionnaire, containing qualitative and quantitative response
questions, to gather data from practicing project managers is designed and used in an IT company.
Cronbach’s alpha is used to analyze the data and multiple regression is used to find the equation relating
project success to project management success.
Findings – A comprehensive variable called Project Health Index (PHI) has been identified. Using this
variable, one can predict whether a project is likely to succeed or not. This comprehensive, composite variable
is calculated by using 17 other project-related metrics identified from the responses to the questionnaire.
Research limitations/implications – The PHI has been calculated for the company studied. However,
more studies need to be performed before it can be established that the PHI can also be used in other
companies and projects. What has been established and validated is that PHI can be used in the studied
company and that the methodology to calculate PHI is valid.
Practical implications – The PHI can be used as a predictive variable, i.e. one that can be used to take
corrective and preventive actions to make a project successful. The PHI can also be used to allocate resources,
prioritize the allocation and improve project management during the course of project execution.
Social implications – By implementing projects efficiently, resource utilisation increases and leads to waste
avoidance. Improved sustainability is the end result.
Originality/value – The work is original. The contents and the conclusions drawn, as well as the use of the
PHI will enable IT companies to implement projects efficiently, reduce cost and enhance profit.
Keywords Interviews, Questionnaire, Best practices, Nine knowledge areas of PMI, Project Health Index,
Project Management Institute (PMI), Three bands
Paper type Research paper
1. Introduction
According to Forrester Research, global spending on information technology (IT) was
expected to rise to 6.2 percent, i.e. US$2.22 trillion in 2014, and the growth was likely to
quicken in 2015 by 8.1 percent (Kanaracus, 2014). India, being a major IT hub, was expected to
contribute to the underpinnings of this growth. NASSCOM, the national trade association of
Indian IT and information technology enabled services (ITES) industry expected the domestic
IT sector to grow from 12 to 14 percent, while IT exports were likely to reach US$86 billion in
2014-2015 by adopting new technologies and entering into new geographies (Bhoola, 2015).
IT companies around the world deploy project management practices, such as discussions
with customers to understand their requirements, design systems and software configurations;
develop applications software using computer languages like Java and C+; test the developed
Journal of Organizational Change
applications in-house and also with the clients; and then deliver the output. Additional services Management
which are performed after the system has been installed can also be part of the project. Vol. 31 No. 2, 2018
pp. 385-409
These services can include operations of the system, refinement of the developed product, © Emerald Publishing Limited
0953-4814
correcting any errors found and soliciting customer feedback. In order to carry out these DOI 10.1108/JOCM-12-2016-0301
JOCM activities, IT companies recruit, train, deploy teams, provide hardware resources like buildings,
31,2 power connections, uninterrupted power supply devices for uninterrupted and stable power
supply, supervise the work, co-ordinate the team interfaces, provide in-house testing facilities
and take care of other team requirements. They also deploy marketing teams to solicit and
obtain orders; define the requirements to the software teams; act as an interface with the clients
to seek and clarify issues arising periodically during project execution.
386
2. Purpose and basis of this research
In the IT industry, a “successful project” is the one which not merely delivers on time and
under budget, but also ensures the ease of operation by the client, ease of maintenance of the
software and meets the expectations of the customer in his environment on an on-going
basis. Needless to say, every IT company desires that all its projects are successful.
The design and delivery of products and services of an IT company is a much
researched and developed subject. For example, the “waterfall” model has been replaced
with “scrum.” Using lean and waste reduction methodologies, many efficiency
improvements have been achieved. While these methods are useful at the aggregate
level, the knowledge of the details which make up for the aggregate, such as, deployment
of a highly skilled, trained and competent workforce, team work, accurate scoping and
scope management and use of appropriate “best practices,” well-designed processes and
continuous improvement, will provide an IT company with the abilities to deliver
“successful projects.” The business excellence (BE) literature emphasizes that the trio of
“enablers-processes-results” is the modern way to run successful companies (Baldrige
Model for Performance Excellence, 1987, and European Foundation for Quality
Management, 1989). Therefore, our research was designed to identify the “enablers,”
the factors, as aforementioned, which make for successful project management in the IT
company that we studied. Doing so will enable the company to sharpen its project
management practices and compete on the basis of customer delight.
