Transmission Line Reliability and Security PDF
Transmission Line Reliability and Security PDF
i
This page intentionally left blank
Transmission Line
Reliability and
Security
iii
Library of Congress Cataloging-in-Publication Data
Pansini, Anthony J.
Transmission line reliability and security/Anthony J. Pansini.
p. cm.
ISBN 0-88173-471-3 (print) -- ISBN 0-88173-472-1 (electronic)
1. Electric power transmission. 2. Electric power systems--Secu-
rity measures. 3. Electric circuits--Reliability. I. Title.
TK3091.P3132 2004
621.319--dc22
2004043334
10 9 8 7 6 5 4 3 2 1
iv
To the three women in my life…
v
This page intentionally left blank
Contents
Preface .......................................................................................... ix
vii
This page intentionally left blank
Preface
In 1992, Congress passed legislation essentially permit-
ting electric (and other) utilities to be unregulated, resulting
in transmission displacing local generation as the main sup-
ply to local communities and creating problems of service
reliability. In 2001, events associated with 9-11 created prob-
lems of security. Although solutions to both can be coordi-
nated, focus must be directed on security. Attention will be
given to prevention, damage limitation and rapid restoration
Criteria for arriving at solutions are: Electrically, circuits
must be so arranged that the shutting down of one or two
does not cascade into an area blackout. Mechanically, new
circuits should have a low profile so as not to attract undue
attention; fences, surrounding the structures should be pro-
vided to thwart saboteurs from their intentions; circuits
should be designed so that any damage or destruction is lim-
ited; and procedures updated for rapid restoration of facili-
ties when several simultaneous points of damage or
destruction are involved. For new and existing lines, struc-
tures should be surrounded by barbed wire topped fences
and the installation of battery operated sensors that would
radio back to the system operator an alarm of intrusion and
its location.
The criteria may also limit the voltage class of the trans-
mission line to 138 kV because of code clearance require-
ments of distances between conductor and ground and,
between conductors, take up space available on the tallest
wood structure. This also happens to be the limit for ‘solid’
type insulation (no gas or oil accessories) underground
cables that may be installed in sections or branches of the
circuit, and it is also the approximate limit for working from
insulated bucket vehicles.
ix
Meeting the criteria mentioned above, the usual eco-
nomic considerations may have to be strained to new limits,
and in some instances ignored. Some attempt should be
made to separate charges to anti-terrorist protection activi-
ties from those associated with the improvement of service
reliability; the former may perhaps be charged to the federal
government, while the latter may not.
Deregulation resulted in the utility being restructured
into three separate and independent enterprises: generation,
transmission and distribution (although almost all three be-
came parts of the original utility as a holding company).
Allegedly, this mode of operation would result in competi-
tion between the several owners of these new operating
units, allowing any single consumer the opportunity to
choose his or her supplier, taking advantage of less expen-
sive sources of energy—with the quality of service equal to
or better than that of the replaced utility.
This discussion of the transmission systems would not
be complete without some explanation of the effect on and
by these three units on each other.
Increasing demands for electric service required the
timely construction and installation of new generating facili-
ties. For environmental and economic reasons, sites for such
new installations were/are becoming extremely difficult, if
not impossible, to find somewhere within the franchise area
(not to mention load centers) of each of the several indepen-
dent companies.
The situation was/is mitigated by allowing new con-
struction to be postponed by the introduction of so-called
cogeneration or merchant generation. Here, larger industrial
and commercial consumers are encouraged to install their
own generating facilities with excess generation during their
cycles of operation to be sold to the local utility by connect-
ing to their transmission or distribution systems (a reversal
x
of policy in some instances). In some states, this consumer
generation is not only mandated, but its unit cost is also set
at that of the least efficient unit of the utility’s generation
sources.
Later, a smaller version, known as distributed genera-
tion, was developed to be connected to the distribution sys-
tem at strategic points. These mainly consisted of small
units, generally driven by small gas turbines, but also in-
cluding a few fuel cell experimental applications; these may
be both utility or consumer owned. These units, and the
cogeneration units are not usually competitive with utility
owned units that have the advantage of economy of scale.
Some cogeneration and distributed generation units
may impact negatively on the safety of operations. Although
standards for the selection, installation and maintenance of
equipment to connect and disconnect these units from the
system to which they supply electric energy are furnished
the consumer by the utility, these standards are not always
followed, particularly those relating to maintenance. This
constitutes a hazard to persons who may be working on the
system; believing it is de-energized, they may be the victims
of an improper, unannounced connection energizing the sys-
tem to which they are connected. Similarly, should a fault
develop on the utility system to which they are connected
and the equipment fail to disconnect their generation from
the system, overloads and fires and explosions may occur.
Further, while they are under the supervision of the system
operator, they tend to dilute his attention to other events
occurring on the electric system to which they may be con-
nected.
Transmission systems, restructured into separate entities
for privately owned and operated utilities, have assumed a
more important and sensitive position in the supply chain of
electricity to the ultimate consumer. Their role has essen-
xi
tially been reversed, from providing backup and peak power
to local generator based systems. They now will become the
primary source of supply, with local generators (if any) as
backup and peak power sources for the new transmission
systems.
In this respect, the restructured transmission systems
essentially follow those of some publicly owned power sys-
tems, such as TVA, Hoover Dam, Grand Coulee, and oth-
ers—systems designed and operated to supply large
amounts of available power to load centers at relatively long
distances from the power sources.
In both instances, the associated transmission lines are
located generally away from populated centers in sparsely
inhabited areas, in the “boondocks,” for economic and envi-
ronmental reasons. Often, the structures support two cir-
cuits, and occasionally more. They are very vulnerable, not
only to vandalism and the vagaries of man and nature, but
especially to the saboteur, as they are extremely exposed.
No attempt is made in this dissertation to describe the
detailed planning, design, and normal operation and main-
tenance of transmission facilities. Many excellent works exist
sufficient to fill the needs of such endeavors. Here, the dis-
cussion is based primarily on the effect of deregulation on
the reliability of the newly deregulated systems, and consid-
eration of what may be done to maintain or improve the
reliability of the now deregulated transmission systems.
Some phenomena occurring in electric theory are included,
in non- or semi-technical terms, for the benefit of non-tech-
nical people and to refresh the memories of engineers.
It is obvious that reliability and security go hand in hand.
But whereas reliability encompasses contingencies resulting
from flaws in design and human errors, security tends to ne-
gate damage and destruction of property and injury or death
to humans deliberately caused by other humans.
xii
While steps are taken to provide security for generating
stations, the transmission lines, which are the delivery sys-
tems for their product, under the deregulated system, pro-
vide literally thousands of miles of opportunity for saboteurs
to deny that product from being delivered to consumers, all
with relative ease and safety.
Electric service has become a necessity not only in the
lives of individuals, but also in the operation of public ser-
vices; e.g., water supply, sewage disposal, communications,
transportation, health activities, etc. Already military sur-
veillance and protection has been extended to nuclear power
installations, and probably may be extended to large power
generating facilities. As the main source of supply to large
areas of the country, should not transmission facilities re-
ceive attention, possibly by some sort of paramilitary agen-
cies? And/or, should not another look be taken at the
methods of supply of electric energy, in view of events of
September 11, 2001?
xiii
This page intentionally left blank
Circuit Arrangements 1
Chapter 1
Circuit Arrangements
5
6 Transmission Line Reliability and Security
Chapter 2
Electrical Criteria
9
10 Transmission Line Reliability and Security
Figure 2-3.
Electrical Criteria 13
Figure 2-4a. Simplified cable circuit (above) shows how power deliv-
ered to load is affected by a shunt reactor. In the absence of shunt
reactors, this power decreases to zero at some critical length.
14 Transmission Line Reliability and Security
LIGHTNING PROTECTION
SINGLE
PARALLEL-CONTINUOUS
DOUBLE
PARALLEL-CONTINUOUS
RADIAL
CONTINUOUS
AND RADIAL
Chapter 3
Mechanical Criteria
19
20 Transmission Line Reliability and Security
STRUCTURES—TOWERS
Suspension or Tangent
Suspension or tangent type are towers in which the in-
sulators to which the conductors are attached are free to
swing (Figure 3-4). The spans on either side of the insulator
string approximately even so that the structure carries only
the weight of the conductors, ice coated, and the force of the
wind against them.
Angle or Corner
Angle or corner type towers (Figure 3-5), as the descrip-
tion implies, are designed to hold the spans of conductors on
either side that are at an angle with each other. They are
usually also of dead end design. These towers are of great
strength, and may also be guyed to take care of the forces
due to the uneven balance of conductors attached to the
crossarm on the tower.
Mechanical Criteria
Figure 3-4. Tangent or suspen- Figure 3-5. Angle or corner tower.
sion tower constructions.
23
24 Transmission Line Reliability and Security
Dead-end
Dead-end type towers (Figure 3-6) also carry the weight
of the span of conductor, but the spans may be unequal in
length and the spans on either side are dead-ended, each
mounted through the insulators directly to the crossarm at-
tached to the tower. The strength of this type is greater than
that of the suspension tower, designed purposely to with-
stand failure if all the conductors on one side break and no
longer balance the ice-laden, wind-driven conductors on the
INSULATORS
LIGHTNING ARRESTERS
CONDUCTORS
and may also contain some filler material to keep the steel
wires centered in the conductor. The conductors are attached
to the insulators holding them by means of “shoes” that are
placed on the top and bottom of the conductor to spread the
pressure applied in holding them there, this to avoid hot
spots if a narrow clamp were used and the pressure applied
at only a very narrow place on the conductor. Care should
also be taken not to break any of the strands of the conductor
as this not only may reduce the current capacity of the con-
ductor, but also create a hot spot in the conductor that may
cause its ultimate failure.
Mechanical Criteria 35
CABLE
Chapter 4
Substation Criteria
for the branch supply, two from one main source and the
third from a separate source, if available, left open if it is de-
sired to operate as an open loop circuit. Refer to Chapter 1.
