Chad-Cameron Pipeline Project Case Study Managing Credit Risk Assessment 2
Chad-Cameron Pipeline Project Case Study Managing Credit Risk Assessment 2
Chad-Cameron Pipeline Project Case Study Managing Credit Risk Assessment 2
1
TABLE OF CONTENTS
1. Introduction..................................................................................................................................4
4. Financing structure................................................................................................................10
6. Discussion..............................................................................................................................12
7. Evidence................................................................................................................................13
8. Analysis.................................................................................................................................13
9. Principal problem...................................................................................................................14
12. Conclusion...............................................................................................................................15
2
13. References................................................................................................................................17
3
1. Introduction
While investing in any sector or project, certain risks are meant to be considered by
investors. These risks are described in terms of debtors’ failure to meet the obligations of credit.
In delivering credit to the projects for their successful completion, the financial institutions
experience credit risks (Hu and Cheng, 2016). These risks are observed when the project is not
functioning properly and that may be because of several reasons including weak business case,
inadequate planning, and other issues. For reducing the level of credit risks in the project
effective risk, management practices are required to be performed so that the risk level can be
The current report is developed for identifying and mitigating the credit risks that arose
during the delivery of the Chad-Cameroon pipeline project. Furthermore, the report will explain
the project finances and its financing structure for understanding the ownership and the
contractual relationship between the investment parties. The report will also analyze the level of
risks along with the principal problem and it will end with a project summary and conclusion.
The term project finance can be described as the funding or financing of industrial and
public service projects with limited resources of the financial structure based on the debt and
equity shared by the project investors. These debts and equity of the project investors are paid to
the financial institutions when the project starts to generate cash flows (Morrison, 2016). Delmon
(2015) had described project financing activities as a loan structure that is heavily dependent on
4
Weber, Staub-Bisang and Alfen, (2016) discusses the fact that project finance usually
creates value for the project investors through the reduction in the costs of project funding,
reducing corporate taxes, improving risk management practices, and reducing the level of costs
associated with the market imperfection. Yet, Lu et al., (2015) had explained the fact that project
finance activities can be difficult for the project if it does not perform in the described manner.
This is because; it will increase the costs of operations in the project. Therefore, there is a need
for economic motivation so that the project investors can easily be motivated while making
The selected case for understanding the management of credit risk is the Chad-Cameroon
Petroleum Development and Pipeline project which turns into different controversies while
performing its functions for increasing the production capacity of the oilfields of Doba, Chad to
the floating storage and offloading vessel at the Cost of Cameroon. The developed pipeline
project was around 1,070-kilometre long pipeline (Muñoz and Burnham, 2016). The
controversies that surround the pipeline project were related to corruption and diversion of
revenues acquired by the proper function of the project. Other controversies that were related to
the pipeline project were the adverse environmental effects caused by the construction of the
pipeline (Yonkeh, 2018). Different communities in Chad and Cameroon were against the project
operations as it was harming the natural habitats of the region, especially, the coastline of
Cameroon that was supporting the delivery of the produced oil. It was explained by Murrey,
(2015) that during the construction of the Chad-Cameroon pipeline, the community members of
Cameroon Coast thought that there could be oil leakage in the region. The community members’
speculation was confirmed correct in January 2007 and October 2010. Yet, the oil spill over was
5
monitored and controlled by the authorities; but the community members of Cameroon observed
Chad and Cameroon Oil pipeline project is a $3.7 billion development project that was
supported by the practices of the World Bank and IMF for delivering the funds for the
development of a project (World Bank, 2000). The development of the project was done for
extracting oil from nearly 300 wells in Chad and deliver this oil to the Cameroon coastline where
oil-shipping vessel arrives. The basic purpose of the project was to support the economic
activities of Chad as it was a land lock from its surroundings and has experienced many civil
wars after its independence from France. It was thought that the development of the pipeline
project was supposed to bring economic improvement in the region (Marchal, 2016; Dimitriou,
When the pipeline project started its operation in 2004, the researchers identified
different distinctive features. These distinctive features can easily be described through the
benefits that have a favourable impact on the economy of the country (Murrey, 2015). First of
the benefit was described by the World Bank report of 2000 as the fact that the project has
captured the eyes of all the non-governmental organisations (NGOs) for helping the people of
Chad (World Bank, 2000). This brings in the concept of scrutiny in the country operations that
6
7
8
Data Source: World Bank
Moreover, the Chad-Cameroon Pipeline Project (CCPP) helped Chad Gross Domestic Product
(GDP) growth. Evident from the charts and historical data above shows that before the onset and
start of the CCPP in 2000, Chad GDP was $1.39 billion while the GDP was $2.74 billion after
the project completion in the 2003 (Macrotrends, 2020). Subsequently, Chad GDP growth
increased tremendously by $4.41 billion in 2004 (Macrotrends, 2020). The increase in the GDP
makes Chad become one of the fastest-growing countries in the world (World Bank, 2000).
