Computation OF Dead Loads: Surigao State College of Technology

The document computes the dead loads for a truss structure. It provides tables of material densities and calculates the loads from various structural elements. These include the roofing, purlins, truss members, ceiling, and reactions at the joints. Comprehensive calculations are shown to determine the weight contributions from each component based on the material densities and geometries. The total reactions at the joints are summed to solve for the vertical support reactions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
209 views26 pages

Computation OF Dead Loads: Surigao State College of Technology

The document computes the dead loads for a truss structure. It provides tables of material densities and calculates the loads from various structural elements. These include the roofing, purlins, truss members, ceiling, and reactions at the joints. Comprehensive calculations are shown to determine the weight contributions from each component based on the material densities and geometries. The total reactions at the joints are summed to solve for the vertical support reactions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 26

SURIGAO STATE COLLEGE OF TECHNOLOGY

8400, NARCISO ST, SURIGAO CITY, SURIGAO DEL NORTE

COMPUTATION
OF
DEAD LOADS

SUBMITTED BY: SUBMITTED TO:

MALLILLIN, KARL ADRIAN C. ENGR. RICHARD A. BADIOLA, RMP,


SALUTAN, MARVIN M. M.ENG’G, D.ENG’G (CAR)

MARCH, 2018
DATE SUBMITTED
TABLE OF DENSITIES
MATERIALS DENSITY
CONCRETE, REINFORCED: 23.6kN/m3
STONE, INCLUDING GRAVEL
STEEL, COLD-DRAWN 77.3kN/m3
PLYWOOD 5.7kN/m3
ZINC, ROLLED SHEET 70.5kN/m3

TRUSSES:
“SOLVING THE REACTIONS AT THE FULL TRUSS 1”

a) TRIBUTARY AREA OF THE COLORED ROOF:

kN
γ =77.3
m3
Solving of weight: (thickness = 0.003m)

A1 = 2.65m (0.08758m+.35m) = 1.16m2; WR1 = (77.3kN/m3) (0.003m) (1.16m2) = 0.269kN


A2 = 2.65m (0.7m) = 1.86m2; WR2 = (77.3kN/m3) (0.003m) (1.86m2) = 0.431kN
A3 = 2.65m (0.35m + 0.5m) = 2.25m2; WR3 = (77.3kN/m3) (0.003m) (2.25m2) = 0.522kN
A4 = 2.65m (0.5m + 0.5m) = 2.65m2; WR4 = (77.3kN/m3) (0.003m) (2.65m2) = 0.615kN
A5 = 2.65m (0.5m + 0.5m) = 2.65m2; WR5 = (77.3kN/m3) (0.003m) (2.65m2) = 0.615kN
A6 = 2.65m (0.5m + 0.5m) = 2.65m2; WR6 = (77.3kN/m3) (0.003m) (2.65m2) = 0.615kN
A7 = 2.65m (0.58758m) = 1.56m2; WR7 = (77.3kN/m3) (0.003m) (1.56m2) = 0.362kN

b) C-PURLINS + WEIGHT OF ROOF; CLEATS; SAG ROD:

kN
γ =77.3
m3
*Cleat:

A = (0.00625m) (0.05m + 0.05m) = 6.25x10 -4m2


L = 0.05m
WCL = (77.3kN/m3) (6.25x10-4m2) (0.05m) = 2.42x10-3kN
*Sag Rod:
2
π d 2 π (0.0125 m)
A= = =1.23 x 10−4 m 2
4 4

kN kN
(
W SR=1.23 x 10−4 m2 77.3
m 3)=9.49 x 10−3
m
LS1 = 0.63291m LS4 = 0.98529m
LS2 = 0.67687m LS5 = 0.98529m
LS3 = 0.98529m LS6 = 0.96037m

*C – Purlins:

