Item No. Description Unit Derived/ Output (Unit/Mandays) (Unit/Hours) I. Earthworks

The document provides production rates for various construction activities measured in units per man day or hour. It includes rates for earthworks like clearing, excavation and embankment. It also provides rates for concrete works like formwork installation and stripping, reinforcement fabrication and placing, and concreting. Additional rates are given for masonry, carpentry works and hardware installation. The rates are intended to estimate productivity and schedule for multiple construction tasks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
282 views9 pages

Item No. Description Unit Derived/ Output (Unit/Mandays) (Unit/Hours) I. Earthworks

The document provides production rates for various construction activities measured in units per man day or hour. It includes rates for earthworks like clearing, excavation and embankment. It also provides rates for concrete works like formwork installation and stripping, reinforcement fabrication and placing, and concreting. Additional rates are given for masonry, carpentry works and hardware installation. The rates are intended to estimate productivity and schedule for multiple construction tasks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 9

DERIVED/ OUTPUT

ITEM NO. DESCRIPTION UNIT


(UNIT/MANDAYS) (UNIT/HOURS)
I. EARTHWORKS
800 - Clearing and Grubbing
a) Undergrowth and trees 12" dia sq.m. 136.00 m2/MD 17.0000 m2/Hr
b) Undergrowth and small bushes sq.m. 272.00 m2/MD 34.0000 m2/Hr

803 - Structures Excaation


a) Common Earth cu.m. 1.00 m3/MD 0.1250 m3/Hr
b) Sand cu.m. 1.30 m3/MD 0.1625 m3/Hr
c) Clay cu.m. 0.90 m3/MD 0.1125 m3/Hr
d) Rock cu.m. 0.85 m3/MD 0.1063 m3/Hr

804 - Embankment
a) Backfilling cu.m. 2.50 m3/MD 0.3125 m3/Hr
b) Spreading, Tamping and Grading cu.m. 2.50 m3/MD 0.3125 m3/Hr
c) Placing Escrombo Fill cu.m. 2.50 m3/MD 0.3125 m3/Hr
d) Gravel Fill
d-1) Hand Placed cu.m. 1.36 m3/MD 0.1700 m3/Hr
d-2) Placing Binder-grael cu.m. 4.00 m3/MD 0.5000 m3/Hr

II. TERMITE CONTROL


1000 - Termite Control Works
a) Soil Poisoning - Cordoring sq.m. 20.40 m2/MD 2.5500 m2/Hr
b) Soil Poisoning - Drenching sq.m. 34.00 m2/MD 4.2500 m2/Hr
c) Wood Preservation sq.m. 20.40 m2/MD 2.5500 m2/Hr

III. DAMPROOFING/MOISTURE CONTROL


SPL - Damprooifng/ Moisture Control
a) Polyethelene Sheets (Spreading) sq.m. 54.40 m2/MD 6.8000 m2/Hr
b) Hydrolithic Waterproofing sq.m. 20.40 m2/MD 2.5500 m2/Hr

IV. CONCRETE WORKS


900 - Reinforced Concrete
A. FORMWORK INSTALLATION
a) Wall on ground sq.m. 3.40 m2/MD 0.4250 m2/Hr
b) Wall above ground sq.m. 2.86 m2/MD 0.3575 m2/Hr
c) Beams sq.m. 2.18 m2/MD 0.2725 m2/Hr
d) Columns sq.m. 2.86 m2/MD 0.3575 m2/Hr
e) Suspended Slab
e.1) 0 to 0.50 m sq.m. 4.01 m2/MD 0.5013 m2/Hr
e.2) 0.50m to 1.0m sq.m. 2.04 m2/MD 0.2550 m2/Hr
e.3) 1.0m up sq.m. 2.04 m2/MD 0.2550 m2/Hr
f) Elevated & Shored Slab
f.1) Forming Only sq.m. 0.75 m2/MD 0.0938 m2/Hr
f.2) Forming and Shoring sq.m. 0.61 m2/MD 0.0763 m2/Hr