Reliability of both incoming and outgoing circuits is
provided by the bus arrangement. From least to some high
degree, they all depend on the use of and arrangement of
circuit breakers. Each additional circuit breaker provides
greater flexibility of operation with a greater degree of reli-
ability, including the ability to sectionalize both incoming
and outgoing open-loop circuits at that point. The greater
the number of circuit breakers, the greater the cost. Figure, 4-
2 shows the application of these arrangements when the,
incoming circuit voltage is to be raised to a higher outgoing
voltage circuit. Note the application of reactors to limit the
supply, of fault current to generators where transformers do
not intervene in the circuitry. Figure 4-3 shows a modifica-
▼ ▼ ▼
High
voltage
ring
▼
bus
• • •
Low
voltage
▼
ring
bus
▼
• • • • • • • • • • • •
▼ ▼ ▼ ▼ ▼ ▼ ▼ ▼ ▼ ▼ ▼ ▼
Same
Distribution loop circuits
▼
• • • • • • • • • • • •
•
Switches
normally
open
Section- • ▼
alizing
switches
▼
Emergency ties
•
EC ➔
EA ➔
➔
b
EB
•
•
•
EB ➔
EA
➔
c
•
➔ EC
•
•
•
Re 50°
➔ ➔ R Rej 60°
➔
Zm Zm
Im =
➔
➔
Ix Im =
➔
Ir Zm
➔
Ir Ix
➔
➔
Ir + Ix I r + Ix
•
Chapter 5
Figure 5-1. DC transmission used over very long distances. The two
AC buses may be hundreds of miles apart and do not have to be syn-
chronized, or in phase, to permit power to flow between systems.
Chapter 6
Operations Criteria
ELECTRICAL
MECHANICAL
A G
B H
C
F
Figure 6-1.. Open loop supply of transmission system (no grid or mesh)
This page intentionally left blank
Economics 57
Chapter 7
Economics
MISCELLANEOUS
A few thoughts on research that should be expedited,
perhaps by one new “Manhattan Project.”
1. Conductors of zero resistance (or even negative values)
under load. Work on this has been very successful, but
much remains for it to be practical and economically
competitive.
2. Development of a DC transformer that can rival its AC
present counterpart.
3. Development of a means to store electricity directly,
probably a DC solution.
4. A direct means of generating electricity. Present steam
turbo-generators are about 30% efficient (from the fuel
to the end product) and nuclear units are even much
less.
ACKNOWLEDGMENTS
Appendix A
Insulation:
Porcelain Vs. Polymer
59
60 Transmission Line Reliability and Security
61
62 Transmission Line Reliability and Security
65
66 Transmission Line Reliability and Security
67
68 Transmission Line Reliability and Security
Figure A-5(c).
72 Transmission Line Reliability and Security
Figure A-5(e).
Appendices 73
75
76 Transmission Line Reliability and Security
Appendix B
The Grid
Coordinate System:
Tying Maps to Computers*
INTRODUCTION
*Reprinted (with modifications) from Consulting Engineer,® January 1975, vol. 44, no. 1, pp.
5 1-55.© by Technical Publishing, a company of the Dun & Bradstreet Corporation, 1975.
All rights reserved.
79
80 Transmission Line Reliability and Security
dom, but have some meaning. Like any graph, these two
coordinates represent measurements from a reference point;
in this respect they are similar to navigation’s latitude and
longitude measurements.
Further subdivision of the basic grid areas into a series
of smaller grids is possible, each having a decimal relation
with the previous one (i.e., by dividing each horizontal and
vertical space into tenths, each resultant area will be one-
hundredth of the area considered). By using more detailed
maps of smaller scale, it is possible to define smaller and
smaller areas simply by carrying out the coordinate numbers
to further decimals. For practical purposes, each of these
grid areas should measure perhaps not more than 25 ft by 25
ft (preferably less, say 10 ft by 10 ft) and should be identified
by a numeral of some 6 to 12 digits.
For example, by dividing by 10, an area of 1,000,000 ft
by 1,000,000 ft (equivalent to some 190 miles square) can be
divided into 10 smaller areas of 100,000 ft by 100,000 ft each,
identified by two digits, one horizontal and one vertical.
This smaller area can again be subdivided into 10 smaller
areas of 10,000 ft by 10,000 ft each, identified by two more
digits, or a total of four with reference to the basic 1,000,000-
ft square area. Breaking down further into 1000- by 1000-ft
squares and repeating the process allows these new grids to
be identified by two more digits, or a total of six. Again
dividing by 10 into units of 100 ft by 100 ft, and adding two
more digits, produces a total of eight digits to identify this
grid size. One more division produces grids of 10 ft by 10 ft
and two more digits in the identifying number-for a total of
10 digits, not an excessive number to be handled for the grid
size under consideration; see Figure B-1.
This process may be carried further where applications
requiring smaller areas are desirable; however, each further
breakdown not only reduces the accuracy of the measure-
Appendices 81
Standard References
To give these numerals some actual physical or geo-
graphical significance, they may be tied in with existing local
maps. U.S. Geological Survey maps, coast and geodetic sur-
vey maps, state plane coordinate systems, standard metro-
politan statistical areas, or latitude and longitude bearings.
They may also be tied in with maps independent of all of
these.
While reference to state and federal government sys-
tems lends some geographical significance, it produces iden-
tifying grid numbers with several additional digits. It is not
necessary for any grid coordinate system to have this refer-
ence to a government system, but if it is desired, it is a rela-
tively simple procedure to develop a computerized look-up
program that can translate such coordinates.
Basic grid coordinate maps may be developed from the
conversion of existing maps to a usable scale, if such maps
are reasonably accurate and complete, both as to their geog-
raphy and content. They may also be developed from exact
land surveys, from aerial surveys, or from combinations of
all of these.
Excellent maps are also available for most of the coun-
try. U.S. Geological Survey maps show latitude and longi-
tude lines every few miles; they also show numerous
triangulation stations with the latitude and longitude for
each station determined to an extreme degree of accuracy.
Appendices 83
Earth’s Curvature
Errors occur in mapping the earth’s curved surface on a
flat map; see Figure B-2. For example, in the case of the
approximate 190-mi square mentioned previously, in the
continental United States, the error introduced by this curva-
ture, measuring from the center (95 mi in the longitudinal, or
north-south direction) would probably not exceed 2 percent,
a tolerable error. These errors need not be of great import,
except in establishing match lines between maps. No gaps or
Data Retrieval
Data contained in the files may be retrieved by means of
the computer and may be presented visually by means of
CRTs for one-time instant use, or by printouts and automatic
plotting for repeated use over an indefinite time period. Data
presented may be the exact original data as contained in one
or more files, or extracted data obtained as a result of corre-
lating data residing in one or more files, or a combination of
both; such extracted data may or may not be retained in
separate files for future use.
These data may be retrieved for an individual consumer
or an individual item of plant facilities, or may be other data
for a particular area, small or large. The various specific
purposes determine what data are to be retrieved and how
they are to be presented. They also determine the programs
and equipment required. Data thus retrieved then are used
with data contained on the map to help in forming the de-
cisions required. The decisions may include new data that
can be reentered in the files as updating material, that can be
plotted or printed for exhibit purposes, or that can be reen-
tered on maps for updating or expanding the material
thereon; all of these may be done by means of the computer.
The grid coordinate number is applied to utility facili-
ties for ease of location and positive identification in the
field. In the case of electric utilities, these may include ser-
vices, meters, poles, towers, manholes, pull boxes, trans-
formers, transformer enclosures, switches, disconnects,
fuses, lightning arresters, capacitors, regulators, boosters,
streetlights, air pollution analyzers, and other equipment
and apparatus; also the location of laterals on transmission
and distribution circuits.
Appendices 91
OTHER APPLICATIONS
ECONOMICS
Appendix C
Surface
1 inch2 = 645.2 mm2 1 millimetre2 = 0.00155 inch2
1 inch2 = 6.452 cm2 1 centimetre2 = 0.155 inch2
1 foot2 = 0.0929 m2 1 metre2 = 10.764 foot2
1 yard2 = 0.8361 m2 1 metre2 = 1.196 yard2
1 acre = 0.4047 hectare 1 hectare = 2.471 acres
1 mile2 = 258.99 hectare 1 hectare = 0.00386 mi2
1 mile2 = 2.59 km2 1 kilometre2 = 0.3861 mile2
Volume
1 inch3 = 16.39 cm3 1 centimetre3 = 0.061 inch3
1 foot3 = 0.0283 m3 1 metre3 = 35.314 foot3
1 yard3 = 0.7645 m3 1 metre3 = 1.308 yard3
1 foot3 = 28.32 litres 1 litre = 0.0353 foot3
1 inch3 = 0.0164 litre 1 litre = 61.023 inch3
1 quart = 0.9463 litre 1 litre = 1.0567 quarts
1 gallon = 3.7854 litres 1 litre = 0.2642 gallons
1 gallon = 0.0038 m3 1 metre3 = 264.17 gallons
Weight
1 ounce = 28.35 grams 1 gram = 0.0353 ounce
1 pound = 0.4536 kg 1 kilogram = 2.2046 lb*
1 net ton = 0.9072 T (metric) 1 Ton (metric) = 1.1023 net tons**
*Avoirdupois
**1 ton = 2000 lb
Compound units
1 lb/ft = 1.4882 kg/m 1 kilogram/metre = 0.6720 lb/ft
1 lb/in2 = 0.0703 kg/m2 1 kg/cm2 =14.223 lb/in2
93
This page intentionally left blank
Appendices 97
Appendix D
Eric Hirst
Consulting in Electric-Industry Restructuring
Oak Ridge, Tennessee
Brendan Kirby
Oak Ridge National Laboratory
Oak Ridge, Tennessee
Introduction
Transmission Planning Practices
Traditional Utilities
Current Planning Environment
Review of Recent Plans
Review of RTO Transmission Planning
Proposed Planning Process
Key Transmission Planning Issues
Planning Criteria: Reliability and Commerce
Economies of Scale
Congestion Costs
Generation and Load Alternatives
New Technologies
Merchant Transmission
Projections of New Generation and Load Growth
Recommendations
Conclusions
Acknowledgments
References
97
98 Transmission Line Reliability and Security
INTRODUCTION
Centralized vs
To what extent can private investors, rather
decentralized
than RTO planners, decide on and pay for
transmission
new transmission facilities? Can they, in spite
planning and
of networkexternality effects, capture enough
expansionof the benefits of such transmission projects
to justify their investment? How can new
technologies advance private investment?
