Assignment 1 For Class
Assignment 1 For Class
Name:
Student Number:
Activity 1 can start immediately and has an estimated duration of three weeks.
Activity 2 can start after activity 1 is completed and has an estimated duration of three weeks.
Activity 3 can start after activity 1 is completed and has an estimated duration of six weeks.
Activity 4 can start after activity 2 is completed and has an estimated duration of eight weeks.
Activity 5 can start after activity 4 is completed and after activity 3 is completed. This activity takes four weeks.
5. The resource working on activity 3 is replaced with another resource who is less experienced. The activity will now take 10
weeks. How will this affect the project?
6. Using the original information, after some arguing between stakeholders, a new activity 6 is added to the project. It will take
11 weeks to complete and must be completed before activity 5 and after activity 3. Management is concerned that adding the
activity will add 11 weeks to the project. Another stakeholder argues the time will be less than 11 weeks. Who is correct?
7. Based on the information in number 6 above, how much longer will the project take?
1. Imagine that this project has a project float of -3 (minus three) months. Which activity or activities presented above would you
crash to save three months on the project, assuming that the activities listed above represent critical path activities?