12SEAGC1996 Deep Excavation Work Near MRT Structures, Chua Tong Seng
12SEAGC1996 Deep Excavation Work Near MRT Structures, Chua Tong Seng
12SEAGC1996 Deep Excavation Work Near MRT Structures, Chua Tong Seng
SYNOPSIS The convenience of the fast and reliable Singapore MRT system attracts many building development projects
near its stations. However, the construction activities especially geotechnical work would require special consideration to
minimise any disturbance to this existing sensitive structures. This paper briefly describes a deep excavation work using a
unique semi Top-Down method for a major development project near a MRT station and viaduct. The design of the
diaphragm wall which acts a temporary retaining wall as well as a permanent wall, using a 1-D and a 2-D analysis will be
discussed. The result of an extensive inst1umentation scheme used to monitor the effect of the excavation work on the
smTOunding will be reported and compared with the predicted values.
The fast and reliable Singapore Mass Rapid Transit (refer to As shown in Fig. 2, the project is located beside Boon Lay
Fig. 1), which began construction in late 1983, has been in MRT Station and is bounded by Jurong West Central 2 and
operation since late 1987. The convenience of the Upper Jurong Road. It involves the construction of 3-level
efficiently run Mass Rapid Transit attracts many building basement for carpark and shopping and 6 storeys of
development projects nears its stations. The construction shopping and offices. Diaphragm wall was proposed as
activities, however, have to be carried out in a manner that earth retaining structure during const'ruction of basement
will not cause any significant disturbance to these existing and form part of permanent structure after the co1npletion of
sensitive structures. Under this condition, conventional the building. The lowest excavation level is 12.0m below
method of analysis and design may not be adequate, as the ground level. The Boon Lay MRT Station is an above
magnitude of movement of the surrounding structure ground structure supported on bored piles foundation.
caused by the works will govern the design. This paper
aims to· highlight some of the design consideration,
techniques and construction method for an excavation work
for a prestigious project near a MRT station.
=
lll\D U�
Q
lli:'<'.TtD
Q ��!Al"'!<
"' o:n= ""'"'�
0 0.t\'.<.1<I> ..AUON
The subsurface soil profile on site consists of firm silty clay In order to meet the completion date specified by the
fill followed by swampy soils of very soft peaty clay. This developer, a unique method of construction was adopted.
As shown in Fig. 3, during the initial excavation stages, two
is underlain by residual soils of firm to hard clayey silt. The
residual soil layers are founded on bedrocks of siltstone levels of composite struts were used to support the
and sandstone (Jurong Formation). The thickness of the fill diaphragm wall during the bulk excavation to the B2
varies from l .3m at the eastern end to 4.2m at the western basement slab level. The second level of strut were
removed when B2 basement slab has gained sufficient
end of the site. Similarly, the very soft peaty clay layer
strength. This is followed by the casting of BI basement
becomes thicker in the westward direction. The thickness of
slab and removal of first level strut. The first storey slab
residual soils ranges from 6.1 m to 2 l .3m. The bedrock
was then cast to provide sufficient rigidity before
formation appears to dip towards the south from the
excavation proceed in a Top-Down manner from B2 level
northern end and eastern end of the site.
to B3 level. At the same time, construction for the
superstructture was carried out. In order to facilitate Top
Down construction from B2 level to B3 level, plunge-in
4.0 THE DIAPHRAGM WALL SYSTEM
column using steel H-section were installed. The plunge-in
column shown in Fig. 4 were designed to take part of the
In view of the proximity of the MRT station, a stringently
superstructure load during construction stage and were later
designed retaining wall system is required to ensure safe
incorporated into the permanent column to carry full service
excavation works. The presence of bedrock at relatively
load. The plunge-in column were installed, using a steel
shallow depth rules out the use of sheetpiles. Prebored H
frame guide, coincide with bored piles which is the
piles was not feasible due to potential ground water
foundation system for this project.
drawdown problem. After studying various methods, it was
found that diaphragm wall was the most feasible solution.
The diaphragm wall acts as earth retaining wall during 6.0 METHODS OF ANALYSIS AND DESIGN
excavation works (temporary stage) and formed the
basement wall of the substructure. The layout of the Typical sections of the diaphragm wall are identified
diaphragm wall is detailed in Fig. 2. The diaphragm wall according to the proximity of the MRT station, depth of
system consists of 800mm thick panels near MRT reserve excavation and subsoil conditions. A one dimensional finite
and 600mm thick panels for area away from MRT reserve. element computer program was used for the analysis of the
retaining wall. The program has the capability to model the
interaction between the soil, retaining wall and struts taking
into account the sequence the construction and the non
UJnW
reversible stress-strain characteristics of the soil. The soil is
JMOOnC Wt!! >
.,;.
