This document contains details regarding shotcrete testing for a tunnel construction project. It includes information on the mix design, application process, and penetrometer test procedure and results. The penetrometer test involves measuring the force required to push a 3mm diameter plunger 15mm into the shotcrete specimen at various time intervals. Test results are provided in a table showing the average force measured at 6 minutes, 10 minutes, 30 minutes, and 60 minutes post application. The required forces and strengths are also listed for comparison at each interval.

Uploaded by

jitendra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
326 views14 pages

78-85 F Shotcrete Test Formats

This document contains details regarding shotcrete testing for a tunnel construction project. It includes information on the mix design, application process, and penetrometer test procedure and results. The penetrometer test involves measuring the force required to push a 3mm diameter plunger 15mm into the shotcrete specimen at various time intervals. Test results are provided in a table showing the average force measured at 6 minutes, 10 minutes, 30 minutes, and 60 minutes post application. The required forces and strengths are also listed for comparison at each interval.

Uploaded by

jitendra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 14

Client: Project: No:

Dated :-
Rev:-0
Four laning of Parwanoo-Solan Section of NH-22 Page :- 010f 01

Barog Tunnel

SheetNo:-
SITE
Grade of Shotcrete
SHOTCRETE SITE CONTROL Date of Spraying
Chainage
Location

Approved Mix Proportions


Batch Qty Cement 10mm Crushed Sand Natural Sand Water HRWR

Batch Weight Mix Data


Batch Moisture
Quantity, Water Adjustment Corrected
Moisture Batch
Mix Ingredeints SSD condition Absorption Source Remarks
Content (%) quantity
(Kg) (%)
(%) (Kg) (Kg)
--------m3

Cement

10mm

C.Sand

N.Sand

Water

Admixture
Initial 30minutes 1hr.
Slump

Concrete Temperature Air Temperature

………………………………………………………………………………………
Particulars of Specimen Cast ……………………………………………………………………………………
…………………………………………………………………………………..
……………………………………………………………………………………..

Issued by Contractor: Approved by Engineer:

Name: ................................ Name: ................................

Sign : ................................ Sign : ................................


Date : ................................ Date : ................................

Page-78
Page-78
Client: Project: No:
Dated :-
Rev:-0
Four laning of Parwanoo-Solan Section of NH-22 Page :- 010f 01

Barog Tunnel

Sheet No:-
SITE
SHOTCRETE Date of Testing
COMBINED AGGREGATE Aggregate Source
GRADATION
Aggregate Location
Sampling By

Batch Weight Mix Data


Combined Aggregate
Sieve Individual % Passing Limits
Gradation Combined Approved
Size
10mm Sand 1 Sand 2 % Passing Gradation
(mm) 10mm Sand 1 Sand2 Upper Lower
(…….%) (…..%) (…..%)
12.5
10
4.75
2.36
1.18

0.6

0.3
0.15

100

90

80

70

60

50

40

30

20

10

0
0,15 0,30 0,6 1,18 2,36 4,75 10 12,5 20

Issued by Contractor: Approved by Engineer:

Name: ................................ Name: ................................

Sign : ................................ Sign : ................................


Date : ................................ Date : ................................

Page-79
Page-79
Client: Project: No:

Dated:-
Four laning of Parwanoo-Solan Section of NH-22
Rev: 0
Page :- 01 0f 01
Barog Tunnel

Sheet No:-
Tunnel
SHOTCRETE TESTING: Heading
PENETROMETER TEST Tunnel Meter (TM) to
Round Number

Date / Time of Spray Mix Design


Temp. Air / Mix Accelerator Brand
Shotcrete pump Accelerator %
Nozzleman

Test Procedure: A penetrometer with a 60 degree pointed 3mm diameter plunger is pushed 15mm
into the specimen and the required force read. At each time interval 10 tests are
carried out within a maximum of 1 minute and the average calculated.
For calibration reference see Austrian Guideline for Shotcrete, Figure 12/5.

Test No. 6 Minutes 10 Minutes 30 Minutes 60 Minutes


Force Remarks Force Remarks Force Remarks Force Remarks
[N] [N] [N] [N]
1
2
### 3
4
5
6
7
8
9
10
Sum
Average
Req. Force 125 N 150 N 225 N 325 N
Strength N/mm 2
N/mm
2
N/mm 2
N/mm2
Req. Strength 0.20 N/mm2 0.25 N/mm2 0.35 N/mm2 0.50 N/mm2

Remarks:

Issued by Contractor: Approved by Engineer:

Name: ................................ Name: ................................

Sign : ................................ Sign : ................................


Date : ................................ Date : ................................

Page-80
Client: Project: No:
Dated :-
Rev:-0
Four laning of Parwanoo-Solan Section of NH-22 Page :- 010f 01

Barog Tunnel

Sheet No:-
SITE
SHOTCRETE TESTING : Chainage
PANEL SPRAYING Location
Date of Casting
Sample Id. Mark

Grade of Shotcrete NozzleMan


Concrete Temp. Accelerator Brand
Ambient Temp. Accelerator %

Mix Proportions
Batch Qty Cement 10mm Crushed Sand Natural Sand Water HRWR

Tests Done Penetrometer Test Refer attached Format No

Tests To be Done

Remarks:

Issued by Contractor: Approved by Engineer:

Name: ................................ Name: ................................