—————————————————————————————
102 Transmission Line Reliability and Security
Traditional Utilities
Historically, transmission planning was much simpler
than it is today and than it is likely to be in the future. Until
the mid-1990s, the U.S. electricity industry featured verti-
cally integrated utilities. As a consequence, transmission
planning was closely coupled to generation planning. Utili-
ties, because they owned generation and transmission, could
optimize investments across both kinds of assets. With re-
spect to operations, utilities routinely scheduled generation
day-ahead and redispatched generating units in real time to
prevent congestion from occurring. The costs of such sched-
uling and redispatch were spread across all customers and
reflected in retail rates.1
In addition, utilities had good data and forecasting tools
to estimate current and future loads and generating capacity.
Because each utility was the sole provider of retail electricity
services, it had considerable information on current and
likely future load levels and shapes. Because each utility was
Figure 4. National Grid USA’s assessment of the best and worst loca-
tions within New England to locate new generating units.
Appendices 115
3This works out to a transmission investment of more than $400 per new kW of
remote generation, a very high cost. If new coal and wind generation costs about
$1000/kW, the supporting transmission would add 40% to the initial cost. By
comparison, the new transmission planned for the Pennsylvania-New Jersy-
Maryland Interconnection (PMJ, 2001b) region ($720 million to connect 27,500
MW of new generation) is expected to cost only $26 per new kW of generation.
Part of this cost difference occurs because the distances between generation and
load centers are much greater in the west than in the mid-Atlantic region.
Appendices 117
4The Tennessee Valley Authority faces a similar situation. It has received appli-
cations from independent power producers for 90,000 MW of new generation,
more than three times the amount of existing generation (Whitehead, 2001). TVA
would need an extra 50 system planners to clear the backlog of interconnection
studies associated with all these new generators.
118 Transmission Line Reliability and Security
• Finally, the ISO will assess the ITC’s Outlook and ap-
prove a regional plan. This assessment will consider
other alternatives proposed by the ISO and stakehold-
ers. The ISO review will provide “a check that the Out-
look is not biased in favor of transmission solutions at
the expense of generation or other market-based solu-
tions.” “The decision to proceed with [transmission
projects] will be made by the market [participants] for
market based proposals (including merchant transmis-
Appendices 123
7The results of Steps 2 and 3 should be sufficiently detailed that other parties can
assess for themselves market solutions to solve these problems (e.g., those dis-
cussed in Step 6).
Appendices 127
behavior that might occur. Such behavior will be a strong function of the RTO
operating and market rules as well as the physical infrastructure (amounts and
locations of generation, transmission, and load).
10Uncertainties are much greater than in the past. Today, they include load shape
and levels, generator locations (new construction and retirements), market opera-
tions, market prices for energy and ancillary services, transmission pricing (in-
cluding locational pricing for losses and congestion), patterns and levels of
commercial transactions, weather, fuel price volatility, and new generation and
transmission technologies.
11For example, consider the risks associated with cost recovery for a new trans-
mission line needed to connect a new generator to the grid. This risk could be
eliminated by requiring the generation owner to pay the capital costs up front
rather than through rates over a 20-year cost-recovery period.
128 Transmission Line Reliability and Security
12Such pricing schemes should encompass access charges as well as charges for
congestion and losses.
Appendices 129
Table 2.
Checklist of important characteristics of a transmission plan
————————————————————————————————
• Public involvement throughout planning process
Economies of Scale
It is generally cheaper per megawatt of capacity to build
larger transmission lines (Table 3). For example, the cost per
MW-mile of a 500-kV transmission line is about half that of
a 230-kV line. Higher-voltage lines also require less land per
MW-mile than do lower-voltage lines (right side of Table 3).
A 500-kV line requires less than half the land per MW-mile
132 Transmission Line Reliability and Security
of a 230-kV line.
Both of these factors argue for overbuilding lines rather
than trying to size lines to exactly match current and short-
term forecast needs. (Overbuilding includes the use of larger
conductors, construction of larger towers that can carry more
than one set of circuits, and the use of higher-voltage lines.)
Overbuilding a line now will (1) reduce long-term costs by
avoiding the much higher costs of building two smaller lines
and (2) reduce the delays and opposition associated with
transmission-line siting by eliminating these costs for the
now unneeded second line.
Congestion Costs
Decisions on whether to build new transmission are
complicated by uncertainties over the future costs of conges-
tion. (To some extent, the prices of firm transmission rights
show how the market values certain transmission paths.)
These uncertainties relate to load growth, the price respon-
siveness of load, fuel costs and therefore electricity prices,
additions and retirements of generating capacity and the
locations of those generators, the exercise of market power
by some generators, and transmission pricing. The ISO New
England (2001) analysis, summarized in Figure 3, shows this
complexity very well. Analysis conducted for the New York
ISO showed that the large number of proposed generating
projects in or near New York City and Long Island “would
reduce the level of congestion observed on the…bulk power
system, with the biggest congestion decreases occurring in
New York City and on Long Island” (Sanford,
Banunarayanan, and Wirgau, 2001).
We developed a simple hypothetical example to explore
these issues and their complexities and interactions. This
example involves two regions, A and B, separated by 200
miles. Region A contains 31 GW of generating capacity and
no load. Region B contains 32 GW of generating capacity and
50 GW of load. Both regions contain a wide range of gener-
ating capacity, with running costs (or bids) that vary from
zero to almost $160/MWh. The load in Region B ranges from
20 to 50 GW, with a load factor of 63%.
We calculated the cost of congestion as the difference be-
tween (1) the cost of generation (including generators in
134 Transmission Line Reliability and Security
the two units there is no benefit from adding more than 1.5
GW of generating capacity in Region B because other gen-
erators are less expensive. Once again, the results are highly
nonlinear.
If loads grow at 2% a year, the annual cost of congestion
(assuming no additions to either generating or transmission
capacity) increases from $87 million in the initial year to
$125, $162, and $250 million in the second, third, and fourth
years. Such increases in load make transmission investments
substantially more cost-effective. If loads respond to prices,
such that loads are higher at low prices and lower at high
prices, congestion costs would be reduced. In this example,
as the price elasticity of demand increases from 0 to 0.02,
0.04, and 0.08, congestion costs are reduced from $87 million
to $48, $25, and $7 million a year. For the ranges in load
growth and price elasticity considered here, congestion costs
vary from $7 to $250 million a year when the amount of
transmission capacity between the two regions is 21 GW.
Making decisions on how much money to invest in equip-
ment with lifetimes of several decades is difficult in the face
of such uncertainties about future load growth; customer
response to dynamic pricing; and the amounts, locations,
and running costs of new generating units.
The discussion so far has focused on the benefits of re-
ducing congestion. But not all market participants benefit
when additional transmission is built to relieve congestion.
In particular, loads on the low-cost side of the constraint and
generators on the high-cost side of the constraint lose money
when congestion is reduced. For example, a generator in
Region B with a bid price of $42/MWh would earn $6.9/kW-
year when the transmission capacity between regions A and
B is 20 GW. Expanding transmission capacity to 21 or 22 GW
would reduce that generator’s earnings to $4.6 and $3.7/kW-
year, reductions of 33% and 46%, respectively. Such large
Appendices 137
New Technologies
Superconductivity, power electronics, information sys-
tems, and other new technologies could revolutionize trans-
mission and make it easier to expand the system through
merchant, rather than regulated, projects. According to
Howe (2001), “Recent advances in materials science offer the
prospect of another industry paradigm: one based on robust
facilities-based competition in network services, without the
environmental and land-use impacts of traditional ‘big iron’
142 Transmission Line Reliability and Security
Merchant Transmission
The kinds of new technologies discussed above make it
possible for unregulated, for-profit entities to build what are
called merchant transmission projects. Under such circum-
stances, the need for centralized transmission planning is
greatly reduced. Three such merchant projects have been
proposed in the United States:
Investment? Monitoring
Yes
▼ Enough Response
Have Viable Market-Base No Issue RFP that Meet RFP
▲
Recommendations
As the electricity industry continues its long and com-
plicated transition to a fully competitive state, the require-
ments for transmission planning are changing and
expanding. This paper outlined a proposed planning process
that RTOs might adopt in a restructured electricity industry.
However, most of the details for this process are not yet
developed. Similarly, FERC’s requirement in Order 2000 that
“the RTO must have ultimate responsibility for both trans-
mission planning and expansion within its region” is largely
undefined. These gaps lead to several recommendations for
the U.S. Department of Energy (DOE), FERC, and RTOs to
consider:
Conclusions
Maintaining a healthy transmission system is vital for
both reliability and commerce. Because electricity is essential
to our modern society, public policy should ensure suitable
expansion of the nation’s transmission grids. Unfortunately,
the historical record shows a clear and long-term decline in
U.S. transmission adequacy (Hirst and Kirby 2001). Specifi-
cally, the amounts of new transmission added during the
past two decades have consistently lagged growth in peak
demand. To make matters worse, projections for the next five
and ten years show continued declines in adequacy, al-
though some of the projected need for new transmission
may be met by the construction of generating units close to
load centers.
To further compound the problem, transmission plan-
ning is not keeping pace with the need for such planning.
Because transmission owners and ISOs are receiving so
many requests for generator interconnections, they are un-
able to devote the staff resources needed to develop proac-
tive transmission plans. That is, they are focused primarily
on preparing the system-impact and facility studies required
for these new interconnections. Thus, some transmission
plans are little more than compilations of individual genera-
tor-interconnection studies.
Because transmission planners have insufficient time
and resources, little information is being provided
proactively to energy markets on the costs and locations of
congestion. Such information could help potential investors
in new generation decide where to locate new units. Such
information could also help loadserving entities decide what
152 Transmission Line Reliability and Security
Acknowledgments
We thank John Adams, Kenneth Donohoo, Philip Fe-
dora, Trudy Harper, Michael Henderson, Steven Herling,
Douglas Larson, George Loehr, Paul McCoy, Mark MacLeod,
Stephen Metague, David Meyer, Wayman Robinett, Jose
Rotger, Richard Sedano, Alison Silverstein, Brian Silverstein,
Dorothea Stockstill, Perry Stowe, and James Whitehead for
their very helpful comments on a draft of this paper.
