Guide For Site Investigation PDF
Guide For Site Investigation PDF
Guide For Site Investigation PDF
Guide to
Site Investigation
Guide to
Site Investigation
Prepared by:
This Geoguide is a continuously updated version incorporating amendments issued since the
Geoguide was last published. The continuously updated version is released in e-format only
on the CEDD website. This Geoguide is to be cited as “GEO (2017). Guide to Site
Investigation (Geoguide 2) (Continuously Updated E-Version released on 18 December 2017).
Geotechnical Engineering Office, Civil Engineering and Development Department, HKSAR
Government, 349 p.”
3
Foreword
This Geoguide presents a recommended standard of good practice for site investigation
in Hong Kong, the need for which was formally recognized as early as July 1983 by the
Subcommittee of the Building Authority Working Party on Geotechnical Regulations. In its
format and content, the Geoguide follows closely the British Standard BS 5930 : 1981, Code
of Practice for Site Investigations, but the recommendations in the British Standard have been
adapted to suit local conditions and practices. It should be used in conjunction with the
companion document, Guide to Rock and Soil Descriptions (Geoguide 3). These Geoguides
expand upon, and largely replace, Chapter 2 of the Geotechnical Manual for Slopes.
It should be noted that this Geoguide gives guidance on good site investigation practice
and, as such, its recommendations are not mandatory. It is recognized that the practitioner
will often need to use alternative methods. There will also be improvements in site
investigation practice during the life of the document which will supersede some of its
recommendations.
The Geoguide was prepared in the Geotechnical Control Office (GCO) under the general
direction of Mr J.B. Massey. The main contributors to the document were Dr A. Cipullo, Mr
K.S. Smith and Mr D.R. Greenway, with significant contributions during the final stages of
preparation from Dr P.L.R. Pang and Dr R.P. Martin. Many other members of the GCO made
valuable suggestions and contributions.
To ensure that the Geoguide would be considered a consensus document of the civil
engineering profession in Hong Kong, a draft version was circulated widely for comment in
early 1987 to contractors, consulting engineers and Government Departments. Many
organizations and individuals made useful and constructive comments, which have been taken
into account in finalizing the Geoguide, and their contributions are gratefully acknowledged.
Practitioners are encouraged to comment at any time to the Geotechnical Control Office
on the contents of this Geoguide, so that improvements can be made to future editions.
E.W. Brand
Principal Government Geotechnical Engineer
September 1987
4
Contents
Page
No.
Title Page 1
Foreword 3
Contents 4
Part I : Introduction 17
1. Scope 18
2. Terminology 20
4. General Procedures 23
4.1 Extent and Sequence of Investigation 23
4.1.1 General 23
4.1.2 Adjacent Property 23
4.2 Desk Study 24
4.3 Site Reconnaissance 25
4.4 Detailed Examination and Special Studies 25
4.5 Construction and Performance Appraisal 25
4.6 Site Investigation for Tunnel Works 26
6. Aerial Photographs 30
6.1 General 30
6.2 Topographic Maps and Aerial Photographic Imagery 30
5
Page
No.
Page
No.
10.6 Spacing 44
10.7 Depth of Exploration 45
10.7.1 General 45
10.7.2 Foundations for Structures 45
10.7.3 Embankments 47
10.7.4 Cut Slopes 47
10.7.5 Pavements 47
10.7.6 Pipelines 47
10.7.7 Marine Works 48
10.8 Specific Guidance for Silt- and Clay-rich Layers of Rock Cut 48
Slopes
10.9 Specific Guidance for Tunnel Works 50
10.9.1 Preliminary Design Stage 50
10.9.2 Detailed Design Stage 51
Page
No.
Page
No.
Page
No.
19.6.1 General 89
19.6.2 The Delft Continuous Sampler 90
19.7 Sand Samplers 90
19.8 Rotary Core Samples 90
19.9 Block Samples 92
19.10 Handling and Labelling of Samples 92
19.10.1 General 92
19.10.2 Labelling 93
19.10.3 Disturbed Samples of Soil and Hand Specimens of Rock 93
19.10.4 Samples Taken with a Tube Sampler 94
19.10.5 Rotary Core Extrusion and Preservation 95
19.10.6 Block Samples 96
20. Groundwater 97
20.1 General 97
20.2 Methods of Determining Groundwater Pressures 98
20.2.1 Response Time 98
20.2.2 Observations in Boreholes and Excavations 98
20.2.3 Standpipe Piezometers 99
20.2.4 Hydraulic Piezometers 99
20.2.5 Electrical Piezometers 100
20.2.6 Pneumatic Piezometers 100
20.2.7 Installation of Piezometers 101
20.2.8 Varying Groundwater Pressures 102
20.2.9 Soil Suction 103
20.3 Groundwater Samples 103
Page
No.
Page
No.
Page
No.
Page
No.
Page
No.
Page
No.
Page
No.
References 194
Tables 215
List of Tables 216
Tables 217
Figures 233
List of Figures 234
Figures 237
Plates 284
List of Plates 285
Plates 286
Appendices 298
Appendix A: Information Required for Desk Study 399
Appendix B: Sources of Information 307
Appendix C: Notes on Site Reconnaissance 331
Appendix D: Information Required for Design and Construction 336
Appendix E: Safety Precautions 341
17
Part I
Introduction
18
1. Scope
This Geoguide deals with the investigation of sites in Hong Kong for the purposes of
assessing their suitability for civil engineering and building works, and of acquiring knowledge
of site characteristics that affect the design and construction of such works and the security of
adjacent properties. It is essentially BS 5930 : 1981, Code of Practice for Site Investigations
(BSI, 1981a), modified as considered desirable for use in Hong Kong.
While the basic structure and philosophy of BSI (1981a) has been maintained in this
Geoguide, topics of particular importance in Hong Kong have been supplemented or rewritten
in the light of local conditions and experience. Other sections of BSI (1981a) have been
repeated herein without significant amendment, and this has been denoted by an italic script.
Less relevant or rarely-used portions of BSI (1981a) have been incorporated only by reference,
or have been specifically deleted.
In this Geoguide the expression "site investigation" has been used in its wider sense. It
is often used elsewhere in a narrow sense to describe what has been termed herein "ground
investigation". The use of soil and rock as construction materials is treated only briefly;
further information on this is given in BSI (2009). [Amd GG2/01/2017]
Part VI. Part VI deals with the preparation of field reports and
borehole logs, the interpretation of the data obtained from the
investigation and the preparation of the final site investigation
report.
The last section of BSI (1981a), which deals with the description of soils and rocks, is
not covered in this Geoguide. A companion document, Geoguide 3 : Guide to Rock and Soil
Descriptions (GCO, 1988), has been devoted entirely to this topic, and the reader should refer
to it for guidance on the description and classification of Hong Kong rocks and soils.
19
It may be noted that there are some imbalances in treatment of the various topics, with,
in some cases, more comprehensive coverage given to methods that are less frequently used.
Because it would not be possible to include full coverage of all available site investigation
techniques, methods that are well documented elsewhere in the literature receive abbreviated
coverage in this Geoguide.
This Geoguide represents a standard of good practice and therefore takes the form of
recommendations. Compliance with it does not confer immunity from relevant statutory and
legal requirements. The recommendations given are intended only as guidance and should not
be taken as mandatory. In this respect, it should be realized that improvements to many of the
methods will continue to evolve.
20
2. Terminology
A few commonly-used descriptive terms for geological materials and types of ground
investigation are often interpreted in different ways and therefore require definition. In this
Geoguide, the terminology given in the following paragraphs has been adopted.
"Rock" refers to all solid material of natural geological origin that cannot be broken
down by hand. "Soil" refers to any naturally-formed earth material or fill that can be broken
down by hand and includes rock which has weathered insitu to the condition of an engineering
soil. Further guidance on the use of these terms is given in Geoguide 3 (GCO, 1988).
Excluding any boulders or cobbles, a "fine-grained soil" or a "fine soil" is one that
contains about 35% or more of fine material (silt and clay size particles). A "coarse-grained
soil" or a "coarse soil" contains less than 35% of fine material and more than 65% of coarse
material (gravel and sand size particles). Further guidance is given in Geoguide 3.
A "cohesive soil" is one which, usually by virtue of its fines content, will form a coherent
mass. Conversely a "granular soil" or a "cohesionless soil" will not form a coherent mass.
These simple terms are useful in the classification of materials during ground investigation for
the purpose of choosing a suitable method for sampling the ground. A fine soil is generally
cohesive.
The "matrix" of a composite soil refers to the fine-grained material enclosing, or filling
the spaces between, the larger grains or particles in the soil.
Part II
General Considerations
22
In addition, site investigations may be necessary in reporting upon the safety of existing
features and works (see Section 8.3), for the design of extensions, vertical or horizontal, to
existing works, and for investigating cases where failure has occurred (see Section 8.2).
23
4. General Procedures
4.1 Extent and Sequence of Investigation
4.1.1 General
The extent of the investigation depends primarily upon the magnitude and nature of the
proposed works and the nature of the site.
A site investigation wil1 normally proceed in stages, as follows : desk study; site
reconnaissance; detailed examination for design, including ground investigation, topographic
and hydrographic survey and special studies; follow-up investigations during construction
(Figure 1). This may be followed by appraisal of performance. Some of the stages may
overlap, or be taken out of sequence; for example, the site reconnaissance may well take place
before completion of the desk study.
The costs of a site investigation are low in relation to the overall cost of a project and
may be further reduced by intelligent forward planning. Discussion at an early stage with a
specialist contractor will help to formulate an efficient and economic plan. The technical
requirements of the investigation should be the overriding factor in the selection of
investigatory methods, rather than their cost.
As far as possible, assembly of the desk study information should be complete, at least
in respect of those aspects related to ground conditions, before ground investigation begins. A
preliminary ground investigation may be desirable to determine the extent and nature of the
main ground investigation. The extent of the ground investigation is discussed in Chapter 10.
For regional studies or site investigation of projects covering large areas, e.g. road,
tunnel or transmission line routes, techniques such as engineering geological and
geomorphological mapping, terrain classification and hazard analysis may be useful to
delineate critical areas so that detailed investigations can be concentrated in areas where they
are most required (Brand et al, 1982; Griffiths & Marsh, 1984; Hansen, 1982).
Because of the dense urban development in Hong Kong, construction activities can often
affect adjacent property. It is therefore essential that investigations should cover all factors
that may affect adjacent property, including features such as slopes and retaining walls (see
Chapter 7 and Section 8.3). Where possible, records of ground levels, groundwater levels and
relevant particulars of adjacent properties should be made before, during and after construction.
Where damage to existing structures is a possibility, adequate photographic records should be
obtained.
Adjacent buildings, structures and buried services, including pipes conveying water, gas
or sewage, should be specifically considered, as they may be affected by vibrations, ground
settlement or movement, or changes in groundwater levels during and after construction
activities on the site. Hospitals and other buildings containing sensitive instruments or
apparatus should be given special consideration.
24
Special permission or approval must be obtained when the site is above or near the Mass
Transit Railway Corporation's tunnels or structures, or is within the Mid-levels Scheduled Area
(see Appendices A and B; see also Chapter 7). The approximate locations of these two features
are shown in Figure 2.
As a first stage in a site investigation, a desk study is necessary and Appendix A indicates
the types of information that may be required. Much information about a site may already be
available in existing records. A summary of the important sources of information is given in
Appendix B. Readers are advised to take note of any warning messages on the data, check
with the relevant data owners on the reliability, accuracy and completeness of the data they
require where necessary, taking into account the needs of their project. Readers are also
invited to provide feedback to the GEO should the need to update this Geoguide 2 be identified.
[Amd GG2/01/2017]
A new geological survey is currently underway in Hong Kong to replace the existing
1:50 000 scale geological maps and memoir (Allen & Stephens, 1971); new 1:20 000 scale
geological maps will become available between 1986 and 1991 (Figure 3). The new
geological survey uses different nomenclature for certain major rock divisions and rock types
(Addison, 1986; GCO, 1988; Strange & Shaw, 1986); this should be used wherever possible.
The Geotechnical Information Unit also contains numerous records of boreholes from
throughout the Territory, as well as useful records of landslides, rainfall and piezometric data,
and laboratory test results on soil and rock samples. Relevant data can be easily accessed by
geographical location of the site. Further details of the Geotechnical Information Unit are
given in Appendix B.
At an early stage, a thorough visual examination should be made of the site. The extent
to which ground adjacent to the site should also be examined is, in general, a matter of
judgement (see Section 4.1.2). In the intensely-developed urban areas of Hong Kong, it will
usually be necessary to inspect existing slopes and retaining walls within and surrounding the
site and adjacent properties during the site reconnaissance stage. Appendix C gives a
summary of the procedure for site reconnaissance and the main points to be considered but
should not be regarded as necessarily covering all requirements.
Nearby cut slopes can reveal soil and rock types and their stability characteristics, as
can old excavations and quarries. Similarly, in the vicinity there may be embankments or
buildings and other structures having a settlement history because of the presence of
compressible or unstable soils. Other important evidence that might be obtained from an
inspection is the presence of underground excavations, such as basements and tunnels. The
behaviour of structures similar to those intended should also provide useful information, and
the absence of such structures may be significant, as may be also the presence of a vacant site
in the midst of otherwise intensive development.
Examples of earlier uses of the site that may affect the new construction works are given
in Chapter 5.
For most projects, the design and planning of construction will require a detailed
examination of the site and its surroundings (see also Appendix D). Such requirements may
necessitate a detailed land survey (see Appendix D.2), or an investigation of liability to flooding.
The investigation of ground conditions is dealt with in Parts III and IV. Other requirements
may entail studies of special subjects such as hydrography (see Appendix D.3);
micrometeorology (see Appendix D.4); sources of materials (see Appendix D.5); disposal of
waste materials (see Appendix D.6); or other environmental considerations.
The possibility of disused tunnels affecting the site should also be considered (see
Section 5.2).
In areas where underground cavities are suspected (Culshaw & Waltham, 1987), it may
be necessary to carry out a special study to assess the suitability of the site for development (see
Section 7.1).
There are inherent uncertainties in the subsurface geology and hydrogeology, regardless
of the extent of site investigation. Also, physical constraints, e.g. existing buildings and
subsurface installations could limit the pre-tender site investigation for particular sections of
tunnel works. Therefore, it is essential to make provision for additional ground investigation
in the works contract to check and monitor continuously the actual conditions against those
assumed, and to take measures to deal with conditions not anticipated but having significant
impact on the design, construction, or on life and property.
[Amd GG2/01/2017]
The US Army Corps of Engineers Manual (USACE, 1997) includes a practical guide to
the relative cost of site investigation as a proportion of the estimated construction cost. Based
on this guide, the typical cost of site investigation for a deep tunnel located in difficult ground
conditions and in a dense urban area is about 3-4% of the estimated construction cost.
Notwithstanding, the cost of site investigation for a particular project depends greatly on the
quality, suitability and adequacy of available information, and the data needed for the design
and risk management of the types of tunnel works involved. The client should include
adequate funding for site investigation in the project cost estimate. [Amd GG2/01/2017]
Site investigation for projects involving tunnel works should be phased. This approach
is necessary as different phases of the project have different requirements. Also, the tunnel
alignment and design requirements can change during route planning or design.
[Amd GG2/01/2017]
Using the data obtained at each phase, the impact of the proposed excavation method on
the sensitive receivers identified and the geotechnical risks at each tunnel section should be
assessed. The risk assessment should be reviewed when the tunnel alignment is fixed and as
more information becomes available. [Amd GG2/01/2017]
Some simple guidelines on site investigation for tunnelling are given in ITA (2009).
An outline of the engineering considerations and site investigation techniques for rock tunnels,
based on IMMM (2003), is given in Table 13. Supplementary information on ground
investigation techniques is given in Appendix F. [Amd GG2/01/2017]
The Hong Kong Geological Survey (HKGS) section of GEO/CEDD has the most detailed
information on the geology of Hong Kong and offers an advisory service. HKGS should be
consulted, especially at the planning stage of new projects involving tunnel works, in the
formulation of geological models, anticipation of difficult areas, and the verification of
significant geological features (faults, dykes, contact zones between geological units, etc.).
This consultation process in actual projects also allows feedback of important geological
information from the project to existing geological archives maintained by HKGS.
[Amd GG2/01/2017]
28
If a site has been used for other purposes in the past, this can have a significant effect
on the present intended use. A careful visual inspection of a site and the vegetation it sustains
may reveal clues suggesting interference with the natural subsoil conditions at some time in the
past. Examples are given in Sections 5.2 to 5.6.
Due to the relatively short history of development in Hong Kong, many instances of
previous use of a site can be discovered by an inspection of early maps, aerial photographs and
other historical records (see Appendices A and B).
5.2 Tunnels
The presence of nearby tunnels may have a profound effect on the intended use of the
site, and should be fully considered. In addition to tunnels in active use for water supply,
sewage conveyance, roads and railways, underground shelters and disused tunnels (of average
dimensions 2 m high and 3 m wide) exist in places throughout the Territory as a result of
previous wartime activities.
Waste tips, used for the disposal of domestic refuse, industrial waste and other refuse,
may be found in places throughout the Territory. The location of past or present 'controlled
tips' operated by Government are documented, but other tips may also exist. Harmful
industrial wastes may also be encountered. The use of waste tip sites for other purposes must
consider fully the effects of combustible gas, toxic leachate and ground settlement.
Furthermore, sites in the proximity of waste tips may also be subject to the effects of laterally
migrating combustible gas and leachate.
Much of the low-lying land of Hong Kong has been extended by successive stages of
reclamation in the past 80 to 90 years. Former seawalls and other obstructions may therefore
be encountered beneath these areas. The fill materials used have been variable, often
containing large boulders and building debris. The fill is often underlain by soft compressible
29
marine sediments.
Natural slopes and boulders, and older cut and fill slopes and retaining walls, are often
prone to landslides and other forms of instability. It is of paramount importance that all slope
features on or adjacent to the site should be examined for areas of past, current or potential
instability at an early stage in the site investigation.
A list of gazetted historical sites is maintained by the Antiquities and Monuments Office
of the Government Secretariat, and a permit is required before commencement of any work
within a gazetted historical site. It is advisable to consult the Antiquities and Monuments
Office before entering any historical site, even ungazetted sites. During site investigation, any
discovery of antiquities or supposed antiquities should be reported to the Antiquities and
Monuments Office (see Appendices A and B).
30
6. Aerial Photographs
6.1 General
Aerial photographs can be used in the preparation and revision of maps and plans, and
they can assist in the identification and general assessment of natural and man-made features,
including geology, geomorphology, hydrology and vegetation, on or in relation to a site. They
are particularly useful in the assessment of site history (i.e. changes in form, materials and land
use) and can provide valuable information for the assessment of slope stability (Geological
Society, 1982).
Black and white aerial photograph coverage of Hong Kong is extensive. Although
partial coverage of the Territory is available from 1924, the first complete coverage was
obtained in 1963, as summarised in Table 2. For almost any site in the Territory, repeated
aerial photograph coverage records the land use and development changes that have occurred,
as well as any history of recent instability. The small scale black and white photographs
obtained at flying heights of over 6 000 m are more suitable for obtaining an overall view of
the Territory. A small number of true colour, (false) colour infrared and black and white
infrared photographs are also available. Advice on how to obtain the aerial photographs is
given in Appendix B.3.3. [Amd GG2/01/2017]
Accurate topographic maps and plans can be produced from aerial photographs. A
partial catalogue of maps and plans available from the Lands Department is given in Table 1
(see also Appendix B.3.l). Large scale plans (scales 1:500 to 1:1 000) are usually most
appropriate for site investigations of small areas, whereas plans with scales of 1:5 000 to
l:20 000 are more appropriate for district or regional studies. [Amd GG2/01/2017]
Despite these sources of distortion, for sites which can be identified within the central
third of a vertical aerial photograph and which contain terrain of broadly similar elevation,
reasonably accurate scaled images can be obtained by proportioning the distances between
objects identifiable on a map (or plan) and a contact print of an aerial photograph, and by using
this proportion ratio as an enlargement factor. Most aerial photography has been obtained
31
using cameras with large format negatives. Prior to 1963, the sizes of the contact prints vary,
but are usually 162 mm by 175 mm. With few exceptions, the negatives obtained from 1963
to the present are 228 mm by 228 mm. The image produced on contact prints is extremely
sharp, and clear images can be obtained either by viewing the contact prints with a magnifying
lens or stereoscope, or by enlarging all or part of the negative. Enlarged prints can be used
even for studies of small areas of the size of an individual building site.
Orthophoto maps and plans, which consist of rectified (true to scale) photographs
overprinted with contours or grids can be made (overseas only) for both vertical and oblique
aerial photography. Rectification of the image can be performed optically or digitally; the
accuracy is determined by the number of control points supplied, the degree of rectification
desired and the scale of the original photography.
Aerial photographs can be interpreted at a range of scales and levels of detail to provide
information valuable to both the design of site investigations and to the interpretation of the
results. The design of site investigations for large projects such as route corridors (e.g. roads,
railways, pipelines or transmission lines) can benefit enormously from a preliminary aerial
photograph interpretation (API) survey. This can highlight the natural and man-induced
characteristics of the terrain, noting in particular hazards and resources that may have a
significant effect on the feasibility or design of the project. Even when performed for smaller
sites, an API study can often provide useful information on the distribution and thickness of
natural and fill materials, and may reveal potential problems originating from adjacent land.
Sequences of aerial photographs taken at different dates can be compared to determine the
location, extent and approximate time of filling and reclamation, and the sequence of
development of an area.
All the features mentioned above may be important for the interpretation of site
32
conditions. Early identification by API of major changes in soil and rock types and features
that are likely to have a significant influence on the local groundwater regime can be of great
assistance in the design of the ground investigation and in establishing a geological model for
the site.
Reviews of API and related mapping techniques are contained in Geological Society
(1982). Some good examples of the use of API techniques are provided by Ho et al. (2006),
Lueder (1959), Van Zuidam & Van Zuidam-Cancelado (1979), Verstappen & Van Zuidam (1968)
and Way (1978). [Amd GG2/01/2017]
In Hong Kong, API techniques have been successfully applied to both specific problems
and regional appraisals. Examples of the former are given in Brimicombe (1982), Bryant
(1982) and Koirala et al (1986). Systematic regional API studies have been undertaken within
the Geotechnical Area Studies Programme (GASP) to provide information for planning,
resource appraisal and engineering feasibility studies (see Section 4.2). The first of the
regional GASP reports was available in 1987 (GCO, 1987) and a further eleven reports in the
series were published between 1987 and 1989. All GASP maps are available for inspection
in the Geotechnical Information Unit (see Appendix B).
Figure 6 shows an example of a vertical black and white aerial photograph of part of
Hong Kong Island and includes the corresponding portion of the 1:20 000 scale geological map
(GCO, 1986). Some features of the bedrock structure can be interpreted from the aerial
photograph. For example, the location of the fault line shown on the geological map can be
clearly seen as a straight, deep valley in the centre-east part of the photograph. Near the north
eastern corner of the photograph, the photolineaments indicated on the map can be seen to
correspond to less clearly-defined valleys.
33
Part III
For new works, the objectives of ground investigation are to obtain reliable information
to produce an economic and safe design and to meet tender and construction requirements.
The investigation should be designed to verify and expand information previously collected.
In Hong Kong, because of intense urban development, it is often necessary to investigate the
effects of new works on the safety of existing features and works; in particular, the effects on
the stability of existing slopes and retaining structures (see Sections 4.1.2 and 8.3).
Of primary importance will be the establishment of the soil profile or soil and rock
profile, and the groundwater conditions. The profile should be obtained by close visual
inspection and systematic description of the ground using the methods and terminology given
in Geoguide 3 (GCO, 1988), or a suitable alternative system. In many cases, this,
supplemented by limited insitu or laboratory testing, will suffice. In others, it will be
necessary to determine in detail the engineering properties of the soils and rocks. The extent
of the ground investigation is discussed in Chapter 10. Where appropriate, the geometry and
nature of discontinuities should be established (see Section 12.11).
In many cases, especially in slope design, it will be very important to determine the
variations in the groundwater regime in response to rainfall.
The investigation should embrace all ground in which temporary or permanent changes
may occur as a result of the works. These changes include : changes in stress and associated
strain, changes in moisture content and associated volume changes, changes in groundwater
level and flow pattern, and changes in soil properties such as strength and compressibility.
Materials placed in the ground may deteriorate. It is therefore necessary to provide
information from which an estimate of the corrosivity of the ground can be made (see
Chapter 13).
Before commencing ground investigation, all relevant information collected from the
sources discussed in Part II should be considered together to obtain a preliminary conception
of the ground conditions and the engineering problems that may be involved. This will assist
in planning the amount and types of ground investigation required.
Planning of the ground investigation should be flexible so that the work can be varied
as necessary in the light of fresh information. On occasions, especially on large or extended
sites, a preliminary investigation may be necessary in order that the main investigation may be
planned to best advantage (see Sections 4.1.1 and 10.4).
The ground investigation should be largely completed before the works are finally
designed. It is therefore important that sufficient time for ground investigation (including
dealing with all legal, environmental, contractual and administrative matters, reporting and
interpretation) is allowed in the overall programme for any scheme. For example, in slope
design, piezometers should be installed well in advance to obtain sufficient groundwater data
for the design. Should changes in the project occur after completion of the main investigation,
additional ground investigation may be required. If so, the programme should be adjusted to
allow for the additional time required.
Since backfilled pits and boreholes might interfere with subsequent construction, they
should be sited and backfilled with care. It is essential that the precise location of every
excavation, borehole or probing is properly referenced to the 1980 Hong Kong Metric Grid and
recorded during the execution of the fieldwork. It is also essential to establish and record the
ground levels of these locations. The records should be such that the locations and levels can
be readily incorporated into the report on the investigations (see Sections 10.5 and 40.2.8).
Investigations for new works and all other building works within the Mid-levels
36
Scheduled Area (Figure 2) must comply with the provisions of the Buildings Ordinance
(Government of Hong Kong, 1985), including the submission of the ground investigation plan
to the Buildings Ordinance Office for approval and consent to commence the work.
Where the proposed investigation is in the vicinity of the Mass Transit Railway, or within
the limits of the railway 'protection boundary', details and locations of the proposed works,
including the depths of any proposed boreholes, should be forwarded to the Mass Transit
Railway Corporation for agreement prior to commencement of the work.
Should it appear during the course of the investigation that items of archaeological or
historical significance have been encountered, the Antiquities and Monuments Office should be
notified (see Section 5.6).
To obtain the greatest benefit from a ground investigation, it is essential that there is
adequate direction and supervision of the work by competent personnel who have appropriate
knowledge and experience and the authority to decide on variations to the ground investigation
when required (see Chapter 15).
In the project planning stage for tunnel works, alternative tunnel routes and potential
shaft locations are typically considered. It is sufficient to have only a general picture of the
subsurface geology and hydrogeology, to define the preferred route corridor and to estimate the
order of project cost. The site investigation should largely comprise desk studies and site
reconnaissance, and include only limited ground investigation, if any is needed. Reference
should be made to information available from nearby tunnel projects (see, for example, the
references given in GEO (2016)). [Amd GG2/01/2017]
Investigations for new works differ from the other types of investigation mentioned in
Chapter 7, in that they are usually wider in scope because they are required to yield information
to assist in selecting the most suitable location for the works, and the design and construction
of the works. For example, when slope excavation has to be carried out, a knowledge of the
subsurface materials and groundwater conditions should indicate :
On the design side, it is necessary to assess such considerations as bearing capacity and
settlement of foundations, stability of slopes in embankments and cuttings, earth pressures on
supporting structures, and the effect of any chemically aggressive ground conditions. For the
design of new works, it is important that the range of conditions, including least favourable
conditions, should be known. This entails not only a study of the degree of variability in the
soil and rock profiles over the area of the site, but also an appreciation of the possible injurious
effects of groundwater variations and weather conditions on the properties of the various
subsurface materials. Where works require excavations into or within rock, including
weathered rock, the orientation and nature of discontinuities in the rock may be the most
important factors.
Investigations should assess whether the proposed works may induce ground
movements which could affect adjacent land, services and structures, and whether the
hydrogeological regime may be adversely affected (see Sections 4.1.2 and 8.3).
The investigation of a site where a failure has occurred is often necessary to establish
the cause of the failure and to obtain the information required for the design of remedial
measures.
38
In the case of slope failure, or where such failure is considered imminent, it is common
practice to monitor movements both of the surface and underground. The former is conducted
by conventional survey methods and the latter by means of slip indicators or inclinometer
measurements. These techniques are fully described in the Geotechnical Manual for Slopes
(GCO, 1984). It is also usually necessary to monitor groundwater pressures within the
various underlying zones (see Chapter 20). [Amd GG2/01/2017]
Because of the dense urban development in parts of Hong Kong, it is often necessary to
investigate existing features and works in the immediate vicinity or even remote from the site
of the proposed new works, to decide whether the existing works are likely to be affected by
changes in the ground and groundwater conditions brought about by the new works.
Existing slopes and structures may be affected by changed conditions such as the
following :
(c) Stresses that the new structure may impose on existing slopes
or structures, or on the foundation materials below adjacent
39
8.3.3 Procedure
In the investigation of the safety of existing features or works, the first requirement is an
appreciation of the changes to the ground that are likely to occur. The ground investigation
will need to provide knowledge of the subsurface materials, together with the examination and
testing of samples to assess the effect that the changed conditions are likely to have on these
materials. In some cases, it may be necessary to carry out a detailed analysis to estimate the
effect of the changed conditions on the safety of the existing features and works.
The object of geological mapping is to assess the character, distribution and structure of
the soils and rocks underlying the area. Interpretation of the geological conditions at the site
may not be possible without mapping a larger area. An understanding of geological features
is a pre-requisite to interpreting the geological conditions at the site, and a suitably trained
specialist should normally undertake this task.
As a base map or reference, the new 1:20 000 scale geological maps are most useful.
These maps will become available between 1986 and 1991 (Figure 3). Two existing 1:50 000
geological maps (which cover the entire Territory) are also available (Allen & Stephens, 1971).
Methods used for geological mapping at the regional scale are equally suitable for site specific
mapping for ground investigations (Geological Society, 1982; Strange, 1986) and may be
supplemented by interpretation of aerial photographs (see Chapter 6) and geophysical
investigations (see Chapter 33).
Natural exposures and artificial exposures, such as cut slopes and quarries, beyond the
site may provide data on the material and mass characteristics of soils and rocks, including,
for example, the orientation, frequency and character of bedding and jointing discontinuities,
weathering profiles, and the nature of the junction between superficial and solid formations.
Such information should be used as a guide only to conditions likely to be present at the site.
Caution is needed in extrapolating data; geological deposits may vary laterally, and very
important geological structures, such as faults and other major discontinuities, may have only
a restricted extent.
Slope surface stripping is also commonly used in Hong Kong for the purpose of
geological mapping (see Section 18.1).
The extent of the ground investigation is determined by the character and variability of
the ground and groundwater, the type of project, and the amount of existing information. It is
important that the general character and variability of the ground should be established before
deciding on the basic principles of the design of the works.
In Hong Kong, soils derived from insitu rock weathering generally exhibit great
variability even within relatively short distances. Granitic and volcanic rocks, which together
form the major portion of the solid geology of the Territory, may be weathered to soils typically
to depths of 30 m and 10 m respectively. Under certain geological conditions, granitic rocks
may be weathered to over 100 m deep. Examples can be found in the Mid-levels area, Ma On
Shan and Yuen Long. It is important to recognize that ground conditions may not always
improve with depth; on occasions, hard rock at the ground surface may be underlain by thick
zones of weaker material. Similarly, fill materials within reclamations may vary considerably.