--,tr--==;;c--=;'::;: :::�
i<�:-.,� ::;: modeled based on the Rankine approach (elasto-plastic soil
.. � . ...,.,, ....
<>-•"""'·"'
·- .....�""'"
�J
.. ::.=�.;,:1Hl
...
�:· ,,.
: ......� .. .
VXllT SQIT
�1.ATY Cl.AT
• <
�
.. �
•,
c
"'1".
aDi: =-·"'"'-
!' ·
Sll,TSTO�f. IQO
Stage 0 Installation of diaphragm wall The effect of the bulk excavation on the MRT structure was
analyzed using a two dimensional finite difference analysis.
Stage 1 Excavation to 3.2m below !st storey level The soil was based on the Mohr-Coulomb failure criteria,
Stage 2 Installation of !st row of struts at 2.7m while the diaphragm wall, MRT piles, slabs and struts were
modeled as beam elements. Before modeling the actual
Stage 3 Excavation of 6.4m level construction activities , a finite difference mesh was set up
Stage 4 Installation of 2nd row of struts at 5.9m and boundary conditions imposed . The size of the mesh is
set up to be large enough so that the effect of boundary
Stage 5 Excavation to 7.5m level conditions on the analyzed zones may be minimized.
Stage 6 Casting of basement 2 slab at 7.0m level Initially undrained soil parameters were adopted for total
stress analysis and gravity run was carried out to simulate
Stage 7 Removal of 2nd row of struts the existing soil conditions, followed by modelling the
Stage 8 Casting of basement I slab at 3.5m level installation of MRT piles and diaphragm wall. The results
of the analysis (Fig. 5), suggested that the effect on the
Stage 9 Removal of 1st row of struts existing MRT pile is not significant.
Stage I 0 Casting of 1st storey slab
Stage 11 Backfill soil to I st storey level -�
Based on the analysis, the required diaphragm wall depth MFH Pll£S
mo>.1.S2nvn
was 20m. The maximum bending moment for 800mm and
600mm wall were 933 kNm/m and 773 kNm/m,
respectively. The estimated strut load were 15T/m for the
first level and 20T/m for the second level. The required
preload was 6.25T/m for both levels.
Fig. 5 Results of 2-D Analysis
T. S. CHUA, B. C. TAN and T. L. YU
If
L&M Geotechnic (Singapore) Pte Ltd
8. GEOTECHNICAL INSTRUMENTATION
::o:::.
an inclinometer, a piezometers and a water standpipe were - ""
!
0 0 0
!
I
I
2
-
- 2 1-� I i
·--
2
i
!
i
'
4 4 4 -
6 6 6
8 8 f--- ·-
I- 8
T
. I I
1--,�i_Jl
10 10 10
E 12
I/ I E 12
I
E 12
I I
.c .c
I
r
a.
.,
a.
., -4./ %
.,
1 '/
14 14 0 14
0 0
'!I ,1 I
'II I
16 16 16
I
./ I I
I
7/ I I
18 18 18
I
• Stage 1 • Stage 1
20 f--*l'----H o Stage 3 20 o Stage 3 20
I Final Stage
,. Stage 5 ;. Stage 5 i • 13A
--- --
22 - 22 22 --·- -�··-
'
o Stage 12 o Stage 12 • 14A
+Final +Final 0 1D
24 24 24
I I
D 2D
26 -- I I J
26 26
·5 0 5 10 15 20 25 ·3 0 3 6 9 12 15 .5 0 5 10 15 20 25
Fig. 7 lnclimometer 13A Readings Fig. 8 Inclinometer 14A Readings Fig. 9 ·co111parison of Lateral Movement
'
·
soil immediately next to the wall was generally smaller. For
example, the maximum movement in soil recorded in I', 1 '
II
" LLI..LLl-'.J.C..L..J��'=-'-:;;;:;-�.LI
I
inclinometer, 13, was 10 mm as compared to 1 6mm in the
"'"'°1:-10-�··0-E:.,,.':''·t.••.�··:..,.'it''fo.,,�···�... �··-r..,,...
later. ��