Api 510 - Book 6
Api 510 - Book 6
Api 510 - Book 6
Using the rules for corrosion evaluation in API 510 the following
conclusion can be made about the evaluation of the vessel for its
continued service without repair;
a. The thickness at the weld governs calculations.
b. The thickness remote from the weld governs calculations.
c. No such rule exits in API 510
d. Separate calculations will be required to determine which thickness
governs.
API 510
16. A 2 to 1 ellipsoidal head has experienced uniform corrosion on its inner
surface. To determine the governing thickness and evaluate the head
for continued service or the need for repair or derating we would.
a. Calculate the required thickn ess of the knuckle region using the
formula given in UG-32 of Section VIII Div 1.
b. Calculate the thickness required of the spherical portion of the head
using the formula from UG-27 of Section VIII Div, 1 for a spherical shell
c. Calculate the equivalent shell based on the heads inside diameter
d. Calculate both 1 and 2 above to determine the need for repair or
derating.
e. SEC VIII
17. A 2 to 1 ellipsoidal head has experienced corrosion in the central
portion of the head and will require calculations for continued service
Using the following information, what is to be used as the dimension of
the spherical segment when evaluating the corrosion?
The vessel’s shell diameter is 96 inches
a. 96 inches
b. 76.8 inches
c. 80 inches
d. 38.4 inches
The vessel’s Category A and D Type 1 joints are fully radiographed . All
Category B joints are Type 1 also and have been spot radiographed per
UW-11(a) (5) (b)
The vessel MAWP must be 350 PSI at 450ºF. The shell will see 11 psi of
static head at its bottom.
a. .6072”
b. .7388”
c. .7159”
d. .6266”
SEC viii
23. A hemispherical head formed form solid plate is 48.0 inches in inside
diameter this head is attached to a seamless shell and has not had
radiography on the Category A type 1 weld that attaches the head to the
shell. The vessel is horizontal and operates at 500 PSI water pressure
with an allowable stress on the head’s material of 15,000 PSI. The
head’s thickness required is?
a. .5741”
b. .5761”
c. 1.1432”
d. .2356”
Sec viii
24. A 3 1/2” weld procedure test coupon must be tensile tested. This will
require the cutting of the test coupon into smaller pieces. The tensile
testing machine is capable of pulling up to 1” thick specimens. How
many pieces will be required to for a complete test per section IX?
a. 6
b. 8
c. 2
d. 12
This vessel has been in service for 6.5 years and all components had
an original thickness of0. 250 inch. The engineer calculated a
minimum thickness of the top head to be .145” and the bottom head
minimum thickness to be .155” and the shell’s minimum thickness to
be 0. 205” Based on the readings what is the Corrosion Rate for the
shell element?
a. 0.025”/ year
b. 0.0023”/ year
c. 0.020”/ year
d. 0.00384”/ year
API 510
Sec Viii
TEST PRESSURE
X 15,000/13,800 X 125 = 176,63Ø PSI
So Answer B
4) tmin = 0.377”
t1 + t2 > 1 ¼ tmin
t1 + t2 > 1.25 x .377 “
t1 + t2 = 0.47125”
5) UG – 32 (d) t= PD/2SE-0.2P
P=50
t= p t=[50x120/{ (2x15,000x1.0)-(0.2x50)]}=6,000/29,990
S=15,000
E=1.0
D=10’x12=120” t= 0.200”
2. 25,800/..306 = 84,313.725
Next internal inspection one-half remaining life or 10 years, use the smaller.
½ x 5.64=2.82 Yrs
80% OF 96=76.B”
96”
76.8”/2=38.4
.521”/2 = 0.2605”
.88/3 = 29.33”
3rd Revision
22) t=? t=PR/SE-0.6P
P=350 psi
S= 17, 500 psi Here p = 350 + 11 = 361
E= 1.0 PER UW-1,2 (a) t= 361x30/(17,500x1,0)-(0.6x361)=
R=60/2 = 30” t= 0.6266”
=12,041.568/20,899.6536 = 0.576161”
2 x 4 = 8 pieces
LOAD
TENSTR AREA
LOAD 14,876
AREA 0.19867
= 74,863 PSI
t= PR
------------ = 153.897x36 = 5540.292
SE – 0.6p ------------------------------- ------------------
(15,500x.85)-0.6x153.897) 13082.6618
=.4234”
------------------ = 0.0038461”
6.5
O.D. = 30.0
t=0.745”
S=15,000 P= 15,000X1.0X0.745
P=? -------------------------
Ro=14.870” 14.87”- (.4X0.745)
E=1.0
11,115
-------------- = 766 .88PSI
14.572”
S=13,000 P= SE
E=80 -------------
t=7/8 = ..875” R+0.6t
R=60/2 = 30”
13,000x.80x0.875
-----------------------
30+(0.6x0.875)
9100
------------ = 298.11 PSI
30,525
95’ 100’
5’
(.25 X 56”)+ 1 ½
15.5”/12” = 1.2916’
95.0
+ 1.2916
--------------
96.2916 X .433 = 41.69 PSI
It is recommended that you take this portion without referring to the ASME
Code or API books on your first attempt, to assess your strengths and
concentrate your studies on the most needed subject areas. It is
suggested that you write your answers on a separate sheet to keep this
copy clean for future studies.
33. What is the greatest allowed time between the testing of pressure
relieving devices per API 510?
a. 5 years
b. Pressure relief valves shall be tested at intervals that are frequent
enough to verify that the valves perform reliably.
c. 10 years.
d. Pressure relief devices must be tested at every shutdown
576
34. Who is responsible for the rerating calculations of a vessel?
a. The manufacturer or an owner-user engineer (or his designated
representative)
b. The chief inspector and the unit engineer.
c. The API authorized inspector.
d. A professional engineer only, is allowed to perform these calculations.