Hong Kong soils and rocks are further discussed in Geoguide 3 (GCO, 1988).
Each combination of project and site is likely to be unique, and the following general
points should therefore be considered as guidance in planning the ground investigation and not
as a set of rules to be applied rigidly in every case.
The greater the natural variability of the ground, the greater will be the extent of the
ground investigation required to obtain an indication of the character of the ground. The
depth of exploration is generally determined by the nature of the works projected, but it may be
necessary to explore to greater depths at a limited number of points to establish the overall
geological conditions. The technical development of the project should be kept under
continuous review, since decisions on the design will influence the extent of the investigation.
It is important to realize that the detailed geology of a site can be no more than inferred
from aerial photography, surface outcrops and subsurface information at the positions of the
exploration points. The possibility remains that significant undetected variations or
discontinuities can exist, including lateral or vertical variations within a given layer. The
uncertainties can be reduced but, except by complete excavation, can never be wholly
eliminated by a more intensive investigation. The use of angled boreholes can in certain cases
greatly assist interpreting variations between vertical boreholes (see also Section 10.7.8). In
some circumstances, additional information between investigation points can be obtained by
geophysical methods (see Chapter 33).
43
The investigation should yield sufficient data on which to base an adequate and
economical design of the project. It should in addition be sufficient to cover possible methods
of construction and, where appropriate, to indicate sources of construction materials. The
lateral and vertical extent of the investigation should cover all ground that may be significantly
affected by the new works or their construction. Two typical examples are the zone of stressed
ground beneath the bottom of a group of piles; and an adjacent slope, the stability of which
may be reduced by the works.
Due to the extensive construction of slopes and retaining walls in Hong Kong, detailed
guidance on the nature and content of site investigation for these features is given in Tables 3
and 4. Further discussion of the design and construction of slopes and retaining walls is given
in the Geotechnical Manual for Slopes (GCO, 1984) and in Geoguide 1 : Guide to Retaining
Wall Design (GEO, 1993).
Most structures in Hong Kong are founded on piles. Hand-dug caissons, driven piles,
machine-bored piles and barrettes are commonly used. A general approach to planning a
ground investigation suitable for pile design purposes is given in ICE (1978). The
investigation should make a full appraisal of the site and the ground conditions should be
investigated at depths well below the proposed pile toe level to allow for variations in the pile
design. Knowledge of the groundwater conditions is also required. Further advice on
ground investigation for foundations is given in Section 10.7.2, BSI (1986) and Weltman &
Head (1983).
In areas where major structural defects in rock may occur (e.g. karst features in the Yuen
Long basin, or major shear or fault zones), more intensive investigation and greater exploration
depths than normally recommended may be required. Consideration may need to be given to
locating underground cavities within the zone of influence of the loaded area, and to identifying
other possible significant features such as steeply-dipping rockhead, fractures and alternating
soil and rock layers.
These should be carefully examined, logged and sampled (see Section 18.1).
For large projects requiring staged ground investigations, it will often be useful during
the first stage to carry out a geophysical survey in addition to some widely-spaced boreholes to
identify those areas which require more detailed investigation.
10.5 Location
The points of exploration, (e.g. boreholes, soundings, pits) should be located so that a
general geological view of the whole site can be obtained, together with adequate details of the
engineering properties of the soils and rocks and of groundwater conditions. More detailed
information should be obtained at positions of important structures and earthworks, at points
of special engineering difficulty or importance, and where ground conditions are complicated,
e.g. suspected buried valleys, old slipped areas and underground cavities. Rigid,
preconceived patterns of pits, boreholes or soundings should be avoided. In some cases, it
will not be possible to locate subsurface features until much of the ground investigation data
has been obtained. In such cases, the programme of investigations should be modified
accordingly.
The locations of boreholes and other exploration points should only be planned after the
desk study, site reconnaissance and geological mapping are completed. It is often useful to
locate boreholes at the intended positions of large deep foundations. For slopes, boreholes
should generally be located along anticipated critical slope sections, as well as uphill and
downhill for area and regional stability studies.
For tunnels and inclined shafts, boreholes should be offset so as not to interfere with
subsequent construction. For other structures, the need to offset boreholes and trial
excavations from critical points should be considered. In most cases, boreholes should be
carefully backfilled, concreted or grouted up. Trial excavations should be located outside
proposed foundation areas.
It is essential that accurate locations and ground levels for all exploration points should
be established, if necessary by survey (see Section 7.2).
10.6 Spacing
Although no hard and fast rules can be laid down, a relatively close spacing between
points of exploration, e.g. 10 to 30 m, will often be appropriate for structures. For structures
small in plan area, exploration should be made at a minimum of three points if possible.
Where a structure consists of a number of adjacent units, one exploration point per unit may
suffice. Certain engineering works, such as dams, tunnels and major excavations, are
particularly sensitive to geological conditions, and the spacing and location of exploration
points should be more closely related to the detailed geology of the area than is usual for other
works.
In the case of a proposed cut slope extending from soil into rock, the level of bedrock
45
along the face of the cutting is important. Consideration should be given to obtaining the
subsurface profile by additional drilling and geophysical means. In the case of reclamation,
very closely spaced boreholes may be required to locate and delineate buried obstructions such
as remnants of an old seawall.
The depth of exploration is governed by the depth to which the new project will affect
the ground and groundwater or be affected by them. Normally, exploration should be taken
below all deposits that may be unsuitable for foundation purposes, e.g. fill and weak
compressible soils, including any weak materials overlain by a stranger layer. The exploration
should be taken through compressible soils likely to contribute significantly to the settlement
of the proposed works, generally to a depth where stress increases cease to be significant, or
deeper.
In Hong Kong, it is common practice to drill into rock for a depth of at least 5 m to
establish whether corestone, boulder or bedrock has been encountered. However, the final
depth of drilling will depend on the need to prove bedrock. In some cases, it will be necessary
to drill deeper than 5 m to establish conclusively the presence of bedrock, for example, in
investigations for end bearing piles (see Section 10.7.2). In other instances, it may not be
necessary to terminate drilling in rock (see Section 10.7.4).
In the case of foundations for structures, the depth of exploration should be at least one
and a half times the width of the loaded area. Commonsense will indicate exceptions to this
guideline; for example, it would not usually be necessary to continue drilling for long distances
in strong rock. For foundations near the surface, the loaded area is considered as either :
In each case, the depth should be measured below the base of the footing or raft.
Where piled foundations are considered to be a possibility, the length of pile usually
cannot be decided until an advanced stage of the project. No explicit rules can be given for
the depth of exploration, but the following offer some guidance :
Based on the information of the probable subsurface profile obtained from the desk study,
the general guidance given in (a) to (e) above, and an assessment of the types of pile likely to
be considered, the engineer directing the investigation should determine the depth of
exploration and be ready during the course of the field work to modify this depth as appears to
be necessary. In any event, exploration should at same points be taken below the depth to
which it is considered likely that the longest piles will penetrate.
10.7.3 Embankments
For embankments on alluvial and marine soils, the depth of the exploration should be
sufficient to check possible shear failure through the foundation materials and to assess the
likely amount of any settlement due to compressible materials. In the case of water-retaining
embankments, investigation should explore all materials through which piping could be
initiated or significant seepage occur.
The depth of exploration for cut slopes should be sufficient to permit full assessment of
the stability of the slope. This may necessitate proving the full depth of any relatively weak
or impermeable materials such as decomposed dykes (Au, 1986). In general, exploration for
slopes should extend a minimum of 5 m below the toe of the slope or 5 m into bedrock,
whichever is shallower. However, one or more exploration points should in all cases extend
below the toe of the slope or excavation, irrespective of bedrock level. Groundwater
conditions, including the possibility of perched or multiple water tables, should also be
determined.
10.7.5 Pavements
For pavements, the depth of exploration should be sufficient to determine the strength
and drainage conditions of possible sub-grades. Exploration to a depth of 2 to 3 m below the
proposed formation level will probably be sufficient in most cases.
10.7.6 Pipelines
For shallow small pipelines, it will frequently be sufficient to take the depth of
exploration to 1 m below the invert level. For deeper pipelines the depth of exploration should
be sufficient to enable any likely difficulties in excavating trenches and supporting the pipelines
to be discovered; a depth at least 1 to 2 m below the invert level may be advisable. Large
48
pipelines, especially those in ground of low bearing capacity, require special consideration.
For marine works, the effects described in Sections 10.7.2 and 10.7.3 may apply and, in
addition, consideration should be given to the effects of tidal variations.
In many cases of reclamation, it may be sufficient to terminate drilling shortly below the
base of any soft deposits that are present.
[Amd GG2/01/2017]
10.8 Specific Guidance for Silt- and Clay-rich Layers of Rock Cut Slopes
[Amd GG2/01/2017]
In assessing the stability of a cut slope in volcanic or granitic rock, attention should be
given to establishing whether any of the following geological features are present, and if so,
whether they may adversely affect slope stability: [Amd GG2/01/2017]
(i) laterally persistent (e.g. > 4 m) weak silt- and clay-rich layers
(which predominantly comprise white to buff kaolin, but may
contain other materials, most notably dark brown
manganiferous and iron oxides), within the rock mass,
regardless of thickness,
[Amd GG2/01/2017]
(iii) persistent (e.g. > 4 m), planar, steep joint sets and other
geological contacts (e.g. dykes, faults etc.) that could form
release surfaces. [Amd GG2/01/2017]
The following additional ground conditions are often indicative of the presence of
49
geological features listed in previous paragraph and should also be checked: [Amd GG2/01/2017]
In site investigation, the following items are recommended to facilitate the identification
of geological features that may be adverse to slope stability: [Amd GG2/01/2017]
(i) The desk study should establish the history of any past
failures (including the mechanism and type of failure) and
continuous seepage, and, where site formation photographs
are available, the presence of significant geological features.
[Amd GG2/01/2017]
alignment and the scope of works, including risk mitigation measures based on assumed
methods of excavation. Ground investigation with a geophysical survey could be undertaken
to refine the geological model, to gain additional information on significant geological features,
identify sensitive receivers and to establish baseline conditions.
[Amd GG2/01/2017]
Boreholes should extend well below the anticipated depth of the tunnel and shafts to
allow for any subsequent changes in the vertical alignment of the tunnel in the detailed design
stage, and because the zone of influence of the tunnel may be extended by the nature of the
ground at a greater depth. [Amd GG2/01/2017]
Long horizontal boreholes parallel to the proposed tunnel alignment are extremely useful,
particularly where the location of the proposed tunnel is overlain by thick layers of deeply
weathered rock (McFeat-Smith, 1987). [Amd GG2/01/2017]
Soil permeability tests and Lugeon tests at close spacings should be undertaken in the
boreholes to assess the soil mass and rock mass permeability, respectively. It is important not
to overlook areas of apparently strong bedrock, as the mass permeability of these areas may be
high and may affect significantly construction of the tunnel works. The test results should be
used for development of the hydrogeological model, defining the hydraulic boundary
conditions for the design and for assessing the need to control groundwater inflow/drawdown
during construction. [Amd GG2/01/2017]
In the detailed design stage, when the tunnel alignment has been fixed, the main aim of
the ground investigation should be to obtain information for the reference design or detailed
design of the tunnel works and the associated temporary works. The ground investigation
should also identify conditions at likely problematic areas along the chosen alignment. The
ground investigation data should be adequate for preparing the design of the ground support,
ground treatment, groundwater control works and the risk mitigation measures. It should also
be adequate for planning the inspection, testing and monitoring works during construction.
[Amd GG2/01/2017]
Where existing boreholes are found close to or intercepting the tunnel, the risk of these
boreholes not properly grouted should be assessed and mitigation measures, where necessary,
should be carried out to ensure that these boreholes would not form preferential flow paths that
could jeopardize the tunnel construction. [Amd GG2/01/2017]
New boreholes along the chosen tunnel alignment and shaft locations should generally
extend to a sufficient depth below the invert of the tunnel/shafts to obtain information for the
assessment of possible failure mechanisms/limit states, and/or construction of the tunnel/shafts.
For tunnels in rock, this should be a least 2.5 times the tunnel diameter (or the crown to invert
dimension) below the invert. [Amd GG2/01/2017]
stage, in order to yield early data to maximise its benefit for the design. Despite the cost, the
directional coring together with pumped down packer tests could provide useful information on
the geology and hydrogeology along the tunnel alignment which could not be obtained from
vertical or inclined boreholes. The information along the tunnel alignment would help to
enhance the management of ground risks in tunnel excavation. [Amd GG2/01/2017]
For ground investigation to support the design of shafts, particular attention should be
given to identifying poor ground conditions, which could lead to collapse, excessive ground
deformation/vibration or excessive groundwater inflow/drawdown. For deep shafts with a
significant length in rock, the ground investigation should assess the hydrogeology and inflow
into the unlined sections of the rock mass, and the need for ground treatment and groundwater
control works to prevent excessive drawdown of piezometric pressures in the rock and the soil
overburden. [Amd GG2/01/2017]
For significant temporary works to be designed by the contractor, e.g. major ground
treatment, groundwater control and ground support works, the pre-tender site investigation
should provide sufficient geological and hydrogeological data for the pre-tender reference
designs of such works, which should be carried out to adequately define the scope of the works
required to meet the safety standards and the performance criteria specified.
[Amd GG2/01/2017]
53
Although the character of the ground and the technical requirements are the most
important aspects in the selection of methods of ground investigation, selection may also be
influenced by the character of the site, the availability of equipment and personnel, and the cost
of the methods.
The specialist nature of ground investigation work should at all times be considered.
In most cases it will be necessary to employ a contractor who is experienced in the type of
investigation work which is being proposed, and who has proper equipment and experienced
personnel to carry out the works.
The topography, nature of the ground surface, surface water, the existence of buildings
or other structures and land 'ownership' may cause problems of access to the locations for
boreholes, or interfere with geophysical methods. For example, on very steeply sloping open
sites, it may be necessary to construct an access road or lower the equipment down the slope
or haul it up. Where the working position is on steeply sloping ground, it will be necessary to
form a horizontal working area by excavation or the use of staging (Plate 2A). On sites that
are obstructed by buildings and other structures, it may be necessary to demolish walls to gain
access. Alternatively, it may be possible to lift the equipment over obstructions using a crane
or to use special equipment that can be dismantled and man-handled through the building and
used in a confined space. Gaining access to sites covered by water presents special problems
(see Chapter 14). If the ground surface is soft, it can be traversed only by very light equipment.
Where this would not be effective, access roads for heavier equipment will be required.
Alternatively, the use of helicopters or hovercraft may be appropriate.
Access for drilling rigs should be assessed in the field with the assistance of plans, maps
and aerial photographs. Timber scaffolding is often used in Hong Kong to provide access over
rugged terrain and to construct drilling platforms in very steep terrain (Plate 2B). As such
scaffolding can account for a large portion of the total cost of the investigation, care should be
taken to locate boreholes for ease of access where possible.
54
Most methods of boring and field testing require a supply of water. On a site where
water is not available, it will be necessary to arrange for a temporary supply to be provided.
In the urban area, water can often be obtained from fire hydrants upon application to the Water
Supplies Department for the hire of a metered adaptor. In rural areas water may be obtainable
from wells, rivers or streams. On sites where the provision of water presents a major problem,
it may be necessary to transport the water in bowsers, or to use alternative methods of
investigation; for example, with rotary drilling an air foam flush could be used instead of water
flush (see Section 18.7). Where water is used as the flushing medium, adequate measures
should be provided to prevent silt and other debris in the flushing return from entering the
permanent drainage system, thereby causing siltation and other problems. Such measures may
include settling basins and sand/silt traps.
Other site considerations which may restrict the methods used are as follows :
(b) 'Fung Shui' aspects of some sites are of great social and
religious significance, and local advice should be sought in
planning the investigation.
(c) Buried utilities and services are very common and must be
accounted for, as must subways and other tunnels (e.g. Mass
Transit Railway tunnels) that may pass beneath the site.
(f) The difficulty in storage of spoil may restrict the use of trial
pits on some sites.
This chapter considers the factors involved in the choice of the most suitable procedures
for boring, drilling, sampling, probing and field tests, as determined by the character of the
ground. Specific reference is made to the ground conditions commonly encountered in Hong
Kong; these are further described elsewhere (Brand & Phillipson, 1984; Endicott, 1984; GCO,
1988; Phillipson & Brand, 1985). The following sections should be read in conjunction with
Table 8, which summarises typical sampling procedures for different types of materials (see
Section 19.1). Frequent reference is made to classes of sample quality, which are defined in
Table 9 (see Section 19.2).
Some types of colluvium and alluvium may fall into this category, as may some fill and
soils derived from insitu rock weathering, although the latter two types are considered more
fully in Sections 12.8 and 12.10.
Within the limits of cost, the best method for investigating this type of ground is by
means of a dry excavation (see Sections 18.1 and 18.2). The excavation permits the structure
of the ground to be inspected, samples to be obtained, and field tests to be used to measure
insitu density, strength and deformation characteristics (see Chapters 27, 29 and 30).
If it is necessary to investigate the ground below the groundwater table, dewatering may
be required to obtain a dry excavation. The possible effects on adjacent ground of any
dewatering should first be assessed, however, and it may be necessary in some cases to adopt
alternative methods of investigation below the groundwater table.
Rotary water flush drilling may be employed (see Section 18.7), using a triple-tube core-
barrel with retractor shoe for matrix material and a diamond drill bit for boulders. It may also
be possible to use a U100 sampler (see Section 19.4.4) in matrix material to obtain class 3 or 4
samples. The use of air foam as a flushing medium may enhance core recovery and sample
quality.
During boring, there may be difficulty in advancing the boreholes and, consequently, in
obtaining samples of adequate quality. Boring may be undertaken with the light cable
percussion method using the shell (see Section 18.5), and employing the chisel when rock
fragments too large to enter the shell are encountered. The sides of the borehole must be
supported with casing. Disturbed samples taken from the shell are usually only class 5
(grading incomplete) because the fine fraction may have been washed out and the coarse
56
Borehole tests can be used to obtain an indication of the properties of the ground. The
standard penetration test (see Section 21.2) will give some indication of relative density.
Occasional high values that are unrepresentative of the true relative density will be obtained
when the penetrometer encounters coarse gravel. In ground containing cobbles or boulders,
the standard penetration test gives an increasing proportion of unrealistically high results.
The borehole permeability test (see Section 21.4), may give a reasonable indication of
permeability, and the results can also be used to give a guide to the proportion of fine particles
in the soil. A more reliable assessment of permeability will be obtained from a pumping test
(see Chapter 25). The cone penetration test (see Section 23.3), has limitations where there is
a significant content of boulders or cobbles. It is also limited because of the inability of the
cone to penetrate dense gravel. The ''static-dynamic'' test (see Section 23.4), is useful for this
purpose, although its results will also be affected where cobbles or boulders are encountered.
The pressuremeter is useful in coarse granular soils when held within a slotted casing (see
Section 21.7).
These soils include sands, silty sands and sandy silts, and are fairly common in alluvial
or marine deposits. Boreholes in these materials may be sunk by the light cable percussion
method using the shell, or by rotary drilling. Disturbed samples taken with the shell are likely
to be deficient in fines, and therefore of class 5 only. Samples suitable for a particle size
distribution test, class 4, may be obtained using the split barrel standard penetration test sampler.
Larger class 4 samples can sometimes be obtained using U100 sampling equipment with a core-
catcher.
The action of forcing a sampler into granular soils tends to cause a change in volume,
even if the area ratio is small (see Section 19.4.1(2)), and hence the density of the sample may
not be representative of the layer. In some cases, a piston sampler will be effective (see
Section 19.5); this should produce class 2 samples or, where the soil is loose or very dense,
class 3 samples. However, in both cases the moisture content of the samples may be
unrepresentative of the insitu ground. With clean sand, normal sampling equipment may fail
to recover a sample, and it will then be necessary to use the compressed air sand sampler (see
Section 19.7); sample classes will be similar to those obtained with a piston sampler.
In shallow investigations above the water table, excavations or hand augering (see
Section 18.4), may be used.
A guide to the relative density of granular soils is obtained by the standard penetration
test. However, the results can easily be invalidated by loosening of the soil below the water
table. Where it is important that the relative density should not be underestimated, for
example when a driven pile project is being investigated, the relative density should be assessed
by the cone penetration test.
results of the cone penetration test. Pressuremeter tests are also useful. A more direct
determination requires the use of plate tests carried out in a dry excavation (see Section 21.6
and Chapter 29).
Permeability may be assessed from borehole permeability tests (see Section 21.3), or by
pumping tests (see Chapter 25).
These include clayey sands, clayey silts and silts, and may be encountered in alluvial
and marine deposits. The selection of methods of ground investigation will depend on
whether the material behaves as a granular soil or a cohesive soil.
These include sandy clays, silty clays or clays. They are commonly encountered in
marine and alluvial deposits. The normally consolidated and lightly overconsolidated marine
clays may be sensitive, while the alluvial silty clays are generally insensitive.
Rotary drilling or the light cable percussion method may be used to advance holes in
soft cohesive soil. Considerable care is required with rotary drilling to avoid change of water
content and disturbance by the drilling fluid. Class 1 samples can be obtained by using a
piston sampler. Class 2 or 3 samples can sometimes be obtained with an open-tube sampler.
Continuous samples, usually class 3, can be obtained with a Delft sampler (see Section 19.6).
Disturbed samples from the clay cutter of the light cable percussion method are generally
class 4. Where the borehole contains water, it may be necessary to use the shell, in which case
class 4 samples can be obtained provided that lumps of intact soil can be recovered.
The insitu vane test is by far the most satisfactory means of measuring the undrained
shear strength of soft clays, but the penetration vane test apparatus is much to be preferred to
equipment which is used in boreholes (see Section 21.3). Vane tests are particularly effective
if combined with static cone penetration tests (see Section 23.3). For laboratory test purposes
(particularly oedometer tests) large diameter samples (greater than 150 mm) should be obtained
wherever possible. The compressibility values obtained from Rowe cell tests on large
diameter samples (see Chapter 37 and Table 12) may be used in conjunction with insitu constant
head permeability measurements to give a reasonable estimate of rate of consolidation
settlement.
Rotary drilling can be used, but considerable care is required to avoid change of water
content and disturbance by the drilling fluid. The retractable triple-tube core-barrel can be
used in rotary drilling to obtain class 2 and sometimes class 1 samples. The 100 mm open-
58
tube sampler can be used to obtain class 2 to 3 samples. Alternatively, the light cable
percussion method with clay cutter can be used, which will result in class 5 samples.
Most colluvium and some types of alluvium fall into this category, as may some fill and
soils derived from insitu rock weathering, although the latter two types are considered more
fully in Sections 12.8 and 12.10.
Within the limits of cost, the best method of investigating cohesive soils containing
boulders, cobbles or gravel is by a dry excavation. The excavation will enable the structure
of the ground to be inspected, samples to be obtained, and field tests for the determination of
the insitu density, strength and undrained deformation characteristics to be carried out.
When using borehole methods of investigation, this type of ground presents difficulties
in both advancing the hole and recovering samples of adequate quality. Rotary drilling is often
employed, using triple-tube core-barrels equipped with a retractor shoe for the matrix materials
and diamond-impregnated drill bits for rock fragments and boulders. Class 1 samples can be
obtained by employing air foam flush with the large diameter triple-tube core-barrel. Class 1
to 2 samples may be obtained with retractable triple-tube core-barrels and water flush. The
use of U100 samplers can yield class 2 or 3 samples of the matrix material, while the split barrel
standard penetration test sampler can be used to obtain class 3 to 4 samples. The standard
penetration test is sometimes used to obtain a rough indication of strength, but it may give
misleading results if boulders and cobbles are present.
12.8 Fill
Fill can consist of replaced natural ground, or waste materials of various origins. The
uniformity of fill will depend on the degree of control which has been imposed, on the quality
of the incoming material and on the method of placing and compaction. In older fill, there
may have been little or no control of the filling operation, and the major problem in planning
the ground investigation will be to assess the variation in character and quality across the site.
Often, the variation will be random.
12.9 Rock
Rotary diamond bit core drilling with water flush is normally used in rock. Soils
derived from insitu rock weathering are further considered in Section 12.10. Double-tube or
triple-tube core-barrels may be employed, with triple-tube core-barrels giving better core
recovery and causing less disturbance, especially in highly fractured or jointed rock. The use
of larger-sized equipment producing cores of about 100 mm diameter or more will also help to
improve core recovery.
Soft infilling of rock discontinuities can sometimes be lost due to erosion by the flush
water, and air or air foam flush drilling may be desirable. In general rotary core drilling with
a diamond drill bit will produce samples which may allow an assessment of the character and
engineering properties of the intact rock material. Such samples may also give some
indication of the frequency and dip angle of the discontinuities but not their dip direction, unless
special techniques are used. The use of borehole periscopes, impression packers, cameras,
and television cameras may be useful in this connection (see Section 21.8). In many cases,
rotary core samples give no indication of the character of any infilling of the discontinuities.
In a ground investigation using light cable percussion boring or rotary core drilling, an
indication of the properties of the rock mass can be obtained from tests in boreholes. For
certain of such tests, however, it will be necessary to take into account the probable effects of
disturbance of the ground by the drilling process. The standard penetration test (see
Section 21.2), can give a rough indication of the variation of strength and compressibility in
weak rock. The permeability test (see Section 21.4), or the packer or Lugeon test (see
Section 21.5), may give a measure of the mass permeability, which in turn can give an indication
of the presence of open joints and other water-bearing discontinuities. Where applicable, the
plate test (see Section 21.5), and dilatometers such as the pressuremeter (see Section 21.7), can
be used to investigate deformation properties and possibly also the strength.
The best method for determining the properties of a rock mass, including the orientation
of discontinuities, is visual inspection, and field tests carried out in excavations, caissons or
headings (see Chapter 18).
Weathered rock that can be regarded and treated essentially as soil from an engineering
viewpoint occurs extensively throughout Hong Kong. These materials are derived primarily
from the chemical decomposition of the parent bedrock, and their character depends on the
parent rock type. Soils derived from granite are typically silty or clayey sands, while those
derived from tuff and other volcanic rocks are often sandy or clayey silts. These soils very
often contain corestones of less decomposed rock within a more decomposed matrix, and it is
not uncommon to encounter granite corestones as large as 3 m or more. The depth over which
decomposed material changes to fresh rock is extremely variable and is related to the rock type,
joint pattern, the spacing of the joints, faulting, alteration, and the position of the water table
(GCO, 1988).
Where these soils occur at shallow depth, pits are probably the most effective means of
60
investigation; class 1 block samples of the matrix material can usually be obtained for
laboratory testing and the exposure can be fully described and logged.
Borehole tests can be used to obtain an indication of the properties of the ground. The
standard penetration test will give some indication of density and degree of weathering,
although the presence of corestones may give unrealistically high results. The standard
penetration test can generally provide useful information for the initial assessment of likely pile
founding depths. The borehole permeability test may give a reasonable indication of
permeability. The pressuremeter may be useful for measuring ground stiffness.
12.11 Discontinuities
In most rocks, the mass properties depend largely on the geometry and nature of the
discontinuities. This can require the engineering properties to be measured in the plane of the
discontinuities along specific orientations determined by the anticipated directions of the
stresses to be applied. The control by discontinuities over the strength and deformation
characteristics of a ground mass is less obvious in soils derived from insitu weathering than in
moderately weathered to fresh rock, but may be equally important.
There are no satisfactory drilling or boring techniques available for ensuring that the
core recovered can be orientated over the full depth penetrated, but borehole discontinuity
surveys can be conducted (see Section 21.8). In soils, the discontinuities are often destroyed
by the drilling and therefore overlooked. Where discontinuities are important to the
engineering problems involved, insitu exposures of discontinuities are necessary to obtain data
on their orientation and nature. After initial investigations using interpretation of aerial
photographs, surface outcrop logging and the drilling of vertical and inclined orientated holes,
it may be necessary to form full surface exposures, large diameter boreholes, trenches, pits or
adits to allow visual inspection around and within the undisturbed ground mass, and
measurement of the relevant discontinuity data (see Chapter 26). In some projects, suitable
exposures may be provided in excavations necessitated by the permanent works. The
extraction or insitu preparation of orientated test samples can be carried out in these
excavations, together with orientated large scale tests. The orientation of the excavations
controls their intersection with the discontinuities and, consequently, the discontinuity data that
can be obtained. Generally, three orthogonal exposures are required to define fully the spatial
distribution of the discontinuities. The extent of the excavations is governed by the spacing
between discontinuities and the size of the works.
61
12.12 Cavities
Ground containing natural or man-made cavities can be found in Hong Kong (e.g.
caverns in karst, disused tunnels and old mineshafts) and the cavities may be vacant or infilled
(Culshaw & Waltham, 1987). Difficulties may be experienced in advancing a borehole
through such ground. A variety of drilling techniques may need to be tried, and precautions
should be taken to prevent dropping of the drill string, and to maintain verticality of the hole.
Care may also be required to avoid ground subsidence during investigation (see Section 8.3.2).
Close supervision is essential for such investigations.
62
In some areas, soil, rock and groundwater may contain certain constituents in amounts
sufficient to cause damage to Portland cement concrete or steel. While insitu weathered rocks
and their associated soils in Hong Kong are generally not aggressive, this should be confirmed
by ground investigation and laboratory testing whenever the use of ground anchors, reinforced
fill structures or other susceptible structures are contemplated. Investigations for aggressive
ground and groundwater should be considered for all sites where transported soils are
encountered, and for all marine sites.
The principal constituents causing damage to concrete are sulphates, which are most
common in clay soils and acidic waters. Total sulphate contents of more than 0.2% by weight
in soil and 300 parts per million in groundwater are potentially aggressive (BRE, 1981).
Laboratory tests to assess the aggressiveness of the ground and groundwater against
Portland cement concrete include determination of pH value and sulphate content (GEO, 2017a).
Reference should be made to BRE (1981) regarding the determination of water-soluble sulphate
concentrations. The pH value may be altered if there is a delay between sampling and testing,
so field determinations should be made if possible.
[Amd GG2/01/2017]
Water sampled from boreholes may be altered by the flushing water used in drilling, or
by other flushing media employed. Therefore sulphate and acidity tests carried out on samples
from boreholes may not be representative unless special precautions are taken (see Section 20.3).
The likelihood of corrosion of steel can be assessed from tests of resistivity, redox
potential, pH, chloride ion content, total sulphate content, sulphate ion content, and total
sulphide content. Details of these tests, and relevant limits for a relatively non-aggressive
environment for steel, are given in Geoguide 6 (GEO, 2017b). Chemical tests should be done
on undisturbed specimens which have been placed in clean airsealed containers immediately
after sampling. If bacteriological attack is expected, undisturbed specimens should be placed
63
in sterilized containers and tested in accordance with BSI (1990) (see also Section 13.2 and
Table 12). [Amd GG2/01/2017]
Industrial waste products can contain a wide range of chemicals, depending on the
industrial processes from which the waste products are derived. Some chemicals are highly
aggressive to concrete or steel in underground structures, and some can be highly obnoxious
or even poisonous. The last two characteristics can present major construction problems, e.g.
the disturbance or disposal of contaminated ground, or the disposal of contaminated
groundwater. Local enquiries may give some indication of the origins of the waste materials,
and the pH value and sulphate content for the fill and the groundwater will generally give some
indication of the magnitude of the contamination. It may then be necessary to carry out a
detailed chemical study of the ground conditions.
