PLTP DIENG UNIT 1

PEKERJAAN JASA SEWA ALAT BERAT DAN PENGADAAN


MATERIAL PERSIAPAN WORK OVER PAD#10
PLTP DIENG UNIT 1

WEEKLY REPORT #1

Period : July 3 - July 9, 2020

0 B Issued for Approval


Prepared Checked Approved Approved
REV DATE SC DESCRIPTION
Sub Conttractor Client
STATUS CODE (SC): A = Issued for Review, B = Issued for Approval

DOCUMENT NO :
001/WR/WJA/GEO-PRJ2/020
WEEKLY PROGRESS REPORT
Pekerjaan Jasa Sewa Alt Berat Dan Pengadaan Material Persiapan Work Over Pad#10 Unit Dieng

No. of Week : Week #1


Period : 03-Jul-20 to 09-Jul-20

Weigth Last comulative week Progress this week comulative Progress


Sect. Description Unit Qty
(%) Qty Progress Weigth Qty Progress Weigth Qty Progress Weigth
% % %
1 Mobilisasi & Demob Peralatan ls 1 4,88 - - - 0,33 33,33 1,63 0,33 33,33 1,63
2 Sewa Excavator PC. 75 Jam 300 24,40 - - - 62,00 20,67 5,04 62,00 20,67 5,04
3 Sewa Excavator Pc. 200 Jam 200 24,40 - - - 62,00 31,00 7,56 62,00 31,00 7,56
4 Sewa Dump Truck hari 20 32,53 - - - 7,00 35,00 11,39 7,00 35,00 11,39
5 Material base course m3 185 13,79 - - - 0,00 0,00 0,00 - - -

Total Progress 100,00 - 25,62 25,62

Prepared by, Review by, Acknowledge Approved by,

B. Wasqitho
Site Manager
PT. Wirana Jayatama Abadi PT. Geodipa Energy (Persero) PT. Geodipa Energy (Persero) PT. Geodipa Energy (Persero)
DAILY PROGRESS REPORT
Pekerjaan Jasa Sewa Alt Berat Dan Pengadaan Material Persiapan Work Over Pad#10 Unit Dieng

No. of Week : Week #1


Period : 03-Jul-20 to 09-Jul-20

Weigth Progress this week Total


Sect. Description Unit Qty
(%) 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul Total Total Total
Progress Progress Progress Progress Progress Progress Progress
0 0
Qty (% /QTY) weigth (%) Qty (% /QTY) weigth (%) Qty (% /QTY) weigth (%) Qty (% /QTY) weigth (%) Qty (% /QTY) weigth (%) Qty (% /QTY) weigth (%) Qty (% /QTY) weigth (%) QTY Progress weigth
1 Mobilisasi & Demob Peralatan ls 1 4,88 0,33 33,33 1,63 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,33 33,33 1,63
2 Sewa Excavator PC. 75 Jam 300 24,40 6,00 2,00 0,49 9,00 3,00 0,73 10,00 3,33 0,81 10,00 3,33 0,81 9,00 3,00 0,73 9,00 3,00 0,73 9,00 3,00 0,73 62,00 20,67 5,04
3 Sewa Excavator Pc. 200 Jam 200 24,40 6,00 3,00 0,73 9,00 4,50 1,10 10,00 5,00 1,22 10,00 5,00 1,22 9,00 4,50 1,10 9,00 4,50 1,10 9,00 4,50 1,10 62,00 31,00 7,56
4 Sewa Dump Truck hari 20 32,53 1,00 5,00 1,63 1,00 5,00 1,63 1,00 5,00 1,63 1,00 5,00 1,63 1,00 5,00 1,63 1,00 5,00 1,63 1,00 5,00 1,63 7,00 35,00 11,39
5 Material base course m3 185 13,79 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00

Total Progress 100,00 25,62


Bulletin Weekly Report
Pekerjaan Jasa Sewa Alt Berat Dan Pengadaan Material Persiapan Work Over Pad#10 Unit Dieng

No. of Week Week #1


Period 03-Jul-20 to 09-Jul-20

1. Construction Progress Summary

Duration Progress
Week no.
Sect. Description (week) Plan Actual Variance
Plan Actual % % %
1 Base Line work 6 1 24,08 25,62 1,54
Reference : S-Curve and schedule approval

2. Construction Progress Detail

Progress
Sect. Description Plan Actual Variance
% % %
1 Mobilisasi & Demob 1,63 1,63 0,00
2 Sewa Excavator PC. 75 4,49 5,04 0,55
3 Sewa Excavator Pc. 200 6,57 7,56 0,99
4 Sewa Dump Truck 11,39 11,39 0,00
5

24,08 25,62 1,54

3. Highligths

No Description Remark
1 Pekerjaan sudah dimulai dr tgl. 3/7/2020
2
3
4

4. Work Related Accident or Incident Report

Progress
No Description
Last week This week Total

1 Fatallity 0,00 0,00 0,00


2 Medical Treatment Case 0,00 0,00 0,00
3 First Aid Case 0,00 0,00 0,00
4 Day Away from Work 0,00 0,00 0,00
5 Lost Time Injury 0,00 0,00 0,00
6 Nearmiss 0,00 0,00 0,00

5. Weather Report

Time
No Date
8-9 AM 9-10 AM 10-11 AM 11-12 AM 12-1 PM 1-2 PM 2-3 PM 3-4 PM 4-5 PM
1 03 Juli 2020 C C C C C C C C C
2 04 Juli 2020 C C C C C C C C C
3 05 Juli 2020 C C C C C C C C C
4 06 Juli 2020 C C C C C C C C CL
5 07 Juli 2020 C C C C C C C C CL
6 08 Juli 2020 C C C C C C C C CL
7 09 Juli 2020 C C C C C C C C CL

Legend:
C = Clear
CL = Cloudy
R = Rainy
F = Fog
Weekly Report
Progress Picture

Kondisi Awal Pad 10


Weekly Report
Progress Picture

Kondisi Awal - Akhir


Weekly Report
Progress Picture

Kondisi Awal - Akhir


Weekly Report
Progress Picture

Konidisi Awal - Akhir


Weekly Report
Progress Picture

Project Activity