References
American Electric Power Service Corp. et al. 2000. Alliance Companies
Compliance Filing, Docket Nos. ER99-3144-003 et al., submitted to
the Federal Energy Regulatory Commission, Columbus, OH, Sep-
tember 15.
American Transmission Company. 2001. Initial Ten Year Transmission Sys-
tem Assessment, Waukesha, WI, June 1.
Avista Corp. et al. 2000. Supplemental Compliance Filing and Request for
Declaratory Order Pursuant to Order 2000, Docket No. RT01-35-000,
submitted to the Federal Energy Regulatory Commission, Spokane,
WA, October 16.
Bonneville Power Administration. 2001. “Transmission Integration Re-
quests Pour In,” Journal, DOE/BP- 3365, Portland, OR, March.
Detmers, J., A. Perez, and S. Greenleaf. 2001. “Valley-Rainbow Transmis-
sion Project,” Memorandum to California Independent System
Operator Board of Governors, Folsom, CA, page 3, March 23.
Emerson, A. and J.D. Smith. 2001. Revised Biennial Transmission Assess-
ment 2000–2009, Arizona Corporation Commission, Phoenix, AZ,
July.
Appendices 155
David H. Meyer
Consultant, Electricity Policy and Regulation
Alexandria, Virginia
Richard Sedano
Regulatory Assistance Project
Montpelier, Vermont
Introduction
Assessment of Current Siting Regime
Description of the Transmission Siting Process
Due Process in Transmission Siting.
Key Difficulties in the Current Transmission Siting Process
Two Instructive Transmission Siting Cases
Successes in Siting Transmission
Critical Elements of Success and Characteristics that Lead to
Conflict
Business Uncertainties and the Current Siting Process
The Regional Perspective
Some Generic Considerations Regarding the Regional Approach
Alternative Designs for Regional Siting Institutions
Defining “Regional Transmission Facilities”
Objective Criteria
Functional Tests
Economic Test
Improving the Existing State-Based Siting Process
Accountability
Improvements to Siting Processes
Improving Agency and Industry Practices
Effective Presentation of Alternatives
Advantages of Open Planning
Deterministic and Probabilistic Planning
157
158 Transmission Line Reliability and Security
INTRODUCTION
In order to construct new transmission facilities or to
significantly upgrade existing facilities in the U.S. electricity
system, developers typically need approval from several
state and federal agencies. This process has, in recent years,
become protracted and difficult. The difficulty is hardly sur-
prising given that transmission facilities are highly visible
structures that may span long distances and must somehow
fit into physical surroundings that are already in use for
other purposes. Incorporating these facilities into the land-
scape and taking fair account of the wide range of legitimate
interests affected by them is challenging.
Nevertheless, many observers and participants in the
electricity sector now regard transmission siting and permit-
ting procedures as a major reason why the development of
new transmission facilities is not keeping up with the need.
Critics say that the siting and permitting process has become
unnecessarily cumbersome, delay prone, and subject to
breakdown. Some observers argue that current state-based
regime for managing siting and permitting is not well
adapted to the review of proposed large-scale multistate
transmission projects that are or may soon be needed to
Appendices 159
1
With the exception of the federal power marketing administrations and the
Tennessee Valley Authority, which have their own siting authorities.
162 Transmission Line Reliability and Security
5
There is no practice or mechanism for determining regional or interstate need.
The Electric Reliability Council of Texas (ERCOT) performs this function in a way
that some expect will become typical for Regional Transmission Organizations
(RTOs)—providing unbiased and competent information to clarify and focus the
work of individual utilities on addressing validated needs.
6
Demonstrating this particular need requires competence in either deterministic
or probabilistic transmission planning models as explained briefly in Section 6.
Using just one approach leaves the applicant vulnerable to challenge.
7
For some states, serving regional commerce is a vital purpose of the grid. For
others, it is secondary to maintaining reliability.
Appendices 165
———————————————————————————
Substitutability of
Transmission and Nontransmission Resources
8
One commenter at the public workshops organized for the National Transmis-
sion Grid Study (NTGS) by the U.S. Department of Energy suggested that inad-
equate attention is being given to transmission needs associated with bringing
some new generation on line. If this is true, a need buildup may be accumulating
that could result in belated justification for new power lines in some areas.
9
Texas requires submittal of alternative route options as well as analysis of the
usefulness of demand-side management and distributed generation in lieu of
new lines.
166 Transmission Line Reliability and Security
10
In September 1995, the Florida Public Service Commission (PSC) voted to allow
Florida Power to recover $23 million in costs spent on a proposed 500-kV line
that was never built. The line was approved by the PSC in 1984 for reliability.
However, continued local opposition led to protracted and costly litigation.
Florida Power eventually developed an alternative plan involving more intensive
monitoring of the status of key transmission lines in the area, interruption of
service to a limited number of customers in emergency situations if necessary,
and reactivation of a 115-kV line that had earlier been retired from service. (Elec-
tric Utility Week, 1995.)
Appendices 167
11
This concern is spoofed in The Hitchhiker’s Guide to the Galaxy, by Douglas
Adams, in which notice to demolish the Earth was posted at Alpha Centauri.
168 Transmission Line Reliability and Security
12
Some of the most tenacious non-government intervenors have wealthy benefac-
tors or pro bono advocates. In rare cases, states provide funding, usually as-
sessed from the applicant, for intervenors.
Appendices 169
13
There are many examples. In Illinois, a transmission project was approved only
after the utility produced information requested by the commission staff; the staff
had recommended that the project be denied because the information offered at
the outset was inadequate. Illinois Commerce Commission Docket 92-0121 (P.R.
Buxton, Personal communication).
Appendices 171
ods are used for different options. For example, if the siting
authority is not the regulatory commission, the authority
may not have sufficient experience in demand-side measures
to determine whether they may be superior to a power line
as a means of meeting a system need. Introducing competi-
tion to the wholesale generation market has added another
dimension of difficulty. Investments in generation, transmis-
sion, and demand-side measures come in regulated and
competitive forms and pass through different channels for
approval, so there is no single standard for comparing them,
and there may be no formal opportunity for a side-by-side
evaluation.
Success indicators
• Link to a generation project—A transmission project
that interconnects a needed generation project to the
grid is less likely than other types of projects to encoun-
ter heavy opposition. The transmission component may
be seen as incidental to the generation project.
14
New tools for managing the grid may enable operators to maintain reliability
standards while reserving less transmission capacity for contingency flows. This
will relieve constraints in some areas at some times.
Appendices 181
———————————————————————————
A Case of a Failure to Communicate
The siting proceedings described below for a generation and trans-
mission project that had regional impact demonstrate how communica-
tion can go wrong among two states and a federal regulator, and how
ignoring a project’s regional dimensions in the early stages can cause
difficulties later.
In 1989, FERC granted the city of Jackson, Ohio, a license to con-
struct a hydro generation project on the Ohio River. AMP-Ohio, a whole-
sale power provider to 77 Ohio municipal utilities, joined the project as
a co-developer and helped finance the project. A decision was made to
site the project at Belleville, West Virginia, to take advantage of a West
Virginia law that exempted municipal hydro projects from state tax.
However, because the economic benefits of the Jackson project would go
mostly to retail consumers served by AMP-Ohio’s utility customers, con-
troversy arose in West Virginia where it appeared that citizens would
suffer environmental impacts but few economic benefits. Accordingly,
the West Virginia Senate passed a bill in 1994 removing the tax exemp-
tion for the project and threatening its economic viability. Although the
governor of West Virginia vetoed the bill, saying that it was unfair to
treat out-of-state municipalities differently from those of West Virginia,
an agreement was reached before the veto that the project sponsors
would make payments to West Virginia in lieu of taxes and that the
transmission line linking the hydro plant to the grid would be located
entirely wholly in Ohio even though that would approximately double
its length.
In 1996, Ohio regulators approved the transmission line, but Ohio
Public Utilities Commission (PUC) chair Craig Glazer filed a “concurring
opinion” strongly criticizing the review process and its outcome. Glazer
complained that Ohio was not consulted “in a meaningful way” when
AMP-Ohio negotiated its deal with the governor of West Virginia: “It is
indeed disingenuous for AMP-Ohio to reach an agreement with the West
Appendices 185
Virginia governor to site the line in Ohio and only then come to Ohio and
argue that any routes in West Virginia are not feasible and should not be
looked at in the siting process” (Electric Utility Week, 1996). Glazer ar-
gued that analyses showed “far more environmentally benign and cost-
effective routes through West Virginia for this line.” He criticized FERC,
which had approved the proposed hydro facility, saying that Ohio staff
had attempted to establish a joint siting and information sharing process
that “fell on deaf ears at the FERC staff level.” He continued, “Given
FERC’s utter lack of interest in such a cooperative effort, [Ohio’s] staff
did not pursue more formal requests” for cooperation. He added, “This
is a case study on how applicants, neighboring states, and an intervening
federal agency should not act” (ibid.).
Although there was a good faith effort to resolve the benefit alloca-
tion issue between Ohio and West Virginia in this case, the transmission
line was not considered at that time by AMP-Ohio, so the company was
vulnerable later to the assertion that it had struck an unscrupulous bar-
gain with the governor of West Virginia. PUC Chairperson Glazer noted
that some of these difficulties might have been foreseen at the time of the
original hydro licensing decision and could have been resolved in ad-
vance. Perhaps due in part to this case, Ohio recently adopted a stream-
lined, time-limited siting process that explicitly provides for cooperation
with other states and agencies on siting matters.
———————————————————————————
15
See, for example, comments presented by a Southern Company representative
at DOE’s workshop in Atlanta, September 26, 2001.
16
A further difficulty is that it takes time, once a need is identified, to combine the
many possible resources into a sound mitigating strategy.
Appendices 189
17
These are the 38-mile line from Chisago, Minnesota, to Apple River, Wisconsin,
and the roughly 230-mile line from Duluth, Minnesota, to Wausau, Wisconsin.
The latter has been approved by the state siting authorities, but is the subject of
an appeal in Minnesota. The former was withdrawn and is being redesigned
based on the results of a mediation process.