Sinking boreholes below water presents special difficulties in comparison with working
on dry land. A reasonably stable working platform may be provided, such as a staging, barge
or ship, and the borehole sunk through a conductor pipe spanning between the working
platform and the water bottom. Increasing use is being made of a variety of penetration
testing techniques (Blacker & Seaman, 1985). In some cases, it may be feasible to lower
specially designed boring, drilling or penetration testing equipment to the water bottom to be
operated by remote control or a diver. With remote control, operation is restricted to a single
continuous process. Penetration depths vary from less than 5 m for some devices, to 20 m or
more for others. Geophysical techniques are also used to augment the information obtained
from boreholes, or as a preliminary investigation before putting down boreholes (see
Chapter 33).
The scope of the work, including the methods of drilling, sampling and insitu testing,
requires careful consideration depending on the particular difficulties of the site. When
working over water it is essential that due consideration is given to safety requirements,
navigational warnings, and the regulations of Government Departments and other authorities.
To avoid interference with marine traffic, the Marine Department must be notified of
investigations so that a Notice to Mariners can be issued. Special consideration must be given
to sites where the investigation or associated craft could present a hazard. For example, craft
working close to the runway of Kai Tak Airport must not pose a hazard to aircraft; permission
for any such work must first be obtained from the Civil Aviation Department. Similarly,
permission must be obtained from the Mass Transit Railway Corporation, the Cross Harbour
Tunnel Co. Ltd, the Water Supplies Department, or the various public utility companies if work
is to be carried out near submerged tunnels, pipelines or major utilities (see Appendices A and
B).
Ground investigations conducted from above water are often more expensive and time
consuming than comparable investigations conducted on dry land, and there may be a
temptation to economize by reducing the scope of the investigation. The extent of the
requirement for ground investigations should be realistically assessed, since economies in this
direction can turn out to be false.
Observatory.
Where stable working platforms are available or can be provided, such as oil drilling
platforms and jetties or purpose-built scaffold stages and drilling towers, it is generally
possible to use conventional dry-land ground investigation drilling equipment and conventional
methods of sampling and insitu testing. When working from existing structures, it may be
necessary to construct a cantilevered platform over the water on which to mount the drilling
rig. When drilling close to the shore in relatively shallow water, it may be more convenient to
construct a scaffold staging from land to the borehole location. Alternatively, it may be more
economical to construct a scaffold or other tower at the borehole location, in which case some
means of transporting the drilling equipment to the tower will need to be provided. Some
towers are constructed such that they can be moved from one borehole location to another
without having to be dismantled.
Jack-up platforms, and special craft fitted with spud legs, can be floated into position
and then jacked out of the water to stand on their legs. They can combine manoeuvrability
with fulfilment of the requirement for a fixed working platform.
Jack-up and other fixed platforms effectively overcome the problem of heave and allow
a high standard of drilling, testing and sampling to be achieved. Jack-up platforms currently
available in Hong Kong are capable of operation in water depths not exceeding about 12 m
(Plate 3A).
The design of all staging, towers and platforms should take into account the nature of
the seabed, fluctuating water levels due to tides, waves and swell conditions. It is essential
that such constructions should be sufficiently strong for the boring operations to resist waves,
tidal flow and other currents and floating debris.
The type of floating craft suitable as a drilling vessel depends on a number of factors
such as whether the water is sheltered or open, the anchor holding properties of the seabed,
whether accommodation for the personnel is required on board, the likely weather conditions,
the depth of water and the strength of currents. In inland water, a small anchored barge may
suffice, but in less sheltered waters a barge should be of substantial size, and anchors will
require to be correspondingly heavy. In offshore conditions, a ship is often employed, and it
may then be possible to accommodate the personnel on board, with a saving in auxiliary supply
vessels.
An auxiliary vessel will be required to handle the moorings if a barge is used for the
work, but in certain cases a ship may be able to lay and pick up its own moorings. Generally,
four or six point moorings wil1 be required, and anchors should have the best holding capacity
feasible. In water deeper than 80 m, conventional moorings become difficult, and the use of
vessels maintained in position by computer-controlled thrusting devices should be considered.
66
Special techniques are required to deal with fluctuating water levels due to tides,
waves and swell conditions (Plate 3B), particularly with rotary drilling where a constant
pressure between the drill bit and the bottom of the borehole is required (Smyth & McSweeney,
1985). When the heave is anticipated to exceed about 300 mm, it is necessary to employ a
heave compensator system if high quality samples are to be obtained. Heave compensator
systems allow the drill string and sampling equipment to be isolated from the vertical
movements of the craft (Blacker & Seaman, 1985).
Pontoons and barges should be anchored at the corners using anchor lines at least five
times the depth of water. In exposed waters, motorized mooring winches are necessary.
Sinking boreholes between high and low tide levels may be achieved using scaffold
stagings, platforms (see Section 14.2) or flat-bottomed pontoons, or by moving drilling rigs to
the location during periods permitted by the tides.
Close to shore, borehole positions and other investigation points can be set-out by
radiation from known shore stations with distances measured by Electronic Distance Measuring
(EDM) equipment. Further offshore, or when visibility is bad, electronic position fixing
techniques can be used.
Setting-out by radiation usually involves the initial placement of a marker buoy within
5 m of the specified position. The marker buoy should be fitted with a line of sufficient length
to allow for tidal variations and wave heaving. An auxiliary float on a 5 m line can also be
tied to the marker buoy to indicate the direction of the current. This will help in manoeuvering
the drilling craft into position. Once the drilling craft has been anchored over the sinker of the
marker buoy, further measurements from the known shore stations can be taken. The position
of the drilling craft can be adjusted by means of anchor winches until the borehole is positioned
within 1 m of the required position. All borehole positions should be related to the 1980 Hong
Kong Metric Grid, or if a site grid is used, the site grid should be related to the 1980 Hong Kong
Metric Grid such that standard co-ordinates can be obtained.
Reduced levels are generally transferred to a drilling vessel from shore by setting up a
tide gauge close to the shore. The gauge is read at frequent intervals throughout the tidal
cycles at the same time as readings of water depth are taken on the drilling vessel. Corrections
may be necessary to allow for tidal variations when the distance between the tide gauge and
the vessel is significant.
67
Reading of the tide gauge can be facilitated by noting both the crest and trough levels
of at least six consecutive waves. An average of the mean crest level and mean trough level
can be adopted as the tide level at that instant. The tide gauge should be referenced to Hong
Kong's Chart Datum (which is 0.146 m below Principal Datum), so that the reading can be used
to obtain the reduced levels of the seabed and subsurface geological boundaries.
For marine investigations, the rotary open hole method of advancing a hole is preferred
to the rotary wash boring method (see Section 18.7.l). Drilling mud should be used as a
flushing medium and to stabilize the hole when casing is not required. Cable tool boring
techniques may be used to advantage in some situations, for example the identification of
suitable marine borrow areas. Rotary drilling with a retractable triple-tube core-barrel (see
Section 19.8) is often employed in soils derived from insitu rock weathering, as for land-based
investigations.
If a fixed platform is not used during sampling, particular care must be taken to prevent
sample disturbance due to heave. Continuous sampling of soft soils can be undertaken with a
Delft or Swedish foil sampler, but these are particularly sensitive to heave and should only be
attempted from a fixed platform. With the Delft samplers, care should be taken to prevent
necking of the nylon jacket due to unbalanced fluid pressures, and ripping of the jacket due to
shells in marine deposits.
The person planning and directing the ground investigation should be a suitably
qualified and experienced engineer or engineering geologist. This person should have a
university degree in civil engineering or geology, or an equivalent professional qualification,
and at least four years post-qualification engineering experience, some of which should be local
experience on projects of a similar nature to the one being contemplated. If the ground
conditions at the site are anticipated to be complex and the safety and economy of the project
are significantly influenced by the ground conditions, the person planning and directing the
ground investigation should possess, in addition, specialized qualifications or experience in
geotechnical engineering, and specialized knowledge in site investigation practice in Hong
Kong.
The person planning and directing the ground investigation should be thoroughly
familiar with the project requirements and capable of liaising effectively with the project
designer or client throughout all phases of the investigation (Figure l). This person should
determine the content and extent of the investigation, direct the investigation in the field and
laboratory, and assess the results in relation to the project requirements. Part of these duties
may be delegated to geotechnical specialists or suitably trained and experienced subordinates.
Ground investigation works should generally be carried out under the supervision of a
suitably qualified and experienced engineer or geologist, assisted by trained and experienced
technical personnel. The supervising engineer or geologist should have a university degree in
civil engineering or geology, or an equivalent professional qualification, and at least four years
post-qualification engineering experience, some of which should have been in ground
investigations. Technical personnel should possess a certificate in civil engineering from a
polytechnic and at least one year of specialized training and experience in ground investigations,
including training in the proper logging and description of ground conditions.
The supervising engineer or geologist should be full time or part time on site, depending
on such factors as the :
Increasing size and complexity of the project, as well as increasing complexity of ground
conditions and investigation techniques, or decreasing reliability of the contractor's personnel,
should all lead to heavier time commitments for the supervising engineer or geologist. The
supervisor will normally be required full-time on site whenever it is planned to carry out works
which are critically dependent on a high standard of workmanship for their success or safety.
Only when minor ground investigation works are undertaken for confirmatory purposes, and
where the works involve simple investigation techniques, should full delegation of the
supervision of the works to technical personnel be contemplated.
Technical personnel will normally be required full-time on site. Several technical staff
may be required on site if a number of drilling rigs are operating simultaneously, if several field
tests or instrument installations are being undertaken simultaneously, or if the works are widely
scattered.
The supervising technical personnel (see Section 15.3) should be responsible for
recording the information obtained from boreholes or other investigations as it arises. This
information should include a measured record of the subsurface profile with rock and soil
descriptions, and a record of the drilling and sampling techniques used. In complex ground
conditions, or when the information is particularly important, the supervising engineer or
geologist should record this information as it arises. In some cases, it may be necessary to
obtain specialist advice on the logging and description of ground conditions (see Section 15.6).
Detailed descriptions of the ground conditions encountered and of all rock and soil
samples obtained should be made in accordance with Geoguide 3 (GCO, 1988), or a suitable
alternative system. All personnel undertaking logging and description of ground conditions
should be thoroughly familiar with the system to be used and suitably experienced in its
application.
70
The testing of soil and rock samples should be carried out in a laboratory approved by
the directing engineer or engineering geologist referred to in Section 15.2. The laboratory
testing should be done under the control of a suitably qualified and experienced supervisor, and
all laboratory technicians should be skilled and experienced in the type of test they are
conducting. The laboratory testing schedule should be finalised only after selected samples
have been examined by the person directing the investigation or by the supervising engineer or
geologist. The latter should supervise the more complex tests.
Depending on the complexity of the ground conditions and the nature of the project,
specialist advice on particular aspects of the ground investigation may be needed. For
example, the advice of an experienced engineering geologist may be required on such aspects
as :
15.7 Interpretation
15.8 Operatives
The driller in charge of an individual drilling rig should be skilled and experienced in
the practice of ground investigation by means of boreholes and simple sampling and testing
techniques. Operators of other equipment used in ground investigations should have
appropriate skills and experience. Any timbering, shoring or other support required in
71
excavations or caissons should be installed only by suitably skilled workmen. All operatives
should be familiar with and observant of safety precautions (see Appendix E).
72
16.2 Purpose
The primary purpose of the review during construction is to determine to what extent, if
any, in the light of the conditions newly revealed, conclusions drawn from the ground
investigation are required to be revised.
In some cases, additional information is found which may necessitate amendment of the
design or the construction procedures. In certain cases, it may therefore be appropriate to
initiate a site procedure in the early stages of the contract, so that correct and agreed records
are kept during the duration of the contract by both the engineer and the contractor. The
purposes of these records are :
Accurate descriptions of all material encountered below ground level should be made in
accordance with Geoguide 3 (GCO, 1988), or a suitable alternative system. The subsurface
profile revealed on site should be recorded and compared with that anticipated from the ground
investigation. The descriptions should be made by an engineer or geologist (see Section 15.4).
It may be advantageous to arrange for the site to be inspected by the organization that carried
out the site investigations, particularly if ground conditions appear to differ significantly from
those described in the ground investigation.
16.3.2 Water
It is most important to record accurately all information about the groundwater obtained
during construction, for comparison with information recorded during the investigation. The
information should cover the flow and static conditions in all excavations, seepage from slopes,
seasonal variations, tidal variations in excavations or tunnels near the sea or estuaries, suspect
or known artesian conditions, the effect of weather conditions on groundwater, and any
unforeseen seepage under or from water-retaining structures. The effect of groundwater
lowering should also be recorded in observation holes to determine the extent of the cone of
depression.
Groundwater rises due to the damming effects of new construction or temporary works
should likewise be recorded.
16.4 Instrumentation
On many types of structures, such as earth dams, embankments on soft ground, some
large buildings with underground construction, excavations and tunnels, it is prudent to
consider regular observations by means of instrumentation in order to check that construction
works can proceed safely (Bureau of Reclamation, 1987; DiBiagio & Myrvoll, 1982). Such
observations may include measurement of pore pressure, seepage, earth pressure, settlement
and lateral movements (see also Sections 8.2, 28.3 and 31.2). The instrumentation may be
usefully continued after construction in order to observe the performance of the project. This
is particularly necessary in the case of earth dams for maintaining a safe structure under
varying conditions, and in other cases for gaining valuable data for future design.
information to support the design review of the tunnels, caverns and shafts, in order to ensure
that there is adequate safety margin and performance. [Amd GG2/01/2017]
For the exposed faces in tunnel works, the site investigation should include geological
and engineering geological mapping, and an assessment of the tunnel sections/shafts using a
soil/rock mass classification scheme on which the design may be based. A proforma for
recording the rock mass mapping and classification data in rock tunnels is available from the
Hong Kong Slope Safety Website under the downloading area at http://hkss.cedd.gov.hk.
[Amd GG2/01/2017]
Depending on the tunnel excavation method and the risk assessment, probing ahead of
the tunnel excavation may be carried out. The penetration rate, the quantity of water inflows,
and the colour and nature of cuttings and flushing water returns should be recorded. This
information should be used to assess the ground conditions ahead, in particular the soil/rock
interfaces and sections with potentially high water inflow, and the need for implementation of
robust mitigation measures before further tunnel excavation. In addition to probing, use of
non-invasive techniques and coring during construction may be considered where cost
effectiveness can be demonstrated. For TBM works, further ground investigation may be
necessary prior to or during the TBM drive to confirm the locations of permeable soils and
soil/rock interfaces and the variations in groundwater pressures for design. [Amd GG2/01/2017]
Sufficient time should be allowed in the construction programme for the results of
additional ground investigation and site inspection and monitoring to be fed back into the design
and risk management processes, in order that modifications to the design can be implemented
or other contingency measures undertaken in a timely manner. [Amd GG2/01/2017]
75
Part IV
Insitu tests that are carried out in boreholes as part of a borehole investigation are
described in Chapter 21. Other insitu tests, for which a borehole either is unnecessary or is
only an incidental part of the test procedure, are described in Chapters 24 to 33. Laboratory
tests on soil and rock are discussed in Chapters 34 to 38. The collection and recording of data
is discussed in Chapters 39 and 40.
77
Shallow trial pits are usually dug by hand using a pick and shovel, and commonly extend
to a depth of about 3 m. It is essential that the pit sides are guarded against sudden collapse
in order to protect personnel working in the pit. For this purpose, timber shoring is usually
provided when excavation is deeper than 1.2 m. The spacing of the shoring should be
sufficiently wide to allow inspection of the pit sides. Shallow trial pits may also be dug by
machine; a hydraulic back-hoe excavator is the most commonly used.
Shallow trial pits permit the insitu condition of the ground to be examined in detail both
laterally and vertically, and allow mass properties to be assessed. They also provide access
for taking good quality (block) samples and for carrying out insitu tests. Trial pits are
particularly useful for investigating and sampling soils derived from insitu rock weathering and
colluvium, both of which often exhibit a high degree of variability. Pits may also be used to
investigate the dimensions and construction details of old retaining walls, and to ascertain the
exact position of buried utilities and services.
The field record of a shallow trial pit should include a plan giving the location and
orientation of the pit, and a dimensioned section showing the sides and floor. Ground
conditions should be fully described in accordance with Geoguide 3 (GCO, 1988) or a suitable
alternative system, and samples taken should be fully documented. Two examples of trial pit
logs are given in Figures 7 and 8. Logs should always be supplemented with colour
photographs of each face and of the base of the pit. The positions and results of any field
testing should also be recorded, such as insitu density tests or Schmidt hammer, hand
penetrometer and hand shear vane index tests.
Material excavated from trial pits should be stockpiled in such a manner that it does not
fall back into the pit or cause instability of the pit excavation, e.g. by surcharging the adjacent
ground. Wooden hoardings anchored by steel bars driven into the ground are often used on
steep slopes to retain spoil from falling back into the pit. The spoil should be placed and
covered so as not to be washed downhill during rainstorms or allowed to enter surface drainage
systems.
It is advisable to backfill pits as soon as possible after logging, sampling and testing
have been completed, since open pits can be a hazard. Recommendations on backfilling are
given in Section 18.9. Pits that must be left open temporarily should be covered and sealed so
that rain water cannot enter; they should also be securely fenced off if readily accessible by the
public.
Trial pits can be extended readily into trenches or slope surface stripping. The latter is
used extensively in Hong Kong to investigate both natural and man-made slopes, and generally
consists of a 0.5 m wide strip, extending from the crest to the toe of the slope, in which the
ground has been laid bare of vegetation, chunam plaster or other coverings. Bamboo
scaffolding or access ladders are provided for inspection, logging and reinstatement.
An example of a log sheet for slope surface stripping is given in Figure 9. Colour
78
photographs of salient geological features revealed by the stripping should always be obtained.
Fill is sometimes used to smooth the surface of a cut slope before application of the chunam
plaster; if this is encountered in slope stripping the depth of excavation should be increased if
possible to reveal the true nature of ground beneath.
Deep trial pits, shafts and caissons are normally constructed by hand excavation using
various methods for supporting the sides. Temporary or permanent liners are necessary for
the protection of personnel working in these excavations, but it is also necessary to consider the
need to expose the ground for inspection and logging; considerable judgement and experience
is often required to establish suitable procedures for such excavations.
Hand-dug caissons 1 m in diameter and larger are commonly used in Hong Kong for
foundation construction to depths of 30 m or more. Typically, cast-insitu concrete liners are
used in soil, while the caisson is left unlined in rock. These caissons may be particularly useful
for the investigation of rock at or near the founding level of large foundations (Irfan & Powell,
1985). An example of a caisson log is given in Figure 10. It is recommended that the
guidance notes on the technical and safety aspects of hand-dug caissons issued by the Hong
Kong Institution of Engineers (HKIE, 1981) should be followed.
Working in deep shafts wil1 be dangerous unless the appropriate safety precautions are
strictly followed. Attention should be given to the possible occurrence of injurious or
combustible gases or of oxygen deficiencies. Correct methods of inspection should be
followed and appropriate precautions should be taken (see Section 7.2 and Appendix E).
Oxygen-consuming engines that emit toxic exhaust fumes, such as petrol-driven pump motors,
should not be employed in shafts.
Headings are driven from the bottom of shafts or laterally into sloping ground, and can
be used for the insitu examination of the ground or existing foundation structures, and for
carrying out special sampling or insitu testing. Further considerations are given in BSI (2010).
[Amd GG2/01/2017]
The hand auger boring method uses light hand-operated equipment. The auger and
drill rods are usually lifted out of the borehole without the aid of a tripod, and no borehole
casing is used. Boreholes up to 200 mm diameter may be made in suitable ground conditions
to a depth of about 5 m. The method can be used in self-supporting ground without hard
obstructions or gravel-sized to boulder-sized particles. Hand auger boreholes can be used for
groundwater observations and to obtain disturbed samples and small open-tube samples.
79
Light cable percussion boring cannot be used for boring into or proving rock, and it is
severely restricted in bouldery ground where the frequent use of a heavy chisel is required.
The widespread occurrence in Hong Kong of bouldery colluvium and corestone-bearing soils
derived from insitu rock weathering has therefore curtailed the use of light cable percussion
boring, as has the widespread need to core into and prove rock. However, the method can be
used to investigate the finer-grained marine sediments and alluvium found in the flat coastal
areas.
Mechanical augers, comprising a continuous-flight auger and a hollow stem, are suitable
for augering soft cohesive soils and may be suitable for firm cohesive soils. They are of
limited use in soils with boulders or corestones and are therefore seldom used in Hong Kong.
Further considerations are given in BSI (2010). [Amd GG2/01/2017]
Rotary drilling, in which the drill bit or casing shoe is rotated on the bottom of the
borehole, is the most common method of subsurface exploration used in Hong Kong (Chan &
Lau, 1986). The drilling fluid, which is pumped down to the bit through hollow drill rods,
lubricates the bit and flushes the drill debris up the borehole. The drilling fluid is commonly
water, but drilling mud or air foam are often used with advantage (see Section 18.7.2).
There are two basic types of rotary drilling: open hole (or full hole) drilling, in which
the drill bit cuts all the material within the diameter of the borehole; and core drilling, in which
an annular bit fixed to the outer rotating tube of a core-barrel cuts a core that is returned within
the inner stationary tube of the core-barrel and brought to the surface for examination and
testing. Drill casing is normally used to support unstable ground or to seal off open fissures
which cause a loss of drilling fluid. Alternatively, drilling mud or cement grout can be used
to seal open fissures.
In ground investigations, rotary core drilling has the important advantage over rotary
open hole drilling of providing a core sample while the hole is being advanced, and it is
recommended for most situations. In rotary open hole drilling, drill cuttings brought to the
surface in the flushing medium can only provide an indication of the ground conditions being
encountered. However, rotary open hole drilling is useful for rapid advancement of a borehole
required for field testing or instrument installation, and samples may be obtained between drill
80
Water used as a flushing medium in rotary drilling may have a deleterious effect on both
the stability of the surrounding ground and on the samples obtained, and its use must be
carefully considered (see Section 18.7.2). A crude adaptation of the rotary open hole method,
often termed rotary wash boring, may be particularly detrimental in this regard. This method
involves advancing the hole by casing alone, with the inside of the casing cleaned out by surging
and flushing. Water pressures sufficient to flush the casing are often high and may lead to
increased pore pressures (or reduced pore suctions) in the surrounding ground. When drilling
on a slope or behind an old masonry retaining wall, for example, this may be detrimental to
stability and may actually trigger rapid collapse. Also, in soils containing gravel-sized
fragments, it is impossible to flush out all the coarse fragments, irrespective of the water
pressure employed, and they will accumulate in the base of the hole. These fragments will
affect the representativeness of further sampling and testing done in the borehole. In soft or
loose ground, the flushing water may not only carry the cuttings up through the casing, but also
up around the outside of the casing, thus creating a large zone of disturbed material which can
extend for some distance below the bottom of the hole. As a result, samples obtained from
rotary wash boring may be disturbed, at least over a portion of their length. In marine
investigations, the standard rotary open hole method should therefore be used in preference to
rotary wash boring (see Section 14.7).
Rotary drilling rigs are available in a wide range of weights and power ratings in Hong
Kong. Rigs are normally skid mounted, with a typical configuration as shown in Figure 11.
They are commonly available with a power rating in the range of 10 to 50 horsepower and
capable of stable drill string rotation up to 1 500 or 2 000 rpm. Drilling rigs should be mounted
on a stable platform such that a force of 12 to 15 kN can be applied to the drill bit without
movement of the rig. In choosing a rig, consideration must be given to the expected depth and
diameter of the hole to be drilled, the possible casing requirements, and site access. Rigs
should generally have a minimum ram stroke length of 600 mm, and be able to operate with a
minimum of vibration. The sizes of commonly-used core-barrels, casings and drill rods are
shown in Table 5.
Smaller scale rotary drilling rigs are also available and can sometimes be used to great
advantage in special situations. Hand-portable rotary core drills may often be useful for coring
through existing concrete or masonry retaining walls; horizontal boreholes often enable the wall
thickness and backfill materials to be determined.
Drilling is in part an art, and its success is dependent upon good practice and the skill
of the operator, particularly when coring weathered, weak, partially cemented and fractured
rocks, where considerable expertise is necessary to obtain full recovery of core of satisfactory
quality. This is greatly influenced by the choice of core-barrel and cutting bit type (see
Section 19.8) and by the method of extruding, handling and preservation of the core (see
Section 19.10.5).
employed and suitable for the ground to be drilled is very important. Water is the simplest
flushing medium. Other fluids used as flushing media are drilling muds (which consist of
water with clay or bentonite), water with an additive such as sodium chloride, air foams and
polymer mixtures. The main advantage of these other flushing media is that drill cuttings may
be removed at a lower flushing velocity and with less disturbance to the ground. The use of
drilling mud can also minimise the need for casing of the hole, as it helps to stabilise the sides
and bottom of the hole in caving soils. Another advantage of drilling mud is that it can reduce
soil disturbance and hence improve sample quality. However, drilling mud is not
recommended if permeability tests are to be carried out in the borehole, or if piezometers are to
be installed. Further guidance on the use of drilling mud is given by Clayton et al (1982).
The use of air foam as a flushing medium has enabled increased core recovery and
quality to be achieved in colluvium and soils derived from insitu rock weathering (Phillipson
& Chipp, 1981; 1982). This technique involves the injection of foaming concentrate and
water into the air stream produced by a low volume, high pressure air compressor, as shown
diagrammatically in Figure 12. A polymer stabiliser is added when drilling below the water
table. The foam is forced down the drill rods in the conventional manner, and a slow-moving
column of foam with the consistency of aerosol shaving cream carries the suspended cuttings
to the surface. Compared with water, the air foam has a greater ability to maintain the cuttings
in suspension, and the low uphole velocity and low volume of water utilized serve to reduce
disturbance of the core and surrounding ground. The air foam also resists percolation into
open fissures, and it stabilises the borehole walls. The polymer stabiliser, however, has the
disadvantage of coating the walls of the hole such that insitu permeability testing may not be
representative.
When investigating potentially unstable slopes, or when drilling into failed slopes to
obtain samples from the slip zone, the use of water as the flushing medium may not be advisable
(see Section 18.7.1). Air foam flushing, or in some instances, air flushing should be
considered to reduce the risk of slope movement in such cases.
Inclined holes may be found to deviate in both dip and direction from the intended
orientation (Craig & Gray, 1985). This is particularly common in the vertical plane due to the
weight of the drill rods. Some of the factors which contribute to deviation are :
(a) worn and undersized drill rods, rods much smaller than the
borehole, and overly flexible rods,
containing corestones.
Several instruments are available for measuring borehole orientation or deviation, such
as the Eastman-Whipstock single-shot or multi-shot photographic survey tools, the Pajari
mechanical single-shot surveying instrument and the ABEM Fotobor multi-shot photographic
probe. The function of the Eastman and Pajari tools is to record the orientation of a gimballed
magnetic sphere, by photographic and mechanical means respectively. This precludes the use
of these instruments within steel casings or attached to steel rods, or in areas where other
magnetic disturbances may be anticipated. The ABEM Fotobor records cumulative deflection
measurements photographically within the borehole and it can be used within steel casings.
Multi-shot tools such as the ABEM Fotobor, or the multi-shot version of the Eastman-
Whipstock tool, are useful for undertaking complete borehole surveys, but may be cumbersome
for taking repeated deviation checks during drilling, in which case single-shot tools may be
preferable.
Wash boring utilizes the percussive action of a chisel bit to break up material that is
flushed to the surface by water pumped down the hollow drill rods. In ground which is liable
to collapse, casing may be driven down to support the sides of the borehole, or drilling mud
may be used. The fragments of soil brought to the surface by the wash water are not
representative of the character and consistency of the materials being penetrated, and the
flushing water may disturb the surrounding ground in the same manner as the rotary wash
boring method discussed in Section 18.7. For these reasons, wash boring is seldom used in
Hong Kong.
There are many other methods of boring, which have been developed generally to obtain
maximum penetration speed, e.g. rotary percussive drilling for blast holes and grouting.
When such boreholes are sunk for purposes other than ground investigation, limited
information about ground conditions may be obtained, provided that the boreholes are drilled
under controlled conditions, with measurement of rate of penetration, observation of drilling
characteristics, and sampling of the drilling flushings (Horner & Sherrell, 1977).
One such rotary percussive method is the Overburden Drilling Eccentric method, or
ODEX (Plate 4A), which is based on the principle of under-reaming. During drilling in soil,
83
an eccentric reamer bit swings out and drills a hole larger than the outer diameter of the casing,
which is inserted at the same time as the hole is being advanced. The percussive action may
be provided by either a top hammer or a down-the-hole hammer. When the desired depth has
been reached, the drill rods are rotated in a reverse direction to allow the reamer to be folded in
and the bit to be retracted through the casing, which remains in the hole. Drilling may then
be further extended into rock by replacing the ODEX bit with a normal rock drill bit. This
method is not commonly used in ground investigations as no intact samples are obtained, but it
has been used in Hong Kong to install long horizontal drains in colluvium (Craig & Gray, 1985)
and for drilling through bouldery fill to prove the bedrock profile. It may also be a useful
technique for the location of cavities in karst terrain (Horner & Sherrell, 1977).
Poorly-compacted backfill wil1 cause settlement at the ground surface and can act as a
path for groundwater. The latter effect can cause very serious inconvenience if the backfilled
excavations or boreholes are on the site of future deep excavations, tunnels or water-retaining
structures. It could also lead to the future pollution of an aquifer. For boreholes in dry
ground, it is possible to use compacted soil as a backfill, although the procedure is often
unsuccessful in preventing the flow of water. The best procedure is to refill the borehole with
a cement-based grout introduced at the lowest point by means of a tremie pipe. Cement alone
will not necessarily seal a borehole, on account of shrinkage, and it is often preferable to use a
cement-bentonite grout, e.g. mix proportions about four to one, with no more water added than
is necessary to permit the grout to flow or to be pumped. The addition of an expanding agent
may be necessary. It is possible to compact the backfill of excavations by means of the
excavator bucket or other mechanical means. In some cases, weak concrete may be used, e.g.
to fill a small hole on a steeply sloping face.
84
The main purposes of sampling are to establish the subsurface geological profile in detail,
and to supply both disturbed and undisturbed materials for laboratory testing. The selection
of a sampling technique depends on the quality of the sample that is required and the character
of the ground, particularly with regard to the extent to which disturbance occurs before, during
or after sampling. The principal causes of soil disturbance are listed in Table 6 (Clayton et al,
1982) and are further discussed by Clayton (1984).
It should be borne in mind that the overall behaviour of the ground is often dictated by
planes or zones of weakness which may be present (e.g. discontinuities). Therefore, it is
possible to obtain a good sample of material that may not be representative of the mass.
Because of this, and the frequent need to modify the sampling technique to suit the ground
conditions, very close supervision of sampling is warranted (see Chapter 15). In choosing a
sampling method, it should be made clear whether mass properties or intact material properties
are to be determined (see Section 12.11). The distinction between mass and material
properties is discussed further in Geoguide 3 (GCO, 1988).
There are four main techniques for obtaining samples (Hvorslev, 1948) :
(c) rotary sampling, in which a tube with a cutter at its lower end
is rotated into the ground, thereby producing a core sample
(see Section 19.8),
(d) taking block samples specially cut by hand from a trial pit,
shaft or heading (see Section 19.9).
Samples obtained by techniques (b), (c) and (d) will often be sufficiently intact to enable
the ground structure within the sample to be examined. The quality of such samples can vary
considerably, depending on the technique and the ground conditions, and most will exhibit some
degree of disturbance. A method for classifying the quality of the sample is given in
Section 19.2. Sections 19.3 to 19.9 describe the various sampling techniques and give an
indication of the sample qualities that can be expected. Intact samples obtained by
techniques (b), (c) and (d) are usually taken in a vertical direction, but specially orientated
samples may be required to investigate particular features.