4. Financing structure
Financing can be described as the process of providing and delivering funds for doing
activities related to the project. Many financial institutions provide their financing services to
businesses and other investors so that their goals can easily be achieved (Chen et al., 2020). In
Chad GDP - Historical Data any economic system, the financing activities
Year GDP Per Capita Growth are performed to support the economic success
2018 $11.30B $730 2.64%
of the organization. Gitman, Juchau and
2017 $9.98B $664 -2.99%
2016 $10.09B $693 -6.26% Flanagan (2015), had identified two main
2015 $10.95B $776 2.77%
2014 $13.92B $1,019 6.90% types of financing for the business; the first
2013 $12.95B $980 5.70%
2012 $12.37B $967 8.88% type is equity financing and the other is debt
2011 $12.16B $983 0.08%
financing. Both financing techniques are
2010 $10.66B $892 13.55%
2009 $9.25B $800 4.22% performed after the calculation of weighted
2008 $10.35B $926 3.05%
2007 $8.64B $799 3.27%
2006 $7.42B $710 0.65%
2005 $6.65B $658 17.33%
2004 $4.41B $454 33.63%
2003 $2.74B $292 14.72% 9
2002 $1.99B $220 8.49%
2001 $1.71B $197 11.66%
2000 $1.39B $166 -0.88%
average costs of capital (WACC). These financing activities are performed in the project
In conducting the CCPP, the finances were arranged through loan agreements from the
(EIB), and International Finance Corporation (IFC). Moreover, Chad and Cameroon
governments developed equity stakes under the names of Tchad Oil Transportation Company
(TOTCO) and Cameroon Oil Transportation Company (COTCO) respectively (World Bank,
2000).
The loan provided by IFC was $100 million; this amount was sanctioned through 15
different banks and IBRD provided loans to Chad and Cameroon governments with the values of
As explained earlier, the capital to complete the total cost for the project was loaned from
different financial institutions (World Bank, 2000). The identified data for calculating the ratios
are as follows.
From the above-determined table 1 of ratios calculation, it can be analyzed that the
evaluation is done based on the debt to equity ratio that has been calculated from the amount
provided in the previous quantitative articles published at the World Bank (Bettin, Presbitero,
10
and Spatafora, 2017). The developed ratios calculation explains the analysis that the debts were
more than the amount of equity generated for acquiring the loans with the values reaching to
161.79% for TOTCO; 176.62% for COTCO; 217.39% for IFC; and 530.86% for IBRD. This
means that the country position was not sustainable to repay such loans if the project is not
At the start of the project, government organizations like COTCO and TOTCO owned the
success of the project. The companies have a good contractual relationship with the banks that
have provided them with the loan to complete and successfully operate the CCPP project that has
benefited both countries in different economic and social platforms (Odumosu-Ayanu, 2019).
6. Discussion
At the initial stage of the CCPP, the economists of both countries commented that the
project can be a difficult task as the countries do not have much equity for acquiring the loan of
such quality from the World Bank (World Bank, 2000). This risk was supported by the rebellions
increase throughout the country. These rebellions were working under the order of the former
defence minister of Chad (Murrey, 2016). It was also discussed in the report that the CCPP
would involve the drilling of 300 oil wells in Chad, and these wells will help in extracting
225,000 barrels of oil per day (World Bank 2000). This sort of oil drilling will be performed
through the oil companies who will work for extracting and shipping the oil.
ExxonMobil, Chevron, and Malaysia PETRONAS were involved in making the project
to reach towards completion in a successful manner (Schritt and Behrends, 2018). Yet, the
Malaysian PETRONAS was separated from the contract, as they were not abiding by the policies
established by international law. Exxon assessed this outcome to be uncertain, and their
11
Malaysian expenses increased. The rule of saving arrangement terms from one-sided adjustment
had not been supported (Gab-Leyba, and Laporte, 2015). With one company leaving the
contract, the operations of drilling, processing, and sending the oil to the vessel were performed
7. Evidence
It had been discussed in the World Bank report that the involvement of many financial
institutions and other oil extracting companies have supported the success of the project even
though it was at the brinks of collapse at the start (World Bank, 2000). This success was attained
when significant adjustments were made by COTCO and TOTCO alike. Moreover, the private
sponsors of the project and the Chad-Cameroon Government officials had taken the necessary
steps for making effective control of the prevailing situation (Kounga and Simo, 2019). It was
also mentioned in the report that the NGOs and the local public also support the actions of the
Government for managing the construction in an effective manner (World Bank, 2000). Such
involvement from banks and the Chad and Cameroon governments make it possible to reduce the
8. Analysis
12
From the above-developed table of risks, it is identified that the two key credit risks were
political risks and the commitment level of private sector investors. This is because, if the
political conditions are not supported by the CCPP, then the project can experience failure in the
very beginning, and the political instability will stop the investment from private investors.
