Quotation 1

This document provides an approximate price quotation for the capital costs of installing a solar PV power project in India. It lists 7 major cost components, including PV modules at 57.49% of total cost, civil and general works at 8.5% of cost, mounting structures at 9.35% of cost, and power conditioning units at 5.95% of cost. The total estimated capital cost is 11762.6 lakh rupees or approximately 588.13 lakh rupees per MW generated. The quotation is only an indication and final prices would require a detailed study of tender documents.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
103 views1 page

Quotation 1

This document provides an approximate price quotation for the capital costs of installing a solar PV power project in India. It lists 7 major cost components, including PV modules at 57.49% of total cost, civil and general works at 8.5% of cost, mounting structures at 9.35% of cost, and power conditioning units at 5.95% of cost. The total estimated capital cost is 11762.6 lakh rupees or approximately 588.13 lakh rupees per MW generated. The quotation is only an indication and final prices would require a detailed study of tender documents.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Approximate Price Quotation*

Sl. No Particulars Capital Cost Lakh % of Total Cost Total Cost Lakh
Rs./MW Rs.

1 PV Modules 338.13 57.49 6762.6

2 Civil and General Works 50 8.50 1000

3 Mounting Structures 55 9.35 1100

4 Power Conditioning Unit 35 5.95 700

5 Evacuation Cost (including 60 10.20 1200


transmission)
6 Preliminary and Pre-Operative 50 8.50 1000
Expenses including Contingency

7 Total 588.13 100.00 11762.6

*The quotation above is indicative and the final price can only be determined after detailed study of
the tender documents.