In our research, we have adopted a unique method using a newly defined composite
variable called “Project Health Index” (PHI). The PHI serves multiple purposes and could be
developed into a very powerful tool for refining project management practices in an IT
company and, in the larger context, for all projects. First, the composition of the PHI will
indicate the relative importance of the various project management factors. Second, the value
of PHI will indicate whether a given project will be successful or not. Third, the value helps
compare different projects on the factors that govern successful project management which
can then be used for “post-project completion” analysis. Many companies use the results of
such analyses to make improvements. Other reason for innovating this methodology was to
develop a “user friendly and actionable” decision tool. In a binary method, such as 0/1, there is
no middle ground. While this is appropriate for technological fields, such as electronics, this
may not be suitable for industrial situations, especially manual-oriented project management
situations. A PHI-like tool gives some flexibility in the final value and also in the selection of
the decision variables which make-up the PHI.
In order to provide a basis for calculating the PHI, we describe a case study
using a questionnaire and structured interviews followed by analyses performed in a
Tier-2 IT company in India. We demonstrate how PHI can be calculated and how it
can be used for a successful IT project management. We have used the nine knowledge
areas framework of the PMI to substantiate the validity of using a decision variable such
as PHI, showing how the direction in which PHI moves based on the values of the
variables comprising the PHI is completely aligned with the way the PMI framework
would expect. We discuss the attributes and the usefulness of PHI as a comprehensive
decision variable. We finally offer suggestions for ways in which this work can be
extended and enhanced in the future.
3. IT project risk management literature survey Project Health
A large number of IT projects fail and are never brought to completion. According to a Index
comprehensive report by (The) Standish Group (1999) that presents data on 23,000 IT projects
from 1994 to 1998, 31 percent of IT projects failed in 1994, 40 percent were unsuccessful in
1996 and 28 percent were canceled in 1998 (quoted from Chulkov and Desai, 2005; Jake, 2008,
Standish Group Report, 1995). The report estimates the cost of canceled IT projects in 1998
alone to reach $75 billion. The failure rate of large IT projects with budgets exceeding 387
$1 million was found to be almost 50 percent higher than for the projects with budgets below
$350,000 (Gartner Study and Gartner Report, 2012). The reasons why IT projects fail are
reported in Gartner Study and Gartner Report (2012) study and are shown in Figure 1.
Several researchers have identified the factors that affect the success of software projects
(Ropponen and Lyytinen, 2000; Palitha et al., 2002; Keil et al., 2004; Baccarini et al., 2004;
Athreye, 2005; Bannerman, 2008; Aundhe and Mathew, 2009; Raghu Raman et al., 2007;
Chui-Ha Ng et al., 2013). Pictorially, the effect of impact and probability of risks that arise in
a software project can be visualized, as shown in Figure 2.
For software projects, the risk profiles will depend on the importance of the project to the
client. For example, the SAP type of projects, due to their comparatively higher degree of
complexity arising from their multiple connectivities, greater efforts to customize, longer
gestation periods to install, and difficulty in integrating with company operations, have to
be handled with greater care. Similarly, software projects which develop application
software to run supervisory control and data acquisition devices and automated production
facilities like a pharma tablet production line, a biscuit manufacturing line, a coupled
tandem cold rolling mill are fraught with high risks due to the sensitivity of the technologies
involved, scale of operations, high-speed working of the lines, the large volumes of output
and flexibility expected from these operations. Dey et al. (2007) mentioned that the success of
software development depends on the following criteria: functionality, quality and
timeliness. They also aver that very little work has been done in order to involve all the
concerned stakeholders in managing risk and integrating the risk management process with
a holistic project management approach.
Boehm (1991) identified ten types of risks and several types of cost drivers in software
projects. Together, these give an idea of how risks and costs in a software project are
intertwined. The top ten risk items are as follows: personnel shortfall, unrealistic schedules
Percentage of respondents
100 7
8 6
90 11
12
17
80
12
70 Other reasons
16
60 24 Poor quality
22
14 Canceled after launch
50
High cost variance
40 Substantially late
24 28
23
30 Functionality issues
20
22 24 22
10
Figure 1.
0
Small IT projects Medium IT projects Large IT projects Reasons why IT
projects fail
Source: Gartner Study and Gartner Report (June 2012)
JOCM Residential High cost, large, high
31,2 complexes in new technology/unproven
areas, cinemas, low /new technology
to medium cost projects, projects to
projects, projects produce new products
financed by a group (e.g. integrated
High
of individuals/ steel plant, oil
388 Probability of risk organisations refinery, off shore oil
(e.g. new airports, rig, telecom), IT
retail stores) projects
and budgets, developing the wrong user interface, gold plating, continuing stream of
requirements changes, shortfalls in externally furnished components, shortfalls in
externally performed tasks, real-time performance shortfalls and straining computer
science capabilities. It is not surprising that the first item of risk that Boehm has identified is
related to personnel, which is the key in IT projects. However, Bannerman (2008) cautioned,
quoting from several studies, that risk identification exercises do not always throw up the
same results. For example, Ropponen (1999) re-ranked Boehm’s (1991) list of risk factors in a
different cultural context at a different time and found significantly different rankings. Only
three of the ten were ranked the same and Boehm’s highest ranked item was placed seventh
in the Ropponen’s list (Bannerman, 2008).
