Cap 6 Site Layout PDF
Cap 6 Site Layout PDF
Cap 6 Site Layout PDF
Site activities
The time needed for carrying out the principal activities can be estimated from the data
obtained previously for preparing the material and labour requirements. With repetitive (or
over-lapping) activities estimates will be required to determine the most economical
balance of units which will allow simultaneous construction processes; this in turn will help
to establish staff numbers, work areas and material storage requirements, access facilities
and possibly plant types and numbers. If a particular process presents a choice in the way
the result can be achieved the alternatives must be considered; for example, the rate of
placing concrete will be determined by the output of the mixer and the speed of
transporting the mix to the appropriate position. Alternatives, which can be considered are:
1. More than one mixer
2. Regulated supply of ready mixed concrete
3. On large contracts, pumping the concrete to the placing position.
Efficiency
To achieve maximum efficiency the site layout must aim at maintaining the desired
output of the planned activities throughout the working day and this will depend largely
upon the following factors:
1. Avoidance, as far as practicable, of double handling materials
2. Proper store-keeping arrangements to ensure that the materials are of the correct type,
in the correct quantity and are available when required
3. Walking distances are kept to a minimum to reduce the non-productive time spent in
covering the distances between working, rest and storage areas without interrupting the
general circulation pattern.
4. Avoidance of loss by the elements by providing adequate protection for unfixed
materials on site, thereby preventing time loss and cost of replacing damaged materials
5. Avoidance of loss by theft and vandalism by providing security arrangements in
keeping with the value of the materials being protected and by making the task
difficult for the would-be thief or vandal by having adequate hoardings and fences.
Also to be avoided is the loss of materials due to pilfering by site staff who may
consider this to be a perquisite of the industry. Such losses can be reduced by having
an adequate system of stores’ requisition and material checking procedures.
6. Minimizing on-site traffic congestion by planning delivery arrivals, having adequate
parking facilities for site staff cars and mobile machinery when not in use, and by
having sufficient turning circle room for the types of delivery vehicles likely to enter
the site.
Movement
Apart from the circulation problems mentioned above the biggest problem is one of
access. Vehicles delivering materials to the site should be able to do so without difficulty or
Control
This is mainly concerned with the overall supervision of the contract, including men,
materials and the movement of both around the site. This control should form the hub of
the activities, which logically develops into areas, or zones of control radiating from this
hub or centre. Which zone is selected for storage, accommodation or specific activities is a
matter of conjecture and the conditions prevailing on a particular site but as a rule the final
layout will be one of compromise with storage and accommodation areas generally
receiving priority.
Accommodation
Accommodation for staff is covered by the Construction (Health and Welfare)
Regulations 1966, which sets out the minimum amount and type of accommodation which
must legally be provided for the number of persons employed on the site and the
anticipated duration of the contract. Apart from these minimum requirements the main
areas of concern will be sizing, equipping and siting the various units of accommodation.
2. Car Park
Site personnel, visitors or suppliers need adequate and secure parking space on the site.
This need to be sited preferably in front of the site offices so that:
- the timekeeper can book in arrival and departure times of vehicles
- a material checker at the entrance to site can easily check and direct material supply
- site security may check and ensure that those leaving the site do not carry materials
or components, tools or equipment with them.
3. Site Signboard
Uses of a site identification board include:
It is an advertising aid, hence it should be clearly displayed
It saves traffic and visitors problems in finding the site
In sub-urban or rural locations ‘finger boards’, a form of signboard, is very
useful in directing people to the site as street names are not always easy to
locate.
Items appearing on a signboard for a proposed site include: Name of project, name of
client, name of contractor, name of architect, name of Chief Engineer, name(s) of
mechanical, civil, structural Engineer(s), name of quantity surveyor, name(s) of sub-
contractor(s).
4. Amenities
Although minimum requirements covering operatives’ welfare facilities on site depends
on the size and nature of the site as regards other provisions, most sites will consist of
hutments divided into three groups:
(a) Administrative offices
(b) Operatives’ huts
(c) Storage and general
5. Storage Areas
Storage areas for tools and equipment and materials may be manned or unmanned, open
or under lock and key depending on:
Physical properties – size, shape, weight and mode of delivery will assist in
determining the safe handling and stacking method(s) to be employed on site, which
will in turn enable handling and storage costs to be estimated.
Protection – Building materials and components, tools, plant and equipment will
usually require some form of weather protection to prevent deterioration, especially
those materials classified as non-durable.
Security – many tools and equipment and building materials have a high resale
and/or usage value to persons other than those for whom they were ordered and
unless site security is adequate, losses due to theft, pilferage and vandalism can
become unacceptable.
Organisation – this is the planning process of ensuring that all the materials and
equipment are delivered to site at the correct time, in sufficient quantity, the right
quality, the means of unloading is available and that adequate space for storage or
stacking has been allocated throughout the duration they are on site.
7. Site Security
To enhance security at the site for materials, tools, equipment and plant, site personnel,
vehicles and the construction work in progress, the site management need to consider local
vandalism and pilfering record, security patrol facilities, need for night security, fencing
and hoarding requirements.
Fencing
A building site and the compound can be given a degree of protection by surrounding
with a fence. A fence is an erection put to a property to mark its extent without necessarily
barring one from seeing inside.
The fence fulfills three functions:
1) Defines limit of the site or compound
2) Acts as deterrent to would-be trespassers and thieves
3) Provides protection to the public
A fence can be constructed to provide a physical barrier of solid construction or a visual
barrier of open work construction. If the site is to be fenced as part of the contract it may be
advantageous to carry out this work at the beginning of the site operations. The type of
fencing chosen will depend upon:
i) The degree of security required
ii) Cost implications
iii) Type of neighbourhood, and
iv) Duration of contract
A security fence around the site or compound should be at least 1.8m high above the
ground and include the minimum number of access points which should have a lockable
barrier or gate. (See Fig. 1.3)
Hoardings
These are close boarded fences or barriers erected adjacent to a highway or public
footpath to prevent unauthorized persons obtaining access to the site and to provide a
degree of protection for the public from the dust and noise associated with building
operations.
Under the Highways Act 1959 (Sec. 147 and 148) it is necessary to obtain written
permission from the Local Authority to erect a hoarding. The person, which is in the form
Fig 1
PLOT B
PROPOSED
BUILDING
PLOT A PLOT C
ROAD
3 (a) (i) Give TWO uses of a site identification board on a construction site. (2mks)
(ii) List EIGHT items that would appear on a signboard for a proposed
construction site. (4mks)
(b) Enumerate SIX welfare items that can be provided for workers on a construction
site. (6mks)
(c) State THREE results of improved working conditions on a site. (3mks)
(d) Outline SIX factors on how to achieve maximum efficiency on a well-planned
site. (9mks)
5 (a) To achieve maximum efficiency on a construction site, site layout planning must
aim at maintaining desired output of planned activities throughout the working
day.
State FIVE site planning measures that may be taken to achieve this. (5mks)
(b) Outline the provisions that should be complied with when providing
accommodation for watchmen on site as stipulated in the Building Code. (6mks)