510
35. If the requirements of API 510 are met who determines if a temporary
fillet weld patch may be used in a repair?
a. The API authorized inspector.
b. An engineer competent in pressure vessel design and the API
authorized inspector.
c. A repair concern which holds a valid NBIC R stamp
d. Any of the above
510,sec viii
36. The maximum carbon content of weldable steel per ASME Code is?
a. .35 %
b. .035 %
72. The rules for impact testing of carbon steel in Section VIII vessel
materials require what kind(S) of impact test.
a. Brinell & Rockwell
b. Izod & charpy V-notch
c. Charpy V-notch only is acceptable
d. Brinell only is acceptable.
73. You have measured undercut on a girth weld during the repair to a
vessel, it was found to be 1/32 inch in depth. The base metal is 2 inches
thick, and you should?
a. Reject the weld
b. Accept the weld.
c. Consult the API 510 code for accept/reject criteria before making a
decision
d. Consult with the chief inspector or Engineer
75. The API authorized pressure vessel inspector may give prior
authorization for repairs that do not involve;
a. Pressure tests
b. Radiography
c. Pneumatic testing
d. Final visual inspections
76. The two types of impact tests required by section VIII Div.1 are;
a. Izod and drop weight
b. Brinell and Rockwell
c. Charpy and Drop Weigth
d. Weld metal and Base metal
78. A spot radiograph of a butt weld in a 1 inch thick of a vessel market RT-
3 was found to have a rounded indication, the dimension of such an
indication according to section VIII div 1 is;
a. 1/32 of an inch
b. 1/3 of an inch
c. 2/3 of an inch
d. None, rounded indications are not a consideration with spot
radiography
79. Section VIII Div 1, is very specific about the number of spot radiographs
required when applying it for quality control, the basic premise is to;
a. Insure that all welds are made perfectly
b. Make sure someone is held responsible for any poor welding
c. apply the radiographs immediately after welding in order to take
connective steps if needed.
d. fire as many welders as possible
80. A P No.1 material that is plate has been rolled into a cylinder and butt
welded. The cylinder is exactly 1-14” thick, and it is used in the repair of
a pressure boundary on a U stamped vessel, the following is a true
statement.
a. It must receive full radiography
b. It may be not spot radiographed
c. It may not be fully radiography
d. It may receive spot, full or no radiography depending on original the
original UI form
81. Charpy impact tests are intended to prove that a material is;
a. Tough at the desired MDMT of the vessel to be constructed using that
material
b. Some what prone to brittle fracture.
c. acceptable for use in high temperature service
d. not required to be heat treated
83. The testing apparatus used and the techniques for performing charpy
impact tests are found in;
a. Section VIII Div. 1 paragraph UG-84
b. SA-270
c. SA-370
d. Section IX paragraph 401.32
88. Widely scattered pits may be ignored as long as the following are true
a. No pit depth is greater than one half the vessel’s required wall
thickness exclusive of the corrosion allowance.
b. The total area of the pits does not exceed 7 square inches (45 square
centimeters) within any 8-inch (20-centimeter) diameter circle
c. The sum of their dimensions along any straight line within the circle
does not exceed 2 inches (5 centimeters)
d. ?
90. Before any repair to a pressure vessel in accordance with its code of
construction, what if any additional requirements for inspection may
need to be considered?
a. Jurisdictional requirements that might override the API 510 code
b. Who is doing the repair?
c. The quality of the repair materials
d. The need for qualified welding procedures
92. While inspecting an operating vessel you observe that cracks are
present in the connecting welds for a gauge glass, you also notice
vibrations are occurring in the assembly. Before you recommend
corrective actions you should;
a. Re-evaluate the materials used in the fabrication of the gauge glass
b. Write a report of the location with a recommendation for the type of
repairs needed
c. Research the inspection records for previous failures of this type
d. Check with a pressure vessel engineer to see if the cracks are caused
by fatigue failure
95. The main reason(s) for inspecting heat exchanger bundles after removal
and prior to cleaning is/are;
a. Location of scale on tubes can reveal non-operational problems.
b. Deposits on the tubes can reveal acid contamination problems
c. Color of the tube ends can reveal de-zincification
d. Color of deposits and scale can scale can reveal corrosion problems
99. A new vessel has been installed what must be done in order accept the
vessel for operation?
a. A first internal inspection
b. A first internal inspection, however if a manufactures’ data report (Ut)
assuring that the vessel is satisfactory for its intended service is
available the first internal may be waived
c. Base line thickness readings must be taken per OSHA 1920 (j)
d. Base line thickness reading must be taken per OSHA 1910(j)
111. After removing an exchanger bundle you find a Prussian blue coating
on the tubes, what do you suspect causes this coating?
a. Amino acid
b. Cyanide
c. Ferri-ferrocyanide
d. Phosphoric acid
112. One major area of concern when inspecting guy wires for a vessel is
crevice corrosion where does this occur?
a. On the free end of the turn buckle
b. In the threaded areas
c. On the guy wires
d. Where the wires contact the ground
113. You are inspecting a failure in a vessel wall, what conditions would
you look for if it was believed that the fracture was brittle?
a. There is almost a no lack of ductility
b. The fractured surfaces has a smooth surface
c. The surface of the crack would have jagged edges.
d. There is an almost complete lack of ductility and the failure site will
have a faceted surface
118. The first consideration that must be given when the half bead temper
bead technique of repair is proposed should be;
a. Consultation with the jurisdiction
b. Time required to do the repair, and personnel safety
c. Suitability for a given fluid service and any corrosion resistance
required
d. Close monitoring of the welding operation.
