Method Statement For Testing and Commissioning of Water Supply Pipes Including Chlorination
Method Statement For Testing and Commissioning of Water Supply Pipes Including Chlorination
Method Statement For Testing and Commissioning of Water Supply Pipes Including Chlorination
1. SCOPE............................................................................................................................... 3
2. ABBREVIATION.................................................................................................................3
3. REFERENCES.................................................................................................................... 2
4. RESPONSIBILITIES........................................................................................................... 4
5. SITE PLANNING AND PREPARATION.............................................................................4
6.0 WORK METHODOLOGY & SEQUENCE OF WORK.......................................................5
6.1 TESTING AND COMMISIONING OF WATER SUPPLY PIPES INCLUDING CHLORINATION ...5
7. RESOURCES..................................................................................................................... 6
7.1 TOOLS & EQUIPMENT 8
7.2 MATERIALS 6
7.3 MANPOWER 6
8.0 QUALITY CONTROL........................................................................................................9
9.0 HEALTH, SAFETY & ENVIRONMENT (HSE)..................................................................7
10.0 SAFETY INSTRUCTIONS...............................................................................................7
11.PERSONEL PROTECTIVE EQUIPMENT..........................................................................8
12.ENVIRONMENTAL ISSUES............................................................................................10
12.1 INTRODUCTION.............................................................................................................8
12.2 MITIGATION MEASURES............................................................................................11
13. APPENDIX........................................................................................................................ 9
13.1. Risk Assessment For Testing And Commisioning Of Testing And Commisioning Of Water Supply
Pipes Including Chlorination.9
1.0 SCOPE
The purpose of this method statement is to describe the procedure and methodology to be adopted
as a part of testing and commissioning of testing and commissioning of water supply pipes including
chlorination for the Construction of Mosque, Ablution & Imam’s House at M7 Stables at Saih Al
Salam. This document should be read in conjunction with the Project Quality Plan and Contract
Specifications.
2.0 ABBREVIATION
1. MS - Method Statement
2. RA - Risk Assessment
3. E/E - Employer /Engineer
4. PPE -Personal Protective Equipment
5. HSE - Health Safety and Environment
6. PTW – Permit to Work
7. EPCM- Engineering, Procurement, and Construction management.
3.0 REFERENCES
Safety Manager: Shall be responsible for the implementation of safety procedures on site
and to ensure that the Risk Assessment within this method statement is followed. He shall
assign a competent Safety Officer to enforce these procedures and to provide guidance to
the operations where applicable.
MEP Engineer: Shall be responsible for the overall execution of works, and also responsible
for following all HSE and quality procedure.
Safety Officers: Shall be responsible for the implementation of all safety requirements and
to ensure that the works are undertaken in a safe and proper manner, all in accordance with
the approved Construction Phase HSE Plan, the approved method statement and the
approved Job Safety Analysis.
Quality Control Inspector: Shall be responsible for inspection and verification that the
procedures are properly implemented and that inspections are undertaken in accordance
with the approved Inspection Test Plan in a timely manner.
Ensure all the employees attend site-specific induction covering safety, environment, and
quality.
Acquire approvals and inspection for plant & machinery to enter inside the site locations if
any.
Any PTW for General works will be applied and obtained prior to works on site.
All environmental control will be established in accordance with the Site Environmental
Plan.
Ensure that all the necessary clearances from the Construction team are obtained prior to
start the work.
Check that the shop drawings and material submittals are approved and verify that the
materials are as per the approved by the Engineer.
All material shall be stored in a place free water, dust and adequately covered to
avoid any kind of damaged.
All material shall be transported to work place using adequate manpower.
While unloading, Shifting and storage it shall be ensure that there is no transit damage.
Ensure that the system installation is complete and mechanical completion is approved.
Ensure that no damage occurs between mechanical completion & precommissioning.
Check that the Water Booster piping network is complete with proper valves, water
hammer arrester drains, vents, strainers, pressure switches & instruments in place as per
final approved shop drawing.
Ensure the PRV stations are installed in all the floors & the bypass piping is completed &
properly supported.
Ensure that the Water Booster network is hydraulically pressure tested and approved.
Ensure the water supply network is disinfected in line with the approved method
statement.
Ensure that the entire system is cleaned internally & externally.
Ensure that the water supply pumps are precommissioned & commissioned in line with
the approved procedure.
Ensure all the pressure switches are installed & wired properly.
Ensure the wiring to the DDC from the pump panel is complete.
Ensure all drain valves & vents are installed.
Ensure that the BMS connections are done.
Ensure that the identification of all the pipework are complete.