B. FORMWORKS FABRICATION sq.m. 6.26 m2/MD 0.7825 m2/Hr


C. STRIPPING OF FORMWORKS
a) Wall on ground sq.m. 27.20 m2/MD 3.4000 m2/Hr
b) Wall above the ground sq.m. 5.24 m2/MD 0.6550 m2/Hr
c) Beams sq.m. 6.60 m2/MD 0.8250 m2/Hr
d) Columns sq.m. 7.96 m2/MD 0.9950 m2/Hr
e) Suspended Slab
e.1) 0 to 0.50 m sq.m. 8.16 m2/MD 1.0200 m2/Hr
e.2) 0.50m to 1.0m sq.m. 6.26 m2/MD 0.7825 m2/Hr
e.3) 1.0m up sq.m. 6.26 m2/MD 0.7825 m2/Hr
f) Elevated & Shored Slab sq.m. 1.91 m2/MD 0.2388 m2/Hr
g) Slab on Grade Strip of Forms sq.m. 2.38 m2/MD 0.2975 m2/Hr

D. FORMWORKS
Time required for erecting and
stripping forms per 100m2 of
Contract Surface

a) Concrete Footing and Foundation sq.m. 1.77 m2/MD 0.2213 m2/Hr


b) Concrete on Slab on Grade sq.m. 2.58 m2/MD 0.3225 m2/Hr
c) Concrete Columns and Beams sq.m. 1.22 m2/MD 0.1525 m2/Hr
d) Concrete Walls sq.m. 1.36 m2/MD 0.1700 m2/Hr
e) Concrete Structural Slab
Cast-In-Place Culvert and
Manholes sq.m. 1.29 m2/MD 1.1825 m2/Hr

In general, two men can erect 20BD.FT./HR or remove forms at the rate of 44BD.FT./HR

404 E. REINFORCEMENT
a) Fabrication(cut & bend) kg. 68.00 kg/MD 8.5000 kg/Hr
b) Placing
b.1) Footing and Foundations
Structural kg. 95.74 kg/MD 11.9575 kg/Hr
b.2) Slab on Grade kg. 95.74 kg/MD 11.9575 kg/Hr
b.3) Columns, Beams and R.C. Wall kg. 85.00 kg/MD 10.6250 kg/Hr
b.4) Cast-In-Place Culert and Manholes kg. 61.00 kg/MD 7.6250 kg/Hr

909 F. CONCRETING
a) Place, Finish & Cure Concrete
a.1) Footing anfd Foundation cu.m. 3.32 m3/MD 0.4150 m2/Hr
a.2) Slab on Grade cu.m. 1.89 m3/MD 0.2363 M2/Hr
a.3) Columns cu.m. 1.02 m3/MD 0.1275 m2/MD
a.4) R.C. Walls cu.m. 0.94 m3/MD 0.1175 m2/Hr
a.5) Structural Slabs cu.m. 0.88 m3/MD 0.1100 M3/Hr
a.6) Cast-InPlace Culverts cu.m. 1.32 m3/MD 0.1650 m3/Hr
a.7) Cast-In-Place Manholes cu.m. 2.65 m3/MD 0.3313 m3/Hr
b)Placing Concrete
b.1) Salb on Fill cu.m. 1.36 m3/MD 0.1700 m3/Hr
b.2) Slip Form cu.m. 0.27 m3/MD 0.0338 m3/Hr
b.3) Chute form Truck cu.m. 0.95 m3/MD 0.1188 m3/Hr
b.4) Crane and Bucket cu.m. 0.48 m3/MD 0.0600 m3/Hr
b.5) Wheeling cu.m. 0.20 m3/MD 0.0250 m3/Hr
b.6) Concrete pour on elevated cu.m. 0.34 m3/MD 0.04250 m3/Hr
and shored slab chute and Fortalift
b.7) Floor Fin, Unhardened cu.m. 6.80 m3/MD 0.8500 m3/Hr
b.8) Concrete Fin, Hardened cu.m. 4.76 m3/MD 0.5950 m3/Hr

c) Concrete Mixing
c.1) Manual Mixing sq.m. 0.41 m3/MD 0.0513 m3/Hr
c2) One-Bagger Mixing sq.m. 3.81 m3/MD 0.4763 m3/Hr