L = 2.65m; A = (0.00625m) (0.075m + 2(0.05m) + 2(0.0125m)) = 1.25x10 -3m2


WCP = (77.3kN/m3) (2.65m) (1.25x10-3m2) = 0.26kN

WCP1 = WCP + WR1 + WGUTTER


WCP1 = 0.26kN + 0.269kN + 3(0.2m) (0.001m) (2.65m) (70.5kN/m 3) = 0.641kN
WCP2 = WCP + WR2
WCP2 = 0.26kN + 0.431kN = 0.691kN
WCP3 = WCP + WR3
WCP3 = 0.26kN + 0.522kN = 0.782kN
WCP4 = WCP + WR4
WCP4 = 0.26kN + 0.615kN = 0.875kN
WCP5 = WCP + WR5
WCP5 = 0.26kN + 0.615kN = 0.875kN
WCP6 = WCP + WR6
WCP6 = 0.26kN + 0.615kN = 0.875kN
WCP7 = WCP + WR7
WCP7 = 0.26kN + 0.362kN = 0.662kN

c) WEIGHT OF THE TRUSS (EXCLUDING THE REACTIONS TO THE NODES):

kN
γ =77.3
m3
A=( 0.00625 m ) ( 0.05 m+0.05 m )=6.25 x 10−4 m2
W T = Aγ LT

LT = 0.125m + 0.35m = 0.475m


WT-JA = (6.25x10-4m2) (77.3kN/m3) (0.475m) = 0.023kN
LT = 0.37165m + 0.35m + 0.21486m + 0.5m = 1.437m
WT-JB = (6.25x10-4m2) (77.3kN/m3) (1.437m) = 0.069kN

LT = 0.54421m + 0.34324m + 1m = 1.887m


WT-JC = (6.25x10-4m2) (77.3kN/m3) (1.887m) = 0.091kN

LT = 0.60648m + 0.47162m + 1m = 2.078m


WT-JD = (6.25x10-4m2) (77.3kN/m3) (0.475m) = 0.1kN

LT = 0.68733m + 0.6m + 0.5m = 1.787m


WT-JE = (6.25x10-4m2) (77.3kN/m3) (1.787m) = 0.086kN

LT = 0.125m + 0.72271m + 0.37165m + 0.36135m = 1.581m


WT-JF = (6.25x10-4m2) (77.3kN/m3) (1.581m) = 0.076kN

LT = 0.36135m + 0.21486m + 0.51622m + 0.54421m = 1.637m


WT-JG = (6.25x10-4m2) (77.3kN/m3) (1.637m) = 0.079kN
LT = 0.34324m + 2(0.51622m) + 0.60648m = 1.982m
WT-JH = (6.25x10-4m2) (77.3kN/m3) (1.982m) = 0.096kN

LT = 1.54866m + 0.6m = 2.149m


WT-JJ = (6.25x10-4m2) (77.3kN/m3) (2.149m) = 0.104kN

LT = 1.03244m + 0.47162m + 0.68733m = 2.191m


WT-JI = (6.25x10-4m2) (77.3kN/m3) (2.191m) = 0.106kN

d) CEILING LOAD:

kN
γ =5.7
m3
Thickness(t )=0.00625 m
V T = AT t
W T =V T γ
*Joint A: AT = (2.65m) (0.7m + 0.35m) = 2.783m2
VT = (0.00625m) (2.783m2) = 0.017m3
WCE-JA = (5.7kN/m3) (0.017m3) = 0.099kN
*Joint B: AT = (2.65m) (0.35m + 0.5m) = 2.253m2
VT = (0.00625m) (2.253m2) = 0.014m3
WCE-JB = (5.7kN/m3) (0.014m3) = 0.08kN
*Joint C: AT = (2.65m) (1m) = 2.65m2
VT = (0.00625m) (2.65m2) = 0.017m3
WCE-JC = (5.7kN/m3) (0.017m3) = 0.094kN
*Joint D: AT = (2.65m) (1m) = 2.65m2
VT = (0.00625m) (2.65m2) = 0.017m3
WCE-JD = (5.7kN/m3) (0.017m3) = 0.094kN
*Joint E: AT = (2.65m) (1.5m) = 3.975m2
VT = (0.00625m) (3.975 m2) = 0.025m3
WCE-JE = (5.7kN/m3) (0.025m3) = 0.142kN

e) REACTIONS AT TRUSS:

F A=W T−JA +W CE−JA =0.23 kN + 0.099 kN =0.122 kN


F B=W T−JB +W CE−JB =0.069 kN +0.014 kN=0.083 kN
F C =W T −JC +W CE−JC =0.091 kN +0.094 kN=0.185 kN
F D =W T −JD +W CE−JD =0.1kN +0.094 kN =0.194 kN
F E =W T −JE +W CE−JE =0.086 kN +0.142 kN=0.228 kN
LS 2
(
F F =2W CL+ LS 1+
2 )W SR+W CP1 +W CP 2+ W
T− JF