121. Aluminum chloride can affect stainless steel in which of the following
ways?
a. Severe pitting corrosion only
b. Intergranular cracking only
c. Stress corrosion cracking only
d. Stress corrosion cracking and/or intergranular cracking can occur
123. A bulged metal rupture disk with the pressure on the concave side has
life expectancy of;
a. 5 years
b. 2 years
c. 1 year
d. Indefinite length
125. Which of the following are the materials could be expected to produce
reliable magnetic particle examination results?
a. Monels.
b. Cupro-Nickels
c. Austenitic Stainless Steels.
d. Common Carbon Steels.
130. When looking for surface cracks in a vessel made of ferrous material
which of the following is the most capable of detection?
a. Fluorescent Penetrant Method.
b. Radiography
c. Fluorescent Magnetic Particle Method.
d. Close visual Inspection with good lighting.
134. Under which of the following condition(s) should you require to the
removal of safety relief device(s)?
a. If a pressure test is being conducted in which the test pressure will
exceed the set pressure of the safety relief valve with the lowest
setting.
b. The safety relief device was opening on a regular, usexplainable basis
c. Seepage had been discovered and operators have been consulted.
d. Surface corrosion on the body of the device.
136. Which of the following is a major concern when operating vessels that
utilize the fluidized bed principle?
a. Overheating
b. Erosion
c. Corrosion
d. Cracks
141. When rerating a pressure vessel, one of the steps of the rerating is the
documentation of the;
a. Calculations from the manufacturer or the owner-user’s engineer.
b. Approval of the operation’s engineering department.
c. Report from a professional engineer.
d. Approval of the ASME.
145. The thinned areas of a vessel are to be evaluated for continued service
using the design by analysis methods of Section VIII Division 2. When
using this technique it is always true that;
a. The insurer of the vessel must be consulted with first.
b. Corporate engineering must approve this method of evaluation.
c. Consulation with a pressure Vessel engineer is required.
d. You must determine the materials used in the fabrication of the vessel.
ANSWERS
Q.No. ANSWER
(Example) B
33 C
34 A
35 B
36 A
37 C
38 C
39 D
40 B
41 D
42 B
43 D
44 C
45 C
46 D
47 D
48 A
49 D
50 C
51 B
52 C
53 C
54 D
55 B
56 D
57 B
58 D
59 A
60 C
61 D
62 B
63 D
64 B
65 A
66 C
67 C
10. During an internal inspection a vessel’s shell was measured and found
to have a remaining wall thickness of .486 inches. It was last inspected 4
years ago. The retirement thickness of the vessel shell is .475 inches
and its previous thickness was .500 inches Based on this data, per API
510 what is the present corrosion allowance of the vessel?
a. 0.025”
b. 0.110”
c. 0.011”
d. 0014”
11. A vessel is constructed of rolled and welded SA-516 gr. 70 steel plate. It
is 96 inches in diameter with a communicating chamber, which extends
18 inches below this horizontal vessel. This vessel is in water service
and operates at working pressure of 150 psi. What will be the gage
pressure at working pressure as read on a gage mounted on the bottom
of the vessel’s communicating chamber?
a. 150 psi
b. 154 11 psi
c. 153.46 psi
d. 199.36 psi
13. In corrosive service the wall thickness used in the MAWP calculation
must be the actual thickness as determined by the inspection, but must
not be thicker than original thickness on the vessel’s original material
test report or Manufacturer’s Data Report __________________.
Fill in the blank;
a. Plus twice the estimated corrosion loss before the next inspection.
b. Minus twice the estimated corrosion loss before the next inspection.
c. Minus three times the estimated corrosion loss before the next
inspection.
d. Plus four times the estimated corrosion loss before the next inspection.
14. A weld repair using the preheat and deposition welding methods
described in the API 510 is to be performed on a groove type repair in a
vessel wall, and will require a welding procedure qualified using notch
toughness tests. What would be the allowed depth of repair if the
procedure test groove was 2 inches in depth?
a. 2 inches or more
b. Less than 2 inches.
c. Not more than 1-1/2 inches.
d. Unlimited thickness would be permissible.
15. Per Section VIII Div. I a P number I material is required to be post weld
heat treated when it exceeds what thickness at the joint?
a. 1”
b. 1-1/8” and has not had the required pre-heat applied.
c. 1-1/4” and has not had the required pre-heat applied.
d. 2”
17. Per Section IX a 3/8” PQR coupon will support the following range of
thicknesses in production.
a. 3/16 TO 3/4 inches.
b. 3/8 to 3/4 inches.
c. 3/8 to 1 inches.
d. 3/16 to 1 inches.
18. In order to substitute 4 side bends for the required face and root bend
tests the PQR coupon must be at least what thickness?
a. 1”
b. 3/4"
c. 3/8”
d. 1/2"
19. What is the required holding time at normal PWHT temperature for P
number I material with a thickness of 3”?
a. 2-1/4 hours.
b. 2 hours
c. 2-1/2 hours
d. P number I material is not required to receive PWHT per Section VIII.
20. Per Section IX, the following minimum number of tensile specimens is
required on the PQR.
a. 6.
b. 4.
c. 8.
d. 2.
23. Which of the following is the maximum out-of roundness allowance for
a cylinder per ASME VIII?
a. 1%
b. plus or minus 1%
c. 1.2%
d. 2”
24. If a 3 inch thick welded plate specimen must be impact tested what will
be approximate required absorbed energy requirement if it has a 55 ksi
minimum yield strength?
a. 30 psi
b. 30 ft/lbs
c. 27 psi
d. 27 ft/lbs
26. The set pressure for a relief valve set at 200 psi may not exceed;
a. 206 psi.
b. 200 psi.
c. 203 psi.
d. 199 psi.