V. MASONRY WORKS
506(1) - Masonry Works
a) CHB Laying
a.1)chb 4" sq.m 5.10 m2/MD 0.6375 m2/Hr
a.2) CHB 6" sq.m 4.25 m2/MD 0.5313 m2/Hr
a.3) CHB 8" sq.m 3.40 m2/MD 0.4250 m2/Hr
b) Brick Works (1.0 x 2.0m) sq.m 13.60 m2/MD 1.7000 m2/Hr
c) Red Bricks (1/4" x 2" x 8") sq.m 1.36 m2/MD 0.1700 m2/Hr
d) Laying of Adobe sq.m 5.98 m2/MD 0.7475 m2/Hr

VI. CARPENTRY WORKS


1003 - Carpentry and Joinery
a) Wall
a.1) Plywood Partitons pc. 6.80 PC/MD 0.8500 PC/Hr
a.2) T& G Siding bf. 48.55 BF/MD 6.0688 BF/Hr
a.3) Siding Frame Works bf. 25.16 BF/MD 3.1450 BF/Hr
a.4) wood Wall and Partitions cu.m. 13.60 m3/MD 1.7000 m3/MD
a.5) Wood Walls Partitions cu.m. 13.60 m3/MD 1.7000 m3/MD
a.6) Panel Wall sq.m. 0.95 m2/MD 0.1188 m2/MD
a.7) Double Wall Partiotion cu.m. 5.98 m2/MD 1.7000 m3/MD

b) Floor
b.1) T & G Flooring bf 48.55 BF/MD 6.0688 bf/Hr
b.2) Floor Framing bf 14.01 BF/MD 1.7513 bf/Hr

c.) Wooden Post Erection bf 1.98 BF/MD 1.9975 BF/Hr

d.) Ceiling
d.1) Ceiling Frame(Joist, Nailers, sq.m. 5.10 m2/MD 0.6375 BF/Hr
and handrails)
d.2) Plywood Installation shts. 6.80 shts/MD 0.8500 shts/Hr
d.3) Finer Cement Board Installation shts. 6.80 shts/MD 0.8500 shts/Hr
d.4) Accoustis Ceiling sq.m. 5.64 m2/MD 0.7050 m2/Hr
d.5) Cealing Eaves Installation sq.m. 5.64 m2/MD 0.7050 m2/Hr
d.6) Fascia Board Installation sq.m. 16.32 m2/MD 2.0400 m2/Hr

e.) Cabinet
e.1) Cabinet Framing bf. 52.29 BF/MD 6.5363 BF/Hr
e.2) Cabinet Boarding 37.61 BF/MD 4.7263 BF/Hr
e.3) Built-In Wood Cabinet 37.81 BF/MD 4.7263 BF/Hr

f) Base Board Insatallation lm 34.00 LM.MD 4.2500 LM/Hr


g) Wooden Stairs plight 17.00 plight/MD 2.1250 plight/Hr
h) Wooden Molding/Cornice lm 61.81 Lm/MD 7.7262 LM/Hr

VII. FABRICATED MATERIALS AND HARDWARES


1004 - Hardwares and Accessories
a) Hinges Installation
1. Loose Pin pc. 15.00 pc/Md 1.8750 pcs/Hr
2. Piano Hinges lim.m. 25.00 lm/MD 3.1250 lm/Hr
3. Double Swing pcs. 10.00 pcs/MD 1.2500 pcs/Hr
4. Barrel Boris pcs. 15.00 pcs/MD 1.8750 pcs/Hr