−3 kN
−3
(
F F =2 ( 2.42 x 10 kN ) + ( 0.971 m ) 9.49 x 10
m) + 1.332kN +0.076 kN =1.422 kN

L +L
( )
F G=W CL+ S 2 S 3 W SR +W CP3 +W
2 T −JG
kN
−3
(
F G=( 2.42 x 10 kN ) + ( 0.831 m ) 9.49 x 10−3 )m
+ 0.782 kN +0.079 kN =0. 871 kN

L +L
( )
F H =W CL+ S 3 4 W SR+ W CP 4 +W
2 T −JH
kN
−3
(
F H =( 2.42 x 10 kN ) + ( 0.985 m ) 9.49 x 10−3 )m
+0. 875 kN +0.096 kN =0. 983 kN

L +L
( )
F I =W CL+ S 4 S 5 W SR +W CP 5 +W
2 T −JI
kN
(
F I = ( 2.42 x 10−3 kN ) + ( 0.985 m ) 9.49 x 10−3
m )
+0. 875 kN +0.106 kN =0. 993 kN

LS2
(
F J =2 W CL + LS 1 +
2 )W SR +W CP 6 +W CP7 +W
T−JF
kN
(
F J =2 ( 2.42 x 10−3 kN ) + ( 1.453 m ) 9.49 x 10−3
m )
+1.537 kN + 0.104 kN =1.66 kN

∑ F Y =0 ; R 1+ R 2=F A + F B + FC + F D + F E + F F + F G + F H + F I + F J
R1 + R2=6.741 kN

∑ M R 1=0 ; 3 R 2+ 0.2(F A + F F )=0.5(F B + F G )+1.5(F C + F H )+2.5( F D + F I )+3.5 ¿ ¿)


3 R2=11.8045 kN ∙m−0.3088 kN ∙ m

R2=3.832 kN R1=2.909 kN
“SOLVING THE REACTIONS AT THE FULL TRUSS 2”

a) TRIBUTARY AREA OF THE COLORED ROOF:

kN
γ =77.3
m3
Solving of weight: (thickness = 0.003m)

A1 = 1.5m (0.2m + 0.35m) = 0.825m2; WR1 = (77.3kN/m3) (0.003m) (0.825m2) = 0.191kN


A2 = 1.5m (0.35m + 0.5m) = 1.275m2; WR2 = (77.3kN/m3) (0.003m) (1.275m2) = 0.296kN
A3 = 1.5m (0.7m) + 3m (0.5m) = 2.55m2; WR3 = (77.3kN/m3) (0.003m) (2.55m2) = 0.591kN
A4 = 3m (1m) = 3m2; WR4 = (77.3kN/m3) (0.003m) (3m2) = 0.696kN
A5 = 3m (0.6m) = 1.8m2; WR5 = (77.3kN/m3) (0.003m) (1.8m2) = 0.417kN

b) C-PURLINS + WEIGHT OF ROOF; CLEATS; SAG ROD:

kN
γ =77.3
m3
*Cleat:

A = (0.00625m) (0.05m + 0.05m) = 6.25x10 -4m2


L = 0.05m
WCL = (77.3kN/m3) (6.25x10-4m2) (0.05m) = 2.42x10-3kN
*Sag Rod:
2
π d 2 π (0.0125 m)
A= = =1.23 x 10−4 m 2
4 4

kN kN
(
W SR=1.23 x 10−4 m2 77.3
m 3)=9.49 x 10−3
m
LS1 = 0.6008m LS3 = 0.98529m
LS2 = 0.98529m LS4 = 0.98529m

*C – Purlins:

L = 2.65m; A = (0.00625m) (0.075m + 2(0.05m) + 2(0.0125m)) = 1.25x10 -3m2


WCP = (77.3kN/m3) (2.65m) (1.25x10-3m2) = 0.26kN

WCP1 = WCP + WR1


WCP1 = 0.26kN + 0.191kN = 0.451kN
WCP2 = WCP + WR2
WCP2 = 0.26kN + 0.296kN = 0.556kN
WCP3 = WCP + WR3
WCP3 = 0.26kN + 0.591kN = 0.851kN
WCP4 = WCP + WR4
WCP4 = 0.26kN + 0.696kN = 0.956kN
WCP5 = WCP + WR5
WCP5 = 0.26kN + 0.417kN = 0.677kN

c) WEIGHT OF THE TRUSS (EXCLUDING THE REACTIONS TO THE NODES):

kN
γ =77.3
m3
A=( 0.00625 m ) ( 0.05 m+0.05 m )=6.25 x 10−4 m2
W T = Aγ LT

LT = 0.21486m + 0.5m = 0.715m


WT-JA = (6.25x10-4m2) (77.3kN/m3) (0.715m) = 0.035kN

LT = 0.54421m + 0.34324m + 0.5m + 0.5m = 1.887m


WT-JB = (6.25x10-4m2) (77.3kN/m3) (1.887m) = 0.091kN
LT = 0.60648m + 0.47162m + 1m = 2.078m
WT-JC = (6.25x10-4m2) (77.3kN/m3) (2.078m) = 1kN

LT = 0.68733m + 0.6m + 0.5m = 1.787m


WT-JD = (6.25x10-4m2) (77.3kN/m3) (1.787m) = 0.086kN

LT = 0.72271m + 0.21486m + 0.51622m + 0.54421m = 1.998m


WT-JE = (6.25x10-4m2) (77.3kN/m3) (1.998m) = 0.097kN

LT = 0.51622m + 0.51622m + 0.60648m + 0.34324m = 1.982m


WT-JF = (6.25x10-4m2) (77.3kN/m3) (1.982m) = 0.096kN

LT = 0.51622m + 0.51622m + 0.47162m + 0.68733m = 2.191m


WT-JG = (6.25x10-4m2) (77.3kN/m3) (2.191) = 0.106kN

LT = 0.51622m + 0.6m = 1.116m


WT-JH = (6.25x10-4m2) (77.3kN/m3) (1.116m) = 0.054kN
d) CEILING LOAD:

kN
γ =5.7
m3
Thickness(t )=0.00625 m
V T = AT t
W T =V T γ

*Joint A: AT = (1.4m) (1.5m) = 2.1m2


VT = (0.00625m) (2.1m2) = 0.013m3
WCE-JA = (5.7kN/m3) (0.013m3) = 0.075kN
*Joint B: AT = (1.5m) (0.7m) + (0.5m) (3m) = 2.55m2
VT = (0.00625m) (2.55m2) = 0.016m3
WCE-JB = (5.7kN/m3) (0.016m3) = 0.091kN
*Joint C: AT = (3m) (1m) = 3m2
VT = (0.00625m) (3m2) = 0.019m3
WCE-JC = (5.7kN/m3) (0.019m3) = 0.107kN
*Joint D: AT = (3m) (0.6m) = 1.8m2
VT = (0.00625m) (1.8m2) = 0.011m3
WCE-JD = (5.7kN/m3) (0.011m3) = 0.064kN

e) REACTIONS AT TRUSS:
F A=W T−JA +W CE−JA =0.035 kN + 0.075 kN =0.11 kN
F B=W T−JB +W CE−JB =0.091 kN +0.091 kN =0.182 kN
F C =W T −JC +W CE−JC =1 kN +0.107 kN =1.107 kN
F D =W T −JD +W CE−JD =0.086 kN +0.064 kN=0.15 kN
LS 2
(
F E =2W CL+ LS 1 +
2 )
W SR +W CP1 +W CP 2+W
T−JE
kN
(
F E =2 ( 2.42 x 10−3 kN ) + ( 1.093 m ) 9.49 x 10−3
m )
+ 1.01kN + 0.097 kN =1.119 kN

L +L
( )
F F =W CL + S 2 S 3 W SR +W CP 3+ W
2 T −JF
kN
(
F F =( 2.42 x 10−3 kN ) + ( 0.985 m ) 9.49 x 10−3
m )
+0.851 kN + 0.096 kN =0. 961kN

L +L
( )
F G=W CL+ S 3 4 W SR +W CP4 + W
2 T− JG
kN
(
F G=( 2.42 x 10−3 kN ) + ( 0.985 m ) 9.49 x 10−3
m )
+ 0. 956 kN +0.106 kN =1.013 kN

L
( )
F H =W CL+ 4 W SR +W CP5 +W
2 T −JG
kN
−3
(
F H =( 2.42 x 10 kN ) + ( 0.493 m ) 9.49 x 10−3
m )
+0. 677 kN +0.054 kN=0.741 kN