Appendices 191
———————————————————————————
Regional Transmission Planning and
Development of Cooperative Regional Institutions
Due to the geography of the western U.S., with its comparatively
long distances between cities and some of the natural resources used
in generating electricity, the western states have gained extensive expe-
rience with planning and siting interstate transmission projects. Re-
cently they have begun to develop an institutional framework under
the auspices of the Western Governors’ Association to aid them in
dealing with shared issues related to such projects. Much of this work
is being done through a body named the Committee for Regional Elec-
tric Power Cooperation (CREPC). CREPC was created in 1984 jointly
18
One possible condition would be the case of a regional transmission project
proposed in a state that declines to consider regional costs and benefits.
19
There are also proposals that would allow applicants to invoke federal backstop
authority if a regional entity did not exist and if a state siting agency was not able
to make a timely decision about a proposed transmission project.
192 Transmission Line Reliability and Security
by the Western Interstate Energy Board, which acts as the energy arm
of the Western Governors’ Association, and the Western Conference of
Public Service Commissions. CREPC has representation from the regu-
latory commissions, energy agencies, and facility siting agencies in the
11 states and two Canadian provinces in the Western Interconnection.
Through CREPC, the western states have begun negotiations to de-
velop a common interstate transmission siting protocol, and are aiming
at June 2002 as a target date for a publishable draft.
One of the roadblocks to the formation of comparable institutions
in the Eastern Interconnection is the lack of a clear and urgent agenda.
That is, without either well-developed regional transmission plans or a
collection of actual regional-scale transmission proposals, it is not obvi-
ous which states and federal land management agencies need to be talk-
ing with each other about what issues. Rather than wait for RTOs to be
established and for transmission plans to be developed by them under
FERC’s direction, an interim approach could be considered. DOE and the
FERC could jointly identify key transmission bottlenecks, and FERC
could task administrative law judges to work with appropriate parties in
each bottleneck area to prepare interim transmission plans. By putting
the emphasis on the power of persuasion, such a process would be non-
threatening, which would help to elicit constructive responses from
stakeholders. The resulting plans would probably flag some important
issues affecting groups of states, and thus help to spur the formation of
cooperative regional institutions.
———————————————————————————
———————————————————————————
Why Not Just Centralize Transmission Siting Under FERC?
There are obvious challenges in coordinating and harmonizing the
views of affected states, local governments, tribal bodies, and federal
agencies about proposed transmission facilities. Many observers and
industry participants have asked whether it would not be better to enact
federal legislation making FERC responsible for transmission siting de-
cisions—particularly because FERC already exercises this function with
respect to the siting of natural gas pipelines. Here are some important
considerations:
20
Note that in the case of AEP’s controversial Wyoming-Cloverdale proposal, the
West Virginia Public Service Commission (which must rule upon an application
within 400 days or else it is automatically approved) at one point rejected AEP’s
application as incomplete and advised AEP not to resubmit its proposal until
after the Forest Service had completed its draft environmental impact statement.
Resubmitting the proposal would restart the 400-day clock, and the PSC appar-
ently wanted the clock to start after the Forest Service had issued its impact state-
ment.
194 Transmission Line Reliability and Security
never be easy. Doing this job well will always require an immense
amount of information from local, state, and regional sources, as
well as consultation and negotiation with and among many of these
parties. Transferring transmission siting responsibility to a single
federal agency could mean over-centralization, resulting in delays,
hasty, or poor decisions, or all three.
3. The existing process for siting natural gas pipelines is not necessar-
ily a model to be emulated. Critics emphasize that some pipeline
siting cases have also dragged on for years, and assert that the
process is not sufficiently predictable. They also complain that most
events in the process take place in Washington, D.C., and argue that
this imposes a substantial burden on many participants, and effec-
tively precludes participation by others.
NEPA reviews
If a regional body with siting authority included some
representatives of federal agencies, this raises the question of
what level of federal involvement would trigger the require-
ment for an environmental assessment or environmental
impact statement under the National Environmental Policy
Act (NEPA). If a decision by the regional body would sup-
plant the need for an independent review of the project by
one or more federal agencies, it seems likely that the regional
body would have to conduct an environmental assessment.
Depending on the results of the assessment, an impact state-
ment might be required. In general, major new transmission
projects usually have significant environmental impacts; in
such cases, if federal decisions are required, full environmen-
tal impact statements must be prepared.
Cooperative agreements
A cooperative agreement would establish a regional
entity for the mutual convenience of participating states,
tribes, or federal agencies; the participating agencies would
not cede any existing authority or responsibility to the re-
gional institution. The regional institution’s functions would
be limited to activities such as fostering common siting pro-
cesses and requirements and improving coordination among
members to streamline review of regionally significant trans-
mission facilities. Members would probably find it useful to
agree on a category of facilities that would fall under the
198 Transmission Line Reliability and Security
Interstate compacts
An interstate compact is an agreement among or be-
tween states to establish an institution that has the power to
act for all of them in a specific area. Establishing an interstate
compact is a complex process, especially if more than a few
states are involved. The legislature of each participating state
and the U.S. Congress must approve the compact’s founding
agreement.
For a compact on transmission siting, many states might
have to enact legislation to authorize their public utility com-
missions (PUCs) to cede specific authority to the regional
body or to share authority or provide guidance to the com-
mission concerning the circumstances under which it should
defer to the regional body. The founding agreement would
have to define the class of transmission facilities that would
be subject to the commission’s jurisdiction and establish how
the commission would be staffed and funded.
Agreements for compacts typically specify that the gov-
ernors of the participating states will appoint the compact’s
commissioners. Voting representation on a compact commis-
sion tends to be controversial because of differences in the
sizes of states and how to set each state’s share (e.g., based
on population or contribution to gross domestic product) as
well as the likelihood that some states would probably be
more affected by the commission’s activities than others.
Smaller states tend to prefer one-state, one-vote structures so
as not to be overruled by larger states.
Appendices 199
25
The full text of Section 209(a) reads:
[FERC] may refer any matter arising in the administration of this Part to a
board to be composed of a member or members, as determined by the
Commission, from the State or each of the States affected or to be affected by
such matter. Any such board shall be vested with the same power and be
subject to the same duties and liabilities as in the case of a member of the
Commission when designated by the Commission to hold any hearings. The
action of such board shall have such force and effect and its proceedings
shall be conducted in such manner as the Commission shall by regulations
prescribe. The board shall be appointed by the Commission from persons
nominated by the State commission of each state affected, or by the Gover-
nor of such State if there is no State commission. Each State affected shall be
entitled to the same number of representatives on the board unless the nomi-
nating power of such state waives such right. The Commission shall have
discretion to reject the nominee from any State, but shall thereupon invite a
new nomination from that state. The members of a board shall receive such
allowances for expenses as the Commission shall provide. The Commission
may, when in its discretion sufficient reason exists therefore, revoke any
reference to such a board.
202 Transmission Line Reliability and Security
Objective Criteria
One way to define the transmission facilities that would
fall under the jurisdiction of a regional siting body is to use
objective indices, such line voltage or length or whether the
line would cross state boundaries. Although these criteria
may sound reasonable, they may not always yield the ex-
pected results. For example, in some sparsely populated ar-
eas, lines that serve transmission functions may be
comparatively low voltage; conversely, in some densely
populated areas, distribution lines may be designed for eco-
nomic reasons to operate at high voltages. Another example
is that a facility may be used in part for transmission and in
Appendices 203
Functional Tests
An alternative for defining the jurisdiction of a regional
body is to apply functional tests that gauge whether a facil-
ity would be used primarily or wholly for transmission and
define the degree of its expected contribution to the reliabil-
ity of the regional grid. A significant objection to this ap-
proach is its lack of transparency—applying it could require
hearing and evaluating evidence before a decision could be
made about whether a proposed facility is regionally signifi-
cant.
Economic Test
An economic test could be devised to estimate the prob-
able economic benefits that a line would provide for con-
sumers over a given period through either improved access
to lower-cost generation or mitigation of potential market
power. This estimate could be compared to an agreed-upon
threshold for determining regionally significant projects.
This approach might also require gathering and evaluating
evidence.
In short, there are no easy, straightforward criteria.
However, determining the criteria would be more impor-
tant in some institutional contexts than others. For ex-
24
Many states currently use objective criteria (such as voltage and line length) to
determine whether transmission distribution projects need state approval.
Projects that do not meet the defined threshold in these states still have to meet
local zoning, safety, and other requirements, but they do not have to go through
the full state siting review process.
204 Transmission Line Reliability and Security
25
A recent proposal (not yet filed at a siting authority) would build approximately
2,000 miles of transmission lines to connect new coal generation in Wyoming
with load centers in Chicago and Los Angeles.
206 Transmission Line Reliability and Security
Accountability
Any system of regulation must have and retain public
confidence. Generally, regulators earn public confidence by
being fair, competent, and consistent over time. In the
United States, the general practice is to assign responsibility
for regulation to the level of government that can most effec-
tively serve and protect the interests of the citizens affected.
This practice allows local conditions and differences to be
reflected in regulatory decisions, and non-local consider-
ations can be taken into account when appropriate.
26
For example, recent legislation passed in Colorado modified the standing of
local authorities in transmission siting matters. The PUC can now pre-empt
the decision of local authorities if there is a compelling state interest.
27
Ohio has a statute that explicitly authorizes its transmission siting authority
to cooperate with other states, but this process has yet to be tested. The west-
ern states have begun negotiations concerning a common interstate siting pro-
tocol for the west, which could result in something like a regional one-stop
process.
28
There are many examples of state siting orders that make a special effort to
acknowledge the importance of regional concerns. There are also examples
that do the opposite.
208 Transmission Line Reliability and Security
———————————————————————————
Three Views of State-Based Siting
Three organizations with distinctly different perspectives about
U.S. electricity policy are the Western Governors’ Association, the Edison
Electric Institute, and the Electricity Consumers Alliance. Although
many parties have views about how to change the transmission siting
process, the views of these organizations illustrate that there is a broad
range of opinions.
The Western Governors’ Association (WGA) is a policy forum serv-
ing 18 western states, including Alaska and Hawaii. The organization
has a long-standing interest in transmission siting and energy policy. The
WGA position is:
• If a state rejects a project or does not rule within the allotted time,
FERC should be authorized to take the case as it stands and rule
upon it within a specific time period.
• If federal or state reviews are not complete after the allotted time,
FERC should take and rule on the case.