1005 - Steel Windows


a) Casement Type pc. 1.00 pc/MD 0.1250 pc/Hr
b) Awning Type pc. 1.00 pc/MD 0.1250 pc/Hr
c) French Type pc. 1.00 pc/MD 0.1250 pc/Hr
d) Fixed Steel pc. 1.00 pc/MD 0.1250 pc/Hr
e) Louver Window
1. Fixed Metal Louver pc. 1.00 pc/MD 0.1250 pc/Hr
2. Fixed G.I. Sheets pc. 1.00 pc/MD 0.1250 pc/Hr

1006 - Steel Door and Frames


a) Hollow Metal Door
1.Fabrication pc 0.07 pc/MD 0.0088 pc/Hr
2. Installation pc 1.00 pc/MD 0.0125 pc/Hr
b) Steel Bars pc 1.00 pc/MD 0.0125 pc/Hr

1007 - Aluminum Glass Doors


a) Aluminum Frame pc. 0.68 pc/MD 0.0850 pc/Hr
b) Sliding Glass Door pc. 0.54 pc/MD 0.0675 pc/Hr

1008 - Aluminum Glass Window pc.


a) Aluminum Frame pc. 1.00 pc/MD 0.1250 pc/Hr

1009 - Jalousie Window


a) Aluminum Jalousie sq.m. 2.70 m2/MD 0.3375 m2/Hr
b) Glass Jalousie sq.m. 2.70 m2/MD 0.3375 m2/Hr
c) Wood Jalousie sq.m. 2.70 m2/MD 0.3375 m2/Hr

SPL - Louver Windows


a) Fixed Asbetos pc. 1.00 pc/MD 0.1250 pc/Hr
b) Fixed Glass pc. 1.00 pc/MD 0.1250 pc/Hr

1010 - Wooden Doors and Windows


a) Doors
1. Hollow Core
Fabrication m2 1.03 m2/MD 0.1288 m2/Hr
Installation m3 1.89 m2/MD 0.2363 m2/Hr
2. Panel Door m4 1.89 m2/MD 0.2363 m2/Hr

b) Windows
1. Casement Type m2 1.92 m2/MD 0.2400 m2/Hr
2. Jalousie Type m3 1.92 m2/MD 0.2400 m2/Hr
3. Fixed Wooden m4 1.92 m2/MD 0.2400 m2/Hr

c) Frames and Locksets


1. Wood Door Jambs unit 2.50 uni/MD 0.3125 uni/Hr
2. Wood Window Jambs unit 1.60 uni/MD 0.2000 uni/Hr
3. Steel Door Jambs unit 1.000 uni/MD 0.1250 uni/Hr
4. Steel Window Jambs unit 1.000 uni/MD 0.1250 uni/Hr
5. Door lockset set 4.25 set/MD 0.5313 set/Hr

1011 - Rolling Up Doors pc. 0.27 pc/MD 0.0338 pc/Hr

SPL - Grills and Rollings


a) Steel Gates sq.m. 1.00 m2/MD 0.1250 M2/Hr
b) Window Grills pc. 1.00 pc/MD 0.1250 pc/Hr
c) Steel Railings lin.m 10.00 lm/MD 1.0625 lm/Hr
d) Stainless Railings lin.m 10.00 lm/MD 4.0463 lm/Hr
e) Cyclone Wire sq.m. 2.10 m2/MD 0.2625 m2/Hr
d) Steel Fire Escape set 0.25 set/MD 0.0313 set/Hr

