Maintenance and Repair Works: Canals

Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

Canals 29

Chapter 5

Maintenance and repair works

5.1 INTRODUCTION
This chapter describes why and how a canal system should be maintained. The chapter also
looks at some of the most important repair works in connection with canals.
The performance of an irrigation canal system depends not only on how the system is
operated, but also on the condition of the canals. Irrigation canals function well so long as they
are kept clean and if they are not leaking. If no attention is paid to the canal system, plants may
grow and the problem of siltation may arise. Even worse, the canals may suffer from leakages.
Plant growth and sedimentation not only impede the flow in a canal, they also diminish
the area of the cross-section. As a consequence, the canal capacity may diminish (see Section
3.3). A reduction in the capacity may result in overtopping and a limit on water supply to the
fields. The available water will also be reduced when there are leakages in a canal. To protect
the system from these problems, the canals should be maintained on a regular basis.
It is not just the smaller, tertiary irrigation canals that need to be maintained, it is the
primary and secondary canals as well. Sometimes these canals may be located far from the
farmers’ fields and this can be one reason why farmers show no interest in maintaining them.
However, the smaller canals receive water from these canals and so maintenance of the larger
canals is of vital importance for the proper functioning of the whole system.
Even when a canal is well maintained, serious technical problems may arise. These
problems need to be solved by repair or improvement works. A repair should usually be done
as soon as possible, depending on the severity of the problem. Improvements, such as the
lining of a canal section, may be postponed until the end of an irrigation season, when canals
are dry and farmers have more time available.
After a serious problem is found on an inspection tour, a team of workers or farmers
should be available for repair as soon as possible. Such a team should be formed at the beginning
of the irrigation season in order to have it on call in case of emergencies. The same team may
be asked to do the improvement works. If necessary, a contractor may be asked to do the job.

5.2 CANAL MAINTENANCE

A good maintenance programme can prolong the life of canals. A routine, thorough programme
should be kept to. Maintenance of an irrigation canal system is usually carried out in between
two irrigation seasons, or at times of low water demand. It consists of cleaning, weeding, de-
silting, re-shaping, and executing minor repairs.
30 Maintenance and repair works

FIGURE 29
Weeding, cleaning and de-silting

• Bushes or trees on canal embankments should be removed. They may obstruct the water
flow and their roots will open the compacted soil in the banks and cause the development of
leakages.

• Plants, silt and debris in the canal should be removed. While cleaning the canal bed, care
must be taken that the original shape of the cross-section is kept. For this, a wooden frame,
or template, with the exact dimensions of the designed cross-section of the canal being
cleaned, can be of great help (see Section 5.6.1).

• Breaches and rat holes in the embankments should be filled with compacted soil, inside as
well as outside of the embankment. For compacting, the soil should be wetted.

• Weak sections and sections of canal embankments where people or animals cross the canal
should be strengthened with compacted soil or with bricks.

• Eroded sections of a canal should be rebuilt to the original shape.

See also Figures 29 and 30.


For maintenance operations it is important to organize farmers and to involve them in the
activities. See Figure 31.

5.3 REDUCTION OF SEEPAGE LOSSES


Parts of a canal bank or the entire bank can be highly permeable to water. Water that seeps
through the banks will be lost for irrigation and may create waterlogging in the fields and roads
adjacent to the canal.
There are two ways to overcome seepage problems, either

• reduce the permeability of the canal bank, or

• line the canal.

The second solution, lining, will be described in Chapter 6.


Canals 31

FIGURE 30
Fully covered canal bed

FIGURE 31
Canal maintenance
32 Maintenance and repair works

Reducing the permeability of a canal bank


The permeability of a
canal bank can be re-
duced by compacting
the centre, or core of
the embankment. The
core is first excavated
by digging a narrow
trench, and then re-
placed with soil in
layers, compacting
each layer. The com-
pacted core should
extend above the water
level.
The procedure is:
Step 1 Remove the
vegetation on the canal
bank and the top of the
bank. (Figure 32-A)
Step 2 Excavate a
narrow trench near the
inner side of the canal
bank.
A trench is
excavated in the perm-
eable section of the
canal. The width of the
trench is at least
0.5 x the water depth
in the canal. The
bottom of the trench
should be some 20 cm
below the original
ground surface ele-
vation (Figure 32-B)
Step 3 Compact the
bottom of the trench
with a manual tamper
and replace the soil in
layers of about 5 to 10
cm each. The soil
should be moist when
being compacted.
When the exca-
vated material is rather
Canals 33

