100 General Information: 110 Codes and Industry Practices 100-2
100 General Information: 110 Codes and Industry Practices 100-2
100 General Information: 110 Codes and Industry Practices 100-2
Abstract
The Utilities Manual is a guide for the basic design and construction of utility
systems. It focuses on design fundamentals, guidelines for practical installations,
and specification and purchase of materials and services. It is applicable to large
and small facilities whether used for upstream production, downstream refining,
chemical manufacture, offshore production, or marketing. Its guidelines encompass
the experience of the Corporation’s Operating Companies. The manual is useful to
both engineers and operating personnel.
Contents Page
OSHA regulations strongly encourage use of the B31 codes by stating that compli-
ance with B31 codes and specific OSHA rules is prima facie evidence of compli-
ance with the basic requirements of OSHA.
fittings, valves, and other piping items to meet safety and economic considerations.
No attempt has been made to provide for all the in-between or gray areas.
any possible cross-contamination between the utility system and the connected
system. Avoidance should be such that not even apparently abandoned or tempo-
rarily unused process fluid lines are considered for such connections.
The following installation and permit procedures are provided as guidelines. Discus-
sion relates to all considerations; that is, the making, dismantling, or altering of
connections on any utility service line involving either permanent or temporary
connections. See below for further definition of both permanent and temporary
connections.
fittings must meet the highest piping classification required for the actual
upstream and downstream conditions of the connected systems.
• Temporary connections between freshwater or fire water lines and process or
chemical lines or equipment should have a double block valve, double check
valve arrangement with a bleeder hole between the upstream block valve and
check valve. The bleeder hole should have no valve or other shutoff device,
and while in use, should be observed continually to be certain that only water
is flowing out of the bleeder hole.
• The size and routing of the temporary piping should be adequate to prevent
mechanical failure and should be routed, barricaded, or flagged to prevent a
tripping hazard.
• Temporary utility connections using hoses should comply with plant practice.
• The temporary connections should be dismantled immediately after use.
Offplot Utility Connections. Utility connections for use external to the Company’s
plant should be approved by the plant engineer or manager. These connections
should be constructed as if they were on- plot; the criteria are identical.
Permit Form. Figure 100-2 shows one format used for a Utility Connection Permit
form.