VIII. ROOF RAMING WORKS


402 - Timber Structure
a) Wooden Truss
1. Fabrication Bd.Ft 19.38 bf/Md 2.4225 BF/Hr
2. Erections set 0.10 set/MD 0.0125 set/Hr
3. Installation Bd.Ft 8.50 bf/Md 1.0625 BF/Hr
b)Wood grift Installation Bd.Ft 32.27 bf/Md 4.0463 BF/Hr
c) Wood Plate Installation Bd.Ft 21.90 bf/Md 2.7375 BF/Hr
d) Wood Purlines Intsllation Bd.Ft 25.16 bf/Md 3.1450 BF/Hr
e) Wood Media Aqua Frame Bd.Ft 50.0 bf/Md 6.2500 BF/Hr

403 - Metal Structures


a) Steel Truss
1. Fabrication kg 136.00 kg/MD 17.0000 kg/hr
Heavy Sections
a) Erections set 0.10 set/MD 0.0125 set/hr
b. Installation set 0.10 set/MD 0.0125 set/hr
Light Sections
a) Erections set 0.40 SET/Md 0.0500 set/hr
b. Installation set 0.40 SET/Md 0.0500 set/hr
2. Painting lin.m. 34.00 Lm/MD 4.2500 lm/hr
a) Steel Purlins Installations lin.m. 36.00 lm/MD 4.5000 lm/hr
b) Steel Media Aqua Frame kgs 68.00 kg/MD 8.5000 kg/hr

IX. ROOFING WORKS


1013 - Corrugated Metal Roofing
1014 - Pre-Painted Metal Sheets
a) Installation o GI sheets sq.m. 8.30 m2/MD 1.0375 m2/Hr
b) Installation of Ridge Rolls lin.m. 42.50 lm/MD 5.3125 lm/Hr
c) Installation of Valley Roll lin.m. 42.50 lm/MD 5.3125 lm/Hr
d Installation of Flashing lin.m. 42.50 lm/MD 5.3125 lm/Hr
e) Installation of Gutters lin.m. 42.50 lm/MD 5.3125 lm/Hr

1017 - Roof Drains ans Stainers


a) Installation of Roof Strainers pc 8.00 pc/MD 1.0000 PC/Hr
b) Installation of Downspout lin.m. 51.00 lm/MD 6.3750 lm/Hr
c) Installation of Insulation sq.m 14.00 m2/MD 1.7500 m2/Hr

X. FINISHES
1018 - Ceramic Tiles
a) Ceramic Glazed Tiles sq.m. 2.24 m2/MD 0.28000 m2/Hr
b) Ceramic unglazed Tiles sq.m. 1.56 m2/MD 0.1950 m2/Hr

1019 - Wood Tiles


a) Narra Parquet Finish sq.m. 9.30 m2/MD 1.1625 m2/Hr
b) Tanguile Parquet Finish sq.m. 9.30 m2/MD 1.1625 m2/Hr

1020 - Vinyl Floor Tiles sq.m. 3.81 m2/MD 0.4763 m2/Hr

1021 - Palin Cement Finish


a) Plain Cement Floor Tiles sq.m. 9.52 m2/MD 1.1900 m2/Hr
b) Plain Cement Floor Finish with color sq.m. 4.83 m2/MD 0.6038 m2/Hr

1022 - Stucco Finish


a) Plain Cement Stucco Finish sq.m. 4.08 m2/MD 0.5100 m2/Hr
b) Plain Cement Stucco Finish With Color sq.m. 3.5 m2/MD 0.4375 m2/Hr