sandy, the core should be filled with other material which contains more clay. Each layer is
wetted and the wetted soil is then compacted. Wetting the soil is conditional for good compaction,
since the aggregates in soil that is moist will disintegrate by tamping, while those in dry soil
will not. (Figure 32-C)
Step 4 Fill and compact the trench until the top is reached. (Figure 32-D)

5.4 REPAIR OF A LEAK


Most irrigation canals
will leak.
A hole or a
crack in the bank of a
canal, through which
water is leaking, is
easily observed since
the fields adjacent to
the leaking canal will
be wet. A hole or a
crack in the bed of a
canal is difficult to see,
unless the canal is dry
and the bed is
inspected very care-
fully.
Leaks should be
repaired immediately
after they have been
observed.
The procedure
for repairing a leak is:
Step 1 Empty the
canal and indicate the
location of leakage
with pegs. They are
placed at its entrance in
the canal bed and at its
exit in the outer bank.
Step 2 Remove the
vegetation and keep it
apart. Excavate the
canal bank to well below and besides the leak. The canal bank which leaks is excavated in
steps, with the smallest step well below the leak. (Figure 33-B)
Step 3 Rebuild the canal bank by filling the bank in layers with moist soil, and compact each
layer well. (Figure 33-C)
34 Maintenance and repair works

For lined canals, the same procedure as above can be followed but with one difference:
before the bank is excavated, part of the canal lining should be removed. After filling and
compacting the earth bank, the lining should be reconstructed.
NOTE 1: Repair of a crack in the canal lining alone will not be sufficient, as the lining could
be severely undermined by the leaking water, which will quickly cause a new hole
or crack to appear in the lining.
NOTE 2: Joints between lined sections of a canal should be sealed periodically to avoid
leakages.

5.5 HOW TO AVOID OVERTOPPING


Overtopping of a canal section is caused by an excessive discharge in that section in relation to
the actual canal capacity. Canal banks which are frequently overtopped are very probably
eroded and lowered, and thus the actual capacity will be less than the original capacity for
which the canal has been designed. Overtopping can be avoided in two ways, either:

• reduce the discharge, or


• increase the canal capacity.

No explanation is necessary for the first solution, and so only the second solution, which re-
establishes the canal capacity, is described below.
The procedure to re-establish a canal capacity by rebuilding its banks is:

Step 1 Remove the


vegetation, if any.
Hammer pegs in the canal
bank at both sides of the
section concerned.
(Figure 34-A) (With these
pegs and a rope the level
of the section can be
checked).
Step 2 Excavate the top
and sides of the bank like
stairs. (Figure 34-B)
Step 3 Rebuild the bank
by filling the excavated
portion with clayey soil.
Fill by layers of 5 to 10 cm
and compact it in wet
condition. (Figure 34-C)
While raising the
embankment, check the level regularly.
Step 4 Trim the sides and lay grass sods on the bank when the top is reached. (Figure 34-D).
Canals 35

When it is impossible
to avoid high water levels,
an emergency outlet, or
spillway, can be installed.
An emergency outlet con-
sists of a protected lowered
section of a canal embank-
ment and a protected outlet
to the drainage system.
Such a structure will allow
water to escape into the
drainage system without
damaging the canal banks.
The level and the
length of the structure
should be such that the
excess discharge can be
safely evacuated and the
water level will not rise
higher than the highest
allowed water level (free
board level).