Overall, studies in risk identification and mitigation do not emphasize the critical role
played by team work and motivation levels in a project or the methods used – especially
“best practices“ – that need to be used to promote team work. Such best practices can be
either derived from the literature based on the data and knowledge collected by various IT
companies or can be found from the specific project practices in an IT company executing
IT projects. We postulate that it is better to identify such best practices from each
company’s experience and culture rather than pick them up from databases.
7. Research methodology
Following steps were taken to conduct the study. It was decided to conduct both a
qualitative and quantitative study. Accordingly, a questionnaire was prepared (see the
Appendix) to be used for a survey of selected project managers. Cronbach’s α (Santos, 1999
and Lee Cronbach, 1951) was found to be 0.783, confirming that the data gathered can be
used for measuring the parameters that we set out to study.
The questionnaire prepared was based on a literature review of lean methodology, project Project Health
management and agile methodology as well as a review of the implementation of lean in Index
Wipro and other organizations. In all, 40 questions were included, each one covering a specific
area of work. Of these, 37 questions asked for a scale response between 1 and 5 ( from 1 being
“never” to 5 being “constantly”). There were sub-questions and three questions which were
qualitative in nature for which responses could be descriptive. Responses to these qualitative
questions were used to perform qualitative analysis. In total, 30 projects were selected for 391
specific study and one of the authors interviewed each project management involved in each
of the 30 projects. Project managers of development, enhancement and maintenance projects
of different vertical business units across the organization were interviewed in-person.
For quantitative questions, project managers were asked to rate different parameters of
project execution on a scale of 1 to 5, as shown in Table I.
The survey response data were analyzed to find correlations between variables and their
impact on each other and PHI (the composition of what is PHI will be detailed further on).
Responses to qualitative questions were analyzed to know how different types of tasks are
executed by project managers from which best practices were culled out.
Highly correlated variables, identified through a process of multiple regression, have
been selected to calculate PHI. The equation derived to calculate PHI is as follows:
PHI ¼ 27:5771:975 a4_res_after_proj_billing_date_rate 1:889 c4
_project_delayed_right_resþ1:044 a7_review_session_planned0:859
a13_rework_coding_cust_change_req_rate0:780 a14_info_loss_onsite
_offshore_rate þ1:364 a15_team_meeting_rate2:478 b16_miss_requirement
Scale Description
Table I.
1 Never Scale on which project
2 Rarely manager is asked to
3 Occasionally rate different
4 Regularly attributes of project
5 Constantly delivery
JOCM (6) formal training for business; and
31,2 (7) core resources allocated to project.
Communication:
(1) loss of requirement from onsite to offshore;
(2) frequency of team meetings;
392
(3) confidence on team knowledge;
(4) frequency of client communications; and
(5) understanding of customer business pain points.
Scope:
(1) rate of missing requirement;
(2) rework due to change in customer requirement; and
(3) customer asks extra feature.
Best practices:
(1) gather and implement lessons learnt; and
(2) revisit best practices.
The basis of selecting these variables is shown in Tables II-IV.
Using the equation, the value of PHI for each of the 30 projects was calculated and
plotted as shown in Figure 3.
PHI ranges from 31 to 64. Then, projects were categorized into three parts based on PHI
using following criteria (Table V ).
The methodology shown in Table V is called the “three bands” comparison approach.
Many research workers use the two set comparisons (e.g. Collins, 2001); however, we have
chosen the three bands concept which has proven to be very useful in our study. We believe
Unstandardized Standardized
coefficients coefficients
Model B SE β t Sig.
Model summary
393
Model R R2 Adjusted R2 SE of the estimate
ANOVA
Model Sum of squares df Mean square F Sig.
4
Frequency
1
Mean = 48.87
SD = 7.324
n = 30
Figure 3.
0
Project health vs
30 40 50 60 70 projects
Project health
JOCM 8. How to use the PHI
31,2 First, one must calculate the value of PHI, as shown in Equation (1). Then, the applicable
rule is: if PHI ⩽ 48.87−7.32 ¼ 41.55, then the project is likely to be less successful. If the value
of PHI is ⩾ 48.87+7.32 ¼ 56.19, then the project is likely to be a more successful project.
In between, that is, 41.55 oPHI o56.19, the project is likely to be successful. In practice, the
reasons why a project is likely to be successful could encompass a gamut of activities and
394 the PHI is truly reflective of this composite/comprehensive nature of the underlying
phenomena. That is the strength of the PHI.