Sign : ................................ Sign : ................................


Date : ................................ Date : ................................

Page-81
Client: Project: No:
Dated:-
Rev. 0
Four laning of Parwanoo-Solan Section of NH-22 Page:-01 of 01

Barog Tunnel

Sheet No:- SCCC/


Sample ID Mark
Site
SHOTCRETE TESTING: Chainage
CORE CRUSHING Location
Date of Casting
Date of Extraction
Cores taken from: : Works

: Panels

Penetrometer Test carried out on same Specimen : No Yes, Refer Sheet No


Shot Bolt Test carried out on same Specimen : No Yes, Ref Sheet No

FIELD SUITABILITY TEST QUALITY CONTROL TEST


(Each 5 nos. 3, 7, 28, (56) days) (Each 4 nos. 3, 7, 28, (56) days)

Length Dia of Core Eq. Cube Average


Date of Age Weight Density Load Require
No. of Core Core strength strength Strength
Testing (days) (Kg) (Kg/m3) (Kn) ments
(mm) (mm) (Mpa) (Mpa) (Mpa)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Remarks:

Issued by Contractor: Approved by Engineer:

Name: ................................ Name: ................................

Sign : ................................ Sign : ................................

Page-82
Date : ................................ Date : ................................

Page-82
Client: Project: No:
Dated:-
Rev.
Page:-01 of 01

Barog Tunnel

Sheet No:- SCCC/


CONCRETE / GROUT TESTING: Sample ID Mark
Site
CUBE COMPRESSIVE
Chainage
STRENGTH
Location

Concrete Grade Air Content


Date of Casting Concrete Temperature
Slump Ambient Temperature

Mix Ingredients( Kg/m3)


Cement Aggregates Admixture
Water Remarks
……….. ….. ……. ……..

Specimen Average
Age Compressive
Size Date of Weight Density Load Compressive
S.N. Strength Remarks
Testing Strength
(mm) Days (Kg) (Kg/m3 ) (kN) (Mpa) (Mpa)
1

10

11

12

13

14

15
Remarks:

Issued by Contractor: Approved by Engineer:

Name: ................................ Name: ................................

Sign : ................................ Sign : ................................

Page-83
Date : ................................ Date : ................................

Page-83
Client: Project: Sheet No.:

SCS-
Heading-

Tunnel
SHOTCRETE TESTING: Heading
SHOT BOLT TEST Tunnel Meter (TM) to
Round Number

Date / Time of Spray Mix Design


Temp. Air / Mix Accelerator Brand
Shotcrete pump Accelerator %
Nozzleman

Test Procedure: See Austrian Guideline for Shotcrete, Clause 12.3.2.

Penetrometer Test carried out on same Specimen : No Yes, see Sheet

Shot Gun: Adjustment: Cartridge:

Date / Time Shotcrete Bolt Type Stand Out Penetration Pull Out Calibrated F/L x fc
Age Depth L Force Force F (Sum / n)
[ h:min ] [ mm ] [ mm ] [N] [N] [ N / mm ] [ N / mm ] [ N / mm2 ]

Remarks:

Issued by Contractor: Approved by Engineer:

Name: ................................ Name: ................................

Sign : ................................ Sign : ................................

Page-84
Date : ................................ Date : ................................

Page-84
Client: Project: Sheet No.:

Tunnel
SHOTCRETE TESTING: Heading
THICKNESS VERIFICATION Tunnel Meter (TM) to
Rounds Number to

TM from Location: TM from Location:


1 to 2 to
Round Number Round Number
1. Hole mm 1. Hole mm
2. Hole mm 2. Hole mm
3. Hole mm 3. Hole mm
4. Hole mm 4. Hole mm
Average mm Average mm
Required mm Required mm
Difference mm Difference mm
Remarks: Remarks:

TM from Location: TM from Location:


3 to 4 to
Round Number Round Number
1. Hole mm 1. Hole mm
2. Hole mm 2. Hole mm
3. Hole mm 3. Hole mm
4. Hole mm 4. Hole mm
Average mm Average mm
Required mm Required mm
Difference mm Difference mm
Remarks: Remarks:

TM from Location: TM from Location:


5 to 6 to
Round Number Round Number
1. Hole mm 1. Hole mm
2. Hole mm 2. Hole mm
3. Hole mm 3. Hole mm
4. Hole mm 4. Hole mm
Average mm Average mm
Required mm Required mm
Difference mm Difference mm
Remarks: Remarks:

Issued by Contractor: Approved by Engineer:

Name: ................................ Name: ................................

Sign : ................................ Sign : ................................

Page-85
Date : ................................ Date : ................................

Page-85