FIGURE 35
Emergency outlet

Figure 35 shows an emergency outlet. The water level is lower than the crest of the
emergency outlet. An engineer should be consulted for the design and the installation of an
emergency outlet.
36 Maintenance and repair works

5.6 CANAL REPAIR AND PREVENTING EROSION


5.6.1 Repair
An eroded canal or canal embankment needs at some time to be reshaped. First the repair of an
eroded canal is described, and second the repair of gullies and cracks in an eroded canal
embankment.
Reshaping an eroded
cross-section
The reshaping and
widening of an eroded
cross-section involves the
following steps:
Step 1 Construct a
wooden template.
If the original side slopes
had been constructed too
steeply and thus were un-
stable, make the template
so that the new side slopes
are flatter. The top width
of the canal is then larger
while the bed width re-
mains the same. Care
must be taken to avoid
narrowing the original
canal bank crest widths.
(Figure 36-A)
Step 2 Hammer in reference pegs
to indicate the original level of the
canal banks on each side of the
canal. Excavate the bed and sides
of the eroded canal section in steps
until they reach slightly below the
actual bed level so that the new soil
to be placed will make better contact
with the original ground surface.
(Figure 36-B)
Step 3 Fill and compact moist soil
layer by layer, using the template
for final shaping. Each layer to be
compacted should not be thicker
than 5 to 10 cm. (Figure 36-C)
Step 4 Check the cross-section and bank levels with the template and the reference pegs.
(Figure 36-D)
Canals 37

Repair of cracks and gullies in a canal embankment


The repair of cracks and gullies can be executed as follows:

Step 1 Remove any


plants from banks
which show cracking
and in which small
gullies have been
formed by overtopping
water or by heavy
rainfall. (Figure 37-A)

Step 2 In the case of


deep cracks and gullies,
excavate the bank
partly. Small cracks are
to be filled with fine-
textured soil, moistened
and compacted.
(Figure 37-B)

Step 3 Rebuild the


bank by filling in layers
and compacting the
moist soil. (Figure 37-
C)

5.6.2 Preventing erosion


Erosion of an irrigation canal may be prevented by either:

• reducing the flow velocity, or

• lining the canal.


38 Maintenance and repair works

Reducing the flow velocity


The flow velocity in a canal can be
reduced by reducing the canal bed
slope. Usually the canal bed fol-
lows the slope of the terrain, which
may have a slope which is too steep
for a canal. To avoid such an
excessive canal bed slope in the
steep area, the slope of the canal can
be modified by constructing part of
the canal in cut and part in fill,
which however involves moving
large volumes of earth. The volume
of earth movement in cut and fill
can be reduced by installing drop
structures, which connect two
sections of a canal with different
elevations. See Figures 38-A to C.
When the slope of a canal is
reduced with the installation of drop
structures, the flow velocity will be
less than before. In order to have
the same canal capacity, the canal
cross-section has to be made bigger.
Figure 38-A shows a canal
section which has the same slope
as the field. The field slope is steep
and the flow velocity in the canal
exceeds its limiting value, causing
erosion of the canal. Figure 38-B
shows a canal section where a
flatter slope is obtained by
modifying the existing field slope
by cut and fill, but a large volume
of earth has to be moved in this case
to achieve a canal bed slope which
does not cause erosion. The volume
of earth to be moved increases as
the differ-ence between the natural
field slope and the canal slope is
made larger. Figure 38-C shows a canal section with the same overall canal slope of the section
in Figure 38-B, but the volume of earth to be moved in this case is much less than in Figure 38-
B, but at the cost of including a drop structure, which has to be constructed.
Of course, it is not easy to rebuild an existing canal in order to modify its bed slope. In
such a case it is possible to install series of check structures in the canal to reduce the flow
velocity, as in Figure 39. See also Training Manual 8, Structures, in this series.
Consult an engineer for installing drop or check structures.
Canals 39

FIGURE 39
Series of checks in a steeply sloping canal

Lining the canal


Canal sections which are eroded by fast flowing water can be lined.

• The limiting flow velocity of a lined canal is higher than that of an equivalent unlined
canal. Thus the canal slope can be steeper.

• Because the flow velocity in a lined canal can be higher than that in an unlined canal, the
cross-section of a lined canal can be smaller than that of an unlined canal carrying a
similar discharge.
Lining of canal sections is described in the next chapter.
40 Maintenance and repair works

You might also like