The wiring diagram of pump controls & schematic piping shall be displayed near or inside the
control panel. Check filters are clean and fixed properly.
Ensure that all the precommissioning checks are carried out successfully.
The Water supply system shall be completed tested for proper sequence of operation as
approved.
System pressure will be maintained always at 16 bar. In the event of water consumption, pressure
in the water supply system piping will fall down. Minor drop in pressure shall be compensated by
the expansion vessels, but when the pressure reaches 15.0 bar, Pressure Switch PS1 will cut in
and jockey pump will start. If pressure builds up to 16.00 bar, then jockey will stop
While the jockey pump is in operation, if the pressure drops further to cut in pressure of PS2
(14.50 bar), then Main Booster pump will start and jockey will stop. Main pump will continue to run
till the pressure reaches cut out pressure of PS2 (16.0 bar).
As the main pump starts only below 14.5 bar & stops at 16 bar, there is sufficient time for the
pump to transfer from star to delta thus avoiding the frequent running of pump only in star mode.
Further the star to delta transition time shall be reduced.
While the Main Booster pump is in operation, if the pressure drops further to cut in pressure of
PS3 (13.50 bar), then Second Main Booster pump will start and both the main pumps will run.
Main Booster pumps will continue to run till the pressure reaches cut out pressure of PS2 and PS3
(16.0 bar)
While the Main Booster pumps are in operation, if the pressure drops further to cut in pressure of
PS4 (12.50 bar), then Third Main Booster pump will start and all the three main pumps will run. All
the Main Booster pumps will continue to run till the pressure reaches cut out pressure of PS2, PS3
and PS4 (16.0 bar).
While the 3 Nos. of Main Booster pumps are in operation and due to any reasons any one of the
main pumps fails to work, then the Standby Booster pump (the next available pump) will start and
both the Main Booster pump and Standby Booster pump will continue to run till the pressure
reaches cut out pressure 16.0 bar.
The main pumps will stop in reverse sequence when the system demand reduces.
The above sequence of cut-in and cut-out of main pumps will change during each new demand
cycle. Once the demand reduces all the pumps will stop in reverse sequence. The cyclic
changeover of duty of each pump will carry on during each cycle of operation. This cyclic
changeover of duty and standby pumps shall ensure to have uniform wear and tear of all the
booster pumps.
7. RESOURCES
7.2 MATERIALS
7.3 MANPOWER
The required manpower shall be reassessed for each activity. In general, the following Supervision
& resources will be in deployed:
MEP Engineer
Safety Officers
Foreman and charge hands
Technician
General Labors
All delivered water supply pipes and chlorination shall be subject to inspection and
approval of the Engineer/ Consultant in line with the approved material submittal.
All water supply pipes shall be inspected in accordance with the approved drawings.
Starting instructions will be given by the supervisors at the start of each activity to explain
the methodology of works and to communicate safe working procedures to the operatives.
These talks are structured in a way to highlight to major risks involved in the activity and
the various control measures required in order to minimize the risk. It is delivered in a
manner such as the key points that will be remembered by the operatives receiving it.
Toolbox talk meetings will be held for each crew, on group or employees, regarding more
general topics of the Project HSE Policy; for example, lessons learned, near-miss reports,
implementation of the requirements and message from the LBS management or
Employers HSE personnel.
The persons using cleaning fluid, solvent cement & any other forms of chemicals must
wear hand gloves.
Ensure only qualified personnel shall install, test & commissioned the equipment.
During testing & commissioning, display warning sign boards to be provided and barricade
the area whenever necessary.
All workers will be issued and trained in the use of the required PPE equipment to comply with
contract procedures and local regulations and will be supplemented with PPE as required by MSDS
& COSHH assessments. This will include but will not be limited to;
Hard Hats
Safety Boots with ankle support and steel toe caps
Safety Goggles
High Visibility Vests / Overalls with integrated reflective strips
Hand gloves
Face Masks
A variety of mechanisms, such as method statement briefings and toolbox talks will be
implemented to ensure all relevant personnel is appropriately informed.
In addition to their safety induction received at their arrival on-site, all the workers will have a
toolbox meeting to be briefed about the risks of their specific work task, prior to the start of
works.
12.1 INTRODUCTION
As part of the development of the Organization’s Environmental Management System(s) the
significant issues that are faced both on-site and within offices or other facilities should be
addressed. This approach subsequently allows for a systematic focus upon the important
environmental aspects to be adopted which in turn facilitates prioritization of limited
resources
13. APPENDIX
13.1. Risk Assessment for Testing and commissioning of water supply pipes including chlorination.