28. The inner wall of a jacketed vessel has corroded down to 0.635 inch; the
inner cylinder has a 45” O D in this corroded state, its unsupported
length is 120 inches. The vessel operates at an external pressure of 175
psig and a temperature of 300 ºF. The factor A has been calculated to be
00085, using the CS- 2 factor B chart what is the approximate value of
Factor B?
a. 17,000
b. 14,500
c. 11,500
d. 9,500
30. A Circular flat head at the top of a vessel is measured at 1.25 inches
thickness during inspection. The flat head has a diameter of 14 inches.
The vessel’s data is as follows;
MAWP is 500 psi C=0.33 S=17,500 psi E=1.0 what is required thickness
of this part?
a. 1.35940 inch
b. 1.24563 inch
c. .958633 inch
d. 1.75200 inch
ANSWERS
Q.No. ANSWER
(Example) B
1 C
2 B
3 D
4 D
5 D
6 A
7 C
8 D
9 C
10 C
11 B
12 C
13 B
14 B
15 C
16 C
17 A
18 C
19 A
20 D
21 D
22 D
23 A
24 B
25 C
26 A
27 B
28 C
29 D
30 A
31 C
It is recommended that you take this portion without referring to the ASME
Code or API books on your first attempt, to assess your strengths and
concentrate your studies on the most needed subject areas. It is
suggested that you write your answers on a separate sheet to keep this
copy clean for future studies.
33. The minimum number of penetrameters used for a complete girth seam
of a cylinder which is radiographed in a single exposure containing 30
film holders is;
a. 30, one on each film holder.
b. 15 one every other film holder.
c. 3 which are 120 degrees apart.
d. 10 one every third film holder.
40. The following is a true statement about tensile testing specimens from
Section IX.
a. They are never allowed to fail below the stated UTS of the base metal.
b. They are never allowed to fail in weld metal.
c. They must not fail more than 5% below the listed UTS of the base
metal
d. They must never fail by breaking.
43. When performing a visual examination which of the following tools are
not required to be available;
a. A flashlight.
b. A pit depth gauge.
c. UT thickness measurement equipment.
d. A Bronson Corrosion Metric Device (BCMD).
48. Requalification by written exam is required for an API inspector who has
not been actively engaged in API inspections in the past;
a. One year.
b. Two years.
c. Three years
d. Four years.
49. One primary reason for inspecting pressure relief devices is to;
a. Determine the remaining life of the pressure relief device.
b. Measure and record the thickness data on the body of the valve.
c. Determine whether the device is functioning properly.
d. Clear the outlet piping of rainwater.
52. Which of the following describes types of Image Quality Indicator (IQI)
required in Section V Art 2?
a. IQIs shall be either the hole type or the shim type.
b. IQIs shall be either the wire type or the shim type.
c. IQIs Shall be either the shim type or the stepped type.
d. IQIs shall be either the hole type or the wire type.
55. A welded carbon steel joint has a MDMT which is lower than 120 ºF
above what thickness must impact tested material be used.
a. 6 inches.
b. 4 inches.
c. 2 inches.
d. 3 inches.
56. For alteration or repairs, half bead/temper bead welding may be used as
an alternative for postweld heat treatment on vessels that require notch
toughness tests, but is limited to;
a. P No. 1
b. P No. 3.
c. P Numbers 1,3, and 4 steels.
d. P Numbers 3 and 1 but are restricted to certain group numbers.
58. The mechanical working of weld metals using impact blows is defined
as;
a. Hammering.
b. Forge welding.
c. Impact conditioning.
d. Peening.
60. The maximum inspection interval for a vessel with a remaining life of 16
years is;
a. 10 years.
b. 5 years.
c. 8 years.
d. 16 years.
63. All pressure relieving devices must be tested and repaired by;
a. The original valve manufacturer.
b. The Authorized Inspector.
c. A repair concern which holds the NBIC VR symbol.
d. A repair concern experienced in valve maintenance.
68. The minimum actual thickness and maximum corrosion rate for any part
of a vessel may be;
a. Estimated.
b. Adjusted at any inspection.
c. Changed to fit production schedules.
d. Ignored if the vessel is not operating at pressures above 30 psig.
69. The item(s) that must be given attention when inspection riveted
vessels are;
a. Caisson straps for leaks
b. Strapped bars for corrosion.
c. Fayed edges for deterioration.
d. Caulked edges for leaks.
71. Per API 510 the definition of actual thickness for determining MAWP of
a vessel is;
a. The as measured thickness less 2 times the present corrosion rate.
b. The most critical value of the average thickness that has been
determined.
c. The as measured thickness.
d. The original thickness less the original corrosion allowance.
73. The API authorized inspector shall not approve repairs to a vessel until;
a. After inspection has proven the repairs have been satisfactorily
completed and all required pressure test have been performed and
witnessed.
b. He has satisfied himself that the repairs have been completed.
c. Item b above plus all isolation steps used before the pressure test
have been removed and the vessels have been returned to an
operable condition.
d. He has been given permission by the plant manager.
74. All repair and alteration welding must be performed in accordance with;
a. Acceptable company standards.
b. API approved welding procedures
c. The applicable requirements of the ASME Code or another Code of
construction to which the vessel was built.
d. NBIC.
82. Many of the problems that may develop in pressure vessels can be
traced to faulty materials or fabrication, what are some of the problems?
a. Out of plumb shells.
b. Obtuse components.
c. Cracking, leakage, blockage, and excessive corrosion.
d. Out of alignment source piping.