The mass of sample required for various purposes is determined by the character of the
85
ground and the tests that are to be undertaken. Guidance on the mass of soil sample required
for different laboratory tests is given in Table 7.
The sampling procedure should be selected on the basis of the quality of the sample that
is required, and is assessed largely by the suitability of the sample for appropriate laboratory
tests. A classification for soil samples developed in Germany (Idel et al, 1969) provides a
useful basis for classifying samples in terms of quality (Table 9).
In some cases, whatever sampling methods are used, it will only be possible to obtain
samples with some degree of disturbance, i.e. class 2 at best. The results of any strength or
compressibility tests carried out on such samples should be treated with caution. Samples of
classes 3, 4 and 5 are commonly regarded as 'disturbed samples'.
A further consideration in the selection of procedures for taking class 1 samples is the
size of the sample. This is determined largely by the geological structure of the ground, which,
for soil, is often referred to as 'the fabric' (Rowe, 1972). Where the ground contains
discontinuities of random orientation, the sample diameter, or width, should be as large as
possible in relation to the spacing of discontinuities. Alternatively, where the ground contains
strongly orientated discontinuities, e.g. in jointed rock, it may be necessary to take samples
which have been specially orientated. For fine soils that are homogeneous and isotropic,
samples as small as 35 mm in diameter may be used. However, for general use, samples
100 mm in diameter are preferred since the results of laboratory tests may then be more
representative of the mass properties of the ground. In special cases, samples 150 mm and
250 mm in diameter are used (Rowe, 1972).
GEO (2017a) and BSI (1990) give precise details of the mass of soil sample required for
each type of test. Where the approximate number of tests is known, it is a simple matter to
estimate the total amount of soil that has to be obtained. If the programme of laboratory tests
is uncertain, Table 7 gives some guidance on the amount of soil that should be obtained for
each series of tests. Where materials for mineral aggregates, sands and filters are being
considered, details of the size of sample required are given in CS3:2013 (2016).
[Amd GG2/01/2017]
The quality of the sample depends on the technique used for sinking the borehole or
excavation and on whether the ground is dry or wet. When disturbed samples are taken from
below water in a borehole or excavation, there is a danger that the samples obtained may not
be truly representative of the ground. This is particularly the case with granular soils
containing fines, which tend to be washed out of the tool. This can be partly overcome by
placing the whole contents of the tool into a tank and allowing the fines to settle before
86
The following classes of sample can generally be expected from the various methods of
boring and sampling :
Care should be taken to ensure that the sample is representative of the zone or layer
from which it is removed, and has not been contaminated by other materials.
(1) General. Open-tube samplers consist essentially of a tube that is open at one end
and fitted at the other end with means for attachment to the drill rods. A non-return valve
permits the escape of air or water as the sample enters the tube, and assists in retaining the
sample when the tool is withdrawn from the ground. Figure 13 shows the basic details of a
sampler suitable for general use having a single sample tube and simple cutting shoe. The
use of sockets and core-catcher is discussed in Section 19.4.4. An alternative sampler
incorporates a detachable inner liner.
(2) The cutting shoe. The cutting shoe should normally be of a design similar to that
shown in Figure 13 and it should embody the following features :
(c) Area ratio. The area ratio represents the volume of soil
displaced by the sampler in proportion to the volume of the
sample (Figure 13). It should be kept as small as possible
consistent with the strength requirements of the sample tube.
The area ratio is about 30% for the general purpose 100 mm
diameter sampler, and about 10% for a thin-walled sampler.
Some special samplers have a large outside diameter DT,
relative to the internal diameter Dc, e.g. in order to
accommodate a loose inner liner. The sampling disturbance
is reduced by using a cutting shoe that has a long outside
taper, and is considerably less than that which would be
expected from the calculated area ratio.
(3) Wall friction. This can be reduced by a suitable inside clearance, and by a clean,
smooth finish to the inside of the tube.
(4) Non-return valve. The non-return valve should have a large orifice to allow air and
water to escape quickly and easily when driving the sampler, and to assist in retention of the
sample when removing the sampler from the borehole.
Typical designs of open-tube samplers which are used for various purposes are
described in Sections 19.4.3 to 19.4.5.
Before a sample is taken, the bottom of the borehole or surface of the excavation or
heading should be cleared of loose or disturbed material as far as possible. Some or all of
any such loose or disturbed material that is left will normally pass into the 'overdrive' space.
Below the water table, certain types of laminated soils occurring below the bottom of
the borehole or excavation may be disturbed if the natural water pressure in the laminations
exceeds the pressure imposed by the water within the borehole or excavation. To prevent this
effect, it is necessary to keep the level of the borehole water above the groundwater level
appropriate to the location of the sample.
The sampler can be driven into the ground by dynamic means, using a drop weight or
88
sliding hammer, or by a continuous static thrust, using a hydraulic jack or pulley block and
tackle. There is little published evidence to indicate whether dynamic or static driving
produces less sample disturbance, and for most ground conditions it is probable that there is
no significant difference. The driving effort for each sample may be recorded as an indication
of the consistency of the ground.
The distance that the tool is driven should be checked and recorded as, if driven too far,
the soil will be compressed in the sampler. A sampling head with an 'overdrive' space
(Figure 13 will allow the sample tube to be completely filled without risk of damaging the
sample. After driving, the sampler is steadily withdrawn. The length of sample that is
recovered should be recorded, compared with the distance that the tool was driven, and any
discrepancy investigated. For example, if the length of the sample is less than the distance
driven, the sample may have experienced some compression or, alternatively, the sample tool
may have permitted the sample to slip out as the tool was being withdrawn.
Thin-walled samplers are used for soils that are particularly sensitive to sampling
disturbance, and consist of a thin-walled steel tube whose lower end is shaped to form a cutting
edge with a small inside clearance. The area ratio is about 10%. These samplers are
suitable only for fine soils up to a firm consistency, and free from large particles. They
generally give class 1 samples in all fine cohesive soils, including sensitive clays, provided that
the soil has not been disturbed by sinking the borehole. Samples between 75 mm and 100 mm
in diameter are normally obtained; samples up to 250 mm in diameter are often obtained for
special purposes. It should be noted that disturbance at the base of a borehole in weak soil
will occur below a certain depth because of stress relief. Piston samples penetrating well
below the base of the borehole are therefore preferable (see Section 19.5). A typical thin-
walled sampler is illustrated in Figure 14.
The 100 mm diameter open-tube sampler, often termed the U100 sampler (Plate 4B), is
a fairly robust sampler that can be used for many Hong Kong soils, but the driving action during
sampling is likely to introduce some disturbance. The highest sample quality that can be
obtained is class 2 at best (Whyte, 1984).
The details of the sampler is illustrated in Figure 13 and consists of a sample barrel,
about 450 mm in length, with a screw-on cutting shoe and drive head. The area ratio is about
30%. Sample barrels can be coupled together with screw sockets to form a longer sampler.
Two standard barrels, forming a sampler about 1.0 m in length, are often used for sampling soft
clays (Serota & Jennings, 1958), although the increased length of the sample tube may lead to
some disturbance. In soils of low cohesion, such as silt and silty fine sand, the sample may
fall out when the tool is withdrawn from the ground. Sample recovery can be improved by
inserting a core-catcher between the cutting edge and the sample barrel. When using a core-
catcher, the sample quality is unlikely to be better than class 3.
89
The split barrel sampler is used in the standard penetration test and is described in BSI
(2011b). It takes samples 35 mm in diameter and has an area ratio of about 100%. It is used
to recover small samples, particularly under conditions which prevent the use of the general
purpose 100 mm sampler, and gives class 3 or class 4 samples (see Section 21.2 and Figure 25).
[Amd GG2/01/2017]
The thin-walled stationary piston sampler (Plate 4C) consists of a thin-walled sample
tube containing a close-fitting sliding piston, which is slightly coned at its lower face. The
sample tube is fitted to the drive head, which is connected to hollow drill rods. The piston is
fixed to separate rods which pass through a sliding joint in the drive head and up inside the
hollow rods. Clamping devices, operated at ground surface, enable the piston and sample
tube to be locked together or the piston to be held stationary while the sample tube is driven
down. Figure 15 shows the basic details of a stationary piston sampler. The sample
diameter is normally 75 mm or 100 mm, but samplers up to 250 mm diameter are used for
special soil conditions.
Initially, the piston is locked to the lower end of the sample tube to prevent water or
slurry from entering the sampler. In soft clay, with the piston in this position, the sampler can
be pushed below the bottom of the borehole. When the sample depth is reached, the piston is
held stationary and the sample tube is driven down by a static thrust until the drive head
encounters the upper face of the piston. An automatic clamp in the drive head prevents the
piston from dropping down and extruding the sample while the sampler is withdrawn.
The sampler is normally used in low strength fine soils and gives class 1 samples in silt
and clay, including sensitive clay. Its ability to take samples below the disturbed zone and to
hold them during recovery gives an advantage over the thin-walled sampler described in
Section 19.4.3. Although normally used in soft clays, special piston samplers have been
designed for use in stiff clays (Rowe, 1972).
lighter equipment and offers two sizes of sample, is described more fully in Section 19.6.2.
The samples are cut into 1 m lengths and placed in purpose-made cases, samples taken
with a 66 mm sampler being retained in the plastic tubes. The 66 mm samples are suitable for
a range of laboratory tests. The 29 mm samples are used for visual examination and the
determination of bulk density and index properties. After specimens have been removed for
testing, the samples are split and are then described and photographed in a semi-dried state
when the soil fabric can be more readily identified. For 29 mm samples, only one half of the
split material is used for testing, thus preserving a continuous record of the ground.
The recovery of tube samples of sand from below the water table presents special
problems because the sample tends to fall out of the sample tube. A compressed air sampler
(Bishop, 1948) enables the sample to be removed from the ground into an air chamber and then
lifted to the surface without contact with the water in the borehole. The sampler is generally
constructed to take samples 60 mm in diameter. If the sampler is driven by dynamic means,
the change in volume of the sand caused by the driving gives a sample quality not better than
class 3. However, if static thrust is used, generally class 2 and sometimes class 1 samples can
be recovered. An alternative design (Serota & Jennings, 1958) introduces a bubble of air at
the base of the sampler before it is withdrawn from the ground.
Samples are obtained by the rotary core drilling procedures described in Section 18.7.
The quality of sample may vary considerably depending on the character of the ground and the
type of coring equipment used. [Amd GG2/01/2017]
91
Core-barrel sizes commonly used in Hong Kong are given in Table 5, together with the
core sizes produced. Single-tube core-barrels are seldom used, as the core-barrel rotates
directly against the core and core recovery is usually unsatisfactory. Double-tube and triple-
tube barrels are used, with applicability and limitations as follows :
High quality (class 1) core samples of soils derived from insitu rock weathering and
colluvium can be obtained using the large diameter triple-tube core-barrels in conjunction with
air foam as the flushing medium (see Section 18.7.2). Samples of class 1 to class 2 can also
be obtained using the Mazier sampler in conjunction with air foam or water as the flushing
medium.
Block samples are cut by hand from material exposed in trial pits and excavations.
They are normally taken in fill, soils derived from insitu rock weathering and colluvium in order
to obtain samples with the least possible disturbance. The procedure is also used to obtain
specially orientated samples, e.g. to measure the shear strength on specific discontinuities.
The location and orientation of a block sample should always be recorded before the sample is
separated from the ground. Block samples should be taken and handled as described in
Section 19.10.6. More detailed recommendations for block sampling are given in USBR (1974).
Samples may have cost a considerable sum of money to obtain and should be treated
with great care. The usefulness of the results of the laboratory tests depends on the quality of
the samples at the time they are tested. It is therefore important to establish a satisfactory
procedure for handling and labelling the samples, and also for their storage and transport so
that they do not deteriorate, and can readily be identified and drawn from the sample store
when required.
The samples should be protected from excessive heat and temperature variation, which
may lead to deterioration in the sealing of the sample containers and subsequent damage to the
samples. The temperature of the sample store will be influenced by the climate, but it is
recommended that the samples should be stored at the lowest temperature practicable within
the range 2°C to 45°C. The daily temperature variation within the store should not exceed
20°C.
93
19.10.2 Labelling
All samples should be labelled immediately after being taken from a borehole or
excavation. If they are to be preserved at their natural moisture content, they will at the same
time have to be sealed in an airtight container or coated in wax. The label should show all
necessary information about the sample, and an additional copy should be kept separately from
the sample; this latter is normally recorded on the daily field report. The label should be
marked with indelible ink and be sufficiently robust to withstand the effect of its environment
and of the transport of the sample. The sample itself should carry more than one label or
other means of identification so that the sample can still be identified if one label is damaged.
The sample label should give the following information, where relevant :
(g) depth of top and bottom of the sample below ground level,
and
Where samples are required for testing, or where it is desirable to keep them in good
condition over long periods, they should be treated as described below.
Immediately after being taken from a borehole or excavation, the sample should be
placed in a non-corrodible and durable container of at least 0.5 kg capacity, which the sample
should fill with the minimum of air space. The container should have an airtight cover or seal
so that the natural moisture content of the sample can be maintained until tested in the
laboratory. For rock samples, an alternative procedure is to coat the sample in a layer of
paraffin wax. A microcrystalline wax is preferred because it is less likely to shrink or crack.
Large disturbed samples that are required for certain laboratory tests may be packed in robust
containers or plastic sacks.
The sample containers should be numbered, and the tear-off slip or a label, as described
in Section 19.10.2, should be placed in the container immediately under the cover. An
94
identical label should also be securely fixed to the outside of the container under a waterproof
seal (wax or plastics). The containers should be carefully crated to prevent damage during
transit. During the intervals while the samples are on site or in transit to the sample store,
they should be protected from excessive heat.
For hand samples of rock, the reference number should be recorded by painting directly
on the surface of the sample or by attaching a label. Samples should then be wrapped in
several thickness of paper and packed in a wooden box. It is advisable to include in the
wrapping a label of the type described in Section 19.10.2.
The following recommendations are applicable to all samples taken with tube samplers,
except those taken with thick-walled samplers (see Section 19.4.5). The precautions for
handling and protection of samples are to be regarded as a minimum requirement for samples
taken by the usual methods. In special cases, it may be necessary to take more elaborate
precautions. For samples that are retained in a tube or liner, procedure (a) should be followed;
for other samples, procedure (b) should be followed.
(a) Immediately after the sample has been taken from the
borehole or excavation, the ends of the sample should be
removed to a depth of about 25 mm and any obviously
disturbed soil in the top of the sampler should also be
removed. Several layers of molten wax, preferably
microcrystalline wax, should then be applied to each end to
give a plug about 25 mm in thickness. The molten wax
should be as cool as possible. It is essential that the sides
of the tube be clean and free from adhering soil. If the
sample is very porous, a layer of waxed paper or aluminum
foil should be placed over the end of the sample before
applying the wax.
Any remaining space between the end of the tube or liner and
the wax should be tightly packed with a material that is less
compressible than the sample and not capable of extracting
water from it, and a close-fitting lid or screw-cap should then
be placed on each end of the tube or liner. The lids should,
if necessary, be held in position with adhesive tape.
A label bearing the number of the sample should be placed inside the container just
under the lid. The label should be placed at the top of the sample. In addition, the number
of the sample should be painted on the outside of the container, and the top or bottom of the
sample should be indicated. The liners or containers should be packed in a way that will
minimize damage by vibration and shock during transit.
For soft marine soil samples, the tube or liner should be held vertically, keeping the
sample in the same direction as it left the ground, and extreme care should be taken during all
stages of handling and transportation.
After recovery of the core-barrel to the surface, every effort should be made in
subsequent handling to ensure that, as far as possible, the quality of the core is maintained in
its natural state until it is finally stored.
Except in relatively strong and massive rocks, core is almost inevitably disturbed if it is
removed from the barrel held in a vertical position and then placed into the core box. The
barrel should be held in a horizontal position, and the core extruded into a tray in such a
manner that it is continuously supported. Rain-water guttering or other conveniently
available rigid split tube can be used for this purpose. When it is required to preserve the core
such that it does not dry out, a convenient method is to extrude it from the core-barrel into
sleeving formed of thin-gauge polyethylene, again supporting the core with rigid split tube.
Where selected lengths of core are to be preserved at their natural moisture content for
laboratory testing, any drilling mud contamination and softened material should first be
removed; the sample should then be wrapped in foil, coated with successive layers of waxed
cheese cloth and labelled as described in Section 19.10.2.
In the extrusion process, the core should preferably be extruded in the same direction as
it entered the barrel. Extruders should be of the piston type, preferably mechanically activated,
since water-pressure type extruders can lead to water contact with the core, and to damage by
impulsive stressing of the core. It should be noted that in weak, weathered or fractured rocks,
extrusion can lead to core disturbance, however carefully it is done. The use of a low-friction
transparent plastic liner in the inner tube of a modified conventional double-tube swivel core-
barrel overcomes the majority of the problems encountered in core extrusion, and facilitates
preservation of the core in the condition in which it is recovered. The general practice is to
tape the outside of the sleeved core every 200 mm, and lengthwise along the overlap in the
plastic sheet, and then, with the aid of plastic guttering for extra support, the core can be boxed
without too much disturbance to the fabric. However, the presence of abrasive and fractured
rocks may preclude the use of such liners.
The difficulties of extrusion and preservation can be overcome by the use of triple-tube
core-barrels with low-friction liners (see Section 19.8). Split liner tubes are an ideal method
of examining the recovered core without further damage after the drilling process. On the
other hand, seamless metal liners and plastic liners are particularly useful where core is to be
96
removed from site for logging or where confined, undisturbed samples are required for sample
preservation and subsequent laboratory testing.
It is usual to preserve all core obtained from the borehole for the period of the main
works contract to which the core drilling relates. This is conveniently achieved with wooden
or plastic core boxes, usually between 1 m and 1.5 m in length and divided longitudinally to
hold a number of rows of core. The box should be of such depth and the compartments of such
width that there is minimal movement of the cores when the box is closed (Geological Society,
1970). The box should be fitted with a hinged lid and strong fastener, and should be designed
so as not to be too heavy for two persons to lift when the box is full of core.
In removing the core from the barrel and placing it in the box, great care should be taken
to ensure that the core is not turned end for end, but lies in its correct natural sequence.
Depths below ground surface should be indicated by an indelible marker on small spacers of
core diameter size that are inserted in the core box between cores from successive runs. Where
there is failure to recover core, or where specimens of recovered core are removed from the box
for other purposes, this should be indicated by spacing-blocks of appropriate length. Both the
lid and the box should be marked to show the site location, borehole number and range of depth
of the core within the box, in addition to the number of the box in relation to the total sequence
of boxes for that borehole. Core box marking should be done so as to facilitate subsequent
photography which, if required, should be carried out as soon as is practicable after recovery
of the core, and before description, sampling and testing.
Sample cutting should be carried out as quickly as possible to prevent excessive moisture
loss, and the sample should be protected from rain and direct sunlight. The sample should be
trimmed to size in plan while still connected at its base (Plate 5A). The sides should be
protected with aluminium foil or grease-proof paper, and then coated with a succession of layers
of microcrystalline wax, reinforced with layers of porous fabric (e.g. muslin), if required. A
close-fitting box with the top and bottom lids removed should then be slid down over the sample
(Plate 5B). The top of the sample should be trimmed flat, marked with location and orientation,
coated as described above, and the top lid attached to the box, ensuring a close fit. The sample
may then be cut along its base, and turned over slowly and carefully for trimming and coating
of the bottom prior to attachment of the bottom lid. A strong, rigid, close-fitting box is
required to minimize sample disturbance during transport and to prevent discontinuities from
opening.
97
20. Groundwater
20.1 General
The determination of groundwater pressures is of the utmost importance since they have
a profound influence on the behaviour of the ground during and after the construction of
engineering works. There is always the possibility that various zones, particularly those
separated by relatively impermeable layers, will have different groundwater pressures, some of
which may be artesian. The location of highly permeable zones in the ground and the
measurement of water pressure in each is particularly important where deep excavation or
tunnelling is required, since special measures may be necessary to deal with the groundwater.
For accurate measurement of groundwater pressures, it is generally necessary to install
piezometers. The groundwater pressure may vary with time owing to rainfall, tidal, or other
causes, and it may be necessary to take measurements over an extended period of time in order
that such variations may be investigated. When designing drainage works, it is normally
desirable to determine the contours of the water table or piezometric surface to ascertain the
direction of the natural drainage, the seasonal variation and the influence of other hydrological
factors.
The monitoring of groundwater levels and pore pressures, and their response to rainfall,
is carried out routinely in Hong Kong, as this information is vital to the design and construction
of slopes, excavations in hillsides, and site formation works. The choice of piezometer type
depends on the predicted water pressures, access for reading, service life and response time
required. Open-hydraulic (Casagrande) piezometers are often used in soils derived from insitu
rock weathering and colluvium, which are generally relatively permeable. Other piezometer
types may be used for specific projects; the available types are described in Sections 20.2.3 to
20.2.6, and their advantages and disadvantages are summarized in Table 10.
Slope failures in Hong Kong are normally triggered by rainstorms. The response of
the groundwater regime to rainfall varies widely from site to site, ranging from virtually no
response to a large immediate response. The measurement of transient response is therefore
very important (see Section 20.2.8). In order to provide design data, groundwater monitoring
should extend over at least one wet season; this wet season should ideally contain a storm that
has a return period of greater than ten years. For site formation works which involve
substantial modifications to the hydrogeological characteristics of the site, the period of
monitoring may need to be extended to beyond the end of the site formation works. Ground
conditions in Hong Kong may produce perched or multiple water tables which must also be
considered when installing and monitoring piezometers (Anderson et al, 1983).
It may also be necessary to measure negative pore water pressures, or soil suction (see
Section 20.2.9). In many cases, existing groundwater data in the vicinity of the site will be
available in the Geotechnical Information Unit (see Section 4.2), and may be useful in planning
an appropriate groundwater monitoring scheme.
analysis of groundwater and related interpretation techniques such as trilinear plotting of cation
and anion contents are given in ICE (1976).
Borehole permeability tests are described in Section 21.4, packer, or Lugeon, tests are
described in Section 21.5 and large-scale pumping tests are described in Chapter 25.
All the methods described in Section 20.2 require some flow of water into or out of the
measuring device before the recorded pressure can reach equilibrium with the actual
groundwater pressure. For an excavation or a borehole, a large volume of water may flow
before the water level reaches equilibrium with the groundwater pressure. On the other hand,
some types of piezometer require only a very small change in volume of water in order that the
groundwater pressure may be read. The rate at which water flows through the soil depends
on the permeability. The time required for a measuring device to indicate the true
groundwater pressure is known as the response time and depends on the quantity of water
required to operate the device ('volume factor'), the 'shape factor' of the piezometer (Brand &
Premchitt, 1980), the permeability of the porous element, and the permeability of the ground.
The selection of a suitable method for measuring the groundwater pressure will largely be
determined by the response time (Penman, 1986).
The main advantages of an open-hydraulic piezometer are its simplicity and reliability.
Also, water can be pumped down the pipe to flush out blockages. Moreover, it can be used to
determine the permeability of the ground in which the tip is embedded (see Section 21.4). Its
main disadvantage is slow response time in soils of low permeability.
diameter plastic tubes to a remote point, where the pressure is measured, usually with a mercury
manometer, Bourdon gauge or pressure transducer. Air in the tubes will cause erroneous
readings, and because of this the tubes must be kept full of water and routinely de-aired.
Various types of hydraulic piezometers are available, the most common being the twin-
tube types shown in Figure 20. In these piezometers, the tip is connected to the measuring
point by two tubes, so that water can be circulated to flush out any air bubbles. This should
be done in such a way that the pressure in the tip is left approximately at working pressure.
In order to avoid cavitation, the measuring point and connecting tubes should not be
more than 7 m above the piezometric level being measured (Penman, 1978). Hydraulic
piezometers are not self de-airing and regular maintenance is required for satisfactory
performance. The hydraulic leads facilitate remote reading, and the measuring point can be
separated laterally from the piezometer tip by fairly long distances.
A closed-hydraulic piezometer has a small response time and can be used for measuring
rapid changes in pore water pressure due to rainfall infiltration, pressure changes due to tidal
variation or to changes of stress induced by superimposed loads or excavations. It can also
be used for insitu measurements of permeability. In zones of high permeability, care should
be taken to see that the limiting permeability of the porous tip is considered.
Electrical piezometers have a pressure transducer located close to the porous element.
Very rapid response times can be achieved provided the tip is de-aired. Where long term
stability is required, or the signal is to be transmitted over a long distance, the transducer is
usually of the vibrating wire type. The main disadvantage of the electrical piezometer is that
it requires calibration, which cannot be checked easily after installation. It should be noted
that some transducers have temperature-sensitive elements, so that check calibrations should
be carried out at groundwater temperature. Moreover, it is not always easy to check that the
instrument is behaving reliably. De-airing is not possible after installation, and misleading
results can be obtained, particularly in unsaturated soils or soils containing gas, e.g. methane
in organic soils. The electrical piezometer cannot be used for insitu permeability
measurements (Penman, 1960).
Pneumatic systems comprise two air-filled tubes connecting the measuring point to a
valve located close to the porous element. When the air pressure in the input line equals the
water pressure in the porous element, the valve operates, thereby holding constant the pressure
either in the return line or in the supply line. The operation of the valve requires a small
volume change in the porous element, and in impermeable clays this can lead to difficulties.
Also, dirt entering the lines can prevent valve operation. The pneumatic piezometer is cheap
and easy to install and has a rapid response. It cannot be used for insitu permeability
101
The success of pore water pressure measurement depends upon the care taken during
installation and sealing of the piezometer or standpipe. The porous element should be fully
saturated and filled with de-aired water before installation.
In soft ground, the porous element can often be pushed or driven into position. It is,
however, necessary to avoid clogging the porous element if it is pushed through soft clays.
This can be achieved by using a drive-piezometer which has a removable sleeve that covers the
element during driving (Parry, 1971). In clay, a pushed or driven piezometer shears and
remoulds the clay, destroys the fabric in the clay adjacent to the porous element, and can lead
to erroneous measurements of insitu permeability. It should also be noted that the action of
pushing or driving may set up high excess pore-pressures, which in soils of low permeability
may take a long time to dissipate. In harder ground, the instrument is installed in a borehole
with the porous element surrounded by well-graded sand. Above the sand, the borehole
should be sealed off, preferably with grout.
Bentonite should be used to provide a seal above the sand pocket, and if the piezometer
has not been installed near the base of the borehole, a bentonite seal should also be placed
beneath the sand pocket. The length of bentonite seals is typically 0.5 m, although longer
seals may be preferable, especially on the upper side of the piezometer. Bentonite balls
approximately 25 mm in diameter, formed from powdered bentonite and water, may be used to
form the seals. An alternative is to use compressed bentonite pellets, in which case sufficient
time should be allowed for the swelling action of the pellets to occur before grout is placed on
top of the seal.
The remaining sections of the borehole, both above the upper seal and beneath the lower
seal (if applicable), should be filled with a cement-bentonite grout of the same or lower
permeability than the surrounding soil. A tremie pipe should be used to place the grout. The
volume of grout used should be compared with the volume of the hole to be grouted.
The composition of the grout mix will depend on a variety of factors, such as the
availability of materials, the required permeability, the type and make of bentonite, the
102
condition of the borehole and the groundwater levels. The grout should be easily pumped, of
the required permeability, and flexible. The constituents should not segregate while the grout
is still liquid. A typical mix might be four parts of bentonite mixed thoroughly with eight to
twelve parts of water, to which is added one part of ordinary Portland cement. Special mixes
and chemical additives may be necessary if the grout is to be used in sea water or very acid
water.
Poor sealing of the piezometer will permit the migration of water from one level to
another, and may render the readings meaningless. The installation of more than one
piezometer in a single borehole is not generally recommended. If two piezometers are placed
in a single hole, great care must be taken to achieve proper seals.
In addition to varying response to rainfall, water pressures may show seasonal variation,
response to tidal changes or may be affected by abstraction from neighbouring wells or by other
causes. Where it is important to take account of these effects, adequate periods of observation
should be adopted.
might typically be placed at 0.5 m intervals within the range of 2 m both above and below the
critical groundwater level assumed in the design. A typical data sheet is shown in Figure 24.
Care should be taken when handling the string to ensure that it does not drop into the borehole
(thus rendering the piezometer useless), or that it does not tangle and reduce the spacing
between the buckets.
An electronic pressure transducer and "Scanivalve" have been used for automatic
recording of a number of piezometers (Pope et al, 1982). Functioning of the system may be
controlled by a microprocessor, allowing variation in the number of piezometers read, the dwell
time on each piezometer, and the interval time between readings.
Measurement of matric soil suction, or negative pore water pressure, in the range 0 to
-80 kPa can be undertaken in the field with tensiometers. A high air entry pressure ceramic
tip allows equilibrium to be achieved between soil moisture and a confined reservoir of water
within the tensiometer. A vacuum gauge is located at the top of the tensiometer. At suctions
greater than -80 kPa, water inside the tensiometer cavitates and is lost through the ceramic tip.
An example of a tensiometer is shown in Plate 6C.
The pressure exerted by the column of water within the tensiometer must also be
considered; for example, if the tip were located 1.5 m vertically beneath the gauge, the
maximum soil suction that could be measured would be reduced to -65 kPa. When suction
measurements are required at greater depths, a caisson may be excavated and tensiometers
installed through the sides of the caisson (Sweeney, 1982). The reliability of a tensiometer
depends on a good contact between the soil and the ceramic tip, and a good seal between the
tensiometer tube and the soil.
For measurement of soil suctions beyond the range of tensiometers, psychrometers may
be used (Richards, 1971), although their accuracy is doubtful. The measurement of soil
suction in Hong Kong slopes has been reviewed by Anderson (1984).
Care should be taken to ensure that samples are representative of the water-bearing zone
from which they have been taken and that they have not been contaminated or diluted by surface
water or water used for boring. Water samples should be taken as soon as possible after the
water-bearing zone has been met in the borehole. If other water-bearing zones occur at higher
levels, these should be sealed off by the borehole casing. As far as is possible, all the water
in the borehole should be removed by pumping or baling, and the sample taken from water
104
which collects by seepage. About one litre should be collected in a clean glass or inert plastic
bottle, rinsing the bottle three times with the water being sampled before filling. More
stringent requirements may apply in certain cases, e.g. use of sterilized containers (see
Chapter 13). Even when precautions are taken, water samples from boreholes may be
unrepresentative. Better results can be obtained if samples can be taken from a standpipe
piezometer sealed within the relevant zone. Water samples may deteriorate rapidly and should
therefore be tested as soon as possible after sampling.
105
This chapter describes various tests that may be conducted as supplementary to a ground
investigation carried out by boreholes. The tests described are generally undertaken as an
integral part of the drilling operation. Additional field tests are described in Chapters 24 to
33, and include some tests which can also be conducted in boreholes. The division of the
subject matter has been somewhat arbitrary; therefore, where coverage of a particular test is not
given in this chapter, it should be sought in later chapters.
The standard penetration test is a frequently used dynamic penetration test and is
described in BSI (2011b). A small disturbed soil sample (quality class 3) is normally obtained
when the split barrel sampler is used (Figure 25 and Plate 7A). The test results have been
related empirically to soil parameters and foundation conditions, especially in sands and gravels.