We have checked literature on non-IT project management and found that such an
approach (i.e. the three band approach) has not been used (see, e.g. Odeyinka and Yusif,
1997; Assaf and Al-Hejji, 2006; Faridi and Sageh, 2006; Murali and Soon, 2007; Abd El-Razek
et al., 2008; Salama et al., 2008; Challal and Tkiouat, 2012; Marzouk and El-Rasas, 2014;
Ruqaishi and Bashir, 2015).
Projects Criteria
9.2 Validation of PHI through alignment with the nine knowledge work areas of PMI
The basis for validation of PHI is that the factors included in the PMI nine knowledge
areas framework (excluding the last one – procurement – which is not relevant in an IT
project implementation) (http://getpmpcertified.blogspot.in/2011/05/chapter-7-project
management-knowledge.html, Guide to the PMBOK and https://certifedpmp.wordpress.
com/2008/09/18/summary-of-project-management-knowledge-areas/) and those used to
calculate PHI are fully aligned, in content and direction. That is to say, all the factors that
form a part of PHI can be linked and identified (or mapped) to be a part of the PMI
knowledge areas, and the way in which they move will affect the project success in the
same way.
9.2.1 People management. In a Tier-2 IT service organization, people management is one
of the most important project management activities done by the project managers.
Resource allocation. “Associates ramp up and ramp down” are normal phenomena and
have a significant impact on the successful delivery of projects. Our study shows that MSPs
take lesser time to ramp up a new joinee. In a similar fashion, there is lesser ramp down in
MSPs compared to LSPs. It is to be noted that attrition is the major cause of ramp down,
which means that MSPs are able to retain team members more than LSPs. MSPs are also
able to manage to allocate resources on time (see Figure 4).
However, it is interesting to note that both MSPs and LSPs are unable to manage project
timeline due to the unavailability of the right resource. In such scenarios, team members
stretch to deliver the projects on time.
Training. MSPs give more importance to business and technical training and, in turn,
face less business and technical challenges. In fact, MSPs conduct more business domain
training than LSPs. In total, 78 percent of LSPs confirm that the main reason of bug
introduction is due to the issues in understanding (lack of ) of business domain.
Resourcing
4.9
4.1
5.0
3.0 2.9 3.1 2.8
4.0 2.4
3.0 1.7 1.7 1.9
2.0
1.0
0.0
Week needed Resource Days wait to Project Resource ramp
to ramp up allocation after get new delayed due to down
new joinee project start resource unavailability
date of right
Figure 4.
resource
Attributes of
resourcing
More successful projects Less successful projects
JOCM Understanding of business domain helps a developer to understand the project end-to-end
31,2 and leads to fewer bug introduction and successful delivery on-time. It also helps to improve
productivity of developers (Figure 5).
In a low-performing project, more than a three-quarter of bugs are due to the issues in
understanding of business domain (also supported by Hadaya et al., 2012). MSPs conduct
more detailed training of applications than LSPs, which includes detailed walk-through of
396 the project (Figure 4). It also includes walk-through of non-functional requirement of the
projects, such as performance, document requirement, etc. As shown in Table VI, it has been
observed that the projects that conduct detailed walk-through are able to reduce the ramp
up duration of new joinees to three to four weeks.
Subject matter expert (SME)/core resources. High dependency on core resources leads to
low PHI (also supported by Athreye, 2005). It is identified that LSPs have more SMEs and
are more dependent on SMEs compared to MSPs. On an average, MSPs have 33 percent
SMEs, whereas LSPs have around 50 percent SMEs. At the same time, MSPs need less time
to build new SMEs. MSPs require less than six months to prepare SMEs, and LSPs require
more than seven months (see Figure 6).
Motivation. In the software service industry, the motivation of team members is very
important and plays a key role in the successful delivery of the project. Our study identifies
that the activities, as shown in Table VII, impact the motivation of team members in either a
positive or negative manner.
For example, activities, such as delivery of a project on time, which impact project
execution in a positive manner also help to improve the motivation. On the other hand,
factors like requirement miss and escalation from client lower the motivation of the team.
4.7
5.0 3.8 4.1
Figure 5. 3.7 3.7
Detailed walk-through 4.0 2.7
2.6 2.3
to new joinee, 3.0 2.0 1.9
business domain 2.0
challenges faced ,
business training, 1.0
technical challenges 0.0
faced and technical Detailed Business Business Technical Technical
training – comparison walk domain training challenge training
between LSPs through to challenge scheduled faced scheduled
and MSPs new joinee faced
More successful projects Less successful projects
Table VI.