∑ F Y =0 ; R 1+ R 2=F A + F B + FC + F D + F E + F F + F G + F H
R1 + R2=5.383 kN

∑ M R 1=0 ; 3 R 2=1( F B + F F )+2(F C + FG )+3 ¿)


3 R2=8.056 kN ∙ m

R2=2.685 kN R1=2.698 kN
“SOLVING THE REACTIONS AT THE HALF TRUSS”

a) TRIBUTARY AREA OF THE COLORED ROOF:

kN
γ =77.3
m3
Solving of weight: (thickness = 0.003m)

A1 = 3m (0.27136m+0.5m) = 2.314m2; WR1 = (77.3kN/m3) (0.003m) (1.16m2) = 0.269kN


A2 = 3m (1m) = 3m2; WR2 = (77.3kN/m3) (0.003m) (1.86m2) = 0.431kN
A3 = 3m (0.5m) = 1.5m2; WR3 = (77.3kN/m3) (0.003m) (2.25m2) = 0.522kN

b) C-PURLINS + WEIGHT OF ROOF; CLEATS; SAG ROD:

kN
γ =77.3
m3
*Cleat:

A = (0.00625m) (0.05m + 0.05m) = 6.25x10 -4m2


L = 0.05m
WCL = (77.3kN/m3) (6.25x10-4m2) (0.05m) = 2.42x10-3kN

*Sag Rod:
2
π d 2 π (0.0125 m)
A= = =1.23 x 10−4 m 2
4 4

kN kN
(
W SR =1.23 x 10−4 m2 77.3
m 3)=9.49 x 10−3
m
LS1 = 0.98529m LS2 = 0.96037m

*C – Purlins:

L = 2.65m; A = (0.00625m) (0.075m + 2(0.05m) + 2(0.0125m)) = 1.25x10 -3m2


WCP = (77.3kN/m3) (2.65m) (1.25x10-3m2) = 0.26kN

WCP1 = WCP + WR1 + WGUTTER


WCP1 = 0.26kN + 0.269kN + 3(0.2m) (0.001m) (3m) (70.5kN/m 3) = 0.656kN
WCP2 = WCP + WR2
WCP2 = 0.26kN + 0.431kN = 0.691kN
WCP3 = WCP + WR3
WCP3 = 0.26kN + 0.522kN = 0.782kN

c) WEIGHT OF THE TRUSS (EXCLUDING THE REACTIONS TO THE NODES):

kN
γ =77.3
m3
A=( 0.00625 m ) ( 0.05 m+0.05 m )=6.25 x 10−4 m2
W T = Aγ LT

LT = 0.34324m + 0.5m = 0.843m


WT-JA = (6.25x10-4m2) (77.3kN/m3) (0.843m) = 0.041kN

LT = 0.60648m + 0.47162m + 1m= 2.078m


WT-JB = (6.25x10-4m2) (77.3kN/m3) (2.078m) = 0.1kN

LT = 0.68733m + 0.6m + 0.5m = 1.787m


WT-JC = (6.25x10-4m2) (77.3kN/m3) (1.787m) = 0.086kN

LT = 0.60648m + 0.34324m + 0.51622m + 0.20649 = 1.672m


WT-JD = (6.25x10-4m2) (77.3kN/m3) (1.672m) = 0.081kN

LT = 1.03244m + 0.47162m + 0.68733m = 2.191m


WT-JE = (6.25x10-4m2) (77.3kN/m3) (2.191m) = 0.106kN

LT = 0.6m + 0.51622m = 1.12m


WT-JF = (6.25x10-4m2) (77.3kN/m3) (1.12m) = 0.054kN

d) CEILING LOAD:
kN
γ =5.7
m3
Thickness(t )=0.00625 m
V T = AT t
W T =V T γ

*Joint A: AT = (3m) (0.27136m + 0.5m) = 2.314m2


VT = (0.00625m) (2.314m2) = 0.014m3
WCE-JA = (5.7kN/m3) (0.017m3) = 0.082kN
*Joint B: AT = (3m) (0.5m + 0.5m) = 3m2
VT = (0.00625m) (3m2) = 0.019m3
WCE-JB = (5.7kN/m3) (0.019m3) = 0.107kN
*Joint C: AT = (3m) (0.5m) = 1.5m2
VT = (0.00625m) (1.5m2) = 0.009m3
WCE-JC = (5.7kN/m3) (0.017m3) = 0.053kN

e) REACTIONS AT TRUSS:

F A=W T−JA +W CE−JA =0.041 kN + 0.082kN =0.123 kN


F B=W T−JB +W CE−JB =0.1 kN +0.107 kN =0.207 kN
F C =W T −JC +W CE−JC =0.086 kN + 0.053 kN=0.139 kN

F D =W CL + ( L2 ) W
S1
SR + W CP1 +W
T −JD
kN
−3
(
F D =( 2.42 x 10 kN )+ ( 0.971m ) 9.49 x 10−3
m )
+0. 656 kN +0.081 kN =0. 744 kN

F E =W CL + (L S1 + LS 2
2 ) W SR +W CP2 +W
T−JE
kN
(
F E =( 2.42 x 10−3 kN ) + ( 0.973 m ) 9.49 x 10−3
m )
+0. 691 kN +0.106 kN =0. 809 kN

LS 2
F F =W CL + ( ) 2
W SR +W CP3 +W
T−JF
kN
(
F F =( 2.42 x 10−3 kN ) + ( 0.48 m ) 9.49 x 10−3
m)+0. 782 kN +0.054 kN=0.843 kN
∑ F Y =0 ; R 1+ R 2=F A + F B + FC + F D + F E + F F
R1 + R2=2.86 5 kN

∑ M R 1=0 ; 2 R 2=1( F B + F E )+ 2(FC + F F )


2 R2=2.98 kN ∙ m

R2=1.49 kN R1=1.375 kN

“SOLVING THE REACTIONS AT THE COLUMNS”

FRAMES

ROOF BEAM PLAN SECOND FLOOR FRAMING PLAN


“SOLVING THE REACTION OF BEAMS @ROOF BEAM”

kN kN
W beam =0.4 m x 0.2 m x 23.6 =1.888
m 3
m
kN kN
W ¿ wall=h x 0.1 m x 21 . 2 3 =2.12 h
m m

Where, P = reaction of the truss that acts on the beam

@Beam B1 to C1:
kN
R1 + R2=1.888 ( 2.8 m ) +20.4052 kN
m
R1 + R2=25.692 kN
w L2
∑ M R =0 ; 2. 8 R2=
1
2
+3.803 kN +25.714 kN
kN
(1.888 )(2. 8 m)2
m
+29.517 kN
2
R 2=
2.8 m

R1 = 12.507kN ; R2 = 13.185kN
@Beam C1 to D1:
Where R1 = R2
kN
R1 + R2=1.888 (1 . 4 m ) +11.876 kN
m
R1 + R2=17.162 kN
2
∑ M R =0 ; 1.4 R2 = w2L
1
+0.475 kN +7.966 kN
kN
(1.888 )(1.4 m)2
m
+8.441 kN
2
R 2=
1.4 m

R1 = 8.49kN ; R2 = 8.672kN
@Two Beams at E:
R1 = Reaction acting on beam D1 to D2 ; R2 = Reaction acting on column E2
kN
R1 = 1.888 m ( 1 .2 m ) +4.517 kN ; R1 = 6.138kN
kN
R2 = 1.888 m ( 1 .3 m ) + 4.195 kN ; R2 = 6.649kN

@Beam B1 to B2:
kN
R1 + R2=1.888 ( 2.7 m ) +2.909 kN + 7.7274
m
R1 + R2=15.734 kN
w L2
∑ M R =0 ; 2.7 R2 = +0.7 P+1.14(7.7274) ; P = 2.909kN
1
2
kN
(1.888 )(2.7 m)2
m
+0.7 m ( 2.909 kN ) +8.809 kN
2
R 2=
2.7 m

R1 = 9.168kN ; R2 = 6.566kN
@Beam C1 to C2:
kN
R1 + R2=1.888 ( 2.7 m ) +3.832 kN
m
R1 + R2=8.93 kN
2
∑ M R =0 ; 2.7 R2 = w2L
1
+0.7 P ; P = 3.832kN
kN
(1.888 )(2.7 m)2
m
+0.7 m(3.832 kN )
2
R 2=
2.7 m

