Compilation of Lesson Learned
Compilation of Lesson Learned
10 Welding activities being performed with wrong WPS and not as per approved WPS/PQR ( Weld Map)
Fabricated items where release without painting. Galvanizing and painting is required on structures for marine
11
application.
12 Return welds on cope holes where not performed. All welds shall be continuous.
Misfabrication such as, wrong location or size of bolt holes, wrong location or orientation of gusset plates,
13
short or length of fabricated members.
Inspection Application notification lead time is not followed. Inspection activities on ITP requiring witness
14
points from client was not notified.
Purchase and use of materials from India and not approved stockiest. Materials shall be purchase only from
15
the Approved Vendors List.
16 Flange orientation not checked in Isometric drawing .