Relationship between
ramp up duration and
detailed walk-through
of new joinee
5.0
29.8
30.0 Project Health
Index
4.2
23.1 25.0
4.0
3.6 Dependent on core
20.0
resource
Figure 6.
1.0 0.0 Attributes of core
More successful Less successful resources
projects projects
4.0 3.9
3.8
4.0
3.2
3.0
3.0
398 2.6
2.0 1.9
2.0 1.6
Figure 7. 1.0
Attributes of Relationship Info loss → Frequency of Communication Receive Know customer Knowledge
communication with client onsite to team meeting with client escalation from business pain transfer to
management offshore client point stakeholder
More successful project Less successful project
Missed deadline
71%
80%
56%
60%
33% 29%
40%
11%
20% 0%
0%
Figure 9. Never Rarely Regularly
Missed deadlines
More successful projects Less successful projects
2.0 399
1.0
0.0
Stretch in office Allocation based on Figure 10.
task complexity Stretch and allocation
of resources
More successful project Less successful project
compared with LSPs. Overall, a small improvement in each factor of project delivery helps
projects to become more successful (Figure 11).
9.2.5 Scope management. Our study shows that MSPs perform better in all four major
parameters of scope management, as shown in Figure 12. There is a marginal difference in the
performance for the estimation changed by customers, when both types of projects are
compared. Rework due to change from customer is less than half for MSPs than that of LSPs.
In a similar way, in MSPs, clients ask less extra features and also have less requirement misses.
4.9
5.0 4.4 4.3
4.1
3.6 3.4 3.4 3.3
4.0
3.0 2.3
2.0 1.9
2.0 1.3
1.0
0.0
Planned Rework Causal Extra Lession Revisit best
review after coding analysis features learnt practice
Figure 11.
session and analysis provided to documented
Quality management
customer
in IT projects
More successful projects Less successful projects
5.0
3.8
4.0 3.3
1.0
Estimation Requirement Client asks Figure 12.
Rework due to
changed by miss extra feature Project scope
change from
customer management
customer
parameters
More successful projects Less successful projects
JOCM Estimation. The estimation of project requirement is one of the most challenging activities in
31,2 project execution. Proper project planning and control is not possible without an accurate
and reliable estimate. It is important that both project team and client agree on the estimate.
More than 50 percent of projects use standard methodology (Excel sheet) and around
28 percent of projects use Work Breakdown Structure to estimate the scope. However,
17 percent of projects (almost all of them new engagements) use ballpark/experience/gut
400 feel. Project managers should avoid gut feel or only experience to estimate the project, as it
leads to errors and the process cannot be re-used. High training in business domain results
in less rework (also seen in Bloch et al., 2012).
As per response of the project managers, estimation changed by a client is rare but a few
reasons were highlighted by them: estimation was done without understanding the
requirement of the project properly, complexity (non-functional requirement) was not taken
into account for estimation, and pressure from the client to reduce the effort and scope
increases/decreases after initial estimation of the project.
9.2.6 Risk management. Although attrition is one of the major risks in a Tier-2 IT
organization, MSPs are able to manage it better by continuous cross-training and reverse
KTs compared to LSPs. Common risks and corresponding mitigation identified for project
execution are enlisted in Table VIII.
9.2.7 Cost management. In the IT service industry, the cost of a project is mainly related
to the cost of associates working in it. Every project management tries to save money
through better execution. Our study shows that there is no major difference between the
initiatives taken by MSPs and LSPs to reduce the cost of their projects (Figure 13).
1 Attrition Mainly impact small teams, where it is difficult to create backup. Cross-
training and creating backup help to mitigate attrition
2 Business knowledge of Reverse KT helps to identify and minimize the gap in understanding of
developer business domain
3 Unplanned leave Store the code at centralized location and always have a backup of the
associates
4 Dependency on cross flow Keep client aware about dependency on cross flow team.
team Must have basic understanding and details of touch points of cross flow
domain
5 Lack of scope Use query tracker to clarify scope in detail
Table VIII. understanding Use Request Traceability Matrix (RTM)
Risk management 6 Issue due to onsite- Formal communication to transport the requirement
in IT projects offshore communication 15-minute daily standing meeting avoids communication issues
5.0
3.4 3.2
4.0
3.0
2.0
Figure 13. 1.0
Cost management Initiative to reduce cost of the project
in IT projects
More successful projects Less successful projects
9.2.8 Project integration management. Quantitative analysis suggests that a few factors Project Health
work together and have a major impact on the other factors of project execution (Table IX). Index
Identification of best practices. Based on the above analysis, few best practices have been
identified. These are shown in Table X.