R1 = 5.387kN ; R2 = 3.543kN
@Beam D1 to D2:
kN
R1 + R2=1.888 ( 2.7 m ) +2.266 kN
m
R1 + R2=7.364 kN
2
∑ M R =0 ; 2.7 R2 = w2L
1
+1.7 P ; P = 2.266kN -> Reaction coming from the beam of E
kN
(1.888 )(2.7 m)2
m
+1 .7 m(2.266 kN )
2
R 2=
2.7 m
R1 = 3.388kN ; R2 = 3.976kN
@Beam B2 to C2:
Where R1 = R2:
kN
R1 + R2=1.888 (2. 8 m)
m
2 R1=5. 2864 kN
R1 = 2.64kN ; R2 = 2.64kN
@Beam C2 to E2: P1 = 3.976kN -> Reaction coming from the beam of D
P2 = 1.375kN -> Reaction coming from the Half-Truss
kN
R1 + R2=1.888 ( 2.6 m ) +3.976 kN +1.375 kN
m
R1 + R2=10.26 kN
w L2
∑ M R =0 ; 2.6 R2= +1.5 P 1+0.7 P2 ;
1
2
kN
(1.888 )(2.6 m)2
m
+1.5 m ( 3.976 kN ) +0.7(1.375 kN )
2
R 2=
2.6 m
R1 = 5.14kN ; R2 = 5.12kN
@Beam B2 to B3:
kN
R1 + R2=1.888 ( 2.9 m ) +2.909 kN + 8.586 kN
m
R1 + R2=16.97 kN
2
∑ M R =0 ; 2.9 R2= w2L
1
+ 0.45 P+1.45 (8.586) ; P = 2.909kN
kN
(1.888 )(2.9 m)2
m
+0.45 m ( 2.909 kN )+ 12.45 kN
2
R 2=
2.9 m

R1 = 9.488kN ; R2 = 7.482kN
@Beam C2 to C3:
kN
R1 + R2=1.888 ( 2.9 m ) +3.832 kN
m
R1 + R2=9.307 kN
w L2
∑ M R =0 ; 2.9 R2= + 0.45 P ; P = 3.832kN
1
2
kN
(1.888 )(2.9 m)2
m
+0.45 m(3.832 kN )
2
R 2=
2.9m
R1 = 5.975kN ; R2 = 3.332kN
@Beam E2 to E3:
kN
R1 + R2=1.888 ( 2.9 m ) +8.3 kN
m
R1 + R2=13.775 kN
w L2
∑ M R =0 ; 2. 9 R2=
1
2
+12.035 kN
kN
(1.888 )(2. 9 m)2
m
+12.035 kN
2
R 2=
2. 9 m
R1 = 6.887kN ; R2 = 6.888kN
@Beam B3 to C3:
kN
R1 + R2=1.888 ( 2.8 m ) +8.014 kN
m
R1 + R2=13.3 kN
w L2
∑ M R =0 ; 2.8 R2=
1
2
+ 11.22 kN
kN
(1.888 )(2. 8 m)2
m
+11.22 kN
2
R 2=
2. 8 m
R1 = 6.65kN ; R2 = 6.65kN
@Beam C3 to E3:
Where R1 = R2:
kN
R1 + R2=1.888 (2. 6 m)
m
2 R1=4.9088 kN
R1 = 2.4544kN ; R2 = 2.4544kN
@Beam C3 to C5:
kN
R1 + R2=1.888 ( 2.6 m ) +2.698 kN +7.441 kN
m
R1 + R2=15.048 kN
2
∑ M R =0 ; 2.6 R2= w2L
1
+0. 2 P+1.3(7.441 kN ) ; P = 2.698kN
kN
(1.888 )(2.6 m)2
m
+0.2 m ( 2.698 kN ) +9.673 kN
2
R 2=
2.6 m
R1 = 8.666kN ; R2 = 6.382kN
@Beam C5 to E5:
Where R1 = R2:
kN
R1 + R2=1.888 ( 2.6 m ) +7.441 kN
m
R1 + R2=12.35 kN
w L2
∑ M R =0 ; 2.6 R2=
1
2
+1.3(7.441 kN )
kN
(1.888 )(2.6 m)2
m
+9.673 kN
2
R 2=
2.6 m
R1 = 2.4544kN ; R2 = 2.4544kN
R1 = 2.64kN + 5.387kN + 1.322kN = 9.349kN
R2 = 3.543kN + 2.64kN + 5.14kN + 5.975kN = 17.298kN
R3 = 3.332kN + 2.64kN + 2.4544kN + 4.945kN + 3.832kN = 17.2034kN
R4 = 2.662kN + 2.4544kN + 2.698kN = 7.8144kN