Sources: The Western Governors’ Association published its views in Conceptual Plans for
Electricity Transmission in the West, 2001). The Edison Electric Institute (EEI) is a trade
association for investor-owned electric utilities. EEI’s views were conveyed to the authors
in a personal conversation with Rich Loughery and Henry Bartholomew. The Electric
Consumers Alliance (ECA) represents hundreds of rural, senior, low-income, small-busi-
ness, minority and other consumer organizations. ECA conveyed its views at a DOE public
hearing on September 28, 2001.
———————————————————————————
29
A tightly operated pool is one that controls and dispatches all the generators to
reduce overall costs, and internalizes numerous cost allocation decisions in its
rate structure.
210 Transmission Line Reliability and Security
30
The April 2001 Connecticut Siting Council decision to reject the Cross Sound
Cable project included a warning, presumably directed at successor proposals
regarding the allocation of costs as compared to the expected benefits.
Appendices 211
31
Of course, if there is a superior alternative, the process must accommodate it.
Proponents of transmission projects should do their best to ensure that there are
no superior alternatives and expect the review process to ratify that view.
212 Transmission Line Reliability and Security
32
A complete proposal, based on standards established by statute and rule, is key
to making a time limit work. Until a proposal is complete, the “clock” should not
start.
33
Legislators are sometimes reluctant to “open up” a statute for fear that others
will take the opportunity to press for other changes. This concern must be bal-
anced against the need to update an important process.
Appendices 213
34
Utilizing traditional regulatory tools like Construction Work in Progress ac-
counts or simply booking and deferring costs for future regulatory treatment can
provide utilities with assurance that they will recover the costs of needed trans-
mission investment incurred during a rate cap, including a reasonable return on
investment after the end of the rate cap. However, if the cap is part of a perfor-
mance ratemaking plan, and the utility has accepted the risk that such costs may
be needed during the period of the plan, then asset depreciation would start
normally, and the utility could include the depreciated costs in the consideration
of post-plan rates. In this latter case, utilities would still have incentives to pur-
sue cost-effective transmission investments because efficiency improvements in-
ure, at least in part, to the utility’s profits in performance based ratemaking.
35
This subject requires extensive analysis and lends itself to the “best practices”
project discussed below in “Federal Assistance.”
214 Transmission Line Reliability and Security
36
FERC backstop authority could also be exercised if state siting authorities ad-
dressing a regionally important multistate project disagree on whether the
project should be permitted. This is different from a trigger based on a time
deadline because in this case the states would have executed their responsibili-
ties. FERC could determine whether some compromise or blending of interests
among the affected states would be possible.
Appendices 215
37
This is not usually a concern for transmission that will interconnect a generator
with the grid.
216 Transmission Line Reliability and Security
38
Southwestern Public Service, then a subsidiary of New Century Energies, con-
ducted such an open process in building a transmission line in Kansas. As a
result the Kansas Corporation Commission approved the segment of the project
in its state despite the lack of direct and immediate benefit to Kansas. (Personal
communications with Mark Doljac, Kansas Corporation Commission.)
39
An example is a transmission project in New Mexico that was rejected after
local generation and efficiency alternatives were proposed by the state Attorney
General and other intervenors.
Appendices 217
40
A related topic is that the grid in which investments are made today will not
be the same grid in just a few years. Loads will change, new generation will be
built, and some units may be retired. One merit of a transparent process is that
it helps focus on the investments that are most likely to make sense for a wide
variety of futures.
Appendices 219
sion will be far easier to justify than if the same costs are
assigned only to the group of consumers in the region
whose changes in electricity usage have caused the in-
vestment to be necessary.41
41
A corollary to this idea is drawn from experience with highways. If new road-
ways are built to address congestion without addressing lower-cost ways to re-
duce traffic, and if the source of the demand for the new roadways does not pay
the cost for the new construction, the new road can generate more traffic. That
is, more traffic than expected will use the new roadway because it is available,
and congestion will increase more rapidly than highway planners would have
predicted based on prior patterns. Similarly if a new remedial connection to the
grid is built and the costs are assigned to society rather than to the connection’s
direct beneficiaries, the connection can result in increased demand (either from
inefficient generation siting or even greater volumes of long distance energy
trading) and therefore increased congestion. Some would call this an implicit
subsidy. The result of this scenario is increased congestion, much more rapidly
than would be expected based on prior patterns.
220 Transmission Line Reliability and Security
Encouraging Innovation
One way that the transmission siting process can be
improved is for regulators to reward applicants for bringing
forward innovative ways to address transmission grid
needs. There is evidence of this already, as DC proposals,
undersea projects, and flexible AC transmission system
(FACTS) devices begin to appear on grid expansion plans.
Industry and DOE should continue their attention to the
pace and direction of transmission- related research and
development, and the industry should continue to educate
regulators about the merits of new approaches and devices
that can enhance the grid.
42
This idea can be extended to the retail regime as well. The State of Connecticut
directs system benefit funds to support demand-response programs in desig-
nated transmission- and distribution-constrained areas. (Also, see Moskovitz,
2001.)
Appendices 221
• Selective undergrounding,
43
See description of Cross Sound Connector project in the section “Two Instruc-
tive Transmission Siting Cases,” on page E-8.
44
Utilities express concern that premature identification of a route may result in
increased easement costs. In contrast, rumors of a prospective transmission
project may adversely affect land values and burden landowners with uncer-
tainty. We suggest putting all the facts on the table and relying on the siting
authority (and courts if necessary) to rule expeditiously on the project and its
route and to set fair and reasonable easement costs.
222 Transmission Line Reliability and Security
45
Other possible factors include uncertainties regarding cost recovery in a state or
how costs would be allocated among states and companies for interstate projects.
Local politics may also be a factor.
Appendices 223
———————————————————————————
Solving Existing Aesthetic Problems in
Combination with New Transmission Projects
In some cases, a new transmission project can provide the means to
resolving a community’s existing aesthetic problem. Consider the case of
an aging industrial waterfront area that has the potential to be trans-
formed into a civic and tourist center, but its best views are marred by
an accumulation of high voltage lines left over from its industrial past.
Some communities are working with their utilities on such projects by
finding ways to remove some or all of these lines in conjunction with
upgrading other transmission lines nearby. This somewhat radical ap-
proach—removing still-functional facilities from service for aesthetic rea-
sons—can produce a more efficient transmission system, while
strengthening public support for an otherwise intrusive project.
One example is in Minnesota. As part of the controversial Chisago-
Apple River proposal, a mediation process revealed the existence of an
opportunity to clean up the visual effect of accumulated power lines in
the city of Taylor Falls, MN. Power lines would be removed, and one 161
kV line would cross the river in its place. The concept would also place
the new line underground for some distance near the waterfront. Execu-
tion of this idea is still pending; Xcel and Dairyland Cooperative have
not yet filed the new proposal with siting authorities in Minnesota and
Wisconsin.
Another example is in Vermont, where the Vermont Electric Power
Company and the City of Burlington are working together in advance of
a major VELCO transmission siting proposal to see if lines on the re-
developed waterfront of Vermont’s largest city can be removed as part of
the project. Advance planning ensures that regardless of the decision, all
sides will know that great effort was made by VELCO to find positive
collateral benefits.
———————————————————————————
224 Transmission Line Reliability and Security
———————————————————————————
Distribution of Federal Lands in the United States
Although almost 29 percent of the land area of the United States is fed-
erally owned, the distribution of this land is very uneven. Nearly 38
percent of all federal land is in Alaska where almost 68 percent of the
state is federally owned. Another 54 percent of all federal land is concen-
trated in the 11 states of the contiguous U.S. that are located wholly or
partially west of the Continental Divide. Additional details about these
11 states are presented in the following table:
Total Area
State (Acres, in 000’s) % Federal Land
———————————————————————————
Arizona 72,688 45.6
California 100,207 44.9
Colorado 66,486 36.4
Idaho 52,933 62.5
Montana 93,271 28.0
New Mexico 77,766 34.2
Nevada 70,264 83.1
Oregon 61,599 52.6
Utah 52,697 64.5
Washington 42.694 28.5
Wyoming 62,343 49.9
———————————————————————————
Source: Statistical Abstract of the United States, 2000 (U.S. Dept. of Commerce, December,
2000),Table No. 381 (1997 data).
———————————————————————————
226 Transmission Line Reliability and Security
———————————————————————————
The Alturas 345 kV Intertie Project
This project demonstrates some reasons why potential developers
of transmission facilities regard gaining permits from affected federal
agencies as one of the most difficult and frustrating aspects of transmis-
sion siting.
The Alturas line is 163 miles long and runs between Reno, Nevada,
and Alturas, California. About 20 miles of the line is in Nevada and the
balance is in northern California. The line was needed primarily to sup-
port reliability in the fast-growing area around Reno, and to enable the
applicant, Sierra Pacific, to gain access to low-cost hydro from the Pacific
Northwest for the benefit of retail customers in both Nevada and Cali-
fornia.
The project was proposed to the Nevada Public Service Commis-
sion early in 1993 and the Commission approved it in November 1993.
Sierra Pacific then turned to the other affected agencies: the California
Public Utilities Commission (CPUC), and several federal agencies [the
Bureau of Land Management (BLM), the U.S. Forest Service, the
Bonneville Power Administration (BPA), and the U.S. Fish and Wildlife
Service (FWS)]. BLM became as the lead federal agency for the purposes
of preparing an environmental impact statement because it had the most
affected acreage. The Forest Service had two affected areas, three line
miles in the Modoc National Forest in California, and eight line miles in
the Humboldt-Toiyabe National Forest in Nevada. The California Public
Utilities Commission became the lead agency for state environmental
purposes.
In the spring of 1994 BLM and CPUC jointly hired a consulting firm
to prepare an environmental impact report (EIR) for the state and an
environmental impact statement (EIS) for the federal agencies. The appli-
cant paid the cost of this work. The draft statements were issued for
comment in March 1995. In the fall of 1995, the applicant believed that
the comments received could be satisfactorily addressed through several
kinds of mitigating measures. BLM issued the final EIS in November
1995, and approved its portion of the project in February 1996. The
CPUC approved its portion of the line in January of 1996. However, in
February 1996 the manager of the Humboldt-Toiyabe National Forest
issued a “no action” decision, and argued that the EIS had been flawed
because it had not addressed a sufficiently wide range of alternatives,
including the alternative of skirting the Humboldt-Toiyabe National
Appendices 227
Forest entirely.