10. Conclusions
Our study, conducted in a Tier-2 IT firm in India, reveals that there are many factors that 401
affect the success of projects. We have innovated and used a new methodology to compare
and contrast the factors responsible for project success by using a “three bands” framework
where the three bands consist of: LSP, SP and MSP. We believe that this is a unique
methodology which may help future projects benefit in identifying the “best practices.”
We have also introduced a new parameter to signify a holistic approach to measure
project success, in contrast to the traditional view of “time” and “cost” as the sole criterion.
The PHI performs two functions: first, it indicates whether a project is an SP, LSP
or an MSP; and second, what can be done to improve the PHI value. Thus, the PHI is a
composite/comprehensive multivariate decision variable which can be used as a
progress monitor and as a basis for CAPA (corrective and preventive actions, in the
ISO 9000 terminology).
In our study, we have identified “best practices” which are suited to the company that we
studied. We believe that while some generic factors may be involved in determining the
success of IT projects, there could be specific factors which could affect the success in
certain situations obtained in different IT companies. We believe that such an approach may
be more beneficial to IT companies than merely adopting/adapting generic best practices.
Companies should also identify their in-house best practices and use them further for their
commercial interests.
Correlation within
Component Factors variables Comment
Customer Receive escalation from client 0.87 Increase in team ramp down (attrition),
escalation Ramp down of team 0.80 stretch to deliver project, allocation of
Stretch in office to meet 0.74 resource after project billing start date and
deadline customer asking extra features may lead
Resource allocation after 0.70 to customer escalation
billing start date
Customer asks extra 0.63
Resource Frequency of team meeting 0.88 Increase in frequency of team meeting,
dependency Tasks allocation based on 0.86 allocating tasks after analyzing
complexity complexity, detailed walk-through to new
Detailed walk-through 0.80 joinee reduce dependency on core
Dependency on core resource −0.62 resources
Project cost Reduce cost 0.80 Reduction cost of project leads to increase
optimization Communication with client 0.70 in communication with client, business
Business challenge faced 0.62 challenge and dependency on core
Dependency on core resources 0.60 resource increases
Capability Technical training 0.79 Increase in technical and business domain
impact Business training 0.72 training lead to reduction in extra features
Client asks extra feature −0.59 requested by client and rework due to
Rework due to client change −0.53 customer change request
request Table IX.
Confidence Functional awareness 0.85 Increase in functional awareness may lead Parameters relevant to
on team Confidence on team 0.84 to increase in confidence of project project integration in
management on team IT projects
JOCM Area of knowledge
31,2 management according to PMI Best practices identified in the IT project that was studied by us
Project integration Involve support department, mainly practice, RMG, talent acquisition,
management training, human resource department for project kick off
Scope management Prefer 15-minute daily standing meeting than that of long meeting
Use of Query tracker and Requirement Traceability Matrix helps to reduce
402 requirement miss and request by customer for extra features
Onsite should also convey why to do along with what to do
Cost management Analyze risk on continuous basis. Communicate to manager/client with
mitigation plan at earliest
Always update your assumptions
Time management Automate the process, wherever possible to speed up task by reducing
manual work
Use Work Breakdown Structure to identify small component.
Allocate task based on complexity of tasks and experience of resource
Treat change request as new project and plan separately
Human resources management Cross-train/rotate resources across modules/project
Plan and groom the resources by cross-training, resource rotation across
module/shores, mentoring, providing KT by recorded session for application
and at last giving freedom to appropriate decisions
Motivate your resources on continuous basis, as it impacts each and every
factor of project delivery
Assign challenging work to resources, as it is one of the best non-monitory
methods to motivate resources in short duration
Communication management Prefer 15-minute daily standing meeting than that of weekly long meeting
Onsite should also convey business justification along with what to do
Be aware of client’s business pain point, as it is area of opportunity
Risk management Analyze risk on continuous basis. Communicate to manager/client with
mitigation plan at earliest
Always update your assumptions and risk register
Quality management Plan all review activities in project schedule. Capture defects and analyze the
Table X. root cause
Best practices Minimum 60% of UT cases should be written before development
identified from this UT must be either automated or done by peer, preferably junior resources in
study in IT project the team
management Tasks of more than 40 hours should be reviewed by SMEs
References
Abd El-Razek, M., Bassioni, H. and Mobarak, A. (2008), “Causes of delay in building construction
projects in Egypt”, Journal of Construction Engineering and Management, Vol. 134 No. 11,
pp 831-841, 10.1061/(ASCE)0733-9364(2008)134:11(831).
