Management Assignment 1
Management Assignment 1
SCHOOL OF ENGINEERING
ELECTRICAL DEPARTMENT
ENGINEERING MANAGEMENT
MG 531 Assignment 1
Date: 1ST JUNE 2020
Strengths Weaknesses
Opportunities Threats
Elements in the projects external Elements in the external
environment that allow it to environment that could endanger
formulate and implement the integrity and profitability of
strategies to increase profitability the alternative
ii. Decision Matrices – this is a series of values in columns and rows that
allows you to visually compare possible project alternatives and solutions
by weighing their variables based on importance. A decision matrix can be
simple or weighted (importance is assigned to all criteria). This is best
used when situations are assessed from a logical point of view with
enough comparable variables to make a weighted analysis. Consider the
example below which shows how one can use a decision matrix to say buy
a car. Here, each criterion is rated on a scale of 1-10 ranging from bad (1)
to good (10). With the alternative having the higher score at the end
proving to be the best choice. [5]
4. Make a Decision – once all the alternatives have been evaluated, the project
manager should select two or more of the high ranked alternatives and test the
solution against them. The manager should then decide on the solution that has
the best chance at solving the problem at hand.
5. Implement the decision and monitor the results – here the manager puts into
place the preferred solution. However, before this is done, good project managers
make a revision of the project plan, schedule, budget and other resources to
ensure that the solution can be implemented. Thereafter, the outcome of the
implemented solution is tracked and monitored. It may take some time for long
term outcomes to become apparent.
c) A project time management consists of five major processes. Identify and explain in
detail each of these processes.
Project time management has five major processes. These are listed and explained in
detail below.
1) Activity Definition
An activity is an element of work that has a duration, cost and resource management. It is
important that the project team and stakeholders promptly identity the activities they must
perform in order to produce results. [1]
2) Activity Sequencing
To sequence something means to arrange its items or tasks to be performed in a logical
order or pattern, following one thing after another in time. Activity sequencing is thus the
identifying and documenting of relationships between project activities and identifying
which ones need to be performed earlier than others. This process brings to surface what
logical relationship the activities share with each other. [1]
There are two methods of Activity Sequencing. These are,
ii) Arrow Diagramming Method (ADM) – in this method, activities are mapped on
arcs and nodes represent events. Here, arrows are also used to represent activities and
connects them at nodes to show their relationship. It is also known as Activity on
arrows (AOA).
4) Schedule Development
this process involves developing the projects schedule. To do this, activity sequences,
durations and resource requirements all have to be analyzed. Once done, it determines the
planned start and finish dates of the project activities and milestones and also provide
estimates to optimize trade-offs between time, cost and resources. [1]
5) Schedule Control
This process involves controlling and managing changes to project schedules. It involves
monitoring the status of the project to update its progress and manage changes to the
schedule time. [1]
REFERENCES
[1] M. Himooonga, “Project Management,” Eng. Manag. (MG 531) Notes, 2019.
Coppperbelt Univ., pp. 1–13.
[3] R. Siles, “What is the Decision Making Process ?,” no. June, 2018.