Hence, this situation could create problems in the successful completion of the project.
Therefore, the political risks of the country must be resolved, and the political conditions must be
9. Principal problem
In Chad, the principal problem was poverty. This problem was identified by the World
Bank report in the poverty assessment report published in the year 1997 (World Bank, 2000).
The main reason behind such a problem was inadequate healthcare practices and education level.
This lack of education and poor healthcare system also became the problem of the CCPP to be
completed in the assigned time. However, after the project was completed, the poverty problem
1. Selection of private investors must be done based on their investment level. This can help
controlling the large change of revenues generated from project success (World Bank,
2000).
3. Keep a continued level of commitment among the investors of the project (World Bank,
2000).
13
4. A copy of records must be maintained by the government officials for distributing the
12. Conclusion
Whenever investments are made in the government or private sector projects, certain
risks hold great importance for the investors in making their investment. The project report starts
with the description of project finance and develops the path for selecting the case for making an
analytical report. The selected case was Chad and Cameroon Pipeline Project (CCPP) which
started to export the extracted oil from Chad and deliver it to the coasts of Cameroon without any
difficulty.
14
This project can increase the GDP of the chosen countries many times over. The project
was financed through the project finance structure. The finances for the project were acquired
from taking loans from banks and other financial institutions. This was done through effective
relation and contractual development between the parties of the contract. In the end, it was
evident that such project completion has reduced the level of poverty in the Chad region.
15
13. References
Bettin, G., Presbitero, A.F. and Spatafora, N.L. (2017) ‘Remittances and vulnerability in
Chen, Y., Zhang, W., Yan, X. and Jin, J. (2020) ‘The life-cycle influence mechanism of the
Danenas, P. and Garsva, G. (2015) ‘Selection of support vector machines-based classifiers for
Delmon, J. (2015) Private sector investment in infrastructure: Project finance, PPP projects and
Dimitriou, D.J., Mourmouris, J.C. and Sartzetaki, M.F. (2015) ‘Economic impact assessment of
Gitman, L.J., Juchau, R. and Flanagan, J. (2015) Principles of managerial finance. Pearson
Hu, N. and Cheng, H. (2016) ‘Survival Analysis and ROC Analysis in Analysing Credit Risks:
Assessing Default Risks over Time’, Analysing Risk through Probabilistic Modelling in
Isaac, T. (2015) ‘An Economic Analysis of Boko Haram’s Activities in the Chad-Cameroon-
16
Kounga, G.J. and Simo, A.K. (2019) ‘Human rights and environmental justice in development
projects in Central Africa: from the Chad-Cameroon Pipeline to the Mbalam-Nabéba Iron
Lu, Z., Peña-Mora, F., Wang, X.R., Shen, C.Q. and Riaz, Z. (2015) ‘Social impact project
Engineering, 123, pp.300-307.
<https://www.macrotrends.net/countries/TCD/chad/gdp-gross-domestic-product>
Marchal, R. (2016) ‘An emerging military power in central Africa? Chad under Idriss Déby’,
Muñoz, J.M. and Burnham, P. (2016) ‘Subcontracting as corporate social responsibility in the
corporate social responsibility. Dislocations, vol. 18, Oxford: Berghahn, New York, pp.
152-178.
Murrey, A. (2015) ‘Narratives of Life and Violence along the Chad-Cameroon Oil Pipeline’,
17
Murrey, A. (2016) ‘Slow dissent and the emotional geographies of resistance’, Singapore
Odumosu-Ayanu, I.T. (2019) ‘Local communities, environment, and development: the case of
oil and gas investment in Africa’, In Research Handbook on Environment and Investment
Ryan, K. (2020) [2.2] Striking Oil: A Critical Analysis Of Corporate Social Responsibility As
2020].
Schritt, J. and Behrends, A. (2018) “Western” and “Chinese” Oil Zones: Petro-Infrastructures
and the Emergence of New Trans-territorial Spaces of Order in Niger and Chad.
In Spatial Practices. Territory, Border, and Infrastructure in Africa. Germany: Brill, pp.
211-230.
Verdouw, W., Uzsoki, D. and Ordoñez, C.D. (2015) Currency risk in project finance. Winnipeg
discussion-paper. pdf.
investment strategy, sustainability, project finance and PPP. John Wiley & sons.
http://documents.worldbank.org/curated/en/234181468743694143/pdf/multi-page.pdf
18
Yonkeh, H. (2018) The Role Of World Bank In Development And Human Rights: Case Study Of
19