Assaf, S.A. and Al-Hejji, S. (2006), “Causes of delay in large construction projects”, International Journal
of Project Management, Vol. 24 No. 4, pp. 349-357.
Athreye, S. (2005), “The Indian software industry and its evolving service capability”, Industrial and
Corporate Change, Vol. 14 No. 3, pp. 393-418.
Aundhe, M.D. and Mathew, S.K. (2009), “Risks in offshore IT outsourcing: a service provider
perspective”, European Management Journal, Vol. 27 No. 6, pp. 418-428.
Baccarini, D., Salm, G. and Love, P.E.D. (2004), “Management of risks in information technology Project Health
projects”, Industrial Management & Data Systems, Vol. 104 No. 4, pp. 286-295. Index
Baldrige Model for Performance Excellence (1987), available at: www.nist.gov/baldrige (accessed
February 21, 2018).
Bannerman, P.L. (2008), “Risk and risk management in software projects: a reassessment”, The Journal
of Systems and Software, Vol. 81 No. 12, pp. 2118-2133.
Bhoola, V. (2015), “Impact of project success factors in managing software projects in India: an 403
empirical analysis”, Business Perspectives and Research, Vol. 3 No. 2, pp. 109-125, © 2015 KJ
Somaiya Institute of Management Studies and Research, SAGE Publications.
Bloch, M., Blumberg, S. and Laartz, J. (2012), “Delivering large-scale IT projects on time, on budget, and
on value”, Tel Aviv, Düsseldorf, Berlin, October, available at: www.mckinsey.com/business-
functions/digital-mckinsey/our-insights/delivering-large-scale-it-projects-on-time-on-budget-
and-on-value (accessed February 22, 2018).
Boehm, B.W. (1991), “Software risk management: principles and practices”, IEEE Software, Vol. 8 No. 1,
pp. 32-41.
Chacko, G.K. (2004a), “WIPRO: from coding to consulting: a case study”, Management Research News,
Vol. 27 No. 7, pp. 63-95.
Chacko, G.K. (2004b), “Infosys: new game new rules: a case study”, Management Research News,
Vol. 27 Nos 8/9, pp. 1-25.
Challal, A. and Tkiouat, M. (2012), “Identification of the causes of deadline slippage in construction
projects: state of the art and application”, Journal of Service Science and Management, Vol. 5,
pp. 151-159, available at: http://dx.doi.org/10.4236/jssm.2012.52019; www.SciRP.org/journal/jssm
Chandra, A., Fealey, T. and Rau, P. (2006), “National barriers to global competitiveness: the case of the
IT industry in India”, Competitiveness Review: An International Business Journal, Vol. 16 No. 1,
pp. 12-19.
Chui-Ha Ng., Walker, D.H.T. and Levin, G. (2013), “IT project management capabilities enhancement
impacts of contingent employment policy in Hong Kong organisations”, International Journal of
Managing Projects in Business, Vol. 7 No. 1, pp. 144-157.
Chulkov, D.V. and Desai, M.S. (2005), “Information technology project failures”, Information
Management & Computer Security, Vol. 13 No. 2, pp. 135-143.
Collins, J. (2001), Good to Great, Random House Business Books, London.
Dey, P.K., Kinch, J. and Ogunlana, S.O. (2007), “Managing risk in software development projects: a case
study”, Industrial Management and Data Systems, Vol. 107 No. 2, pp. 284-303.
European Foundation for Quality Management (1989), available at: www.efqm.org (accessed
February 21, 2018).
Faridi, A.S. and Sageh, S.M.E. (2006), “Significant factors causing delay in the UAE construction
industry”, Construction Management and Economics, Vol. 24, pp. 1167-1176.
Gartner Study and Gartner Report (2012), available at: https://thisiswhatgoodlookslike.com/2012/06/
10/gartner-survey-shows-why-projects-fail/ (accessed February 21, 2018).
Hadaya, P., Cassivi, L. and Chalabi, C. (2012), “IT project management resources and capabilities: a
Delphi study”, International Journal of Managing Projects in Business, Vol. 5 No. 2, pp. 216-229.
Ilavarasan, V. (2007), “Is Indian software workforce a case of uneven and combined development?”,
Equal Opportunities International, Vol. 26 No. 8, pp. 802-822.
Jake, W. (2008), “IT’s biggest project failures – and what we can learn from them”, available at: www.
computerworld.com/article/2533563/it-project-management/it-s-biggest-project-failures——and-
what-we-can-learn-from-them.html?page=4 (accessed February 21, 2018).
Kanaracus, C. (2014), available at: www.channelworld.in/news/global-it-spending-outlook-better-
subpar-2014-forrester-says (accessed February 21, 2018).