1023 - Granolithic Marble Works sq.m. 2.31 m2/MD 0.2888 m2/Hr


1024 - Pea Gravel Wah Out Finish sq.m. 4.76 m2/MD 0.5950 m2/Hr
1025 - Buh Hammered Finish sq.m. 2.5 m2/MD 0.3125 m2/Hr
1026 - Peeble Wash OuT Finish sq.m. 4.76 m2/MD 0.5950 m2/Hr
1027 - Cement Plaster Finish sq.m. 9.50 m2/MD 1.1875 m2/Hr
1028 Synthetic Adobe Finish sq.m. 2.50 m2/MD 0.3125 m2/Hr
1029 - Granite WAH Out Finish sq.m. 4.76 m2/MD 0.5950 m2/Hr
SPL a) Marble Tile Finish sq.m. 3.40 m2/MD 0.4250 m2/Hr
b) Granite Tile Finish sq.m. 3.40 m2/MD 0.4250 m2/Hr
c) 1/2" X 2" X 8" Red Block sq.m. 1.36 m2/MD 0.1700 m2/Hr
d) Manolithic Terrazo Finish sq.m. 6.04 m2/MD 0.7550 m2/Hr
e) Synthetic Marble Tiles sq.m. 1.49 m2/MD 0.1863 m2/Hr
f) Wall Papers sq.m. 0.88 m2/MD 0.1100 m2/Hr
g) Plastered Ceiling sq.m. 2.24 m2/MD 0.2800 m2/Hr
h) Mozaic Floor Tiles sq.m. 0.82 m2/MD 0.1025 m2/Hr

XI. PAINTING/VARNISHING WORKS


1032 - Painting, Varnishing and other related Works
A. Painting
a) Plain Cement Paint Exterior sq.m. 16.73 m2/MD 2.0913 m2/Hr
b) Plain Cement Paint Metal sq.m. 16.73 m2/MD 2.0913 m2/Hr
c) Exposed Aggregates Tool Paint Finish sq.m. 16.73 m2/MD 2.0913 m2/Hr
d) Ferrous Metal Finish sq.m. 13.94 m2/MD 1.7425 m2/Hr
e) Galvanized Metal sq.m. 13.94 m2/MD 1.7425 m2/Hr
f) Steel Ducco Finish sq.m. 6.97 m2/MD 0.8713 m2/Hr
g) Wood Paint sq.m. 23.05 m2/MD 2.8813 m2/Hr
h) Wood Ducco Finish sq.m. 6.97 m2/MD 0.8713 m2/Hr
i) Textured Paint sq.m. 6.97 m2/MD 0.8713 m2/Hr
j) Glass Paint sq.m. 10.87 m2/MD 1.3713 m2/Hr
B. Varnishing
a) Plain Varnish Paint sq.m. 15.78 m2/MD 1.9725 m2/Hr
b) Ducco Varnish Paint sq.m. 7.89 m2/MD 0.9863 m2/Hr

XII. WATERPROOFING WORKS


1016 - Waterproofing
a) Cement - Base Integral sq.m. 5.00 m2/MD 0.6250 m2/Hr
b) Membrane Waterproofing 12.81 m2/MD 1.6013 m2/Hr
c) Liquid Waterproofing 15.39 m2/MD 1.9238 m2/Hr
d) Hydraulic Waterproofing 12.31 m2/MD 1.5388 m2/Hr
e) Water Installation 10.20 m2/MD 1.2750 m2/Hr

XIII. SANITARY WORKS


1001 - Storm Drainage & Sewage System
a) Laying of RCCP
a.1) 24" dia ln.m. 1.70 lm/MD 0.2125 lm/Hr
a.2) 36" dia ln.m. 1.02 lm/MD 0.1275 lm/Hr
a.3) 48" dia ln.m. 0.61 lm/MD 0.0765 lm/Hr
a.4) 6" dia ln.m. 5.10 lm/MD 0.6375 lm/Hr

b) Laying of Asbestos
b.1) 1/2" dia ln.m. 0.41 lm/MD 0.0531 lm/Hr
b.2) 3/4" dia ln.m. 0.41 lm/MD 0.0513 lm/Hr
b.3) 1" - 1 1/4" dia ln.m. 0.47 lm/MD 0.0588 lm/Hr
b.4) 1 1/2 - 2" dia ln.m. 0.52 lm/MD 0.0650 lm/Hr
b.5) 2 1/2" dia ln.m. 0.62 lm/MD 0.0775 lm/Hr
b.6) 3" dia ln.m. 0.68 lm/MD 0.0850 lm/Hr
b.7)4" dia ln.m. 0.83 lm/MD 0.1038 lm/Hr

