Standard Operating Procedure For (MAINTENANCE SM)
Standard Operating Procedure For (MAINTENANCE SM)
Instrumentation Department
Issue No:02 Rev No:01 Effective Date: 01.07.2016 K-P-1.0
MAINTENANCE SYSTEM
1.0 PURPOSE :
To ensure effective maintenance of plant and equipment.
2.0 SCOPE :
Covers equipment and machinery of cement manufacturing.
3.0 RESPONSIBILITY:
3.1 Instrumentation head assisted by functional personnel, are responsible for the continual
implementation of the Maintenance system.
4.0 SYSTEM DESCRIPTION:
4.1 The maintenance system shall be used to ensure planning, scheduling and monitoring of
the
jobs to increase the equipment availability, effective utilization of the manpower and time
etc.
4.3 Spares required for maintaining equipment shall be procured by raising the Purchase
through SAP & Purchase order generated by the purchase dept.
4.4 The equipment / part drawings/documents shall be developed, for which the OEM's have
not supplied, as per the availability /during shutdowns / breakdowns, when the parts are
removed.
1
This doc. is valid only until it is viewed in General drive of DCBL local area network.The unsigned print out of the same shall be
treated “Invalid doc.” For print out of the same contact MR.
DALMIA CEMENT (B) LIMITED, KADAPA
Instrumentation Department
Issue No:02 Rev No:01 Effective Date: 01.07.2016 H-P-1.0
4.6 While carrying out planned maintenance, the required Safety measures such as line
Clearances, Height permits, confined space permits, excavations permits shall be taken &
implemented.
4.7 Equipment Inspection Checklist
The concerned section Engineers shall be responsible for filling daily checklists at the
required frequency by taking plant rounds. The equipment status as per the checklist shall
be cross verified by the concerned section heads & shall initiate corrective / preventive
actions for the same.
4.7.1 Types of Preventive Maintenance Plans:
a. Time based.
b. Periodic Maintenance schedules
c. Based on condition monitoring
4.8 The list of transactions and usage configured under the standard system, are given below :
2
This doc. is valid only until it is viewed in General drive of DCBL local area network.The unsigned print out of the same shall be
treated “Invalid doc.” For print out of the same contact MR.
DALMIA CEMENT (B) LIMITED, KADAPA
Instrumentation Department
Issue No:02 Rev No:01 Effective Date: 01.07.2016 H-P-1.0
8.1 The system shall be operated by the concerned engineers of the respective departments, to
ensure the preventive maintenance of equipments.
Monthly once all the weighing equipments calibration data are taken by respective section in
charge .If necessary twice in a month taken for critical equipment. Plan accordingly for the
corrective actions either in weekly maintenance or in major shutdown jobs.
Equipment Inspection.
Daily Checklist.
Technical Cell
Observations
3
This doc. is valid only until it is viewed in General drive of DCBL local area network.The unsigned print out of the same shall be
Off On Off -Line
treated “Invalid doc.” For print out of the same contact MR. On -Line
-Line -Line
DALMIA CEMENT (B) LIMITED, KADAPA
Instrumentation Department
Issue No:02 Rev No:01 Effective Date: 01.07.2016 H-P-1.0
8.4.1 Monitoring of malfunctions shall be carried out on weekly basis by the concerned
HOD(Maint) of respective areas.
Action on notifications for abnormalities of critical equipments like MV Drive, Plant automation and
related equipments can be taken during planned stoppage / shutdown. If the abnormalities
observed are serious in nature, same will be rectified by stopping the equipments. However, in
case of abnormalities which can wait,actions will be taken during the next available planned
stoppage. Such notifications shall be closed mentioning the probable date of rectification during
next available shutdown.
8.4.2 The corrective actions taken on the malfunctions shall be entered with relevant details like
activities carried out,skill used,etc. and the notifications shall be closed.
8.6 Detailed breakdown analysis is available in the form of "Why-Why Analysis", which is
generated in the Excel sheet,concerned dept.
4
This doc. is valid only until it is viewed in General drive of DCBL local area network.The unsigned print out of the same shall be
treated “Invalid doc.” For print out of the same contact MR.
DALMIA CEMENT (B) LIMITED, KADAPA
Instrumentation Department
Issue No:02 Rev No:01 Effective Date: 01.07.2016 H-P-1.0
11.0 RECORDS:
5
This doc. is valid only until it is viewed in General drive of DCBL local area network.The unsigned print out of the same shall be
treated “Invalid doc.” For print out of the same contact MR.
DALMIA CEMENT (B) LIMITED, KADAPA
Instrumentation Department
Issue No:02 Rev No:01 Effective Date: 01.07.2016 H-P-1.0
6
This doc. is valid only until it is viewed in General drive of DCBL local area network.The unsigned print out of the same shall be
treated “Invalid doc.” For print out of the same contact MR.