[Amd GG2/01/2017]
Minor variations from the specified equipment and procedures can seriously affect the
results of the test (De Mello, 1971; Ireland et al, 1970; Nixon, 1982; Skempton, 1986). It is
important that the test is carried out precisely as described in BSI (2011b), except that the
following modifications should be incorporated : [Amd GG2/01/2017]
[Amd GG2/01/2017]
It is necessary to clean out the bottom of the borehole. When the test is carried out
below the groundwater level, certain types of soil may be loosened below the base of the
borehole by the action of the boring tools and by pressure differences between the groundwater
and water in the borehole. This effect can be particularly severe in sands. The effect can be
reduced by keeping the borehole topped up with water and by very careful operation of the
boring tools but often these expedients will not be completely successful.
106
The drill casing should not be advanced ahead of the borehole where a standard
penetration test is to be performed.
The great merit of the test, and the main reason for its widespread use, is that it is simple
and inexpensive. The soil strength parameters which can be inferred are very approximate,
but give a useful guide in ground conditions where it may not be possible to obtain borehole
samples of adequate quality, e.g. gravels, sands, silts, clay containing sand or gravel and weak
rock. In conditions where the quality of the 'undisturbed' sample is suspect, e.g. very silty or
very sandy clays, or hard clays, it is often advantageous to alternate the sampling with standard
penetration tests, thereby obtaining a check on the strength. If the samples are found to be
unacceptably disturbed, if may be necessary to use a different method for measuring strength,
e.g. the plate test described in Sections 21.6 and 29.1.
When the test is carried out in granular soils below groundwater level, the soil may
become loosened, even when the test is carried out in strict accordance with BSI (2011b) and
the borehole has been properly prepared. In certain circumstances, it can be useful to
continue driving the sampler beyond the distance specified, adding further drill rods as
necessary. Although this is not a standard penetration test, and should not be regarded as
such, it may, at least, give an indication as to whether the deposit is really as loose as the
standard test may indicate. When there is good reason to believe that unrealistically low
values are being recorded, consideration should be given to the use of some other test which
can be performed independently of a borehole, e.g. the cone penetration test described in
Section 23.3. [Amd GG2/01/2017]
When the test is carried out in soils derived from insitu rock weathering in Hong Kong,
it is commonly extended to high blow counts, sometimes in excess of 200. However, it is
recommended that the test should be discontinued when the blow count reaches 100 or if the
hammer bounces and insignificant penetration is achieved, as is frequently the case when
corestones are encountered. If the test is curtailed due to hard driving, the number of blows
used to achieve the actual penetration should be measured and recorded (e.g. Blow/Penetration
= 100/80 mm), and this may be used to estimate the blow counts for 300 mm penetration.
In the construction of bored piles, the test is sometimes carried out in boreholes
considerably larger in diameter than those used for ground investigation work. The result of
the standard penetration test is dependent upon the diameter of the borehole, and these tests
should not be regarded as standard penetration tests. They may, however, provide useful
information to a piling contractor, particularly if he has considerable experience in their use.
The resulting N value is defined as the number of blows required to drive the standard
split spoon sampler a distance of 300 mm. The sampler is initially driven 150 mm to penetrate
through any disturbed material at the bottom of the borehole before the test is carried out. The
number of blows required for each 75 mm advance in the initial seating drive should be recorded;
107
the test may then proceed, with recording of the number of blows required for each 75 mm
incremental advance of the test drive.
When the test is used in soils derived from insitu rock weathering, it should be noted
that the empirical relationships developed for transported soils between N value and foundation
design parameters, relative density and shear strength may not be valid. Corestones, for
example, can be responsible for misleadingly high values that are unrepresentative of the mass.
In view of this, the test should only be used to give a rough indication of relative strength in
these soils, or to develop site-specific correlations.
A cruciform vane on the end of a solid rod is forced into the soil and then rotated
(Figure 26). The torque required to rotate the vane can be related to the shear strength of the
soil. The method of carrying out the test is described in BSI (1990). Vanes can take the form
of borehole vanes or penetration vanes, the latter being much more reliable. The test can be
extended to measure the remoulded strength of the soil. This is done by turning the vane
through ten complete rotations. A pause of not more than one minute is permitted to elapse
and the vane test is then repeated in the normal way. The degree of disturbance caused by
rotating the vane differs from that obtained by remoulding a sample of clay in the laboratory,
and the numerical value of the sensitivity of the clay determined by these procedures is not
strictly comparable with the results obtained from laboratory triaxial tests.
[Amd GG2/01/2017]
The test is normally restricted to fairly uniform, cohesive, fully-saturated soils, and is
used mainly for clay having an undrained shear strength of up to about 75 kPa. The results
are questionable in stronger clays, or if the soil tends to dilate on shearing or is fissured.
In Hong Kong, the vane test is invaluable in the marine sediments (Fung et al, 1984;
Handfelt et al, 1987). However, some strata are sandy or contain shells, in which case vane
shear results should be interpreted with caution. Marine muds are generally very soft, and it
is often necessary to provide a separate support frame on top of the seabed to carry out the vane
test (see Section 14.7).
It should be noted that the undrained shear strength determined by an insitu vane test is,
in general, not equal to the average value calculated at failure in the field, e.g. in the failure of
an embankment on soft clay. The discrepancy between field and vane shear strengths
generally increases as the clay becomes more plastic (Bjerrum, 1973).
The main advantage is that the test itself causes little disturbance of the ground. This
is particularly apparent in sensitive clays, where the vane test tends to give higher shear
strengths than those derived from laboratory tests on samples obtained with the general
purpose sampler described in Section 19.4.4. In these conditions, the vane test results are
108
generally considered to be much more reliable. If the test is carried out in soil that is not
uniform and contains even thin layers of laminations of sand or dense silt, the torque may be
misleadingly high. The presence of rootlets in organic soils, and also of coarse particles, may
lead to erroneous results.
With the penetration vane test apparatus (vane borer) described in BSI (1990), the vane
and a protective casing (Plate 8) are forced into the ground by jacking. At the required depth,
the vane is advanced a short distance ahead of the protective casing, the test is conducted, and
the casing and vane are then subsequently advanced to the next required depth. However, with
this type of test it is not always possible to penetrate to the desired layer without the assistance
of pre-boring. [Amd GG2/01/2017]
Small hand-operated vane test instruments are available for use in the sides or bottom of
an excavation. These devices can also be used on samples, with tests done either in the field
or in the laboratory. The results thus obtained are generally adequate for the purpose of
classifying the consistency of cohesive soils (GCO, 1988). Comparative hand vane tests
carried out in both the field and laboratory may provide an indication of possible disturbance
during handling and transportation of the sample.
In the simplest form of test, preparation consists of cleaning out the bottom of the
borehole. The test is then conducted by measuring the rate of flow of water out of the borehole
into the soil, or vice versa, through the open end of the casing. The borehole may be extended
beyond the bottom of the casing, thus increasing the surface through which water can flow. If
necessary, the uncased part of the borehole is supported by a suitable filter material. Water
leaking through the casing joints has at times been found to cause misleading results and the
problem has been overcome by the use of fibre rings.
109
Misleading results can also arise if any return flow occurs up the outside of the casing.
Permeability tests can be carried out at various depths in the borehole as drilling
progresses. Figure 27 shows a suitable test arrangement.
Measurements of water level taken soon after cessation of drilling usually do not
represent equilibrium values, and a series of measurements may be necessary. If a piezometer
is finally installed in the borehole, the piezometric data obtained from monitoring may provide
a check on the measurements taken at the time of the test.
The period required for constant-head tests is decreased and the interpretation
simplified if short lengths of borehole are used for the test. Pore pressures should be in
equilibrium before the test is performed, and with clays of low permeability it can take several
months for the pore pressures set up by the drilling of the borehole to equalize. For soils
derived from insitu rock weathering and colluvium, equalization typically occurs very much
faster.
The first operation is either to fill the piezometer tube with water (falling-head test) or
to force the water level down by a foot-pump or bicycle pump (rising-head test). The head in
the borehole is then allowed to equalize with that in the ground, the actual head being measured
at intervals of time from the commencement of the test. The depth of the borehole should be
checked to determine whether any sediment has come out of suspension or whether the bottom
of the borehole has heaved during the test period.
adjusted until a constant head is achieved and, in the simplest form of test, flow is allowed to
continue until a steady rate of flow is achieved. In some ground, this may take a long period
of time, and, in such cases the method suggested by Gibson (1963) may be used, in which the
actual rate of flow is measured and recorded at intervals from the commencement of the test.
There are numerous published formulae for calculating permeability from these tests,
many of them partly empirical. Those given by Hvorslev (1951), which are reproduced in
outline in Section 21.4.6, are much used and cover a large number of conditions. They are
based on the assumption that the effect of soil compressibility is negligible. The method given
in Gibson (1963) for the constant-head test is also indicated. This gives a more accurate result
with compressible soils.
It must be emphasized that the formulae given in Section 21.4.6 are steady-state
equations suitable for calculation of permeability when the test is carried out below the water
table. In Hong Kong, it is often necessary to measure permeability above the water table. In
this case, the steady-state equations can only be used if the time over which the test is conducted
becomes very long. Under these circumstances, permeability should be assessed using the
constant-head test interpreted according to Method 2 in Section 21.4.6(2), with Hc measured
from the centre of the response zone in the test.
q
k (Time lag analysis ) .............................................. (1)
FH c
A
k ............................................................ (2)
FT
or
It should be noted the above formulae assume that the natural groundwater level
remains constant throughout the test. For the case where the natural groundwater varies, see
Hvorslev (1951).
q ........................................................... (4)
k
FH c
2
q r 2
C ......................................................... (5)
n 2
For most types of ground, field permeability tests yield more reliable data than those
carried out in the laboratory, because a larger volume of material is tested, and because the
ground is tested insitu, thereby avoiding the disturbance associated with sampling. The
appropriate choice of drilling method and careful drilling technique are necessary to avoid
disturbing the ground to be tested. In granular soils, the ground may be loosened below the
112
bottom of the borehole; in layered deposits of varying permeability, a skin of remoulded mixed
material may be formed on the walls of the borehole, thus blocking the more permeable layers;
in jointed rock, the joints may be blocked by the drilling debris.
In very soft marine clays, it is very difficult to carry out a successful permeability test
because of the low permeability of the soil, its compressibility, and the possibility of hydraulic
fracture arising from the relatively large head required for a falling-head or constant-head test.
Constant-head tests are likely to give more accurate results than variable-head tests, but,
on the other hand, variable-head tests are simpler to perform. The water pressure used in the
test should be less than that which with disrupt the ground by hydraulic fracturing. It has
been shown that serious errors may be introduced if excessive water pressures are used
(Bjerrum et al, 1972). In general, it is recommended that the total increase in water pressure
should not exceed one half the effective overburden pressure. With soils of high permeability,
greater than about 10-3 m/s, flow rates are likely to be large and head losses at entry or exit and
in the borehole may be high. In this case, field pumping tests, where the pressure distribution
can be measured by piezometers on radial lines away from the borehole, will probably yield
more accurate results; these are described in Chapter 25. When the test is carried out within
a borehole using the drill casing, the lower limit of permeability that can be measured reliably
is determined by the watertightness of the casing joints and by the success achieved in sealing
the casing into the ground. In soil, the reliable lower limit is about 10-8 m/s. In lower
permeability soils and unweathered rock, it is advisable to carry out the test using a standpipe
or piezometer which is sealed within the test length using grout. In ground of low permeability,
the flow rate may be very small, and measurements may be subject to error owing to changes
in temperature of the measuring apparatus.
The compressibility is influenced in a similar way, and this may affect the results
achieved. The accuracy with which the coefficient of permeability may be deduced from
variable-head tests decreases with the coefficient of consolidation of the soil being tested. In
principle, the coefficient of consolidation or swelling may be deduced from the results of both
constant-head and variable-head tests. In practice, results of only limited accuracy can be
obtained, owing to difficulties in interpretation and the extent to which the stress history of the
soil adjacent to the borehole is modified by the installation of the borehole.
Execution of the borehole permeability test requires much expertise, and small faults in
technique lead to errors of up to one hundred times the actual value. Even with considerable
care, an individual test result is often accurate to one significant figure only. Accuracy will
usually be improved by analysing the results of a series of tests. However, in many types of
113
ground, particularly stratified soil or jointed rock, there may be a very wide variation in
permeability, and the permeability of the mass of ground may be determined by a relatively thin
layer of high permeability or a major joint. Very considerable care is needed in interpreting
the test data. In cases where a reliable result is required, the programme of borehole
permeability tests is generally followed by a full-scale pumping test (see Chapter 25).
The packer or Lugeon test gives a measure of the acceptance by insitu rock of water
under pressure. The test was originally introduced by Lugeon (1933) to provide an acceptable
standard for testing the permeability of dam foundations. In essence, it comprises the
measurement of the volume of water that can escape from an uncased section of borehole in a
given time under a given pressure. Flow is confined between known depths by means of
packers, hence the more general name of the test. The flow is confined between two packers
in the double packer test, or between the packer and the bottom of the borehole in the single
packer test. The test is used to assess the amount of grout that the rock will accept, to check
the effectiveness of grouting, to obtain a measure of the amount of fracturing of the rock (Snow,
1968), or to give an approximate value of the permeability of the rock mass adjacent to the
borehole.
The results of the test are usually expressed in terms of Lugeon units. A rock is said to
have a permeability of 1 Lugeon if, under a head above groundwater level of 100 m, a 1 m
length of borehole accepts 1 litre of water per minute. Lugeon did not specify the diameter of
the borehole, which is usually assumed to be 76 mm (N size), but the test is not very sensitive
to change in borehole diameter unless the length of borehole under test is small.
When the packer test is carried out at shallow depths, as is frequently the case in Hong
Kong, the applied water pressure must be limited to a value that will not cause hydraulic
fracturing of the ground (see Section 21.5.3). This often leads to the test being conducted at
pressures of 50 to 500 kPa, and extrapolation is then necessary to obtain the Lugeon value
equivalent to a 100 m water head (approximately 1 MPa pressure).
If the rock discontinuity spacing is sufficiently close for the test section to be
representative of the rock mass, a mass permeability can be calculated as described in
Section 21.5.6. A simple rule that is sometimes used to convert Lugeon values into mass
permeability is to take one Lugeon as equal to a permeability of 10-7 m/s.
As the packer test is used to assess the potential for water to penetrate rock
discontinuities, clean water should be used as the drilling fluid when forming the borehole,
rather than drilling mud. If drilling mud has been used, the hole should be thoroughly flushed
out prior to packer testing; appropriate explanatory notes should also be given with the test data.
In situations where only salt water is available to conduct the test, this should also be clearly
indicated on the test results.
114
21.5.2 Packers
Several types of packer are in use, such as the mechanical tail pipe, the manual
mechanical-expanding packer and the hydraulic self-expanding packer, but by far the most
commonly used is the pneumatic packer.
This comprises a rubber canvas duct tube which can be inflated against the sides of the
borehole by means of pressurized gas (Figure 31). Bottled nitrogen or oxygen is fed down the
borehole through a small diameter nylon tube. The inflation pressure has to be sufficient to
expand the packer against the head of water in the borehole, but not sufficient to cause heaving
of the ground surface or fracturing of the rock. A useful rule of thumb is that the pressure, in
kPa, should lie between 12 times and 17 times the depth, in metres, of the borehole. The
difference between the diameter of the uninflated packer and the diameter of the borehole
should be such that the packer can be easily inserted. At the same time, the inflated diameter
of the packer should be sufficient to provide an efficient seal. A double packer is two packers
connected by a length of pipe of the same length as the test section. The test water is
introduced between the packers.
Water pressure is applied by a flush pump as used for diamond bit core drilling. The
maximum water pressure which should be applied should not be sufficient to cause uplift of the
ground or to break the seal of the packers in deep holes in weak rock. The standard head of
100 m above groundwater level may not be attainable in these conditions.
The applied pressure should not exceed overburden pressure at the test depth, and it may
be necessary to keep the pressure well below the overburden pressure, as under some
circumstances vertical cracks can develop in weak rocks at pressures much lower than this value.
Excessive pressure may be detectable by careful analysis of the test data, e.g. an abrupt change
of slope in a graph plot of applied water pressure versus flow rate may indicate possible
hydraulic fracture during the test.
The pressure to be determined for use in the calculation of permeability is that causing
flow into the rock itself. This is sometimes measured directly, but it is more usual to measure
it at ground level by means of a Bourdon gauge, with the readings adjusted in accordance with
the following expression :
where h is the pressure head causing flow into the rock (m),
P is the Bourdon gauge reading converted to head (m),
H is the height of Bourdon gauge above the mid-point of test section (m),
Hg is the height of natural groundwater level above the mid-point of test section
(m),
Hf is the friction head loss in the pipes (m).
115
The pressure gauge should be positioned so that it will give a true reading without
interference from local pressure variations induced by flow through the pipe work. The
natural groundwater level should be measured before the test begins. This is not always easy,
especially when the rocks are of low permeability, and water has been used for flushing
purposes during drilling. If necessary, separate observation wells should be installed, and the
groundwater levels should be measured over a period to establish the general groundwater
level. Friction head loss in the pipes is best established by means of a calibration test, with
the pipe work laid out on the ground.
Calibration must be carried out for each test arrangement (pump, packer, valves and by-
pass, pressure gauge and flowmeter) with various lengths of drill rods and varying flow rates.
All pressure gauges and flow meters used in the test should be calibrated regularly.
Flowmeters are prone to inaccuracies, especially at low flow rates, and calibrations
should therefore be carefully checked on site. Industrial water meters commonly available in
Hong Kong are not sufficiently accurate for use in the packer test. For very low flows, a
rotameter board with a series of graduated tubes can provide an accurate measurement of flow
rate, as can an orifice plate meter.
The test may be carried out either as a single or as a double packer test. The single
packer test is generally to be preferred because any leakage past the packer can be detected,
whereas leakage past the lower packer in the double packer test cannot. However, the single
packer test normally has to be done periodically during the drilling of the hole, which makes it
more costly. An important point is to ensure that the packer is properly seated in the borehole.
Where a complete core has been recovered from the borehole, or where appropriate logging or
television inspection has been carried out, a careful examination may reveal suitable places to
seat the packer. Where the seating proves unsatisfactory, the length of the test section should
be altered or test sections overlapped, so as to seat the packer at a different depth in the
borehole.
While the number of packer tests carried out in a borehole depends on the requirements
of the project, it is usual to test the whole length of the borehole that is in rock. However, the
116
upper limit of testing may be constrained by the highest level at which a packer can be sealed
satisfactorily. Typically, overlapping tests are used, each having a test section length of 3 to
6 m. In any case, the test section length should not be less than ten borehole diameters so as
to minimise end effects.
It is customary to run a staged test at each location, using different pressures. A five-
stage test is desirable, with the maximum pressure applied in three equal increments and then
reduced with decrements of the same amount (Figure 32). The data obtained from these
measurements are particularly useful in assisting in the interpretation of the behaviour of the
rock under test.
The water level in the borehole above the packer should be observed during each test,
as a rising level may indicate that leakage is occurring around the upper packer.
The varying values of pressure and flow recorded during the test may be plotted as
shown in Figure 33. The interpreted Lugeon value, L, is given by the formula :
Where a test has been conducted at pressure heads considerably less than the standard
100 m head, the Lugeon value may be somewhat over-estimated by the above formula, due to
possible differences in energy loss between laminar flow (at low head) and turbulent flow (at
high head). Further considerations on test interpretation are given by Houlsby (1976).
The plate test is one particular application of the vertical loading test, and the general
procedures for the test are described in Section 29.1. Only the specific problems which arise
from carrying out the test in the bottom of a borehole are discussed in this Section. Wherever
practicable, the test should be conducted in a borehole which is of sufficient diameter for a
technician to enter, clean out the bottom, and bed the plate evenly on undisturbed ground.
Careful attention should be directed towards safety for operators working below ground (see
Section 18.2 and Appendix E). Where, for reasons of economy, the test is conducted in a small
diameter borehole, the cleaning of the bottom and the bedding of the plate has to be done from
the surface, so that it is very difficult to be certain that the plate is not resting on disturbed
material. This would, of course, limit the value of the results.
117
The techniques used for tests in large and small diameter boreholes differ in some
respects and, where differences occur, the methods are described separately in Chapter 29.
The diameter of the plate used should, so far as practicable, be equal to that of the borehole,
provided that care is taken to eliminate cohesion or friction on the side of the plate. Except in
strong materials, the plate should have a skirt as shown in Figure 43 (see Section 29.1.4).
Where the diameter of the plate is significantly less than that of the borehole, the results of the
test become difficult to interpret. At a hole-diameter to plate-diameter ratio greater than
about 3:2, the parameters being measured are those pertaining to a load at a free surface and
not at depth under confined conditions, which are usually the conditions of interest.
21.6.2 Limitations
The general limitations of the vertical load test are discussed in Section 29.1.2 and they
apply similarly to the borehole test. Additionally, in the bottom of a borehole it is more
difficult to achieve a satisfactory bedding of the loading plate on the test surface, and hence
values obtained for the deformation parameters may be of limited significance.
21.6.3 Preparation
Where, necessary, casing should be used to support the sides of the borehole and to seal
off water seepages from materials that are above the test elevation. When the test is to be
carried out below the prevailing water table, dewatering by pumping or baling from within the
borehole may cause seepages which disturb the ground and have an adverse effect on its
deformation characteristics. It would then be necessary to resort to external dewatering (see
Section 29.1.2). If the test is undertaken only for measuring the strength parameters,
disturbance due to groundwater seepage may be a less significant factor and the borehole may
be emptied, if this is possible, while the plate is being installed. The water should be allowed
to return to its normal rest level before the test is commenced. Alternatively, the plate can be
installed under water, although it may not then be possible to set the plate sufficiently accurately
for the deformation characteristics to be measured.
(1) Large Diameter Boreholes. Subject to safety requirements (see Appendix E), a
technician should be lowered to the bottom of the borehole to remove all loose soil manually,
after which the plate is bedded as described in Section 29.1.3.
(2) Small Diameter Boreholes. The cleaning is carried out by means of a suitable
auger or hinged bucket operated at the end of a drill rod assembly. A layer of neat cement
mortar is then placed at the bottom of the borehole by means of a tremie or bottom opening
bucket, and the plate lowered down the hole and lightly pressed on to the surface of the mortar.
Plaster and resins can also be used for bedding.
118
The plate is usually loaded through a column formed by a steel tube, with the load
applied to the column by means of an hydraulic jack operating against the resistance of
kentledge, tension piles or ground anchors, as described in Section 29.1.4.
The movement of the plate under load is generally transmitted to dial gauges at the
surface by means of a settlement measurement rod that is located within the steel tube by which
the load is applied. The rod is restrained from lateral movement by rod guides fixed within
the tube. Methods of supporting the dial gauges are given in Section 29.1.4.
(1) Large Diameter Boreholes. The main use of the test is to determine the strength
and deformation characteristics of the ground. It is sometimes used to establish the working
load of piles (Sweeney & Ho, 1982).
(2) Small Diameter Boreholes. The deformation characteristics obtained are of very
dubious value owing to doubts about the elimination of ground disturbance and errors resulting
from unsatisfactory bedding of the plate. The main use of the test is for measuring the strength
characteristics of those cohesive soils in which undisturbed samples cannot be obtained, e.g.
some gravelly clays and very weak rocks. The plate diameter should be large in relation to
the structure of the ground.
Although not strictly a plate test, a test is sometimes made by insitu methods to determine
the coefficient of friction between the ground and concrete as an aid to the assessment of shaft
friction for pile design. At the bottom of a borehole is placed either a layer of compressible
material or a suitably-designed collapsible container. The shaft above this level is then filled
with concrete while the casing is withdrawn. When the concrete has sufficiently matured, the
load is applied, and the deflection measured in a manner similar to that described in
Section 21.6.6. Where the shaft friction of only part of the ground profile is required, as in a
rock socket, the concrete is first brought up to the level of the top of the ground layer concerned,
and the shaft is continued in smaller diameter.
119
The plate test may also be conducted horizontally within a large diameter borehole or
caisson (Whiteside, 1986). In this case, either two tests can be conducted simultaneously on
opposite sides of the caisson, or the caisson wall opposite the test can simply be used to provide
the necessary reaction force. Casing or lining of the caisson must of course be kept well away
from the test location. Guidance on interpretation of test results is given in Section 29.2.
In a pressuremeter test, a probe is inserted into a pocket below the bottom of a borehole
or directly into the appropriate size of borehole and expanded laterally by compressed air or
gas. The applied pressures and resulting deformations are measured and enable the strength
and deformation characteristics of the ground to be investigated.
The earliest instrument, and that in most general use, is the Ménard pressuremeter
(Ménard, 1965). With this instrument, the lateral load is applied by a probe consisting of a
water-filled central measuring cell flanked by two guard cells, either gas-filled or water-filled,
depending on the type of instrument.
Readings are taken at the ground surface on pressure and volume gauges which are
connected to the central cell by means of a back-pressured annular plastic tube. The pressure
tube and probe must be calibrated on site. The function of the guard cells is to ensure a
condition of plane strain in the ground in contact with the central cell. The probes are
manufactured in four sizes up to 75 mm diameter, and can be operated at considerable depths.
The Ménard pressuremeter can be used in soil or weak rock, but is not suitable for stronger
rock, since the instrument is limited by its sensitivity to the tube calibration. It can be used in
granular soils where special means are used to insert it.
Another pressuremeter that has been developed has an l50 mm diameter gas-expanded
probe in which the deformation is measured directly by potentiometers located in the centre of
the probe (McKinlay & Anderson, 1975). It can be used to determine the deformation
characteristics of the more deformable weathered rocks.
The probe and tubing of the pressuremeter require calibration on site, as follows :
Pressure and volume calibrations should be carried out at the beginning and end of a
testing programme, or whenever lengths of connecting tubes are changed, new sheaths or
membranes are installed, any water line subjected to vacuum or pressure has been suddenly
released, or any other factor affecting the calibration has changed. In addition, the hydrostatic
pressure due to fluid in the test equipment below the pressure gauge should be determined prior
to each test.
The formation of a suitable test pocket is a crucial step in pressuremeter testing, as the
test data are obtained by radial expansion of the probe of only a few millimetres and even a thin
disturbed zone around the pocket will affect the results. The test pocket must therefore be
formed with minimal disturbance of the sidewalls, and with the proper diameter for the
instrument to be used. The water flush rotary open hole drilling technique with open-ended
casing (rotary wash boring, see Section 18.7.1) should not be used to form the test pocket.
Briaud & Gambin (1984) have outlined procedures for preparation of an acceptable test pocket
of the required diameter, as well as methods of placing the probe and conducting the test.
The test is normally conducted by increasing the pressure in equal increments and taking
volumetric readings at time intervals after application of each pressure increment. Values of
the soil deformation modulus are then interpreted from these data. Winter (1982) has
discussed the presentation and interpretation of results for both granular and cohesive soils. A
discussion of the application of the pressuremeter to foundation design in Hong Kong is given
by Chiang & Ho (1980).
The Goodman jack is capable of exerting pressures in excess of 60 MPa within a normal
NX size borehole. A method of estimating the insitu modulus of deformation from tests with
121
The impression packer device is commonly available in sizes to fit N and H size
boreholes. A borehole length of about 1.5 m can be surveyed with each test, after which the
device must be withdrawn from the hole and the thermoplastic film changed. Tests can be
conducted as drilling progresses, but more commonly a series of overlapping tests are run after
drilling has been completed in order to obtain a full survey of the borehole. Use of the device
is usually restricted to vertical or slightly inclined boreholes.
Care must be taken when lowering the device into the borehole so that the thermoplastic
film is not scuffed or damaged. The packer may be inflated by either air pressure or water
pressure applied through a central perforated tube. Two metal leaves, curved to match the
borehole wall, thereby force the impressionable thermoplastic film against the borehole wall,
causing a permanent impression to be registered on the film. The device must be fully deflated
before removal, or the film may be damaged.
The device may be orientated in the borehole in two ways, depending on the accuracy
required :
It is recommended that test sections should be overlapped to the extent that at least one
discontinuity common to adjacent sections is recorded. This will provide data for checking
the north direction between successive impressions. Data from such surveys should also be
122
Several devices are available for determining the orientation of drill core, of which the
Craelius core orientator has been widely used (Hoek & Bray, 1981). This mechanical device
is usually installed in a fixed orientation in a core-barrel, and it initially protrudes ahead of the
barrel in order to sense and record the contour of the rock surface. The core orientator then
proceeds up the core-barrel and core drilling commences. Upon retrieval of the core sample,
the uppermost core segment can again be matched against the core orientator and its relative
orientation can be determined. The remainder of the core run may then be oriented with
respect to the uppermost core segment.
The Craelius core orientator can operate in steeply inclined or horizontal boreholes as
well as vertical holes, but it does not provide information on the aperture or infilling of
discontinuities, nor does it provide a permanent record of discontinuities. In addition, the
orientation of the core must be determined relative to the uppermost core segment, and this may
prove difficult where core recovery is poor or where the core contains sub-horizontal joints
(Gamon, 1984a).
123
The frequency of sampling and testing in a borehole depends on the information that is
already available about the ground conditions and the technical objectives of the investigation.
In general, the field work will cover three aspects, each of which may require a different
sampling and testing programme and may also require phasing of operations. These aspects
are as follows :
In areas where suitable information about the ground profile is available from previous
investigations, it may be possible to reduce the need for this aspect. Otherwise, it is necessary
to determine as far as possible the location, character and structure of each zone in the soil or
rock mass. Some zones may be quite thin, and continuous sampling of the entire borehole
may be required in order to obtain the necessary information.
In soils derived from insitu rock weathering, colluvium and some fill materials, the
ground profile can be defined by taking samples using a triple-tube core-barrel. Samples
should be taken continuously or at close intervals supplemented by standard penetration tests.
Continuous rotary coring should be undertaken in fresh to moderately decomposed rock.
Where a run with the rotary core-barrel results in poor core recovery, it may be useful to try to
recover a small drive sample using the split barrel SPT sampler. However, this does not
obviate the need to adjust the rotary coring equipment and techniques in order to obtain the best
core recovery possible.
In fine cohesive soil, and some silty sand, consecutive drive samples can be obtained
using the 100 mm diameter sampler, or similar. In soft clay or sand, the barrels of the sampler
can be coupled together to form a sampler 1 m in length and, if necessary, the core-catcher can
be used to help retain the samples. In soft clays, it is generally good practice to obtain at least
one complete profile for the site using the continuous piston sampling technique. Special
sampling equipment is available for taking long continuous samples in soft clay, loose silt and
loose silty sand (see Section 19.6).
In coarse granular soil, such as gravel, it is advisable to take disturbed samples from
124
the drill tools (see Section 19.3), together with split barrel standard penetration test samples
(see Section 19.4.5) at about 1 m intervals.
Some of the soil samples obtained by drive sampling or rotary coring, if not required for
'undisturbed' tests, should be split along their longitudinal axis and carefully examined and
described in their fresh condition. This exercise should be repeated later when soil is in a
semi-dried state and the fabric may be more readily identified. Where highly variable ground
conditions are expected, it may be advantageous to sink one or more boreholes first, either by
rotary core sampling or by cable tool boring with continuous tube sampling. The cores or
tube samples can then be examined to give guidance for sampling at selected depths in other
boreholes which are sunk subsequently close to the initial boreholes (see Section 22.4).
Once the zones or materials whose properties are likely to be relevant to the technical
objectives of the investigation have been identified, these properties may be assessed using
routine or special techniques (the latter are discussed in Section 22.5). The programme of
sampling and testing should be varied to suit the particular requirements of the investigation
and the equipment that is in use.