84. One advantage of doing external inspections while a vessel is in service is;
a. The vessels do not then require an internal inspection.
b. The plant can continue to operate until the vessels shows signs of
failing.
c. The required work load can be reduced for the vessel during out of
service inspections.
d. Extra personnel can be eliminated during shut down periods.
85. The most common forms of CUI on vessels are of what descriptions?
a. Asbestos under scale attack and localized corrosion of carbon steel.
b. Asbestos under scale attack and chloride stress corrosion cracking of
austenitic stainless steels.
c. General corrosion of carbon steel and binate corrosion of stainless
steels.
d. Localized corrosion of carbon steel and chloride stress corrosion
cracking of austenitic stainless steels.
88. External corrosion on stairs and ladders is most likely to occur where;
a. Stagnant pools of chemicals collect.
b. On parts where moisture is allowed to collect.
c. The ladders are not painted with an epoxy.
d. Vessels are located with a northern exposure.
91. If settling of a vessel is evident, the things that must be checked in the
vessel are;
a. Adjacent machinery for settlement
b. Ground conditions for water leaks that undermine the vessel
foundation.
c. Distortion and cracking which may have occurred to the vessel’s
nozzles
d. Sinking of the water table in the area.
95. Leaks in a vessel are best found using what test method?
a. Vacuum testing.
b. Acoustic emissions testing.
c. Pressure testing.
d. Variable augmented pressure testing.
97. What can make the installation of heat exchanger bundles extremely
difficult?
a. The length of the bundle.
b. The diameter of the bundle.
c. Out of roundness in the exchanger shell.
d. Dilter- Johnson bundles.
100. As regards a heat exchanger that has two fixed tube sheets, the major
disadvantage it has is;
a. It is limited in its diameter.
b. The bundles are hard extract.
c. The shell side cannot be exposed for cleaning.
d. Its length is limited to 30 feet.
105. Tubes may be tested for thickness during visual inspections using
many different techniques, one of the most common and fastest is to;
a. Tap the tubes using a light ball peen hammer
b. Ultrasonic thickness testing of the tubes.
c. Measure the thickness using outside calipers.
d. Eddy current testing.
108. Which of following does not describes a Rupture Disk Device’s use?
a. Protecting the upstream side of relief valves against corrosion.
b. Protecting the relief valves from plugging or clogging.
c. Minimizing leakage through relief valves.
d. The only pressure protection of vacuum vessels.
110. Which of the following does not describe the main reasons for
inspecting relief devices?
a. To protect personnel and equipment.
b. To determine the condition of a device.
c. To evaluate the inspection frequency.
d. To insure that the device’s protective coating is of the proper type.
111. An important element in the accurate setting of all relief valve’s lifting
pressure is use of ;
a. Salisbury Test Blocks.
b. Properly calibrated gauges.
c. New seats and springs
d. Soap bubble testing.
113. If damaged valve seats are discovered in a relief device what should be
suspected as the cause?
a. Erosion.
b. Severe under sizing
c. Improper or short piping spools at the inlet.
d. Corrosion, severe over sizing. Improper or lengthy piping at the inlet.
114. Sticking of newly installed relief valves can often be traced to;
a. Poor alignment of the valve disk.
b. Incorrect valve disk.
c. Short pipe inlet runs.
d. Long pipe inlet runs.
116. One of the many things that must be considered when evaluating the
failure of newly installed relief device to open at its set pressure is;
a. The type of the gaskets used
b. The possibility of rough handling during shipment or installation.
c. The possibility of turning the valve flanges by a single bolt hole causing
distortion.
d. The valve being to far from the protected pressure vessel
117. When the hydrostatic testing of discharge piping for pressure relief
devices is to be performed what can happen if precaution(s) are not
taken?
a. The disk, spring, and body of the area on the inlet of the valve can be
damaged.
b. The disk, spring, and body of the area on the discharge of the valve
are fouled.
c. The disk, spring, and body of the area on the inlet of the valve can be
damaged.
d. The disk, spring, and body of the area on the inlet of the valve can be
fouled.
118. When setting time intervals between the inspections of relief devices,
which of the following best apply?
a. They must be done at least every 8 years.
b. They must be done at least every 3 years.
c. Definite time intervals must be established.
d. None of the above.
122. Carbon dioxide when combined with moisture will form carbolic acid,
from where can the carbon dioxide be introduced in a process?
a. From decomposition of bicarbonates or from steam used in distillation.
b. From decomposition of tricarbonates.
c. From water used in distillation.
d. From decomposition of poly fluorides.
128. Oxygen reacts with steels at high temperatures to cause what mode of
deterioration?
a. Flaking.
b. Cracking.
c. Scaling.
d. Intergranular cracking
129. As regards steel, its oxidation in air increases with increasing metal
temperature and decreases with increasing;
a. Moisture.
b. Chromium content.
c. Molybdenum content.
d. Carbon content.
132. When austenitic stainless steels are heated to a range 750º F and 1650º
F upon cooling carbide precipitates can form, this is not usually;
a. A common occurrence.
b. A problem unless the steels are exposed to a corrodent.
c. Any concern what so ever.
d. A concern unless welding will be performed on the steel.
135. When two different metals are combined in the same service often one
will corrode and the other will not, the one that corrodes is referred to
as being less noble than the other. Which of the following terms is also
a description of the one which will corrode?
a. Cathodic.
b. Anodic.
c. Cathartic.
d. Anthrax.
138. When Ferritic steels are heated to a temperature above 1,350º F, upon
slow cooling a solid solution of iron and carbon begins to from. What
is contained in this solution?
a. Ferrite and martensite.
b. Martensite and cementie
c. Stalactite and martensite.
d. Ferrite and cementite.
