HQS-HSE-PP-01 Fig040401-040405 Energy Isolation Posters
HQS-HSE-PP-01 Fig040401-040405 Energy Isolation Posters
HQS-HSE-PP-01 Fig040401-040405 Energy Isolation Posters
1 - ENERGY ISOLATION
DECISION PROCESS
Does the
PLANNING Can the equipment unplugged /disconnected
be unplugged from an electrical socket or equipment effect other equipment, systems
Task Assigned YES
disconnected from a mechanical energy or operations, or has it the potential to
Energy Isolation Required source? contain stored
energy?
NO
· Does the Risk Assessment · Does the Risk Assessment · Does the Risk Assessment
determine that an Area Authority determine that a Competent determine that a Basic
Isolation Certificate is required Person Isolation is required Isolation is appropriate for the
(CAKES)? (CAKES)? task (CAKES)?
· Will other systems/equipment or · Is the task specifically for · Is there a single isolation point
operations be affected by the maintenance or repairs by under direct control and in line
isolation? persons designated competent to of sight of the person
· Is Remote operation/activation of the conduct the isolation for the performing the work?
equipment or system possible after defined task? NO
isolation? · Does the Procedure specify the
YES
· Where the Person Performing Work use of a Competent Person
is unable to physically lock to isolate, Isolation?
Is the isolation point and associated · Does the task require removal of
tag outside his visual control guards or other safety devices?
throughout the task? · Is there potential for stored
· Does the Procedure state that an energy to be present after
Area Authority Isolation Certificate is disconnecting power source?
required? · Does the unplugged / ·
·
· Does the task require more than one disconnected equipment effect ·
type of isolation? other equipment, systems or
operations?
CAUTION!
NOTE: OIM or Area Do not proceed! Seek
Is the Is the Is the
Authority at any time, for further advice. A higher
Answer ‘Yes’ to Answer ‘Yes’ to Answer ‘Yes’ to
any task may determine a NO NO NO level of isolation is
ANY of the above ANY of the above ANY of the above
higher level isolation required and must be
questions? questions? questions?
process than indicated in approved through the
this flowchart. Control of Work process
YES YES YES
Effective Date: September 4, 2017 Extract from Energy Isolation Policy (HQS-HSE-PP-01)
FIGURE 4.4.2 - LEVEL 1 ENERGY
ISOLATION PROCESS
Task requires a Level 1 Energy Isolation
All Isolation keys are placed into a lock box and the
Responsible Person, Competent Person and Person
Performing Work place a personal padlock on the
lockbox.
NO CAUTION!
Person Performing Work must ensures all Where a physical lock out is not
persons involved in the task have a personal Have all possible additional processes/
padlock (or personal tag where tag out only means of equipment/system activation been NO controls must be implemented to
is used) on a multi-hasp at each isolation locked out. prevent uncontrolled removal of the
point or on the lock box relevant to the task. energy isolation – for example
YES Restricted Access.
Competent Person, Responsible Person and Person
Performing Work prove the isolation is effective using
Try to Operate from all local and remote control
Switch off and tag
points or by use of test equipment such as a multi-
meter, etc.
(Bleeding off/releasing any stored or trapped energy)
The Person Performing Work must
inform the Control of Work
Administrator on start, completion
Perform the task and suspension of the work and the
Control of Work Administrator must
update the Control of Work Log
accordingly.
Effective Date: September 4, 2017 Extract from Energy Isolation Policy (HQS-HSE-PP-01)
FIGURE 4.4.3 - LEVEL 2 ENERGY
ISOLATION PROCESS
Task requires equipment to be isolated as part of
maintenance or repair by an authorized Competent
Person
Is the CAUTION!
Person Performing Work Do not proceed! Seek further advice.
also the Competent
NO A Level 1 - Area Authority Energy
Person ? Isolation must be used.
YES
Does
the task require more than one type of YES
isolation
NO NO
Are all sources
Can all
of energy activation that cannot be
activation points be physically NO locked out within the individuals’
locked out?
line of sight?
YES YES
CAUTION!
Does the Where a physical lock out is not
YES task require isolation of more than one possible additional processes/controls
activation point? must be implemented to prevent
uncontrolled removal of the energy
isolation – for example Restricted
Isolation padlock key(s) must be placed into a Access.
Lockbox by the Competent Person performing the NO
isolation. The Person Performing Work and all other
personnel physically involved in the task must place Person Performing Work applies isolation
a personal lock on multi-hasp or lockbox. padlock(s)
Effective Date: September 4, 2017 Extract from Energy Isolation Policy (HQS-HSE-PP-01)
FIGURE 4.4.4 - LEVEL 3 ENERGY
ISOLATION PROCESS
Task requires a Level 3 Energy Isolation
Can the
equipment be unplugged from an
(This does not include the opening
electrical socket or disconnected from a YES
or racking out of a circuit breaker)
mechanical energy
source?
NO
Does unplugging
Is the isolation
or disconnecting the equipment
YES required for maintenance
affect other equipment, systems
or repair?
or operations?
NO
NO NO
CAUTION!
Do not proceed! Seek further
Does the advice. A higher level of isolation
CAUTION!
Equipment have a single is required and must be approved
Do not proceed! Seek further
Point of operation/valve remaining through the Control of Work
advice. A higher level of isolation is
required and must be approved
NO in the line of sight and sole control of process
the Person Performing Work
through the Control of Work
for the full duration of
process
the task.
NO
Where practical, try to Operate by Person
Performing Work
At anytime the Person Performing Work (Bleeding off/releasing any stored or trapped
leaves the area/isolated equipment; upon energy)
return, the isolation must be verified by ‘Try
to Operate’ prior to continuing work – where Try to Operate by Person
this is not practical the position of the Performing Work
Perform the Task
operating switch and security of the tag must (Bleeding off/releasing any stored
be verified. or trapped energy)
Effective Date: September 4, 2017 Extract from Energy Isolation Policy (HQS-HSE-PP-01)
FIGURE 4.4.5 - DE-ISOLATION PROCESS
The Person Performing Work must ensure that The Person Performing Work must ensure that Long Term Isolation approved for de-isolation
The Responsible Person, Competent Person
the Task Planning and Risk Assessment process the Task Planning and Risk Assessment process using Control of Work process and an Area
and Person Performing Work must ensure that
is used and that all equipment is ready to is used and that all equipment is ready to Authority is assigned by the OIM
the Task Planning and Risk Assessment process
operate. operate.
is used and that all equipment is ready to
operate.
The Area Authority assigns an appropriate
The Person Performing Work must review the Person Performing Work reconnects power and
continues task. Responsible Person and Competent Person
documented procedure for stored commands,
The Responsible Person, Competent Person and fail-safe positions, reset and / or re-start
Person Performing Work must review the sequence or indexing.
documented procedure for stored commands, The Responsible Person, Competent Person and
fail-safe positions, reset and / or re-start Person Performing Work must ensure that the
sequence or indexing. Task Planning and Risk Assessment process is
All personal padlocks and keys are returned to
used and that all equipment is ready to
dedicated cabinet and departmental registers
operate.
Responsible Person informs Area Authority and are updated accordingly.
Competent Person that work is complete and
equipment can be de-isolated. Responsible Person informs Area Authority and
Competent Person that work is complete and
Person Performing Work de-isolates equipment.
equipment can be de-isolated.
Responsible Person closes EIC and returns it to Responsible Person confirms equipment is
the Area Authority. ready to operate.
Effective Date: September 4, 2017 Extract from Energy Isolation Policy (HQS-HSE-PP-01)