In this method, a borehole is first sunk to ascertain the ground profile. A second
borehole is then sunk adjacent to the first, but at a sufficient distance away from it to avoid the
disturbed zone, and samples are taken at predetermined levels. This method may be used
where high variability in ground conditions is expected, e.g. in variable sedimentary deposits,
or for the location and sampling of the shear zone material in a failed slope.
Some of the equipment used in these techniques is fragile, and easily damaged if used in
unsuitable ground. It should preferably be used only where it is known that ground conditions
are suitable.
Using a special sampling technique, the frequency of sampling in sand and in soft
sensitive clay will in general be determined by similar considerations to those given in
Section 22.3. However, if the material requiring the use of a special sampling technique is of
limited thickness, it may be advisable to take samples at smaller than usual depth intervals so
as to obtain a sufficient quantity of that material.
In the borehole vane test, only the small volume of clay that is rotated by the vane is
tested, and individual results often show a considerable scatter. For this reason, vane tests
should be carried out as frequently as possible. The vertical interval will be determined by
the depth at which the test is carried out below the bottom of the borehole; this interval is
usually 500 mm. Closer spacing can be obtained using the penetration vane apparatus.
The cone penetration, pressuremeter and packer tests, as well as discontinuity surveys,
are generally taken continuously, or such that complete coverage of the borehole is provided.
Where a series of plate tests is required at increasing depths, the minimum spacing is
determined by the depth to which the soil has been stressed by the test. A vertical interval of
about four times the borehole diameter is usually adequate.
126
Probing from the surface probably represents the oldest method of investigating the
depth to a hard layer where the overlying material is weak and not unduly thick. The simplest
probe is a sharpened steel rod which is pushed or driven into the soil until it meets resistance.
The method is still of use where other means of site investigation have disclosed relatively thin
layers of very soft soils overlying much harder soils. In such cases, the thickness of the soft
layer may be determined over a wide area very quickly and economically. The method has
many limitations, and a variety of more sophisticated apparatus has been developed, both in
an attempt to overcome these drawbacks and to extend the use beyond that of detecting a hard
layer, e.g. to give some measure of the allowable bearing capacity of the soils present. Two
distinct types of probe have been developed : one where the probe is driven into the soil by
means of some form of hammer blow; the other where the probe is forced into the soil by a
static load.
The apparatus for dynamic probing comprises a sectional rod fitted at the end with a
cone whose base is of greater diameter than the rod. It is driven into the ground by a constant
mass falling through a fixed distance. A device commonly used in Hong Kong is the GCO
Probe (Figure 36 and Plate 10A), which is essentially a larger and heavier version of the
Mackintosh Boring and Prospecting Tool. Probe results are very useful for assessing the depth
and degree of compaction of buried fill, making comparative qualitative assessments of ground
characteristics, and in supplementing the information obtained from trial pits and boreholes.
Probing has also been carried out in the base of hand-dug caissons (Evans et al, 1982). Probe
results are normally reported as the number of blows per 100 mm penetration, as shown in
Figure 37.
As additional rods are added for probing at depth, the driving energy provided to the tip
is attenuated by the additional mass of the rods. Correction of the probe values is sometimes
made to allow for this effect. The correction is negligible at the shallow depths at which many
probings terminate, and it is unnecessary to apply a correction if only qualitative comparisons
between probe results at similar depth are being undertaken.
The fact that the rod and couplers are somewhat smaller in diameter than the base of the
cone prevents, to some extent, shaft friction from influencing the results; however, at depth in
certain soils, this factor should also be considered.
The primary use of dynamic probing is to interpolate data between trial pits or boreholes
rapidly and cheaply. Therefore, probing should first be carried out adjacent to a trial pit or
borehole where ground conditions are known, and then extended to other areas of the site. As
with other types of penetrometers, probing may sometimes be unsuccessful in soils containing
corestones, cobbles or boulders. In fill or completely decomposed rock, the maximum depth
to which a GCO probe can be driven is about 15 m. In order to minimise damage to the
equipment, probing should terminate when the blow count reaches 100, or when the hammer
127
Several types of static probing equipment have been developed and are in use throughout
the world (De Ruiter, 1982; Sanglerat, 1972). The basic principles of all systems are similar,
in that a rod is pushed into the ground and the resistance on the tip (cone resistance) is measured
by a mechanical, electrical or hydraulic system. The resistance on a segment of the rod shaft
(friction sleeve resistance) may also be measured. Static probing, or cone penetration testing,
is also known by a number of other descriptive terms, depending on the manufacturer or
operator of the particular device being used.
There is no British Standard for cone penetration testing, but suitable recommendations
are given by the ISSMFE (1977) and the ASTM (1985k). Both of these test standards
recognize a number of traditional types of penetrometers, and it is imperative that the actual
type of instrument used is fully documented, as the interpretation of the results depends on the
equipment used. Two common types of penetrometers, mechanical and electrical, are
described further in Sections 23.3.2 and 23.3.3 respectively.
The reaction required to achieve penetration of the cone may be obtained by screw
anchors, the weight of the thrusting machine, kentledge, or a combination of these. When
cone penetration testing is done in shallow water, the thrusting machine may be secured to a
jack-up platform (see Section 14.7).
Two common mechanical cones, the Dutch mantle cone and the Dutch friction sleeve
cone, are shown in Figure 38 (see also Plate 10B). These cones were developed mostly at the
Delft Soil Mechanics Laboratory in the l930's. With either type, the cone is pushed into the
ground by a series of hollow push rods. With the mantle cone, the force on the cone is then
measured as the cone is pushed downward by means of inner rods inside the push rods. This
force is generally measured at the ground surface by a hydraulic load cell. With the friction
sleeve cone, the same initial measurement is made, and then a second measurement is taken
while the cone and friction sleeve are together pushed downward a further increment. The
friction is calculated by deducting the former reading from the latter. This procedure is
normally repeated at regular depth intervals of 0.2 or 0.25 m.
For accurate work, the weight of the inner rods should be taken into account in
calculations. In very soft soils when soundings are carried to a significant depth, the weight
of the inner rods may exceed the force on the cone or cone plus jacket; in these circumstances,
128
it is impossible to obtain readings. This effect can be reduced by the use of aluminium inner
rods. The inner rods should be free to slide inside the push rods, and the cone, and friction
jacket where used, should be checked for free sliding both at the start and at the end of each
penetration test. All push rods and inner rods should be straight, clean and well-oiled
internally. The accuracy of the load and pressure gauges should be checked periodically by
calibration.
The cones are generally parallel-sided, and the friction jacket, where fitted, is
immediately behind the point, as shown in Figure 39a (see also Plate 10B). However, parallel-
sided electrical cones do not give exactly the same results as those obtained with the mechanical
cone penetrometer, although the difference is usually of little importance. Electrical cones
with a profile modified to give better agreement with the mechanical cone are also available
(Figure 39b and c).
One particular type of electrical cone penetrometer is the "Brecone", which has a
combined 5 kN and 50 kN force measurement range (Rigden et al, 1982). It has the advantage
of being able to measure cone resistances in clays containing dense sand layers without
suffering damage to the more sensitive load cell.
(a) The cone cross-sectional area should be 1 000 mm2, and the
cone apex angle should be 60°.
The cone penetrometer test is relatively quick to carry out, and inexpensive in
comparison with boring, sampling and laboratory testing. It has traditionally been used to
predict driving resistance, skin friction, and the end bearing capacity of driven piles in granular
soils. In recent years, the cone penetrometer test has also been used to give an indication of
the continuous soil profile by interpretation of the ratio of friction sleeve and cone resistances.
In addition, there is substantial published information relating cone resistance value with other
soil parameters.
The cone penetrometer test is also the preferred substitute for the standard penetration
test in soil conditions where results of the latter test are suspect, and where hard driving is not
anticipated. The test is also commonly used as a rapid and economical means of interpolating
between boreholes. Although it may be possible to estimate the type of soil through which the
cone is passing as described above, it is preferable to carry out the test in conjunction with
some other means of determining the nature of the soil present.
Cone penetration is limited by both the safe load that can be carried by the cone, and the
thrust available for pushing it into the ground. It is also limited by the compressive strength
of the inner rods; some machines are capable of crushing the inner rods before the rated capacity
of the machine is reached. Because of limited cone capacity, penetration normally has to be
terminated where dense sand or gravel, highly to moderately decomposed rock, or cobbles are
encountered. For this reason, cone penetration testing in Hong Kong has been limited to the
Recent alluvial and marine sediments.
Results are normally presented graphically with cone resistance (and local skin friction
where a friction jacket cone is used) plotted against depth. The friction ratio, defined as
(friction resistance/cone resistance) x l00, may also be plotted against depth. This ratio is
used to assist in interpreting the soil type penetrated. Suitable scales for plotting the results
are given in ISSMFE (1977).
The standard penetration test is rather insensitive in loose materials and is not truly
relevant to cohesive soils. On the other hand, the cone penetrometer is of limited use when
dense or stiff layers are encountered. The static-dynamic test combines the two methods
(Sherwood & Child, 1974). [Amd GG2/01/2017]
130
Part V
Field tests are generally desirable where it is considered that the mass characteristics
of the ground would differ appreciably from the material characteristics determined by
laboratory testing. These differences generally arise from several factors, the most important
of which are the extent to which the laboratory samples are representative of the mass, and the
quality of the sample that can be obtained for laboratory testing. Factors affecting sample
quality are dealt with in Chapter 12 and attention is drawn to factors affecting the
representative nature of a laboratory sample. These factors are partly related to the insitu
conditions of stress, pore pressure and degree of saturation, and can be altered from an
unknown insitu state by the sampling processes. Consequently, their influence cannot be
accounted for in laboratory testing.
The material tested insitu by a field test is analogous to a laboratory sample, and can
be considered as a 'field sample'. The insitu conditions of a field sample may be affected by
the process of gaining access to the test position (e.g. digging a trial pit) but, generally, the
effect is very much less than for a laboratory sample.
More obvious, however, are the controlled effects of the nature, orientation, persistence
and spacing of discontinuities (Geological Society, 1972), the nature of any infilling, and the
size of sample required for it to be representative. To ensure that they are representative, the
selection and preparation of samples in the field is subjected to the same requirements as for
laboratory samples. Considerable attention should be given in the field to these aspects,
because, generally, fewer field tests can be carried out than laboratory tests.
The size of sample tested in a field test will depend on the nature of the ground and type
of test, and may vary from a fraction of a metre, such as in the insitu triaxial state of stress
measurements, to several metres for field trials, to one or two kilometres in the pumping test.
The locations and levels of all field tests should be fully recorded during the execution
of the work. The records should be such that the locations and levels can be readily
incorporated into the report on the investigation (see Sections 10.5 and 40.2.8).
Some field tests are relatively inexpensive and are undertaken on a routine basis (e.g.
field density tests described in Chapter 27, the various borehole and penetration tests previously
described in Chapters 21 and 23, and the index tests described in Section 24.2). Other field
tests are expensive and must be designed specifically to account for both the nature of the works
and the character of the ground mass. These latter tests should not be undertaken before a
comprehensive understanding of the geology and nature of the ground has been obtained.
The point load strength index test measures the strength of rock material by means of a
concentrated load applied to specimens of rock core or irregular lumps of rock (Figure 40).
The test gives an indirect measure of the tensile strength of the rock, which has been correlated
with the uniaxial compressive strength (Bieniawski, 1975; Broch & Franklin, 1972; Norbury,
1984). The test results are a useful aid to rock description and classification (GCO, 1988).
The point load strengths of some Hong Kong rocks are discussed by Gamon (1984b), Irfan &
Powell (1985) and Lumb (1983).
A standard test procedure has been recommended by the ISRM (1985). Specimens of
rock core can be tested in either an axial or diametral mode, as can irregular lumps of rock,
provided specified shape criteria are met. The test results are dependent on the size of the
specimen tested, and a 50 mm standard reference diameter has been selected for the reporting
of results.
The test is intended to measure primarily the intact strength of the rock material, and
specimens for testing should therefore be selected to meet the necessary shape criteria without
incorporating discontinuities. Similarly, the failure surface from each test should be examined,
and if the failure passes along a discontinuity, the test result should be discarded.
The main advantages of the point load test are that a large number of tests can be
completed rapidly, with minimal sample preparation. The test equipment is easily portable,
and by testing samples of the same material in various orientations, indications of strength
anisotropy and tensile (splitting) strength of discontinuities can be obtained.
Point load tests can be carried out in the field or in the laboratory. In either case, the
visual examination and logging of samples described in Section 36.3 should be undertaken prior
133
The Schmidt impact hammer can be used to measure the hardness of rock. This device,
originally developed to measure the hardness of concrete, measures the rebound of a spring-
loaded piston from a metal anvil resting on the surface to be tested. The height of the piston
rebound is taken as an empirical measure of rock hardness, and this value has been correlated
with rock and weathered rock properties (Hencher & Martin, 1982; Hucka, 1965; Irfan &
Powell, 1985).
The Schmidt hammer is a portable, hand-operated device and is available in two models,
i.e. the L type (impact energy of 0.735 N-m) and the N type (impact energy of 2.207 N-m).
The N Schmidt hammer is more robust, and generally to be preferred for field testing of rock
exposures. Brown (1981) recommends a standard test method for the type L hammer, but the
recommendations are equally applicable to type N hammers.
Although the Schmidt hammer is quick and easy to use, great care should be taken when
testing weak rocks, or any rock surface which is rough, cracked or fissured. In such cases, it
is recommended that a number of seating blows are taken initially, to ensure a good contact
between the rock surface and the hammer head. Poole & Farmer (1980) concluded that
reliable values could be obtained by ignoring artificially low readings and selecting peak
rebound values from a minimum of five consecutive impacts at a point. The Schmidt hammer
is relatively insensitive on very weak rocks which yield rebound values below 10, and it cannot
be used on rock core unless the core is held in a heavy vice or a steel cradle.
The Schmidt hammer test provides a rapid quantitative assessment of rock hardness and
is suitable for use in trial pits or caisson excavations, or on surface exposures. Use of the test
results is discussed further in Geoguide 3 (GCO, 1988).
The limiting infiltration rate for water entering the soil can be determined with a double
ring infiltration test (Figure 41). The test is commonly carried out at the bottom of a trial pit
or caisson. Water is fed from graduated bottles to the exposed soil surface in the inner ring,
and to the annular space between the rings. The amount of water flowing out of the bottle is
measured with time. The flow under steady-state conditions is used to determine the limiting
infiltration rate (Figure 42). Because of the percolating water from the outer ring (the 'buffer
zone'), water within the inner ring is constrained to infiltrate vertically into the ground, resulting
in a flow with approximately unit hydraulic gradient. Therefore, the limiting infiltration rate
is roughly equal to the 'saturated' field permeability of the soil. In practice, complete
saturation of the ground may not occur due to entrapped air in the soil voids, in which case the
test result will only give a lower bound value for the saturated permeability (Schmid, 1966).
The test can be performed at successive depths to give a complete permeability profile.
It is also possible to perform simpler single ring infiltration tests and crude soakaway
134
tests (i.e. timing a known water head loss in a steel tube, hole or trial pit of standard dimensions).
However, it must be appreciated that no buffer zone is provided in such tests to encourage
vertical infiltration. The results may be useful in a comparative sense but should not be
regarded as an indication of the true permeability of the soil.
135
In principle, a pumping test involves pumping at a steady known flow from a well and
observing the drawdown effect on groundwater levels at some distance away from the pumped
well. In response to pumping, phreatic and piezometric levels around the pumping well will
fall, creating a 'cone of depression'. The permeability of the ground is obtained by a study of
the shape of the cone of depression, which is indicated by the water levels in the surrounding
observation wells. The shape of the cone of depression depends on the pumping rate, the
duration of pumping, the nature of the ground, the existence, or otherwise, of intermediate or
other boundaries, the shape of the groundwater table, and the nature of recharge.
From the data obtained from the test, the coefficients of permeability, transmissivity and
storage can be determined for a greater mass of ground than by the use of the borehole tests
described in Chapter 21. The results can be used in the evaluation of dewatering requirements
and groundwater resources, as well as in the design of positive groundwater cut-offs. It should
be noted that a given coefficient of transmissivity can result from many different distributions
of permeability with depth. If the test is intended for the evaluation of permeability in the
design of dams and other similar projects where seepage is an important consideration, the use
of down-the-hole velocity profiling at constant outflow can provide a permeability profile of the
ground.
Pumping tests can be expensive, requiring adequately screened and developed pumping
and observation wells, suitable pumping and support equipment, and personnel. Care should
be taken therefore to design a suitable test programme. Before attempting to carry out a
pumping test, reliable data should be obtained on the ground profile, if necessary by means of
boreholes sunk especially for the purpose. The geological units encountered may then be
grouped into hydrological units on the basis of permeability (Leach & Herbert, 1982).
The interpretation of the data from a pumping test can be complicated and is much
affected by the inferred ground conditions and by the influence of any boundaries. Where
necessary, expert advice should be sought.
In Hong Kong, pumping tests have been used occasionally to determine hydrogeological
parameters (as described above) but are more often carried out for the purpose of estimating the
yield of water wells. They are also conducted occasionally to provide data for the design of
major dewatering schemes associated with the construction of deep basements. The possible
effects on adjacent ground and structures, e.g. settlements and inducement of negative skin-
friction on piles, should be carefully considered before conducting a pumping test (see
136
Section 8.3.2(e)). Pumping test proposals for private developments must be submitted to the
Buildings Ordinance Office for approval and consent prior to the commencement of works (see
Appendix A.8).
There are two main types of groundwater conditions, confined and unconfined, and these
should be recognized for analytical and design purposes.
Intermediate between the above two groundwater conditions is a third called the semi-
confined condition. In this case, fully saturated ground is overlain by material of significant
but lower permeability, and significant leakage takes place across the boundary in response to
pumping. Analysis of data from semi-confined conditions is possible, but the condition is less
commonly encountered than the other two types.
The three types of groundwater conditions may be recognized by the test response (BSI,
2010). [Amd GG2/01/2017]
Although the choice of test site may be dictated by practical considerations, such as
access and availability of existing boreholes, the site should be representative of the area of
interest. The hydrological conditions should not change appreciably over the site. It is
essential that discharged water is not able to return to the ground under test.
Pumped wells should be of sufficient diameter to permit the insertion of a rising main
and pump of a suitable type and capacity, together with a standpipe and velocity meter, if
required. They should be provided with an adequate well screen, and filter pack where
necessary, to prevent the withdrawal of fine particles from the surrounding soil. The minimum
borehole diameter which will achieve this purpose is often 300 mm. It is desirable that they
penetrate the full depth, of the water-bearing zone being tested. Where the ground is
composed of two or more independent horizons, each should be tested separately. Where fully
penetrating conditions do not exist, the data have to be corrected before analysis. In all cases,
the screen intake area should be such as to ensure that the maximum velocity of water entering
137
the well is not greater than about 30 mm/s to ensure that hydraulic well looses are of an
acceptable level.
If, during the test, changes in the shape of the cone of depression that are due to
extraneous causes are a significant fraction of those due to pumping, then the resulting estimate
of permeability may become unacceptable. Such influences can be corrected by monitoring
(Walton, 1962), both before and during testing. Where possible, and within the limitations set
by the permeability, the pumping rate should be chosen so that resulting changes in water levels
are much greater than those due to extraneous causes, thus minimizing the effects of the latter
on the results.
Suction pumps can be used where the groundwater does not have to be depressed by
more than about 5 m below the intake chamber of the pump, and drawdown can be increased
by setting the pump in a pit. For greater depths, submersible pumps are preferable. The
more permeable the ground, the greater the pump capacity required to produce measurable
drawdowns in the observation wells.
It is essential that the discharge is kept constant for the duration of the test and that all
the water level observations are related to a time-scale referred to the onset of pumping.
Successful well development results in reduced hydraulic head losses as the water enters
the pumping well but, in any case, these losses (well losses) should be accounted for in the
analyses of test results.
In Hong Kong, pumping tests are sometimes carried out in large diameter hand-dug
caissons. This has several disadvantages, as the caisson may only partly penetrate the aquifer
being tested, and the well storage is large. Also, high well losses are often incurred, and for
this reason observation wells should always be used in conjunction with pumping tests in
caissons.
138
Observation wells should have an internal diameter large enough to permit insertion of
a diameter or other water-level measuring device, but if the diameter is too large this may cause
a time lag in drawdown. Standpipes with an internal diameter of 19 mm are often used.
Observation wells should penetrate the same ground as the pumping well and should permit
entry of water from the full depth of ground being tested. If there is any risk that fine soil
particles may clog the observation wells, they should be surrounded by a suitably graded filter
material.
Although the permeability of the ground may be estimated from the pumping well
drawdown data alone, more reliable values are obtained using data from one or more
observation wells. The recommended minimum number of observation wells required to yield
reasonably representative results is four, arranged in two rows at right angles to each other.
Their distances from the pumping well should approximate to a geometrical series. It may be
necessary to add more wells if the initial ones yield anomalous data. If linear boundary
conditions are associated with the site (e.g. river, canal or an impermeable subsurface bedrock
scarp, fault or dyke), the two rows of observation wells are best arranged parallel and normal
to the boundary.
The minimum distance between observation wells and the pumping well should be ten
times the pumping well radius, and at least one of the observation wells in each row should be
at a radial distance greater than twice the thickness of the ground being tested. However,
unless the pumping rate is very high, and the duration of pumping long, particularly in low
permeability ground under unconfined conditions, falls in water levels may be small at such
distances. Preliminary calculations using assumed permeabilities estimated from borehole
data will help to indicate the likely response in observation wells to pumping. Hence the
appropriate distance of the observation wells from the pumping well and the timing of
observations can be assessed.
Depths to water levels should be measured to within ±5 mm. This usually means that
measurement devices have to be checked at regular intervals against, for example, a graduated
steel tape.
The water levels can be monitored with either an electrical dipmeter or an automatic
well level recording system.
Once the character of fluctuations and other extraneous influences has been established,
the test programme designed and the wells developed, pumping of the ground at a constant rate
should commence. Water levels in all wells are then measured with respect to time since
commencement of the pumping. Typically the frequency of measurement might be at 1 min
139
intervals for the first 15 min and at regular logarithmic intervals thereafter. Sometimes,
shorter intervals may be required initially. Therefore each well may have to be monitored by
independent observers for the first 100 min, and then by one or more observers thereafter. In
distant observation wells where head changes are small, automatic recorders can be used,
although these generally require observation wells of 100 mm diameter or greater.
The measurements should be plotted during the course of pumping to evaluate the
quality of the data, the nature of the response, and the required duration of pumping. Johnson
(1982) and Kruseman & DeRidder (1980) have discussed the time requirements for both steady
and non-steady state pumping tests carried out on confined, semi-confined and unconfined
aquifers.
In all cases, water levels should continue to be monitored with respect to time from
cessation of pumping until recovery of levels to the original values is complete. As in the
drawdown phase, recovery data should be taken at 1 min intervals for 15 min following
cessation of pumping and thereafter at regular intervals on a logarithmic scale.
The simpler form of analysis is the steady state type, but the necessary duration of
pumping can be significantly longer than that necessary for non-steady state analysis. The
analysis technique is also dependent on aquifer response, i.e. whether confined or unconfined
conditions are present. A summary of some of the available analysis techniques is given in
BSI (2012c), and these are further discussed by Johnson (1982) and Kruseman & DeRidder
(1980). [Amd GG2/01/2017]
Discontinuities such as joints usually control the mechanical behaviour of a rock mass.
Where surface exposures or outcrops of the rocks exist, a joint survey may be carried out to
assess the risk of joint-controlled instability, e.g. in cut slopes and excavations.
The methods and equipment used to carry out a joint survey are described in ISRM
(1978), and techniques for analysing the results are given by Hoek & Bray (1981). Further
guidance on joint surveys and description can be found in Geoguide 3 (GCO, 1988).
During analysis, care must be taken that rare but critical joints are not overlooked by the
usual statistical methods of data sorting (Beattie & Lam, 1977; Brand et al, 1983). An
experienced supervising engineer or geologist (see Section 15.3) should visit the site to examine
in detail the nature of those discontinuities that have been identified as critical. The slope or
exposure should be examined again during construction for the presence of unfavourable joint
sets not identified in the survey. The need to carry out a joint survey for cut slopes formed in
soils derived from insitu rock weathering should also be considered; unfavourably orientated
relict joints may cause slope failures.
Site-specific laboratory tests may be carried out to characterise the operational joint
shear strength where considered necessary, with consideration given to the roughness and
persistence of the joint, influence of any weak infill, etc. (Hencher, 1981). [Amd GG2/01/2017]
Procedures for undertaking and interpreting field roughness surveys are described in
detail by the ISRM (1978). The most commonly-used method is to employ a set of thin
circular plates of various diameters. These are taken into the field and a series of discontinuity
dip directions and dip angles are measured in turn for each plate when placed on the
discontinuity surface. The accuracy of these measurements is improved by taking a large
number (e.g. 50 or more) readings for each plate and by ensuring that the discontinuity surface
is relatively large and reasonably representative of a particular joint set. The results are often
presented as contoured polar diagrams on an equal-area stereographic projection. The
smallest base plate will give the largest scatter of readings and the largest roughness angles (and
vice versa). A graphical plot of maximum roughness angles versus plate diameter is often
used to assess the sensitivity of the relationship between roughness angle and length of potential
shear displacement along the discontinuity plane.
The main engineering use of a field roughness survey is for the assess-ment of design
values of discontinuity shear strength (Hoek & Bray, 1981). This is achieved by combining
the survey results with data from direct shear tests or assumed basic friction angles. Methods
for interpreting the contribution of roughness to discontinuity shear strength in Hong Kong
granite are discussed by Hencher & Richards (1982); the application of a roughness survey at
an engineering site in North Point, Hong Kong is described by Richards & Cowland (1982).
142
Field testing of soil bulk density is a common and useful procedure. When coupled
with moisture content determinations, the test results can be used to obtain the dry density of
the soil. A major use of such testing is for the control of compaction of embankments, where
it forms the 'field' portion of a relative compaction test (the other portion of the test being carried
out in the laboratory). Field density testing may also be used in evaluation of insitu materials
and old fills, where it provides a direct determination of density that is independent of the
sampling disturbance normally present in laboratory tests.
In essence, most of the available methods of field density testing depend on the removal
of a representative sample of soil, followed by determinations of the mass of the sample and
the volume it occupied prior to removal. However, the nuclear methods discussed in
Section 27.7 are an exception to this general rule. Mass determinations are relatively
straightforward but accurate measurements of sample volume are more difficult and may lead
to significant variations in test results, depending on the technique used, which is in turn
dependent on the nature of the soil being tested.
All the test methods described below require physical access to the soil insitu.
Therefore, they are normally restricted to soil within 2 to 3 m of the surface, although they can
also be used equally well within caissons or shafts. Use of the nuclear probe technique is an
exception to this depth limitation.
The methods described generally measure bulk density, and representative moisture
contents are required if the dry density is to be calculated. Ideally, the weight of the moisture
content sample should be determined on site, then the sample should be transported to the
laboratory for oven drying in accordance with GEO (2017a). Otherwise, the entire sample has
to be preserved in an airtight container until it can be weighed. Alternatively, a rapid
determination of moisture content can be made using a microwave oven, the 'Speedy' moisture
tester, or one of the rapid methods described in BSI (1990). However, all such rapid
determinations should be thoroughly correlated with the standard oven-drying technique for the
particular soil type being tested. In any case, moisture content samples should be as
representative and as large as practical, or several determinations should be made in order to
obtain a reliable mean value. [Amd GG2/01/2017]
With the exception of the water replacement method for rock fill (see Section 27.8), the
methods outlined below are described further in Geospec 3 (GEO, 2017a) and BSI (1990) or
the ASTM standards quoted. [Amd GG2/01/2017]
GEO (2001) describes two variations on the sand replacement method. The first,
employing a small pouring cylinder, is used for fine and medium grained soils. The second,
using a large pouring cylinder, is suitable for fine, medium and coarse grained soils.
[Amd GG2/01/2017]
143
These methods are unsuited to soils containing a high proportion of very coarse gravel
or larger particles because the apparatus is not large enough to cope with a hole of sufficient
size to obtain a representative sample; also the sand will tend to run into the interstices of the
material, thus leading to inaccurate results. The method cannot be used in soils where the
volume of the hole cannot be maintained constant. It also loses accuracy in soils where it is
difficult to excavate a smooth hole because the sand cannot easily occupy the full volume.
The test should not be carried out when compaction plant is operating nearby, or when
ground vibrations are present.
The calibration of the sand is sensitive to humidity and should be checked daily. The
sand should be oven-dried and stored for about a week for the moisture content to reach
equilibrium with atmospheric humidity. After each test, the sand should be dried and sieved
to remove any extraneous material before further use.
The core cutter method is described in BSI (1990). The method depends upon being
able to drive a cylindrical cutter into the soil without significant change of density and to retain
the sample inside it so that the known internal volume of the cylinder is completely filled. It
is therefore restricted to fine soils that are sufficiently cohesive for the sample not to fall out,
and to completely decomposed rock free of large fragments. The method is generally less
accurate than the sand replacement method because driving the sampler tends to alter the
density of the soil. [Amd GG2/01/2017]
The immersion in water method is described in BSI (1990). It is applicable to any soil
where representative samples occur in discrete lumps that will not disintegrate during handling
and submersion in water. In practice the method is restricted mainly to cohesive soils.
[Amd GG2/01/2017]
and hence the method could be used for coarser soils than the sand replacement method if a
sufficiently large apparatus were constructed.
The densometer allows a simpler and more rapid determination of density than the sand
replacement method, but the apparatus is somewhat cumbersome and may be prone to leakage
(GCO, 1984).
All nuclear techniques utilize radioactive materials, and appropriate safety precautions
must be followed. The use and handling of nuclear instruments should be fully in accordance
with the manufacturer's recommendations and applicable regulations (see Appendix E).
The methods quoted in Sections 27.2 to 27.7 can rarely be used in materials containing
a substantial fraction larger than coarse gravel, and the water replacement method, which is
described below, has been devised for such soils. Although it is not covered by any standard
specification, some experience in its use has been gained. In principle, it consists of
excavating a hole large enough to obtain a representative sample, lining the hole with flexible
polyethylene or similar sheeting and then determining the volume of water required to fill the
hole. A 'density ring' is used as a template for the size of hole and also as a datum from which
145
to measure water levels. This is made up from structural steel plate, and for rock fill may be
2 m in diameter, 200 m in height and provided with a mark on the inside.
The procedure is to place the ring on a levelled surface, packing sand under it where it
is not in contact with the soil, and weighing it down with sandbags. Polyethylene sheeting is
placed over the ring, pressed into it and smoothed out as far as possible so as to line completely
the cylindrical cavity so formed. A measured supply of water is then run into it and the volume
required to fill it up to the mark on the density ring is noted.
The polyethylene sheeting is then removed, the hole excavated, and the spoil loaded into
skips for subsequent weighing and grading, if required. Care is needed in the excavation to
ensure that the density ring is not disturbed and, to this end, the edge of the excavation should
be kept at least 150 mm away from the inner edge of the ring. The sides of the hole should be
trimmed to minimize projecting stones.
Polyethylene sheeting is then placed over the ring and hole and partially secured with
sandbags. Water is then run in from a measured source and, at the same time, the polyethylene
lining is fed into the hole, helping it into crevices and minimizing folds. This continues until
the water level is again up to the mark on the inside of the density ring. The difference in the
two volumes is then a measure of the volume of the hole. It is customary to allow the water to
remain in the hole for a period of time to see whether there is any fall of water level, which
would indicate leaks in the polyethylene lining.