The applicant appealed this decision, first to the regional forest
manager and then to the deputy chief of the Forest Service. The appeal
process took several months, and the results of the appeal were inconclu-
sive. In June 1996 the deputy chief ordered the “no action” decision
withdrawn, but he also directed the Humboldt-Toiyabe manager to ob-
tain whatever information was needed to make a new decision. This led
to several months of dialogue between the applicant and the Humboldt-
Toiyabe manager, and the filing by the applicant of several hundred
pages of additional information. The manager of the Modoc National
Forest, who had not issued a final decision on the portion of the route
that would cross the Modoc area, joined this dialogue.
However, the applicant found that the continuing uncertainty over
the acceptability of the Humboldt-Toiyabe route segment was making it
difficult to gain required permits from local governments in Nevada that
would be needed for the construction phase of the project. These prob-
lems led the applicant to examine the option of an alternative route on
private land around the Humboldt-Toiyabe National Forest, even though
this had several disadvantages. It would put the line into more devel-
oped areas, and make it more visible to local residents. This alternative
route was about the same length as the initial route, but it was more
costly because it would need more expensive towers in several locations,
the right of way was more expensive, and additional legal costs would
be involved. At length Sierra Pacific decided to pursue the private-land
route and withdrew its application to cross the Humboldt-Toiyabe area
in February 1997. Due to these route changes, the applicant had to go
through some local-level processes a second time in Nevada.
In April 1997, the manager of the Modoc National Forest issued a
decision on the EIS, also denying the applicant’s request for a permit.
Sierra Pacific appealed this decision to the chief of the Forest Service in
May 1997, and this led eventually to the issuance of a permit in October
1997. However, several other parties to the proceeding appealed this
latter action. After review, the decision to issue the permit was upheld in
January 1998.
Construction of the project was begun in February 1998 and com-
pleted in December 1998. The applicant estimates that the difficulties
with the Forest Service delayed the project by at least two years and led
to additional costs of well over $20 million.
———————————————————————————
228 Transmission Line Reliability and Security
46
See comments to the DOE by the Electricity Consumers Alliance, discussed in
the section “Improving the Existing State-Based Siting Process” on page E-45.
Appendices 229
47
See the section “Description of the Transmission Siting Process,” on page E-3,
for details on a transmission project that Florida Power abandoned after more
than a decade of effort and expenditures of $23 million.
230 Transmission Line Reliability and Security
• Open planning;
48
An N-1 Contingency refers to the practice of assuring that the transmission
system can withstand the change in power flows resulting from the sudden loss
of any element on the system.
49
FACTS devices are sophisticated solid-state electronic switches that allow op-
erators to control flow on certain power lines. HVDC lines do not operate syn-
chronously with the AC grid but can move large amounts of power over great
distances with almost no losses. HTS can also move large amounts of power with
almost no losses; this technology is under development. See Issue Paper Ad-
vanced Transmission Technologies by J. Hauer, T. Overbye, J. Dagle, and S.
Widergren.
Appendices 231
• Treatment of alternatives;
50
Participation by organizations such as the National Governors’ Association, the
Western Governors’ Association, and the National Association of Regulatory
Utility Commissioners would be important to the success of such a project.
51See previous footnote.
232 Transmission Line Reliability and Security
52Organizations such as the Edison Electric Institute, the American Public Power
Association, the National Rural Electric Cooperative Association, and the Electric
Power Supply Association could provide valuable assistance in the design and
implementation of such a project.
53This is true everywhere in the contiguous United States except Texas.
54See the Issue Paper Alternative Business0 Models for Transmission Investment
55With the exception of the federal power marketing administrations and the
Tennessee Valley Authority, which have their own siting authorities.
Appendices 235
56Examples include AEP’s 765-kV line in Virginia and West Virginia, and the
Cross Sound Connector project between Long Island, New York, and Connecti-
cut, both of which are described above in the section “Assessment of Current
Siting Regime.”
Appendices 239
57The Western Interstate Energy Board, which is the energy arm of the Western
Governors’ Association, and the Western Conference of Public Service Commis-
sions acted jointly in 1984 to create the Committee on Regional Electric Power
Cooperation (CREPC). CREPC has representation from the regulatory commis-
sions, energy agencies, and facility-siting agencies in the 11 states and two Cana-
dian provinces in the Western Interconnection. Through CREPC, the western
states have begun negotiations to establish a common interstate transmission-
siting protocol.
240 Transmission Line Reliability and Security
Regional options
All of the state-level options listed above have regional
significance; that is, if they were considered and applied by
all states in a given region, the result would probably be
greater regional consistency and efficacy in siting policies
and practices. The options below focus on development of
regional institutions that could, among other objectives, pro-
mote such consistency and efficacy. States, federal land man-
agement agencies, and Native American tribes should
consider the following options:
Federal options
Most of the options listed above could be aided through
specific federal actions, including:
(d) Direct that FERC shall be the lead agency for coordi-
nating all reviews of proposed transmission facilities
by federal agencies, that other affected federal agen-
cies shall participate as cooperating agencies, and
that the cooperating agencies will retain their exist-
ing authorities with respect to the issuance of per-
mits for lines crossing lands under their jurisdiction.
ACKNOWLEDGMENTS
References
Alvarado, F. and S. Oren. 2002. Transmission System Operations and Inter-
connection. National Transmission Grid Study, U.S. Department of
Energy.
Bailey, M. and C. Eaton. 2001. “Moving Toward Seamless Energy Mar-
kets: Evidence from the Northeast.” Electricity Journal, v. 14, #6, July.
Buxton, P.R. Engineering Department. Illinois Commerce Commission.
personal communication regarding Illinois Commerce Commission
Docket 92-0121.
Costello, K.W. 2001. “Interregional Coordination versus RTO Mergers: A
Cost-Benefit Perspective.” Electricity Journal, v. 14, #2, March.
Doljac, M. August 14, 2001. personal communication. Kansas Corpora-
tion Commission.
Electric Utility Week (McGraw-Hill). Oct. 2, 1995, p. 15.
Electric Utility Week (McGraw-Hill). April 1, 1996, p. 14.
Electric Utility Week (McGraw-Hill). September 17, 2001, p. 17.
Fox-Penner, P. 2001. “Easing Gridlock on the Grid: Electricity Planning
Appendices 247
Advanced Transmission
Technologies
(National Transmission Grid Study)
John Hauer
Pacific Northwest National Laboratory
Richland, Washington
Tom Overbye
University of Illinois at Urbana-Champaign
Urbana, Illinois
Jeff Dagle
Pacific Northwest National Laboratory
Steve Widergren
Pacific Northwest National Laboratory
Introduction
Background
Power System Components and Reciprocal Impacts
Transfer Capacity
Complexity of the National Transmission Grid
Technologies to Increase Transfer Capacity
Institutional Issues that Affect Technology Deployment
New Demands on the Transmission Grid
Information Gaps in Grid Management
Challenges and Opportunities in Network Control
The Evolving Infrastructure for Transmission Management
Performance Challenges to a New Generation
of Transmission Technology
Technology Challenge #1: Broader Coordination of
Grid Management
Technology Challenge #2: Knowing the Limits of Safe Operation
Technology Challenge #3: Extending the Controllability of
Network Flow
248
Appendices 249
INTRODUCTION
BACKGROUND
Transfer Capacity
A natural question to ask is: what is the transfer capacity
of the transmission system described in Figure 1? That is,
how much power can be transferred from bus 1 to bus 2?
The answer is far from straightforward. At first glance, the
transfer capacity appears to be 420 MW because this amount
of power causes the first line to reach its limit. However, this
answer is based on the assumption that all lines are in ser-
vice. As defined by the North American Electric Reliability
Council (NERC), transfer capacity includes consideration of
reliability. A typical reliability criterion is that a system be
able to withstand the unexpected outage of any single sys-
tem element; this is known as the first contingency total
• what the role will be of the RTO and other grid manage-
ment entities in the overall R&D infrastructure serving
power transmission needs.
ing WAMS effort (DOE 1999). Much R&D for data coordina-
tion would draw upon and directly reinforce the evolving
Reliability Information Network by which Regional Security
Coordinators share grid information in near real time.
ogy.
Devices that improve flow control can be used individu-
ally or in combination to directly regulate power routing on
the grid and to relieve dynamic problems that may limit grid
utilization. Control of this sort is a very attractive alternative
to the construction of new or stronger lines. This is not the
whole story, however, because power system controls are
subject to errors in the control law on which they are based
or the models from which the control law is developed. (This
is in contrast to the functional reliability of a new transmis-
sion line or power plant, which is almost synonymous with
its hardware reliability.) Because of this vulnerability, the
overall reliability of large-scale control systems cannot be
assessed or assured by the straightforward and proven
methods that are used in construction-based reinforcements
to the grid. How, then, should the choice be made between
controls and construction of new transmission capacity?
A full demonstration of controller reliability is rarely
possible. It is always necessary to trade controller benefits
against the risks associated with closing a high-power con-
trol loop around system dynamics that are not fully ob-
served and not fully understood. Controller reliability must
be assessed broadly, incorporating engineering judgment
and sound practice. Uncertainty should be mitigated where
possible, but this is often a slow and technically difficult
process (Hauer & Hunt 1996). Whatever uncertainty cannot
be mitigated should be accommodated in controller design
and operation. All of these measures require that wide-area
control systems be supported by wide-area information sys-
tems, and that the grid management infrastructure include
an appropriate degree of technical expertise in control engi-
neering (Hauer & Taylor 1998).
Wide-area control, whether using FACTS or less ad-
vanced technologies, offers many benefits to the next-gen-
284 Transmission Line Reliability and Security
of the electrical and gas energy systems, with the gas system
providing virtual storage for electrical energy. The IES
would certainly draw upon FACTS technology for the rout-
ing of electrical power and upon dispersed assets such as
distributed generation, energy conservation, direct or indi-
rect load control, and renewable energy sources. WAMS is a
critical element in the information infrastructure needed to
make the IES possible and to insure power system reliability.