140. You are reading a WPS and see that it was qualified using P No. 5A to
P No 5A, you know that;
a. This WPS can be used to weld any P No. 5 material.
b. This WPS can be used to weld any P No. 5A to any metal from P Nos
5A, 4,3, or 1
c. This WPS can be used to weld only P No 5A
d. This WPS can be used to weld any P No. 5A to any metal from P Nos.
5A, 4 or 3.
ANSWER
Q.No. ANSWER
(Example) B
32 C
33 C
34 C
35 D
36 D
37 D
38 B
39 C
40 C
41 C
42 B
43 D
44 B
45 D
46 C
47 C
48 C
49 C
50 D
51 D
52 D
53 B
54 D
55 B
56 C
57 B
58 D
59 A
60 C
61 B
62 A
63 D
64 C
65 C
17,500 22.5
16,800
= 1.0416666
PRESSURE AT TOP
304.6870
+11.0415 .
315.7285 PSI
t = ?
P = 650
S = 14,500 PSI
E = 1.0 FULL RADIOGRAPHY
R = (44.02/2) = 24.51
t=min 1.1290928
C.A 0.1409072”
REMAINING LIFE = = = 5.63 YEARS
C.R 0.0250000”
5.63
= 2.815 YEARS
2
3.5 “ NOZZLE 1
+ 2.0” NOZZLE 2
--------
5.5” TOTAL
2X 2.75” = 5.5”
ANSWER = 5.5”
8) tORIG. .250”
tPRES. - .235
----------
WALL LOSS .015”
.015
CORROSION RATE = =.003” A YEAR
5 YRS
t PRES .235
t MIN .195
-------
REMAINING C.A. .040
C.A .040
REMAINING LIFE = = = 13.333 YEARS
C.R .003
13.333
=6.66 = 6 2/3” A YEAR
2 YRS
17,500
RATIO OF STRESS = = 1.166666
15,000
TEST PRESS
INSPECTION NOT LESS = = PER UG-99
1.3
151.58
= 116.6 PSI
1.3
96” = 8’
ANS .80
P=500 PSI
S=17,500
E=1.0
C=0.33
d=14”
FROM; UG – 34
t=d CP
SE
t= .33x500
14 17,500x1.0
= 14 165
17,500
= 14 x 0.0094285
=14 x .0971004
= 1.3594056”
2. For a hole type penetrameter that has the designation number 15 the
essential 2 T hole diameter must he;
a. 0.060
b. 0.030
c. 0.015
d. 0.045
7. A vessel is marked RT-3 this indicates that all welded joint efficiencies
will be taken from Column B of table UW-12. The vessel contains only
Type 1 welded joints so all welds will have an E of ?
a. .90
b. .85
c. .70
d. .65
11. Local PWHT per API 510 Specifies that the area to be heat treated shall
extend for a given distance from the weld what would be the distance
required for the local PWHT of a 10 inch .500” thick nozzle in a 3 inch
thick shell?
a. 12 inches in all directions.
b. 3 inches in all directions.
c. 1 inch in all directions.
d. 6 inches in all directions.
13. A vessel has pitting in a small area; the area will fit in an 8 inch diameter
circle with its center at the deepest pit. The shell course has a minimum
thickness of 740”. The pits within the circle are more than 2 inches apart
in any straight line with the following depths;
20. Which of the following explains the closest that two isolated un-
reinforced openings can be to each other without reinforcement
calculations being required?
a. 4 times their diameters
b. 3-1/2 times their diameters.
c. The sum of their diameters.
d. There is no such requirement
24. The minimum throat dimension for a fillet weld as shown in Fig UW-16
(c) for a 1” thick nozzle joined to a 2” thick head is.
a. .530”
b. .750”
c. .250”
d. 1.00”
25. A wire type IQI is to be used in lieu of a hole type for a single wall
source side radiograph, the thickness of the material to be radiographed
is 2.250” thick. What is the diameter of the wire that must be must to
evaluate the image quality of the radiograph?
a. 6
b. 8
c. 10
d. 12
29. What is the remaining life of a vessel corroding at a rate of 0.017 inch
per year when the last inspection measured 0.638 inch and the minimum
required thickness is 0.513 inch.
a. 4 years
b. 10 years.
c. 6.3 years.
d. 7.3 years.
Q. No. ANSWER
1 B
2 B
3 B
4 D
5 A
6 B
7 B
8 C
9 C
10 C
11 D
12 C
13 D
14 B
15 C
16 D
17 D
18 D
19 B
20 C
21 A
22 C
23 C
24 C
25 D
26 B
27 D
28 A
29 D
It is recommended that you take this portion without referring to the ASME
Code or API books on your first attempt, to assess your strengths and
concentrate your studies on the most needed subject areas. It is
suggested that you write your answers on a separate sheet to keep this
copy clean for future studies.
32. A hole type IQI is designated as a number 15 and its thickness is 0.015
inch, what would be the diameter of the 2T hole in this penetrameter?
a. 0.015 inch
b. 0.150 inch
c. 0.030 inch
d. 0.300 inch
40. You notice that a pressure relief device has a closed bonnet. What type
of valve is it?
a. Relief Valve.
b. Safety Relief Valve
c. Conventional Safety Relief valve
d. Relief Valve and Conventional Safety Relief Valve.
41. While reviewing maintenance records you notice that the pre-bulged
rupture disks with pressure on the concave side have been in service
for three years. In this O K why or why not?
a. No, the recommended maximum service life for these burst disks is 2
years.
b. Yes, the recommended maximum service life for these burst disks is 3
years.
c. No, the recommended maximum service life for these burst disks is 1
year.
d. Yes, as long as no sign of failure has been revealed by inspection.