The accuracy of the results of this test can be enhanced by attention to the following
details :
Accounts of the practical use of this method can be found elsewhere (Frost, 1973;
Stephenson, 1973).
146
The stresses existing in a ground mass before changes caused by the application of loads
or the formation of a cavity within the mass are referred to as the initial insitu state of stress.
These stresses are the resultant of gravitational stress and residual stresses related to the
geological history of the mass.
Data on the initial insitu state of stress in rock and soil masses before the execution of
works are increasingly important in design, more particularly when using finite element
analysis. The most favourable orientation, shape, execution sequence and support of large
and complex underground cavities and the prediction of the final state of stress existing around
the completed works are dependent on knowing the initial insitu state of stress. Measurements
of insitu stress have shown that in many areas the horizontal stresses exceed the vertical stress,
which in turn often exceeds that calculated assuming that only gravity is acting on the ground
mass.
Measurement of insitu stress in soils may be made, although the equipment used
generally provides an estimate of horizontal stress only. In order that both total and effective
stresses can be estimated, it is usual to measure the pore water pressure in addition to the total
stress.
The methods available are generally based on induced stress changes, achieved in some
cases by over-coring or slotting an instrumented test area.
Over-coring is used for measurement within the rock mass, whereas slotting is used for
surface stress measurements. Measurements taken have to be adjusted to take account of the
redistribution of stresses as a result of formation of the borehole or slot, and, in the case of
underground works, when the measurement is made in the zone of influence of the main access,
such as an adit. The accuracy of most methods of measurement of insitu stress in rock limits
their use to locations where the rock cover is at least 75 m. Stress measurements may also be
determined from the measurement of displacements of the walls of a tunnel, or of an exploratory
adit, close to the working face.
With the exception of the static equilibrium method (Morgan & Panek, 1963), the
available techniques generally require that the material in which the measurements are made
behaves in a near elastic, homogeneous and isotropic manner, and that it is not excessively
fractured or prone to swelling as a result of the effects of drilling water. For the over-coring
methods, the elastic behaviour is assumed to be reversible, the elastic constants being obtained
from laboratory tests.
Stress measurements may be made using electrical strain gauges, photo-elastic discs,
147
solid inclusions and systems for measuring the diametral change of a borehole. Some
equipment is designed to measure stress change with time, or stress change due to an advancing
excavation, whereas other equipment is designed to obtain an instantaneous measurement of
stress. The technique selected has to be chosen in relation to the rock material and mass
quality. Strain gauges cannot be glued reliably to highly porous or wet rock.
Special methods for measuring and interpreting the uniaxial, biaxial or triaxial state of
stress in a rock mass are described in BSI (2010). [Amd GG2/01/2017]
The report on the results of insitu stress measurement should include information on the
following :
(d) Type and sizes of strain gauges, and strain readings to the
nearest 10 micro-strain.
(g) The six components of stress (σx, σy, σz, τxy, τyz, τzx) at
each point to the nearest 100 kPa.
(h) The three principal stresses and their directions (to the
nearest degree), related to both a borehole or adit axis system
and a global axis system.
The analysis of the response of soil masses to applied loads requires reliable data on
their strength and deformation characteristics, and, as these are stress dependent, a knowledge
of the insitu state of stress assists in their evaluation by laboratory testing.
148
Direct insitu measurements of the initial state of stress in soils is difficult because the
disturbance created by gaining access to the ground mass is generally non-reversible, and
several times that produced by a stress-relieving technique. The accuracy of most instruments
that have been developed suffers because of the disturbance created in the ground on insertion.
It is usual to measure only horizontal stress, and to make assumptions concerning the
level of vertical stress based on the overburden depth. Only total stress may be measured;
therefore, to determine the effective stress conditions, the pore water pressure at the test level
has to be measured or assumed. Methods of determining pore water pressure in the field are
discussed in Section 20.2.
In soft clays, hydraulic pressure cells have been carefully jacked into the ground, or
installed in a pre-bored hole (Kenney, 1967). The "Camkometer", a self boring pressuremeter,
reduces disturbance to a minimum by fully supporting the ground it penetrates (Windle & Wroth,
1977). The total horizontal insitu stress may then be obtained by measuring the contact
pressure. Facilities to measure pore pressure are available in the same instrument. Hydraulic
fracturing has also been used to estimate minimum horizontal stresses in soft clay (Bjerrum &
Anderson, 1972).
In large excavations, pressure cells are sometimes used to measure the contact pressure
between the soil and a retaining structure. The type and position of a cell should be chosen
with great care, because the introduction of the cell into the soil causes a redistribution of the
stresses around it, and the errors depend on the geometry of the instrument. Details of the
types of cells available and the problems that may be encountered when using them are given
by Brown (1981) and Hanna (1985). Some of the factors that affect the accuracy of contact
pressure cells are discussed by Pang (1986).
149
Insitu vertical loading tests involve measuring the applied load and penetration of a
plate being pushed into a soil or rock mass. The test can be carried out in shallow pits or
trenches, or at depth in the bottom of a borehole, pit or adit (see Section 21.6). In soils, the
test is carried out to determine the shear strength and deformation characteristics of the
material beneath the loaded plate. The ultimate load is often not attainable in rocks, where
the test is more frequently used to determine the deformation characteristics.
The test is usually carried out either under a series of maintained loads or at a constant
rate of penetration. In the former, the ground is allowed to consolidate under such a load
before a further increment is applied; this will yield the drained deformation characteristics
and also strength characteristics if the test is continued to failure. In the latter, the rate of
penetration is generally such that little or no drainage occurs, and the test gives the
corresponding undrained deformation and strength characteristics.
It should be emphasized that the results of a single loading test apply only to the ground
which is significantly stressed by the plate; this is typically a depth of about one and a half
times the diameter or width of the plate. The depth of ground stressed by a structural
foundation will, in general, be much greater than that stressed by the loading test. For this
reason, the results of loading tests carried out at a single elevation do not normally give a direct
indication of the allowable bearing capacity and settlement characteristics of the full-scale
structural foundation. In order to determine the variation of ground properties with depth, it
will generally be necessary to carry out a series of plate tests at different depths. These should
be carried out such that each test subjects the ground to the same effective stress level it would
receive at working load.
Where tests are carried out in rock, blasting for rock excavation may seriously affect the
rock to be tested. This effect can be minimized by using small charges, and by finishing the
excavation by hand methods.
The main limitation of the test lies in the possibility of ground disturbance during the
excavation needed to gain access to the test position.
Excavation causes an unavoidable change in the ground stresses and may result in
irreversible changes to the properties which the test is intended to study. In spite of this effect,
the moduli determined from plate tests are more reliable and often many times higher than those
obtained from standard laboratory tests. In a project which involves a large excavation, e.g.
a building with a deep and extensive basement, the excavation may cause disturbance to the
ground beneath, with a consequent effect on the deformation characteristics. In such a case,
it will be necessary to allow for this unavoidable disturbance when interpreting the results of
loading tests.
150
When carrying out the test below the prevailing groundwater table, the seepage forces
associated with dewatering may affect the properties to be measured. This effect is most
severe for tests carried out at significant depths below the water table in soils and weak rocks.
It may therefore be necessary to lower the water table by a system of wells set outside and below
the test position.
The even transference of load onto the test surface can best be achieved by setting the
plate on a suitable bedding material, which usually consists of cement mortar or plaster of
paris. Where the test is being performed to measure the deformation characteristics of a
relatively stiff material, considerable care is required in setting the plate, and a series of
bedding layers may be needed (Ward et al, 1968). Changes in water content of the ground
being tested should be kept to a minimum.
The test is subject to scale effects. Several plate sizes and shapes are used, the most
common being circular plates ranging from 300 mm to 1 000 mm in diameter. The choice
depends on the problem being studied. In rocks, plates larger than 1 000 mm diameter may
be used, depending on the jointing frequency. The test arrangement used by the U.K. Building
Research Establishment is shown in Figure 43 and is fully described elsewhere (Marsland, 1971;
1972; Ward et al, 1968).
The need sometimes arises to measure displacements in the ground below the plate
(Marsland & Eason, 1973; Moore, 1974). The plate has to be rigid and the direction of the
resultant applied load has to be vertical and without eccentricity. The loading may be applied
directly by kentledge or jacking against a reaction system provided by means of kentledge,
tension piles or ground anchors. Where kentledge is used, it should be supported on a
properly designed frame or gantry such that there is no possibility of the load tilting or
collapsing. The foundations of this frame or gantry should be sufficiently far away from the
sample not to affect its behaviour to any significant extent. Where tension piles or ground
anchors are used, they should be sited sufficiently far away from the sample so as to have no
significant influence on its behaviour. The normal practice is to maintain a minimum
distance of three times the plate diameter from the centre of the plate to the centre of the pile.
The amount of kentledge or jacking resistance that needs to be provided is governed by the
purpose for which the tests are carried out and also, to some extent, by economic considerations.
151
In general, the nearer the soil or rock under the plate approaches the point of shear failure, the
more worthwhile are the data derived from the tests. The test is sometimes conducted in a
similar fashion to the constant rate of penetration (CRP) test for piles (ICE, 1978).
The penetration or deflection of the plate should generally be measured at the centre
and the edge of the plate. In order to minimize the effect of poor bedding and sample
disturbance, the displacement of the material at some depth beneath the prepared test surface
can be determined by inserting reference datum rods anchored at various depths (Wallace et al,
1969). Such measurements are intended to provide more realistic data on the mass behaviour
of the ground; they are usually taken through a central hole in the loaded plate.
The displacement of the plate is related to a fixed datum. This often consists of a
reference beam supported by two foundations positioned outside the zones of influence of either
the loaded area or the reaction area. The deflection-measuring equipment has to be set up in
such a way that any tilting of the plate will not cause errors in the measurements. Dial
gauges are often used, and the rods transmitting the displacements of the plate should
incorporate a ball joint or other similar device to eliminate the effects of bending. The
reference beam and measuring devices should be protected from the direct rays of the sun and
from wind by means of tarpaulins or other forms of shelter; errors of measurement can easily
arise from these causes.
A comparable arrangement for performing the test in an adit is given in BSI (2010).
[Amd GG2/01/2017]
29.1.5 Measurements
(1) Applied Forces. The load on the plate is best measured by means of a load cell,
which should be capable of reading to an accuracy of 1% of the maximum load. It is advisable
to have the cell calibrated over the anticipated range of loading before and after the test
programme.
(3) Time. Records of time for the various stages of setting-up and testing are required,
particularly where cyclic loading and creep tests are being carried out.
(4) Temperature. The measurement of temperature will be required in the event that
corrections to the settlement or load readings are considered necessary.
(1) General. The test is most frequently used to measure the ultimate bearing capacity.
In cases where settlements and elastic deformation characteristics of the ground need to be
determined, as in rock foundations, care should be exercised to work at stresses that are relevant.
152
The observation of deformation, particularly at low stress levels, requires the utmost care in
sample preparation and setting-up if meaningful results are to be achieved. The errors that
can be introduced by sample disturbance and inaccuracies of measurement can often be similar
in size or greater than the data sought.
The effect of sample disturbance can be reduced, to some extent, by carrying out
preliminary cycles of loading and unloading. The maximum load in these cycles should not
exceed the intended load. The rate of loading should be sufficiently rapid to prevent any
significant consolidation or creep. After two or three cycles, the stress/settlement graph will
generally tend to become repeatable, and the test can then be extended to the main testing
programme. The data from the preliminary load-cycles give an indication of the effect of the
sampling disturbance. The undrained deformation moduli, as measured after preliminary
load-cycling, generally give a more reliable indication of the true properties of the undisturbed
ground.
(2) Maintained Load. The load is usually applied in equal increments, with each
increment being maintained until all movement of the plate has ceased, or an acceptably low
rate of increase has been reached. The increments are continued up to some multiple of the
proposed working load, to failure or to the full available load. When the test is carried out to
investigate the deformation characteristics of the ground, it is preferable to carry out
preliminary load cycling. Cycles of unloading and reloading may also be carried out at
various stages in the main test to gain some indication of the relative amounts of reversible (i.e.
'elastic') and irreversible deformation that have occurred. If the rate of unloading and
reloading is sufficiently rapid, the slope of the load/deformation curve may be used to determine
the undrained deformation modulus, or an approximation to it. However, in relatively
permeable ground this may not apply.
(3) Constant Rate of Penetration. Constant rate of penetration tests are more suitable
for soils. Such tests are described by Marsland (1971) for plates ranging from 38 mm to
868 mm diameter, using a penetration rate of 2.5 mm/min. Where the maximum bearing
capacity is not clearly defined, the value of the bearing pressure at a settlement of 15 per cent
of the plate diameter is used. If the undrained deformation modulus is required, the plate
diameter should be greater than 750 mm, but it is preferable to carry out a separate test with
the load applied incrementally at a rapid rate.
(4) Creep. The measurement of creep under sustained loads is sometimes carried out
in connection with the design of foundations which are highly stressed or where the structures
concerned are particularly sensitive to settlement (Meigh et al, 1973). If the structure is to be
subjected to fluctuating loads, the test programme will probably include cyclic loading.
The assumptions made for the analysis are that the material is homogeneous, elastic,
isotropic and that the classic equation for the penetration of a rigid circular plate on a semi-
infinite plane surface applies :
153
S
q
B
1 2
.................................................... (8)
4 E
This equation can be used when the test is carried out either at the ground surface or in
a pit whose plan dimensions are at least five times those of the plate (Ireland et al, 1970). If
the test is carried out at the end of a borehole, the expression becomes :
S
q
B
1 I
2
................................................. (9)
d
4 E
where Id is a depth correction factor (Burland, 1969). When the test is carried out in an adit,
other modifications to this equation will be required depending on the extent and planarity of
the tested surface (Carter & Booker, 1984). Finite element analysis can sometimes be applied
to problems where rigorous solutions are not available, although the problem of choosing
representative soil parameters to put into the analysis still remains. An equation for
calculating the modulus at any depth beneath the centre line of the loaded plate is given
elsewhere (Benson et al, 1970; Wallace et al, 1970). For jointed rock, Poisson's ratio can be
assumed to be between 0.10 and 0.25 for practical purposes.
For cohesive soils, an estimate of the undrained shear strength, Cu, can be obtained from
the plate test carried out in a borehole by using the following equation :
qu H ..................................................... (10)
Cu
Nc
where qu is the ultimate bearing capacity of the soil under the plate. When this is
not clearly defined the bearing pressure at a penetration of 15% of the
diameter is used,
γ is the bulk density of the soil,
H is the height of soil above test level,
Nc is the bearing capacity factor. For a rigid circular plate at the base of a
deep shaft of the same diameter as the plate, Nc is assumed to have a value
of 9.25. However, if the plate has a significantly smaller diameter than the
shaft, or if the depth is less than four times the plate diameter, the value of
Nc may be smaller and approaches 6.15 for a circular surface load. Some
allowance should be made for side shear on the plate where this is
appropriate.
The correct interpretation of the behaviour of the mass of ground under investigation
154
requires a careful examination of the results, not only of the loading tests, but also of other data
concerning the ground (Sweeney & Ho, 1982). Depending on the objectives of the
investigation, such data might include the geological structure, the nature and distribution of
discontinuities, and the variability of the ground.
Several deformation moduli can be obtained from these tests, depending on the method
used and the application (Brown, 1981). The results obtained will reflect the effects of the
width and frequency of the discontinuities and will give an indication of the mass behaviour
under loading. The stress level at which these parameters should be examined will depend on
the working stress levels. In the case of tests on rock in adits, it may be necessary to consider
the insitu stresses in the test sample.
The moduli to be used for design purposes should be those which relate to the ground at
the time of construction and after it has been affected by the construction procedures; for
example, a deep excavation might affect the deformation moduli of a soil, and blasting may
affect the properties of a rock. Sometimes, the effect of a construction procedure may be
sufficiently severe to justify the examination of alternative methods of construction.
On completion of the test, full identification of the material beneath the loaded area
should be carried out by sampling and testing in the laboratory. Results obtained from these
tests will in many cases assist in extrapolating the test results to other areas on the site.
Basically, horizontal and inclined loading tests are the same as vertical loading tests,
and are carried out and analysed in a comparable way (see Section 21.6.10). Loading tests
at a preferred orientation are carried out to investigate particular characteristics of the ground.
They are frequently carried out in rock for investigations concerning tunnels and underground
excavations (Brown, 1981; Carter & Booker, 1984). A simple lateral loading test, carried out
between the opposite sides of a trial pit or caisson using an hydraulic jack, forms a very
convenient means of measuring the insitu modulus and shear strength of soils. Interpretation
of the elastic modulus of soil from lateral loading tests should follow the advice given by Carter
& Booker (1984). Care should be taken to support the weight of the jack and other loading
equipment so as to prevent the application of shearing forces to the test area.
The test is carried out in an underground excavation or length of tunnel and consists of
charging the chamber with water under various pressures and measuring the deformation
moduli of the surrounding ground. The test is generally carried out for projects involving
tunnels carrying water under pressure.
The test site should preferably form part of the actual excavation, or be of the same size
and parallel to the axis in representative ground. The length of a test section should be at
least five times the excavated diameter, unless allowance can be made for the end effects. The
method of excavation used should be capable of producing a formed surface of similar quality
155
to the actual excavation. In order to ascertain whether the modulus determined is drained,
partially drained or undrained, it is necessary to know the drainage conditions which applied
during the test.
The CBR method of flexible pavement design is essentially an empirical method in which
design curves are used to estimate a pavement thickness appropriate to the CBR of the soil.
There is no unique CBR of a soil, and in any CBR test the value obtained depends very much
on the manner in which the test is conducted. The design curves are usually based on one
carefully specified method of measuring the CBR, and this is usually a laboratory method.
The parameter required for the design of flexible pavements is the CBR attained by the soil at
formation level after all necessary compaction has been carried out, the pavement has been
laid and sufficient time has elapsed for equilibrium moisture content to become established.
Before embarking on insitu CBR tests, it is therefore necessary to consider carefully how
relevant they will be to the proposed design method, and whether the condition of equilibrium
moisture content is likely to pertain.
The test is carried out by the method described in BSI (1990). The load is generally
applied through a screw jack using the weight of a vehicle as jacking resistance, and deflections
are measured by dial gauges carried on a bridge with independent foundations resting on the
ground well clear of the test area. [Amd GG2/01/2017]
The test is unsuitable for any soil containing particles of longest dimension greater than
20 mm because the seating of the plunger on a large stone may lead to an unrepresentative
result. The test is of dubious value with sands because it tends to give results much lower than
the laboratory tests on which the design charts are based. This is because of the confining
effect of the mould in the laboratory tests. The test is most suited to clay soils, subject always
to the soil under test being at equilibrium moisture content. The moisture content at a depth
of 1 to 2 m below ground surface, where the soil is normally unaffected by seasonal moisture
content changes, often gives a good indication of the equilibrium moisture content, provided
that there is no significant change of soil type. An alternative is to carry out the test directly
beneath an existing pavement having identical subsoil conditions to those of the proposed
construction; this method has been used with some success for the design of airfield pavements.
Insitu CBR tests have sometimes been carried out in conjunction with insitu density and
moisture content tests and then linked with laboratory compaction tests. A careful study of all
the resulting data may allow a reasonable design parameter to be chosen for suitable soils.
Attempts have sometimes been made to use the test as a means of controlling the compaction of
fill or natural formations, but they have not usually been successful and the procedure cannot
156
be recommended.
157
In this test, a sample of soil or rock is prepared and subjected to direct shearing insitu.
The applied stresses and boundary conditions are similar to those in the laboratory direct shear
test. The test is generally designed to measure the peak shear strength of the intact material,
or of a discontinuity (including a relict joint in soil), as a function of the normal stress acting
on the shear plane. More than one test is generally required to obtain representative design
parameters.
The measurement of residual shear strength can present major practical problems in
arranging for a sufficiently large length of travel of the shear box, but a useful indication of
residual strength may be obtained by continuing the test to the limits of travel of the apparatus.
In certain applications, the test may be designed to establish the strength of the interface
between concrete and rock or soil.
Insitu shear tests on soil may be carried out either within boreholes (Bauer &
Demartinecourt, 1982; Handy & Fox, 1967) or near the ground surface (Brand et al, 1983b).
Equipment for testing close to the ground surface in trial pits may be adopted to enable testing
to be carried out within deep excavations, large diameter shafts or caissons. Insitu shear tests
on specific discontinuities in rock may also be conducted using similar equipment; the results
may be used to confirm the strength of discontinuities derived from laboratory tests and field
roughness surveys (see Section 26.2).
Samples are generally prepared at the bottom of pits or trenches in soil. Adits are more
common for rock testing. The excavations permit access to the material at the zone of interest,
and in many cases provide a suitable means of setting-up the reaction for the applied forces.
The orientation of the sample and the forces applied to it are generally governed by the
direction of the forces which will become effective during and on completion of the works, but
modified to take account of the orientation of significant discontinuities. In many cases,
however, to facilitate the setting-up of the test, the sample is prepared with the shear plane
horizontal. The normal and shearing stresses are generally imposed as forces applied
normally and along the shear plane. However, an inclined shear force passing through the
centre of the shear plane may be preferred as this tends to produce a more uniform distribution
of stress on the shear surface (Brown, 1981).
As a rough guide, the sample dimension should be at least ten times that of the largest
particle; in rock, the sample size should reflect the roughness of the rock discontinuity being
tested. For stronger rocks, the sample can be rendered with suitably strong cement and
reinforced concrete to ensure adequate load distribution. The equipment should be of robust
construction. Samples between 300 mm and 1 500 mm square have been used for testing soil
and weak rocks. Larger samples may be required in ground containing boulders or in coarse
fill material.
158
Where it is intended to test one discontinuity only, care has to be taken to avoid
disturbance to the surface of the discontinuity, and to prepare the sample so that the forces are
applied correctly in the plane of the discontinuity. The spatial orientation of the discontinuity
should be defined by dip direction and dip measurements.
Where drained conditions are required, suitable drainage layers can be inserted around
the sample and on the loaded upper surface.
With the borehole shear device, there is no sample preparation as such, but care is
required during the formation of the borehole so as to limit disturbance of the surrounding soil
(Bauer & Demartinecourt, 1985).
The equipment for applying the normal load can consist of weights, kentledge, hydraulic
rams, flat jacks acting against the excavation roof, or an anchor system. The reaction system
should ensure the uniform transfer of the normal loads to the test sample and minimum
resistance to the shear displacement, e.g. by the use of low-friction devices such as ball seatings
or rollers (Brown, 1981). A porous piston or other suitable medium can be used to distribute
the load where drained conditions are required. The alignment of the force needs to be
maintained during the test.
The shearing force application system should ensure that the load is applied uniformly
over the plane of shearing, and that the load and geometrical centroids are matched to eliminate
movement. Where an inclined shear force is required, the resultant of the shear force should
pass through the centre of the base of the shearing plane (Brown, 1981). If a constant normal
load is required for this type of test, suitable reduction has to be made to the applied normal
load during testing to compensate for the increase in vertical component with increasing shear
force. The shear force application can be developed by similar means to the normal loading.
In both cases, care has to be taken to ensure that the ground reaction does not extend to the
sample. The reaction system can frequently be provided by the excavation sidewalls. In
certain cases, it may be necessary to provide the shear force by traction on a system anchored
by piles or cables. Sufficient travel in the shear force application system should be provided
so that the complete test can be run without interruption.
159
30.4 Measurements
The stresses applied in the testing programme should be within the range of the relevant
working stresses at the site, including those applied by the final structure, if appropriate.
Where drained test conditions are required, a consolidation stage is necessary to allow the pore
water pressures to dissipate under each increment of normal load. The rate of consolidation
should be monitored, as this is useful for determining the rate of shearing (Brown, 1981). For
drained tests, the rate of shearing has to be sufficiently slow to ensure that induced pore pressure
changes are a very small proportion of the shear stress. At best, the appropriate shear rate can
only be estimated prior to the test, and experience gained in similar soil or rock conditions and
with similar test configurations is beneficial.
On completion of the test, full identification of the material sheared should be carried
out by visual examination, sampling and laboratory testing. Photographs of the shear surface
form a useful record of the test conditions and may assist in the interpretation of results.
Graphs of consolidation behaviour (if applicable) and shear force (or stress) plotted
against both normal and shear displacements are prepared in the analysis. The peak shear
stress and corresponding shear and normal displacements may then be obtained and related to
the applied normal stress. When failure occurs in a plane dipping at an angle to the applied
shearing force, this should be accounted for in the analysis (Bishop & Little, 1967).
For tests on discontinuities in rock, the results from individual tests should not be
extrapolated to the rock mass without confirmation that the surface tested is representative of
the overall roughness of the discontinuity (see Section 26.2).
160
Large-scale field trials are carried out in such a manner that the ground is tested on a
scale and under conditions comparable with those prevailing in the project under investigation.
However, such trials are likely to be costly in terms of instrumentation, the requirements for
purpose-made equipment and technical support. The methods and types of instrumentation
available for monitoring field tests are given in brief outline in the following sections, together
with some of the more common large-scale field trials used to obtain geotechnical data for
design and construction.
Large-scale field trials involve the principles of site investigation embodied in this
document, and would usually include the use of ground investigation techniques already
described. Large-scale field trials are not standard tests, and should be designed to suit the
individual requirements of the proposed works and the particular ground on which or within
which they are to be performed. On large projects, field trials can provide the necessary
design parameters, as well as valuable construction data on excavation, handling and placing,
resulting in considerable savings and enhanced safety. Such methods and trials can be
usefully extended into the construction stage, and also to the monitoring of the interrelated
response of the ground and structure after completion under the working conditions.
Ground movements are generally associated with stress redistribution and pore pressure
changes which are characteristic of the particular ground. Total stress can be monitored
using total pressure cells (see Chapter 28), while normal and shear stresses can be measured
by special transducers (Arthur & Roscoe, 1961). The techniques for the measurement of pore
pressure response are covered in Sections 20.2.3 to 20.2.6.
Ground movements are generally measured in terms of the displacement of points which
can be positioned on the surface of the ground or within the ground mass. The absolute
movement of a point has to be referred to a stable datum, and sufficient measurements should
be taken to define movement in three dimensions if this is required. Some of the commonly-
used techniques permit the movement or relative displacement of points to be referenced to
arbitrary horizontal and vertical planes. This relative movement can be used to obtain strain.
Surface observations of ground movements can be made by an accurate survey (Cole &
Burland, 1972). An accuracy of ±0.5 mm can be achieved in levelling (Froome & Bradsell,
161
1966) and ±(5 mm + 5 ppm) for distance measurement using electro-optical instruments (Mayes,
1985). Care has to be taken to position datum points away from the effects of movements due
to load and water changes.
Photogrammetric techniques can be used to survey inaccessible sites such as steep slopes
and ravines (Borehers, 1968). The accuracy of measurements taken by a photogrammetric
method is about ±1/10000 of the camera to object distance under normal working conditions
(Cheffins & Chisholm, 1980).
The construction of trial embankments may serve three purposes. First, the quality and
compaction characteristics of available borrow materials can be determined at the field scale
and compared with laboratory test results; second, the characteristics and performance of
placing and compacting equipment can be investigated; third, the strength, and settlement
characteristics of the ground on which the embankment is placed can be examined. Failure
of a trial embankment will usually not be of major consequence, and therefore a trial bank may
be constructed so as to induce failure deliberately, either in the embankment alone or in the
embankment and the foundations. However, any installed instrumentation may be destroyed.
Such failures sometimes occur in an unexpected manner, and the engineer should take
precautions to ensure that no injury to persons or unexpected damage is caused. The value of
such a failure is that back analysis (see Chapter 32), can be used to check strength parameters.
Bishop & Green (1973) have described the development and use of trial embankments.
Compaction trials can include experiments with variable borrow materials, layer
thicknesses, amounts of watering and amounts of work performed in compaction.
Measurements should be made of insitu density and water content; the results should be
compared with those from laboratory compaction tests, to obtain a specification standard, and
with insitu borrow pit densities, so that the degree of bulking or volume reduction can be
estimated for given quantities (BSI, 2009). Trials of equipment can also be undertaken.
Care should be taken not to vary too many factors at the same time, otherwise the effects of
variation of an individual factor cannot be estimated. [Amd GG2/01/2017]
Trial excavations yield information on the material excavated and the performance of
excavating equipment; they also permit more detailed examination of the ground than is
162
possible from borehole samples. Excavations can be constructed such that failures are caused
deliberately; hence they can sometimes be used to test the short-term stability of excavated
slopes. However, failures in deep excavations are correspondingly more dangerous than
failures of fills, and increased vigilance is needed.
In many projects, considerable value can be derived from trials carried out before the
commencement of the permanent works. Such trials permit the evaluation of the procedures
to be adopted and the effectiveness of the various expedients. As with all large scale testing,
a prior knowledge of the characteristics of the ground is essential. The results of the trial will
often permit an assessment of the properties of the ground and hence enable a correlation to be
made with other results obtained from routine ground investigation methods.
A wide range of construction methods is commonly tested in trials, e.g. pile tests, ground
anchor tests, compaction tests for earthworks, experimental shafts and adits for tunnels,
grouting, trial blasts for explosives and dewatering.
163
32.2 Failures and Design of Slope Preventive or Remedial Works [Amd GG2/01/2017]
In Hong Kong, numerous landslides are caused by intense rainfall every year, and back
analysis is sometimes carried out to derive shear strength parameters as part of the design
procedure for slope remedial or preventive works. However, a note of caution is necessary
regarding the interpretation and use of the results. Although the failure itself can be studied
in great detail after the event, it is extremely rare to have accurate information on the specific
ground conditions at the time of failure, particularly with regard to pore water pressures
(Hencher et al, 1984). For this reason, back analysis may be just as useful in permitting a
rational, qualitative assessment of the failure mechanism as in deriving information specifically
on shear strength parameters for use in design (Hencher & Martin, 1984).
Whilst the back analysis approach serves as a useful yardstick for assessing the mass
shear strength, this approach should not be used in isolation. The application of the back
analysis approach for the design of slope preventive or remedial works should be accompanied
by rigorous geotechnical investigation, including ground investigation, laboratory testing and
engineering geological mapping in order to provide a more reasonable basis for making
judgement on suitable mass shear strength parameters. [Amd GG2/01/2017]
Extreme care must be taken to avoid the adoption of unduly high shear strength
parameters derived from back analysis which may have incorporated the effect of suction.
Where the ground mass is relatively homogeneous with no corestones or boulders, binding
effect of tree roots, three-dimensional effects of the slope geometry, etc., back-analysed shear
strength parameters which are higher than those determined from laboratory tests on saturated
specimens should not be used. [Amd GG2/01/2017]
164
The notion that the continued stability of an existing slope may be proven by past
rainstorms should be treated with caution. Factors such as deterioration of the slope condition,
progressive slope deformation and possible changes in environmental conditions (e.g. enhanced
infiltration through a dilapidated hard surface cover, leakage from water-carrying services, etc.)
should be carefully considered before one can confidently count on past performance in the use
of the back analysis approach. In particular, the use of the back analysis approach to derive
mass shear strength parameters for designing upgrading works should be done with extreme
caution where the proposed works involve the replacement of a hard surface cover with a
vegetated cover. [Amd GG2/01/2017]
When back analysis is used, it should be for deriving the possible range of strength
parameters. If more than one predominant soil type (e.g. fill and CDG) is involved, the back
analysis approach, if used, should be applied to assess the strength parameters for the particular
soil type with greater uncertainty (e.g. high spatial variability, difficulty in retrieving
representative samples for laboratory testing, etc.), whilst the strength parameters for the other
soil type(s) should be determined by other means such as conventional laboratory tests.