The vision of an IES extends beyond FACTS and per-
haps beyond WAMS. Additional elements include protective
relay systems that “adapt” to widely variable power flows,
diagnostic tools to reduce human error during system main-
tenance, enhanced information tools for emergency manage-
ment, and “intelligent” data miners that sift operating
records for evidence of needed maintenance. Some specific
examples, extracted from much more detailed treatments in
PNNL (1999), are presented below.
Institutional Issues
A formidable number of institutional issues hinder
timely identification, development, and introduction of new
technologies. Today’s utilities are understandably reluctant
to fund R&D that is not promptly and directly beneficial to
Appendices 301
ADVANCED TECHNOLOGY
RELATED RECOMMENDATIONS
References
De Steese, J.G. and J.E. Dagle. 1997. “Electric utility system applications
of fast-acting energy storage as illustrated by SMES.” Int. J. of Global
Energy Issues, Vol. 9, No. 3: 113-127.
EPRI. 1996. Assessment of Information Assurance for the Utility Industry.
Report PNWD-2393, prepared by Battelle Northwest for the Electric
Power Research Institute under Research Project 8024-01, Dec. 1996.
EPRI. 1997. Powering Progress—The Electricity Technology Roadmap Initia-
tive. EPRI Technical Report, May.
EPRI. 2001. The Western States Power Crisis: Imperatives and Opportunities.
June 25. http://www.epri.com/journal/details.asp?doctype=news
&id=161
Fleishman, B.J., 1997. Emerging Liability Issues for the New Electric Power
Industry. 1997 IBC Conference on Ensuring Electric Power Reliabil-
ity in the Competitive Marketplace, San Francisco, CA, September
29-30.
Hauer, J.F. and J.R. Hunt, in association with the WSCC System Oscilla-
tions Work Groups. 1996. Extending the Realism of Planning Models
for the Western North America Power System. V Symposium of Spe-
cialists in Electric Operational and Expansion Planning (SEPOPE),
Recife (PE) Brazil, May 19-24.
Hauer, J.F. and C.W. Taylor. 1998. “Information, Reliability, and Control
in the New Power System.” Proceedings of the 1998 American Control
Conference, Philadelphia, PA., June 24-26.
Lionberger, J. and L. Duke. 2001. “3D Modeling Boosts Transmission
Capacity,” Electric Light & Power, July.
North American Electric Reliability Council. 2001. Working Group Forum
on Critical Infrastructure Protection—An Approach to Action for the
Electricity Sector, April 5. Available at http://www.nerc.com/
~filez/cipfiles.html
Oak Ridge National Laboratory. 1991. Maintaining Electric Power System
Performance: Preparing for the Year 2020, Research Needs. Oak Ridge
National Laboratory Report ORNL-6678, August.
Oak Ridge National Laboratory. 1991. DOE Workshop on Real-Time Control
and Operation of Electric Power Systems. Proceedings of a Department
of Energy Conference at Denver, CO. CONF-9111173. Nov. 19-21.
PA Consulting Group. 2001. The Future of Electric Transmission in the
United States, January.
308 Transmission Line Reliability and Security
Conductors
Advances in conductor technology fall into the areas of
composite materials, and high-temperature superconduc-
tors.
Modular Equipment
One way to gain flexibility for changing market and
operational situations is to develop standards for the manu-
facture and integration of modular equipment.
Objective: Develop substation designs and specifications for
equipment manufacturers to meet that facilitate the
movement and reconfiguration of equipment in a sub-
station to meet changing needs.
Appendices 315
Energy-Storage Devices
The traditional function of an energy-storage device is
to save production costs by holding cheaply generated off-
peak energy that can be dispatched during peak-consump-
tion periods. By virtue of its attributes, energy storage can
also provide effective power system control with modest
incremental investment. Different dispatch modes can be
superimposed on the daily cycle of energy storage, with
320 Transmission Line Reliability and Security
Controllable Load
Fast-acting load control is an important element in ac-
tive measures for enhancing the transmission grid. Auto-
matic load shedding (under-frequency, under-voltage),
operator-initiated interruptible load, demand-side manage-
ment programs, voltage reduction, and other load-curtail-
ment strategies have long been an integral part of coping
with unforeseen contingencies as a last resort, and/or as a
means of assisting the system during high stress, overloaded
conditions. Future advances in load-control technology will
leverage the advent of real-time pricing, enabling consumers
to “back off ” their loads (either automatically through grid-
friendly appliances or through manual intervention) when
the price is right.
Generation
Devices that are designed to improve the efficiency or
interface of generation resources can be used for power sys-
tem control. Advanced converter concepts will play an in-
creasing role, providing power conversion between DC and
AC power, for resources such as wind, solar, and any non-
synchronous generation. Converter concepts such as pulse
width modulation and step-wave inverters would be par-
ticularly useful for incorporating DC sources into the grid or
providing an asynchronous generation interface. Asynchro-
nous generation has been proposed for increasing the effi-
ciency of hydroelectric generation, which would also have
the advantage of providing control functions such as the
ability to modify the effective inertia of generators.
Real-time Monitoring
This section discusses the impact of new hardware tech-
nology on the capacity to sense in real time the loading and
limits of individual system devices as well as the overall
state of the system. The capability of the electricity grid is
restricted through a combination of the limits on individual
devices and the composite loadability of the system. Improv-
ing monitoring to determine these limits in real time and to
measure the system state directly can increase grid capabil-
ity.
Power-System Monitors
Objective: Collect essential signals (key power flows, bus
voltages, alarms, etc.) from local monitors available to
site operators, selectively forwarding to the control cen-
ter or to system analysts.
330 Transmission Line Reliability and Security
Index
A C
a-c circuits 49 cables 35
AC transmission system 267 capacitive reactance 9, 13, 47
access roads 20 capacitive reactors 13
active reinforcing equipment 316 capacitors 37
advanced composite conductors capital and operating costs 138
312 cascading 7, 41, 53
air switches 43 circuit breakers 3, 6, 7, 13, 29, 37,
Alliance RTO 121 40, 41, 53, 57
alternating current 47 circuits 1, 3, 6, 8, 37, 39, 40, 41,
(AC) network 105 53, 54, 57
circuits 13 circulating currents 49
alternating magnetic 47 closed loop 6
angle type towers 22 code clearances 26
arrester 17 compact transmission lines 292
automation 3 conductors 13, 19, 22, 25, 26, 27,
33, 34, 47, 310
B congestion 134, 135, 136, 137
backup 1 costs 133
barbed wire 20, 29 controllable load 323
fencing 26, 43 controller reliability 283
strands 25 cooperative agreement 199
batteries 54, 320 copper 35
blackout 7, 41, 53, 54 clad steel 35
bolometers 54 corner type towers 22
Bonneville Power Administration counterpoise 18, 26, 47
116, 117 creeping distance 32
breakers 7, 8, 37 criteria 37, 53
bucket vehicle 25 Cross Sound Connector 174
bulk-power system 125 cryogenic devices 293
buried cables 292
buses 29, 37, 39, 40, 41 D
bushings 29 d-c circuit 47, 49
331
332 Transmission Line Reliability and Security
I MAPP 111
ice 26 mechanical 54
independent regional entity 199 merchant transmission 144, 150
independent system operators mesh 53
(ISOs) 106, 109 metering 37
indirect measurement of trans- Mid-Continent Area Power Pool
former coil temperature 328 (MAPP) 110
inductive 13, 47 modular equipment 314
reactance 9 mutual reactance 10
reactors 12
insulated bucket vehicles 27, 54 N
insulation 47 National Electric Safety Code 20
insulators 17, 22, 24, 29, 32, 34 National Environmental Policy
intelligent building systems 324 Act (NEPA) 197
intelligent energy system (IES) National Grid USA 113
295 national transmission grid (NTG)
interstate compact 198 249, 255
inverters 49 network 53
ISO New England 111, 112 New England Transmission
isolating switches 6, 37 Owners 122
non-transmission alternatives 165
L
leased 8 O
life-cycle analysis 295 oil accessories 35
lighting arrester 15 open loop 6, 53
lightning 26, 43 circuit 8, 40
arresters 15, 26, 33, 54
protection 15, 43 P
live line 54 passive reinforcing equipment 310
load 252 peak supply 1
local generation 1 phase 12
long leaf yellow pine 26 phasor measurement units
loop 6, 7, 8 (PMUs) 330
circuits 37 pilot wire 8
flow 260, 261, 284 plastic(s) 29, 32
systems 3 insulators 29
polymers 29, 59, 62, 66, 68, 73
M porcelain 29, 59
magnetic fields 49 insulators 29, 68
334 Transmission Line Reliability and Security
posts 29 sensing 54
power beaming (wireless power shield wire 15, 17
transmission) 315 shoes 34
power factor 9, 13, 37 shunt reactor 13
power-flow control devices 282 six-phase and 12-phase transmis-
power-system device sensors 326 sion line configuration 314
power-system monitors 329 skin effect 13
price-responsive load 323 solid type insulation 35
pumped hydro and compressed- spans 22, 24, 25, 26
air storage 321 stability 7, 8
state-based siting 208
R process 205
reactance 9, 10, 13 steel 35
reactors 37, 40, 47 steel towers 26
real-time monitoring 326 structures 26
real-time operational system data substation 37, 53
274 super-conducting magnetic
reconductoring 291 energy storage (SMES) 142,
rectifiers 49 321
redundant relaying 8 suspension tower 22, 24, 25
regional transmission organiza- system operator 41
tion (RTO) 98
regional-scale transmission T
planning 236 tangent type towers 22
relaying 6, 8, 37, 53, 57 telephone wire 8
relays 7, 18, 296 Tennessee Valley Authority 117
reliability 1, 3, 39, 40, 41, 54, 121, three-phase circuit 12
130, 131, 140, 141, 146 thyrite 49
right of way 20 tower 26, 35
ring bus 41 tower design tools 313
RTO 99, 123, 138, 146, 149, 150, towers 20, 21, 22, 25, 35
270 transfer capacity 253, 257, 261
RTO West Planning 120 transformers 29, 37, 39, 40, 41
transmission 35, 252
S capacity 98
safety 18, 26, 32, 43, 49 circuit 10
sag 20, 26 grid 183, 260
sectionalizing switches 3 investments 138, 139
security 1, 3, 298, 299 line 1, 8, 10, 13, 19, 20, 25,
Index 335