JOCM Keil, M., Smith, H.J., Pawlowski, S. and Jin, L. (2004), “ ‘Why didn’t somebody tell me?’: Climate,
31,2 information asymmetry, and bad news about troubled projects”, The Database for Advances in
Information Systems, Vol. 35 No. 2, pp. 65-84.
Lacity, M.C. and Rottman, J.W. (2009), “Effects of offshore outsourcing of information technology work on
client project management”, Strategic Outsourcing: An International Journal, Vol. 2 No. 1, pp. 4-26.
Lee Cronbach, J. (1951), “Coefficient alpha and the internal structure of tests”, Psychometrika, Vol. 16
No. 3, pp. 297-334.
404
Marzouk, M.M. and El-Rasas, T.I. (2014), “Analyzing delay causes in Egyptian construction projects”,
Journal of Advanced Research, Vol. 5 No. 1, pp. 49-55, doi: 10.1016/j.jare.2012.11.005.
Murali, S. and Soon, Y.W. (2007), “Causes and effects of delays in Malaysian construction industry”,
International Journal of Project Management, Vol. 25, pp. 517-526.
Odeyinka, H. and Yusif, A. (1997), “The causes and effects of construction delays on completion cost of
housing projects in Nigeria”, Journal of Financial Management of Property and Construction,
January, pp. 31-43.
Palitha, R.K., Mandal, P. and Smith, R. (2002), “IT project implementation strategies for effective
changes: a critical review”, Logistics Information Management, Vol. 15 No. 2, pp. 126-137.
Raghu Raman, S., P., Budhwar and Balasubramanian, G. (2007), “People management issues in Indian
KPOs”, Employee Relations, Vol. 29 No. 6, pp. 696-710.
Ropponen, J. and Lyytinen, K. (2000), “Components of software development risk: what influences it – a
project manager survey”, IEEE Transactions on Software Engineering, Vol. 26 No. 2, pp. 98-112.
Rosacker, K.M. and Rosacker, R.E. (2010), “Information technology project management within public
sector organizations”, Journal of Enterprise Information Management, Vol. 23 No. 5, pp. 587-594.
Ruqaishi, M. and Bashir, H.A. (2015), “Causes of delay in construction projects in the oil and gas industry in
the Gulf cooperation council countries: a case study”, Journal of Management in Engineering, Vol. 31,
available at: file:///C:/Users/Ja/Downloads/Most%20Important.pdf (accessed December 18, 2015).
Salama, M., El Hamid, M.A. and Keogh, B. (2008), “Investigating the causes of delay within oil and gas
projects in the UAE”, in Dainty, A. (Ed.), Proceedings of the 24th Annual ARCOM Conference,
September 1-3, pp. 819-826.
Santos, J.R.A. (1999), “Cronbach’s Alpha: a tool for assessing the reliability of scales”, Journal of
Extension, Vol. 37 No. 2, pp. 1-5.
Standish Group International (1995), “The chaos report: why projects fail”, available at: www.csus.edu/
indiv/v/velianitis/161/ChaosReport.pdf (accessed December 12, 2015).
(The) Standish Group (1999), “CHAOS: the recipe for success”, research report, available at: www.
standishgroup.com/chaos_resources/index.php
Toor, T.P.S. (2008), “People management: an imperative to effective project management”, Business
Strategy Series, Vol. 10 No. 1, pp. 40-54.
Further reading
Aibinu, A.A. and Jagboro, G.O. (2002), “The effects of construction delays on project delivery in Nigerian
construction industry”, International Journal of Project Management, Vol. 20 No. 8, pp. 593-599.
Costa, H.R., Barros, M.D.O. and Travassos, G.H. (2007), “Evaluating software project portfolio risks”,
The Journal of Systems and Software, Vol. 80 No. 1, pp. 16-31.
Dmitriy, V., Chulkov Mayur, S. and Desai (2005), “Information technology project failures”, Information
Management & Computer Security, Vol. 13 No. 2, pp. 135-143.
Lars, M., “Gartner reports show why projects fail”, available at: http://thisiswhatgoodlookslike.com/20
12/06/10/gartner-survey-shows-why-projects-fail/ (accessed December 12, 2015).
Martinez, E (1994), “Avoiding large scale information systems project failures: the importance of
fundamentals”, Project Management Journal, Vol. 25 No. 2, pp. 17-25.
Project Integration Management. Chapter 4, ©1996 Project Management Institute, Upper Darby, PA,
pp. 39-46.
Appendix. Questionnaire used for survey in the company Project Health
Index
405
JOCM
31,2
406
Project Health
Index
407
JOCM
31,2
408
For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: [email protected]