42. A pilot operated safety valve has been installed in heavy crude services
is this OK?
a. Yes, these valves are very effective in this type of service.
b. No, these valves are not intended to operate at normal temperatures.
c. Yes, these valves have closed bonnets and are leak proof.
d. Possibly not, these valves may not operate properly in this service due
to the possibility of deposits clogging small pilot circuits, unless
equipped with filtration or other protective means.
43. Which of these is from the major groups of corrosion sources found in
refining operations?
a. Corrosion from components of slop oil.
b. Corrosion from chemicals used for cleaning.
c. Salt water corrosion.
d. Corrosion from components of crude oil.
50. What principle of cooling is used with exposed tube bundles under a
cooling tower?
a. Conductive
b. Radiant
c. Evaporative
d. Isometric
52. If carbon steel vessels cannot resist a corrosive fluid, what method of
construction is not normally used for such a vessel?
a. Plain carbon steel
b. Lined vessel using an alloy liner.
c. Lined vessel using a refractory liner.
d. Lined vessel using a glass liner.
53. Which of the following does not describe how metallic liners can be
installed in a pressure vessel?
a. The liner material is explosion bonded to the carbon steel part.
b. The liner material is rolled to the carbon steel plate as part of the
manufacturing process.
c. The liner material is welded to the carbon plate.
d. The liner material is attached with a high temperature thermo chemical
endothermic process.
55. An inspector should be familiar with the current ASME Codes and
previous editions of the Code, what other publications should be
knowledgeable of?
a. The API Industry Informer Magazine for the latest industry alerts.
b. Local, state and federal regulations and other specifications for the
construction of pressure vessels
c. ASNT rules for materials
d. There are no other publications to be concerned with
58. Cracks in vessels are most likely to occur in vessels in what locations?
a. At sharp changes in shape, size or near weld seams
b. At weld seams.
c. At attachment welds for internals.
d. Where previous repairs have been performed
59. Before an inspection starts in a vessel, who else besides the safety man
should be informed?
a. Coworkers who will assist in the inspection.
b. Operations.
c. Repair concerns.
d. All persons working in the area of the vessel
61. If a vessel has had previous internal inspections, what should the
inspector do prior to his inspection?
a. Alert operations.
b. Review API 572 for methods of failure that pertain to the vessel to be
inspected
c. Review previous inspection records.
d. Call the vessel manufacturer and obtain all records held on file.
62. How may cracks be made to stand out from the surrounding areas being
inspected?
a. Highly burnishing the area.
b. Abrasive grit blasting
c. Abrasive grit blasting followed by etching
d. Etching followed abrasive grit blasting.
63. Who should make the decision to trepan metal from a vessel for
metallurgical evaluation?
a. The API inspector.
b. The API Authorized Inspector
c. The NBIC Authorized Inspector.
d. Someone who knows how to analyze the problems related to repairing
the sample holes.
68. What must an inspector consider when recommending the filling of pits
with an epoxy?
a. Is this permitted by the repair concern?
b. Will this epoxy hold up in this service?
c. The strength the epoxy will add to base metal being repaired.
d. What will be required to clean the pits prior to application of the epoxy?
71. The difference between GMAW and the GTAW welding process is;
a. One uses alternating current and dc voltage the other does not.
b. Both use a consumable electrode made of tungsten and the other does
not.
c. One uses a shielding gas and the other can not.
d. One is usually considered manual and the other semi-automatic.
73. List three places where category B welds are located in an ASME Code
Section VIII Div 1 vessel.
a. Longitudinal joint in shells, in nozzles and communicating chambers.
b. Circumferential joints in transitions in diameter, connecting heads to
communicating chambers and hemispherical heads to shells.
c. Circumferential joints in transitions in diameter, connecting heads to
communicating chambers and ellipsoidal heads to shells.
d. Circumferential joints in transitions in diameter connecting heads to
communicating chambers and the joints used to make a sphere from
two hemispheres.
74. Describe a Type 3 weld in accordance with ASME Section VIII Div.1.
a. A weld made form one side only with a backing ring, which remains in
place.
b. A weld made from both sides, and which is restricted in diameter and
thickness limits.
c. A weld made from both sides.
d. A weld made from one side only, which does not have a backing ring.
75. What type material is always required to have a mill test report in
accordance with Section VIII Div 1 of the ASME Code?
a. ASTM pipe.
b. ASTM forged pressure parts.
c. Gray cast iron parts used for pressure.
d. Plate.
76. Plate that has been rolled into a cylinder retains its shape, this is
because;
a. It is not a spring
b. Plastic deformation has occurred
c. It has been stretched beyond its elastic point.
d. It has experienced the Bolinger effect.
80. A New weld repair project is just starting, as the inspector you should
review the
a. The repairs concerns quality plan.
b. The procedures (WPR) (PWR).
c. The materials chemical test reports, as they become available
d. Welder’s certifications, the welding procedures, and the MTRs.
82. You notice a workman applying blows to a weld with a pneumatic tool,
what is he doing?
a. Conditioning
b. De-fluxing
c. Re-distribution of weld metal
d. Peening
84. The pulse echo contact method can be applied to any material in which
ultrasonic waves will propagate at a ________________ throughout the
part, and from which back reflections can be obtained and resolved.
a. Varying velocity
b. Constant velocity
c. Constant velocity with attenuation
d. Varying velocity with attenuation
89. A welding electrode has the following marking E-7018-1. Explain the
meaning of the number-1 on the end.
a. The first lot of 7018 electrodes produced that month at the plant.
b. The electrodes are certified to be moisture free.
c. The electrodes have passed testing which allows use in certain impact
tested vessel fabrications, without further testing of the weld metal.
d. First quality electrode according to the Section IX.