c) Cast Iron Pipe


c.1) 2" dia ln.m. 1.39 lm/MD 0.1738 lm/Hr
c.2) 4" dia ln.m. 2.07 lm/MD 0.2588 lm/Hr
c.3)6" dia ln.m. 3.11 lm/MD 0.3888 lm/Hr
c.4) 8" dia ln.m. 4.15 lm/MD 0.5188 lm/Hr
c.5) 10" dia ln.m. 6.22 lm/MD 0.7775 lm/Hr
c.6) 12" dia ln.m. 6.57 lm/MD 0.8213 lm/Hr
c.7) 14" dia ln.m. 7.63 lm/MD 0.9538 lm/Hr
c.8) 16" dia ln.m. 8.67 lm/MD 1.0838 lm/Hr
c.9) 18" dia ln.m. 9.72 lm/MD 1.2150 lm/Hr
c.10) 20" dia ln.m. 10.37 lm/MD 1.2963 lm/Hr
c.11) 22" dia ln.m. 11.51 lm/MD 1.4388 lm/Hr

1012 - Plumbing Works


a) G.I Pipes
a.1) 1/2" dia lin.m 16.70 lm/MD 2.0875 lm/Hr
a.2) 3/4" dia lin.m 15.18 lm/MD 1.8975 lm/Hr
a.3) 1" dia lin.m 13.80 lm/MD 1.7250 lm/Hr
a.4) 1 1/4" dia lin.m 12.54 lm/MD 1.5675 lm/Hr
a.5) 1 1/2" dia lin.m 11.41 lm/MD 1.4263 lm/Hr
a.6) 1 3/4" dia lin.m 10.35 lm/MD 1.2938 lm/Hr
a.7) 2" dia lin.m 8.65 lm/MD 1.0813 lm/Hr
a.8) 3" dia lin.m 7.20 lm/MD 0.9000 lm/Hr
a.9) 4" dia lin.m 6.00 lm/MD 0.7500 lm/Hr

b) PVC Pipes
b.1) 1/2" dia lin.m 0.42 lm/MD 0.0525 lm/Hr
B2.) 1- 1/2" dia lin.m 1.56 lm/MD 0.1950 lm/Hr
b.3) 1 1/2" - 2" dia lin.m 1.70 lm/MD 0.2125 lm/Hr
b.4) 2 1/2" dia lin.m 2.04 lm/MD 0.2550 lm/Hr
b.5) 3" dia lin.m 0.68 lm/MD 0.0850 lm/Hr
b.6) 4" dia lin.m 0.83 lm/MD 0.1038 lm/Hr
b.7) 5" dia lin.m 1.04 lm/MD 0.1300 lm/Hr
b.8) 6" dia lin.m 1.56 lm/MD 0.1950 lm/Hr

XIV. ELECTRICAL WORKS


1100 - Conduits, Boxes and fittings
a) Conduits lin.m 36.00 lm/MD 4.5000 Lm/Hr
b) Boxes and Fittings pcs 28.00 pc/MD 3.5000 pc/Hr

1101 - Wire and Wiring Devices


a) Wiring lin.m. 15.00 lm/MD 18.7500 lm/Hr
b) Devices set 10.00 set/MD 1.2500 pcs/Hr
1102 - Power Load Center, Switch Gear and Panel Boards
a) Lighting sets 8.00 set/MD 1.0000 set/Hr
b) Panel Boards circuit 8.00 set/MD 1.0000 set/Hr

SOURCES AND REFERENCES


1. DPWH Standard Specifications, vol. II & III, 1995 edition
2. DPWH - BOC dta on various building structures previously implemented
3. Construction Manpower Development Foundation (CMDF)
4. Construction Estimate Handbook by Velasco