R1 = 3.303kN + 2.64kN + 5.195kN = 11.138kN


R2 = 3.543kN + 2.64kN + 5.14kN + 5.975kN = 17.298kN
R3 = 2.454kN + 5.12kN + 2.7376kN + 1.49kN = 11.8016kN
“SOLVING THE REACTION OF BEAMS @SECOND FLOOR FRAMING PLAN”

kN kN
w=0.4 m x 0.2 m x 23.6 =1.888
m 3
m

wL
R=
2
@Beam B1 to C1:
kN
(1.888 )(2.8 m)
m
R= =2.6432 kN
2
@Beam C1 to D1:
kN
(1.888 )(1.4 m)
m
R= =1.3216 kN
2
@Two Beams at E:
R1 = Reaction acting on beam D1 to D2 ; R2 = Reaction acting on column E2
kN
R1 = 1.888 m (1. 2 m) ; R1 = 2.266kN
kN
R2 = 1.888 m (1. 3 m) ; R2 = 2.454kN
@Beam B1 to B2:
kN
(1.888 )(2 .7 m)
m
R= =2. 5488 kN
2
@Beam C1 to C2:
kN
(1.888 )(2. 7 m)
m
R= =2. 5488 kN
2
@Beam D1 to D2:
kN
R1 + R2=1.888 ( 2.7 m ) +2.266 kN
m
R1 + R2=7.364 kN
2
∑ M R =0 ; 2.7 R2 = w2L
1
+1.7 P ; P = 2.266kN -> Reaction coming from the beam of E
kN
(1.888 )(2.7 m)2
m
+1.7 m(2.266 kN )
2
R 2=
2.7 m
R1 = 3.388kN ; R2 = 3.976kN
@Beam B2 to C2:
kN
(1.888 )(2.8 m)
m
R= =2.6432 kN
2
@Beam C2 to E2: P = 3.976kN -> Reaction coming from the beam of D
kN
R1 + R2=1.888 ( 2.6 m ) +3.976 kN
m
R1 + R2=6.4304 kN
w L2
∑ M R =0 ; 2.6 R2= +1.5 P ;
1
2
kN
(1.888 )(2.6 m)2
m
+1.5 m ( 3.976 kN )
2
R 2=
2.6 m
R1 = 1.6824kN ; R2 = 4.748kN
@Beam B2 to B3:
kN
(1.888 )(2. 9 m)
m
R= =2. 7376 kN
2
@Beam C2 to C3:
kN
(1.888 )(2. 9 m)
m
R= =2. 7376 kN
2
@Beam E2 to E3:
kN
(1.888 )(2. 9 m)
m
R= =2. 7376 kN
2

@Beam B3 to C3:
kN
(1.888 )(2.8 m)
m
R= =2.6432 kN
2
@Beam C3 to E3:
kN
(1.888 )(2. 6 m)
m
R= =2. 4544 kN
2
@Beam B3 to B4:
kN
(1.888 )(1.6 m)
m
R= =1.5104 kN
2
@Beam A4 to C4:
kN
R1 + R2=1.888 (3.8 m ) +1.5104 kN
m
R1 + R2=8.6848 kN
w L2
∑ M R =0 ; 2.6 R2= 2 +0. 9 P ; P = 1.5104kN
1

kN
(1.888 )(3.8 m)2
m
+0. 9 m(1.5104 kN )
2
R 2=
3.8 m

R1 = 4.7398kN ; R2 = 3.945kN
@Beam C3 to C5:
kN
R1 + R2=1.888 ( 2.6 m ) +3.945 kN
m
R1 + R2=8.854 kN
2
∑ M R =0 ; 2.6 R2= w2L
1
+1.7 P ; P = 3.945kN
kN
(1.888 )(2.6 m)2
m
+1.7 m(3.945 kN )
2
R 2=
2.6 m

R1 = 3.82kN ; R2 = 5.034kN
@Beam C5 to E5:
kN
(1.888 )(2.6 m)
m
R= =2.4544 kN
2

*By Applying the fixed walls directed to the columns + weight of the slab