94. The term ‘Full Radiography” in Section VIII Div. 1 means that a vessel
must have;
a. 100% of its welds radiographed
b. All of the welds required by code to be fully radiographed examined
c. 100% of the all of the welds which exceed NPS 10 and or 1-1/8”
radiographed
d. Radiography applied to all types of weld including fillet welds.
95. Indications observed by the dye penetrant NDE method are often larger
than the actual imperfection in the material. What is the accept reject
criteria based on?
a. The dimensions of the imperfection revealed by the inspection.
b. The dimensions of the developed test.
c. The dimensions of the developed test, following a written procedure.
d. The dimension size allowed by the prevailing code.
100. Corrosion rates vary markedly for vessels in crude oil service based
upon.
a. Type of stock processed in the unit.
b. Temperature in the process.
c. Material of construction.
d. Type of stock processed in the unit, temperature in the process, and
materials of construction.
104. Some relief valves are manufactured using resilient O-ring seals.
Which of following is a reason for these O-rings?
a. Resistance to chemical attack
b. To resist high temperature.
c. To promote a higher degree of tightness in the sealing surfaces.
d. To make metal parts slide easier.
106. What is the first step taken in the repair process when a relief valve
enters the repair shop before it is dismantled?
a. Profiling and reference charting.
b. Pop pressure test.
c. Chemical cleaning and decontamination
d. Visual inspection.
113. For clad vessels constructed with P-3, P-4 or P-5 base materials, the
base material in the area of a welded repair should be examined for
cracks using;
a. Visual inspection
b. Magnetic particle inspection
c. Ultrasonic examination
d. Dye penetrant examination
121. The hydrostatic head must be considered when rating a liquid filled
vessel’s
a. Bottom shell course’s material of construction.
b. Top formed head’s geometry.
c. Reinforcement pad material selection
d. Each component MAWP.
122. A vessel is undergoing a hydrostatic test per the rules of the ASME,
the pressure it shall be visually inspected at is;
a. The test pressure divided by 1.3
b. No less than the test pressure divided by 1.3
c. No less than the test pressure divided by 1.1.
d. No less than 4/5 the test pressure.
124. A vessel due to corrosion has a remaining thickness that is below the
minimum required thickness. If the thinned areas are to be evaluated
for continued service using the design by analysis methods of Section
VIII Division 2. When this approach is used it is always true that;
a. The NBIC Authorized Inspector must be consulted.
b. Operations must agree.
c. Consultation with a pressure vessel engineer experienced in pressure
vessel design is required.
d. The materials used in the fabrication of the vessel and their notch
toughness must be known.
133. A balanced safety relief valve uses a bellows or other means to;
a. Seal the valve internals
b. Allow for part expansion during temperature increases.
c. Create backpressure at desired components in the valve.
d. Minimize the effects of backpressure on the operating characteristics
of the valve.
134. If heads are formed so that the pressure is on the concave side they
are considered by the ASME to be
a. Minus heads.
b. Seamless.
c. Plus heads
d. Spun heads.
135. A forget flat head attached to a vessel by butt welding must follow all
the rules for
a. Circumferential welds given in Part UW of Section VIII
b. Longitudinal welds given in Part UW of Section VIII
c. Circumferential welds given in Part UCS of Section VIII
d. Longitudinal welds given in part UCS of Section VIII
137. One time that the manufacturer of a pilot operated pressure relief
device should be consulted about their device’s setting procedure is
when;
a. The device is very old.
b. The device is in a non-corrosive service
c. The device will be set using water.
d. The device is in corrosive service
138. After a test and inspection cycle in a unit, pressure relief devices
should not be checked for;
a. Installation of the correct device
b. No gags or blinds left in place.
c. Seals installed to protect spring settings have not been broken.
d. Weather proof caps made of the proper material
140. Normally when relief valves are removed from a system the inlet and
outlet piping is inspected, if block valves are closed and the unit is in
service what can be done to inspect this piping?
a. Use of special borescope, which utilizes a pressure chamber.
b. Radiographs can be performed to indicate major fouling or blockage.
c. Do in a hot tap in the vicinity of the suspected blockage
d. Probing using a high pressure sealed probing device.
142. The range of the IG position in degrees as used in welding for its
inclination of axis is;
a. 15 to 80.
b. 5 to 15.
c. 0 to 15.
d. 80 to 90.
Q.No. ANSWER
30 C
31 C
32 C
33 A
34 C
35 C
36 C
37 D
38 D
39 C
40 D
41 C
42 D
43 D
44 D
45 C
46 D
47 C
48 C
49 A
50 C
51 C
52 A
53 D
54 B
55 B
56 B
57 A
58 A
59 D
60 D
61 C
62 C
63 D
64 B
65 C
66 B
t Previous .630”
t Actual - .525”
----------
Remaining C.A - .105”
Remaining Life:
PRESSURE = 172.7
------- = 157.0 PSI
1.1
C=0.33 X M.
2 x 3 “= 6” IN ALL DIRECTIONS
.740/2=.370” <.385”
P= SET
------------
Ro-0.4t
t=.498”
E=1.0
Ro=95.82÷Z=47.91”
S=13,800PSI
P=?
P= 13,800X1.0X.498 6872.4
------------------------- = ----------
47.91-(0.4.X.498) 47.7108
P=144.04
Tmin =3/4”
ANS: .250”
WALL COSE
48” + (,500 – 369) = 48.131”
= .125
------- = 7.35 Years
0.017