[Amd GG2/01/2017]
The back-analysed shear strength parameters for a certain slope section should not be
applied to other sections of the slope in the case of a sizeable slope with highly varied
characteristics (e.g. in terms of slope geometry, geology, catchment characteristics, etc.) along
its length. Different sets of strength parameters may need to be obtained by back-analysing
suitably selected sections. [Amd GG2/01/2017]
Back analysis of a landslide or a slope with signs of distress can be useful where there
is sufficient and reliable information on the ground conditions and the geometry of the rupture
surface. This can assist in the diagnosis of failure mechanisms and examination of the likely
combinations of soil shear strength and groundwater conditions at the time of failure. For the
design of remedial works, however, the back-analysed groundwater conditions prevailing at the
time of the landslide should not necessarily be taken as the design groundwater conditions.
This is because the groundwater response for rainstorms with differing characteristics in terms
of intensity, duration and return period may be different, and because the hydrogeological
setting of the failed slope may be altered by the landslide and/or the proposed remedial works.
[Amd GG2/01/2017]
The above guidance on the use of the back analysis approach is also generally applicable
to the design of preventive or remedial works for retaining walls. [Amd GG2/01/2017]
Although back analysis is carried out typically when slope failures or significant ground
movements have occurred, it can be useful in other cases where conventional predictive
methods may not lead to realistic design solutions. An example of this application in Hong
Kong is in the design of preventive works for existing steep slopes formed in soils derived from
insitu rock weathering. In such cases, conventional slope stability analysis will often yield
factors of safety less than unity even when a slope has stood safely without signs of distress for
many years. Shear strength parameters obtained from back analysis of hypothetical failure
165
surfaces through the existing slope often allow a more realistic form of stability improvement
to be made than would be possible from conventional analysis. However, it is very important
to check that the assumptions made in the back analysis are valid; for example, the failure
surfaces selected should be realistic and the proposed works should not result in any substantial
change to the form of or loadings on the slope. Similarly, in the prediction of settlements in
variable ground, or in ground from which it is impossible to retrieve representative samples,
back analysis of settlement data from an adjacent site in similar materials may be the only
satisfactory means of producing sensible predictions.
166
The aim of most geophysical methods of ground investigation is to locate some form of
subsurface anomaly where the materials on either side have markedly different physical
properties. These anomalies may take, for example, the form of a boundary between two rock
types, a fault, underground services, or a cavity. In the initial stages it will almost always be
necessary to check the true nature of these anomalies by physical means, normally by boreholes.
Once a correlation between the geophysical test results and the underground phenomena has
been established, the geophysical investigation may then yield useful results rapidly and
economically. It follows that, where there is no distinct change in physical properties across
the anomaly, the geophysical investigation may not detect a boundary. Geophysical methods
can also be used to deduce soil and rock parameters; when this is done, the results obtained
should always be confirmed by directly measured parameters.
Good results in geophysical techniques are obtained when the geological conditions are
relatively simple, with large clear-cut contrasts in the relevant physical properties between the
formations. However, less favourable ground conditions may still warrant consideration of
geophysics, particularly at an early stage in an investigation, because of the relatively low cost
and high speed of the methods, e.g. to assist in eliminating alternative explanations of the
geology. It may at times be necessary to use two or more methods on a trial and error basis
167
This technique is used for investigating the simpler geological problems. A current is
usually passed into the ground through two metal electrodes, and the potential difference is
measured between two similar electrodes (BSI, 1990). With suitable deployment of the
electrodes, the system may be used to provide information on the variation of geo-electrical
properties with depth (depth probes), lateral changes in resistivity (constant separation
traversing) or local anomalous areas (equipotential survey), e.g. karst features, disused tunnels
or shafts. The unsuspected presence of electrical conductors, e.g. pipes or cables, under the
site will, of course, render the results unreliable. The interpretation of the results obtained by
this method does not always provide a definite solution, particularly as the number of
subsurface layers increases, because it involves a curve matching technique which requires the
assumption of idealised conditions. [Amd GG2/01/2017]
33.2.2 Gravimetric
In ground investigation, the gravity survey is normally limited to locating large cavities
or faults. Precision levelling and positioning of the instrument at each station is essential.
With the more accurate instruments now available, it is possible that the gravity survey method
will become a useful tool in locating hidden shafts and smaller cavities.
33.2.3 Magnetic
Local changes in the earth's magnetic field are associated with changes in rock types.
In suitable circumstances, the technique may locate boundaries (e.g. faults or dykes) between
rocks which display magnetic contrasts. However, its main use in the civil engineering field
is the location of buried metalliferous man-made objects, such as cables or pipelines. It can
sometimes be used for locating old mine shafts and areas of fill. In using this method to detect
the location of faults or dykes, it is, of course, essential to eliminate the possibility that the
anomaly detected is in truth buried metal.
168
33.2.4 Seismic
The seismic technique, either reflection or refraction, may be used to locate subsurface
boundaries which separate materials having different values of sonic wave velocities. In
carrying out geophysical surveys on land, the refraction method is the one most frequently used.
It involves producing seismic waves, either from a small explosive charge or from a mechanical
source (e.g. a hammer), and measuring accurately the time taken for them to travel from the
point of origin to vibration detectors (geophones) at varying distances away.
The greatest use of this technique is in the determination of bedrock level (McFeat-Smith
et al, 1986). Therefore, it is commonly used in the estimation of quantities of soft materials
available from a borrow area site. One limitation of seismic refraction, however, is that when
the velocity of transmission in the upper layer is greater than that below (e.g. if very compact
gravel overlies a clay), then the intervening boundary cannot be detected and false layers may
appear to be present. Another use of this technique is to provide wave velocity data for the
assessment of insitu dynamic modulus values of rock masses (Meigh, 1977). Only rarely wil1
the dynamic and static modulus values be the same. Environmental considerations sometimes
limit the application of this test. For example, explosives cannot be used in urban areas, and
where the site lies near to the source of vibrations, such as a busy road, the induced vibration
may not be detectable.
Direct seismic measurements can also be taken between two boreholes, or from surface
to borehole or borehole to surface. These techniques may be useful for assessing the
properties of the intervening rock mass, and in detecting geological features such as cavities.
Cross hole surveys, i.e. between boreholes, may provide the best geophysical means for
detecting cavities at depth (McCann et al, 1987), but results can only be confirmed by
subsequent drilling.
The principle of the Gamma Density method is to irradiate the target material with
medium-high energy collimated gamma rays and to measure their attenuation between the tool
source and the detectors. The attenuation is a function of the electron density of the target
material, which in turn is closely related to its mass density. [Amd GG2/01/2017]
Based on the relative density contrast between target materials, the technique can be
used, within a drillhole, to identify weak layers in the ground at a practical logging speed of
1 m/min. Such weak layers include clay-rich layers, weathered seams and disturbed zones
that are of comparatively lower mass density. The resolution of the method increases with the
increase in relative density contrast between the target and the adjacent materials. The
resolution decreases if casing is used and as the dip angle of the weak layer becomes aligned
with the drillhole axis (i.e. sub-vertical in a vertical drillhole). [Amd GG2/01/2017]
169
Two examples are shown in Figures 45 and 46. Figure 45 shows strong signatures for
the weak clay-rich layers at locations A to D where the density contrast is high between the
weak layers and the adjacent materials. In this case the method was able to identify weak
layers as thin as in the centimeter range. The clay-rich layers at E to I as a whole give a strong
signature in the log, but the individual layers cannot be clearly distinguished. Figure 46 shows
poor correlation for those weak clay-rich layers at locations A to H where the density contrast
between the weak layers and the adjacent materials is low. [Amd GG2/01/2017]
The method is most suitable for use in uncased or plastic-cased drillholes and where the
relative density contrast between the target (weak layers) and adjacent materials is high.
However, caution needs to be exercised in interpreting the data as the absence of a strong
signature does not necessarily confirm the absence of weak layers in the ground.
[Amd GG2/01/2017]
The Spectral Gamma Ray method is based on the principle that decomposition of
potassium-bearing minerals leads to a progressive loss of potassium ions (K). Naturally
occurring potassium contains radiogenic K. Thus the amount of radiogenic K present in the
material is related to the degree of decomposition of potassium-bearing minerals in the parent
rock and hence the degree of weathering of the rock mass. The Spectral Gamma Ray method
produces a log of the potassium count rate along the drillhole. [Amd GG2/01/2017]
The location along the drillhole where the count rate shows a significant reduction
compared to the adjacent materials can be interpreted as a more weathered, weak layer.
However, interpretation of the data is dependent on the origin of the target material, which may
significantly affect the potassium count rate. For instance, where a clay layer does not
originate directly from the decomposition of the adjacent materials, the potassium count rate of
the layer may not necessarily be lower than those of the adjacent materials. Also, if thin layers
are to be identified, a slow logging speed will be required, e.g. 0.05 m/min for a resolution of
50 mm. [Amd GG2/01/2017]
This method does not require the use of any radioactive source and it can be used in
drillholes lined with different types of casing. Also it is much cheaper than the Gamma
Density method (about half the price based on term contract rates in 1999/2000). The Spectral
Gamma Ray method, when applied to materials of the same origin and preferably backed up by
site-specific calibration, can give an indication of the degree of weathering. Although the
method is not as good as the Gamma Density method in identifying thin weak clay-rich layers,
there is potential for it to be used in verifying ground conditions, especially in the case of a
large number of drillholes without the need for sampling, e.g. drillholes for installing soil nails,
raking drains, observation wells and piezometers, etc. [Amd GG2/01/2017]
The example in Figure 45 shows that the potassium count rate log gives signatures for
the weak clay-rich layers at locations A, B and C. The potassium count rate log in Figure 46
is unable to identify any of the weak layers (A to H). However, the trend of increasing
potassium count rate in less weathered material is evident. [Amd GG2/01/2017]
170
The principle of the Neutron Porosity method is to irradiate the target materials with fast
neutrons. The neutrons collide with particles having similar mass as the neutrons in the target
material, reducing their speed and becoming thermal neutrons. Within the ground, those
particles that would normally have similar mass as the neutrons are mainly hydrogen nuclei.
If the ground is saturated, the hydrogen content equates with water content and that in turn is
related to porosity. So the neutron porosity log gives an indication of porosity if the target
material is saturated. [Amd GG2/01/2017]
Based on the relative moisture content contrast between the target materials, the
technique can be used in open and steel-cased drillholes to identify weak layers in saturated
ground at a practical logging speed of 1 m/min. However, in unsaturated ground, the relative
moisture content between target materials does not truly reflect the porosity and misleading
results will be given by the method. [Amd GG2/01/2017]
The method does not work where plastic casing is used because the hydrogen molecules
in the plastic absorb the neutrons and affect the results. [Amd GG2/01/2017]
With suitable modifications of equipment, the land survey techniques, such as seismic
refraction, magnetic and gravimetric techniques, may be extended to the marine environment.
Of greater use, however, are the techniques that have been developed specifically for offshore
work; these are described in the following three sections. It is necessary to apply tidal
corrections to the data obtained, reducing them to an appropriate datum level for proper
interpretation. It is also important to establish precise survey control if the capacity for
detailed structural identification is to be exploited fully. Where appropriate, electronic
navigation systems should be employed.
In Hong Kong, the presence of sewage-rich seabed layers and certain naturally gassy
marine mud deposits results in 'masked zones', which can severely limit the effectiveness of a
geophysical survey.
33.3.2 Echo-sounding
A continuous water depth profile along the track of a survey vessel is obtained by using
an instrument that measures the time taken for a short pulse of a high frequency sound wave to
travel from a transducer attached to the survey vessel down to the seabed and back again.
Such profiles are combined to produce a bathymetric chart. However, additional control may
be required to ascertain whether the sounding is reproducing reflections from soft surface
sediments or higher density material underneath, and dual frequency sounders may be useful
for this.
171
The results may give a visual representation of geological features, but quantitative data
on depths to interfaces can only be determined if velocities of transmission are known.
There are two main limitations to the technique. Firstly, it cannot usually delineate the
boundary between two different materials that have similar geophysical characteristics;
secondly, in water depths of less than about 2 m, near-seabed reflectors may be obscured by
multiple reflections originating from the seabed. Other problems are described in Table 11.
Electrical resistivity may be used to assess the corrosivity of soils towards ferrous
materials. Conventional traverses with fixed intervals between electrodes enable rapid
coverage of the ground and the location of areas of low resistivity. The spacing between
electrodes should be appropriate to the depth of burial of the ferrous material. The
conventional 'expansion' technique using "depth probes" (see Section 33.2.1) may also be used
to determine the variation in soil resistivity with depth. Generally, the likelihood of severe
corrosion decreases as the resistivity rises (see Chapter 13 and Table 12).
The Gamma Density and Spectral Gamma Ray methods (see Sections 33.2.5 and 33.2.6
for further elaboration) are recommended for use as supplementary ground investigation
techniques to help to identify weak layers in the ground. These methods have been included
in CEDD’s ground investigation term contracts to facilitate their use in government projects.
[Amd GG2/01/2017]
Useful results may be obtained from the Neutron Porosity method (see Section 33.2.7)
in identifying weak layers in ground that is saturated with water. However, in unsaturated
ground, the method can give misleading results. [Amd GG2/01/2017]
The Self Potential method, Acoustic Borehole Televiewer method, 4-arm Dipmeter
method, 3-arm Caliper method and Electrical Cylinder method did not give consistent and
reliable results in the identification of weak layers. [Amd GG2/01/2017]
173
The aims of laboratory testing of samples of soil and rock may be summarized as follows :
(a) to identify and classify the samples with a view to making use
of past experience with materials of similar geological age,
origin and condition, and
The general procedures for handling and labelling of samples in the field are given in
Section 19.10. Samples should be treated with equal care on arrival at the core store or at the
laboratory.
An important feature is a sufficient area for the temporary stacking of the samples, and
an adequate amount of bench space for the actual inspection. The following equipment should
be provided :
(e) a water supply and appropriate sieves for washing the lines
out of samples of soils to facilitate description of the coarser
particles, and for cleaning rock cores and block samples,
The examination and description of samples of soil and rock is one of the most important
aspects of ground investigation. The results of a ground investigation may need to be used
long after the disposal of the samples, in which case the descriptions are, in many cases, the
only remaining evidence of what was discovered.
Detailed guidance for the description of soils and rocks is given in Geoguide 3 (GCO,
1988).
36.2 Soil
All disturbed soil samples, both jar and bulk, should be examined individually and
described by means of a permanent record made either on site or shortly after the samples
arrive in the laboratory. It is customary during sample description to examine the ends of
undisturbed samples or to examine the jar sample obtained from the cutting shoe where it has
been used, or both. However, all undisturbed samples should be re-examined each time a
specimen is taken for testing as colour changes or drying of the sample may have taken place.
When it is known that no further soil testing is likely to be required, the remaining undisturbed
samples should be extruded and split down the middle for examination, description and
photographing.
36.3 Rock
A complete rock description should cover both the rock material and rock mass
characteristics. The latter cannot be determined from individual samples, but may be deduced
to some extent from many sample descriptions and other data. Where the material
characteristics are not obvious, thin sections are a valuable aid to first assessments made with
a hand lens.
In the examination and description of large rock samples and rock cores, particular
attention should be paid to the location and nature of discontinuities. The reduced level of
shear zones and other major discontinuities should be deduced and recorded. Other details
such as orientation, roughness and infilling should also be noted. If the discontinuities contain
infilling material, both this and the adjacent materials should be described. Where possible,
an undisturbed sample of both the infill and its surrounding material should be extracted for
testing purposes. For projects where the nature of discontinuities is particularly important, a
separate detailed discontinuity log should be prepared (Figure 35).
purpose of the photographs is to provide a continuous record, the same scale should be used
throughout. The photographs should be free from distortion normal to the surface and should
contain a clear scale.
In many cases, a field test will give more realistic results than a laboratory test because
of reduced problems of sample disturbance. However, there is a large body of practical
experience behind some of the common laboratory tests, and when the data derived from them
are used with skill, reliable predictions can be obtained. The general considerations set out
in the following four sections should be borne in mind.
Quality classes are defined in Section 19.2. It is essential that the sample used is of
sufficiently high quality for the test in question. Handling of samples in the field is described
in Section 19.10. When samples arrive in the laboratory, all necessary steps should be taken
to ensure that they are preserved and stored at their natural moisture content and suffer the
minimum amount of shock and disturbance. Very often tests are carried out on 'undisturbed'
samples which are far from undisturbed. In addition, the sampling process itself will have
released the initial state of stress in the sample.
In preparing the laboratory test specimen, there is further disturbance and unavoidable
change in the stress conditions, and hence the test is not generally carried out under the same
stress conditions as those which exist in the natural ground (see Section 37.4).
For disturbed samples, the amount of soil required for any particular test is given in
Table 7. As the behaviour of the ground is greatly affected by discontinuities, 'undisturbed'
samples should ideally be sufficiently large to include a representative pattern of these
discontinuities. This can often be achieved by the use of large 'undisturbed' samples.
Where the test can be carried out under several different sets of conditions, e.g. in the
179
determination of soil strength, the particular test selected should be the one in which the
conditions correspond most closely to those that will exist in the field at the particular time
which is being considered in the design.
Some laboratory tests are suitable only for particular types of soil. In cases, where a
test has been carried out and it is found later that the test was not relevant to the actual sample
used, the result should be discarded.
180
The behaviour of rock masses is often controlled by the nature of the discontinuities
present and their orientation to the stresses created by the works or during their construction.
In most cases, the scale of discontinuities is such that tests on laboratory specimens may yield
results which cannot be applied directly to the behaviour of the rock mass. In considering
laboratory tests on rock, a clear distinction needs to be made between tests which relate to the
behaviour of the rock mass as affected by the proposed construction and tests which are relevant
only to the rock material.
Part VI
The essential requirement of a field report is that it should contain all the data necessary
for the subsequent interpretation and use of the borehole or field test. Field report forms
should be easy to fill in and well laid out so as to encourage the operator or field supervisor to
record all necessary data. Such forms can in many cases be based upon the illustrative logs
contained in this Geoguide, but these need not be regarded as standard as other forms may also
be satisfactory. Examples of other field report forms can be found in BSI (1990a) and the
appropriate Parts of BSI (2011a, 2011b, 2012a, 2012b, 2012c, 2012d, 2012e, 2012f).
[Amd GG2/01/2017]
The existing ground level, the location of any boreholes, and the location and level of
any points of sampling or testing, should always be recorded. Where possible, the locations
should take the form of reference coordinates based on the Hong Kong Metric Grid and levels
should be referenced to the Hong Kong Principal Datum.
Daily reports form the basis of good field reports on rotary drilling. It is not uncommon
for drillers to keep their records on odd scraps of paper while drilling is in progress and to make
up their daily report forms from these notes at the end of the day. This practice should be
strongly discouraged and the driller should be provided with a standard notebook which can, if
necessary, be checked against the daily report at a later date.
183
A copy of all descriptive reports should normally be lodged in the data bank of the
Geotechnical Information Unit (see Appendix B).
40.2.2 Introduction
The report should have an introduction stating for whom the work was done, the nature
of the investigation and its general location, the purpose for which the investigation was made
and the period of time over which the work was carried out.
should include street names together with Hong Kong Metric Grid references and a location
map at an appropriate scale. The description should also include general statements on site
conditions at the time of investigation.
40.2.4 Geology
An account should be given of the geology of the site, and the sources from which the
information was obtained should be stated (see Section 4.2). The amount of the data included
will depend upon the nature of the work being planned and also upon the amount of data
available. The soil and rock types identified and described in the report should be linked with
the known geology of the site, see Geoguide 3 (GCO, 1988).
An account should be given of the methods of investigation and testing used. It should
include a description of all equipment used, e.g. types of drilling rigs and tools. A note should
be made of any difficulties experienced, e.g. problems in recovering samples. The dates when
the exploratory work was done should also be recorded, together with a note about the weather
conditions where appropriate. The report should contain a drawing indicating the positions
of all pits, boreholes, field tests, etc. It should contain sufficient topographical information so
that these positions can be located at a later date.
(1) General. The final borehole logs should be based on the visual examination and
description of the samples, the laboratory test results where appropriate, the driller's daily
report forms and what is known of the geology of the site. Being an interpretation of ground
data which may at times be conflicting, the logs should be finalised only when the appropriate
field and laboratory work has been completed. It is important that all relevant data collected
by the driller, once checked and amended where necessary, should be recorded.
The method of presentation of the data is a subject on which there can be no hard and
fast rules. In principle, the borehole logs should give a picture in diagrams and words of the
ground profile at the particular point where the borehole was formed. The extent to which
minor variations in soil and rock types should be recorded, together with any discontinuities
and anomalies, will depend on the various purposes for which the information will be used.
Most organizations carrying out site investigation have standard forms for borehole logs.
It is seldom practicable in these to make allowance for all data which may possibly need to be
recorded. It is therefore important that an adequate space for remarks is available to allow a
record to be made of items that are not specifically covered. An expedient which makes a
standard form rather more flexible is to leave one or more columns without headings so that
they can be used according to the data to be recorded.
All borehole logs are a compromise between what it is desirable to record and what can
185
be accommodated. What is actually presented will need to be considered individually for each
investigation. Where the data are copious, it may be preferable to record part of them
elsewhere in the report, with a cross-reference on the logs. The subsections which follow
indicate the data which a well-prepared borehole log may contain.
(2) General Data Common to All Logs. The following should be recorded on all logs :
(j) diameter of casing and depth to which the casing was taken,
(k) a depth scale such that the depth of sampling, tests and
change in ground conditions can be readily determined,
(3) Legend and Symbols. The ground profiles should be illustrated by means of a
legend using the symbols illustrated on figures in this document, and more fully presented in
Geoguide 3 (GCO, 1988). The legend is most commonly placed near the centre of the sheet,
which enables reduced levels, depths, thicknesses and sampling data to be arranged
conveniently on either side. An alternative is to have it as the extreme right hand column,
which enables the logs of adjacent and nearby boreholes to be readily compared without folding
or cutting the sheets.
Apart from the symbols referred to above, no recommendations are given for the many
186
other symbols required for the preparation of borehole logs. Many different types are in use,
and provided an adequate key is given with every set of borehole logs, there should be no
difficulty in interpreting them. The symbols may be given on a separate sheet or on each sheet.
Both methods have advantages and corresponding disadvantages. The first saves space on
the actual logs, thus enabling a greater depth to be logged on each sheet or a larger 'remarks'
space to be provided. It does have the disadvantage that the reader may need constantly to
refer back to the key.
(4) Light Cable Percussion Boring. For light cable percussion boring, in addition to
the items referred to in Sections 40.2.6(2) and 40.2.6(3), the following information should be
recorded in the log :
(b) The depth and level of each change of zone or material type.
(c) The depth of the top and bottom of each tube sample, or bulk
sample and its type (see Chapter 19); the depth of each small
disturbed sample.
(d) The depth at the top and bottom of each borehole test, and the
nature of the test.
(5) Rotary Drilling. For rotary drilling, in addition to the items referred to in
Sections 40.2.6(2) and 40.2.6(3), the following information should be recorded in the log :
(c) The depth of the start and finish of each core run.
(e) For rock, the fracture state, expressed in terms of one or more
of the following : rock quality designation (RQD), solid core
recovery or fracture index (GCO, 1988).
(f) The date when each section of the core was drilled.
(g) An indication of the drilling water recovery for each core run,
with a note on any change in colour.
(h) A record of the depth of water in the hole at the start and
finish of a shift and the depth of the casing, where used, at the
time the observations were made.
The report should contain a plan showing the precise location and top level of each
borehole (see Chapter 39).
188
Where test procedures are covered by recognized standards, the reporting of the results
should be in accordance with those standards; where they are not so covered, relevant data
should be given. For example, in a triaxial compression test the actual numerical result on
each specimen should be given and not only the interpreted parameters. Where an extensive
programme of testing has been undertaken, a summary should be provided in addition to the
detailed results. The precise test carried out should also be stated without ambiguity. Where
the test is reasonably standard, for instance "consolidated drained triaxial compression test on
100 mm diameter samples", the name alone will suffice, but where the test is not standard, a
full description should be given.
The visual descriptions of all samples tested should appear in the report. The precise
method of recording them will depend upon circumstances. It may be convenient to show them
on the same sheets as the results of the laboratory tests, or a separate table may be preferable.
In any event, the descriptions should all appear in one place. At times, the results of
the laboratory tests, and in particular the identification tests, will indicate a soil different from
that indicated by the visual description. The original description should not be discarded on
that account but should be preserved as a record of the observer's opinion. If soil descriptions
have been modified in the light of laboratory test data, this should be indicated clearly in the
report, see Geoguide 3 (GCO, 1988). The laboratory report forms and data sheets should be
filed for possible future reference (see Section 40.2.1).
Methods of analysing ground data and applying them to the solution of engineering
problems are not covered in this Geoguide. Guidance on analysis and application of ground
data may be found in various British Standards (e.g. BSI, 1974; 1986; 1991; 2004; 2007; 2009)
and local guidance documents (e.g. Geotechnical Manual for Slopes and Geoguide 1).
Sections 40.3.2 to 40.3.9 deal with the form of the report, and list the most common topics on
which advice and recommendations are required. These sections also contain some guidance
on what should be included. The topics are listed briefly under the general headings : design,
construction expedients, sources of materials, and failure. It is likely that in many cases the
client commissioning the investigation will indicate those aspects of the project on which he
requires advice and recommendations; the topics listed below are intended as a guide where
this may not have been done. [Amd GG2/01/2017]
The data on which the analysis and recommendations are based should be clearly
indicated. The information generally comes under two separate headings :
constructed.
40.3.4 Design
The following list, which is by no means exhaustive, indicates the topics on which advice
and recommendations are often required, and also what should be included in the report.
Comments and recommendations are often required on the points listed below. Safety
aspects should be included where appropriate.
(c) Groundwater: likely flow, head and quantity and how to deal
with it.
40.3.7 Failures
Where site investigation has been undertaken in an attempt to identify the cause of
failures the undermentioned points may be relevant.
40.3.8 Calculations
Where calculations have been made, they should be included as an appendix, or a clear
indication of the methods used should be given.
40.3.9 References
Factual engineering geological and hydrogeological data relating to the tunnel project
should be fully documented including any field data obtained from the excavation faces or
inferred from the equipment/processes adopted for the tunnel works. [Amd GG2/01/2017]
Survey and monitoring reports should include factual data, details of the survey and
monitoring methods, and equipment/system calibration. [Amd GG2/01/2017]
References
Addison, R. (1986). Geology of Sha Tin, 1:20 000 Sheet 7. Hong Kong Geological Survey
Memoir No. 1, Geotechnical Control Office, Hong Kong, 85 p.
Akroyd, T.N.W. (1969). Laboratory Testing in Soil Engineering. Soil Mechanics Ltd,
London, 249 p.
Allen, P.M. & Stephens, E.A. (1971). Report on the Geological Survey of Hong Kong, 1967-
1969. Hong Kong Government Press, 116 p, plus 2 maps.
American Public Health Association (1985). Standard Methods for the Examination of Water
and Wastewater. (Sixteenth edition). Part 427-Sulfide. American Public Health
Association, Washington D.C., pp 470-478.
Anderson, M.G. (1984). Prediction of Soil Suction for Slopes in Hong Kong. GCO
Publication No. 1/84, Geotechnical Control Office, Hong Kong, 242 p.
Anderson, M.G., McNicholl, D.P. & Shen, J.M. (1983). On the effect of topography in
controlling soil water conditions, with specific regard to cut slope piezometric levels.
Hong Kong Engineer, vol. 11, no. 11, pp 35-41.
Arthur, J.R.F. & Roscoe, K.H. (1961). An earth pressure cell for the measurement of normal
and shear stresses. Civil Engineering and Public Works Review, vol. 56, pp 765-776.
ASTM (1985a). Standard test method for penetration test and split-barrel sampling of soil.
Test Designation D1586-67. 1985 Annual Book of ASTM Standards, American Society
for Testing and Materials, Philadelphia, vol. 04.08, pp 298-303.
ASTM (1985b). Standard test method for density and unit weight of soil in-place by the
rubber balloon method. Test Designation D2167-84. 1985 Annual Book of ASTM
Standards, American Society for Testing and Materials, Philadelphia, vol. 04.08, pp 342-
347.
ASTM (1985c). Standard test method for triaxial compressive strength of undrained rock core
specimens without pore pressure measurements. Test Designation D2664-80. 1985
Annual Book of ASTM Standards, American Society for Testing and Materials,
Philadelphia, vol. 04.08, pp 429-434.
ASTM (1985d). Standard test method for laboratory determination of pulse velocities and
ultrasonic elastic constants of rock. Test Designation D2845-83. 1985 Annual Book
of ASTM Standards, American Society for Testing and Materials, Philadelphia,
vol. 04.08, pp 445-452.
195
ASTM (1985e). Standard test methods for density of soil and soil aggregate in place by
nuclear method (shallow depth). Test Designation D2922-81. 1985 Annual Book of
ASTM Standards, American Society for Testing and Materials, Philadelphia, vol. 04.08,
pp 463-472.
ASTM (1985f). Standard test methods for direct tensile strength of intact rock core specimens.
Test Designation D2936-84. 1985 Annual Book of ASTM Standards, American Society
for Testing and Materials, Philadelphia, vol. 04.08, pp 473-477.
ASTM (1985g). Standard test method for unconfined compressive strength of intact rock core
specimens. Test Designation D2938-79. 1985 Annual Book of ASTM Standards,
American Society for Testing and Materials, Philadelphia, vol. 04.08, pp 484-487.
ASTM (1985h). Standard test methods for moisture content of soil and soil aggregate in
place by nuclear methods (shallow depth). Test Designation D3017-78. 1985 Annual
Book of ASTM Standards, American Society for Testing and Materials, Philadelphia,
vol. 04.08, pp 508-513.
ASTM (1985i). Standard test method for direct shear test of soils under consolidated drained
conditions. Test Designation D3080-72 (Reapproved 1979). 1985 Annual Book of
ASTM Standards, American Society for Testing and Materials, Philadelphia, vol. 04.08,
pp 514-518.
ASTM (1985j). Standard test method for elastic moduli of intact rock core specimens in
uniaxial compression. Test Designation D3148-80. 1985 Annual Book of ASTM
Standards, American Society for Testing and Materials, Philadelphia, vol. 04.08, pp 519-
525.
ASTM (1985k). Standard test method for deep, quasi-static, cone and friction cone
penetration tests of soil. Test Designation D3441-79. 1985 Annual Book of ASTM
Standards, American Society for Testing and Materials, Philadelphia, vol. 04.08, pp 550-
557.
Au, S.W.C. (1986). Decomposed dolerite dykes as a cause of slope failure. Hong Kong
Engineer, vol. 14, no. 2, pp 33-36 (Corrigendum, vol. 14, no. 9, p 24). (Discussion,
vol. 14, no. 5, p 13, and no. 8, p 43).
Baguelin, F., Jezequel, J.F. & Shields, D.H. (1978). The Pressuremeter and Foundation
Engineering. Trans Tech Publications, Clausthal, Germany, 617 p.
Bauer, G.E. & Demartinecourt, J.P. (1982). The modified borehole shear device.
Geotechnical Testing Journal, vol. 6, pp 24-29.
Bauer, G.E. & Demartinecourt, J.P. (1985). The application of the modified borehole shear
device to a sensitive clay. Geotechnical Engineering, vol. 16, pp 167-189.
Beattie, A.A. & Lam, C.L. (1977). Rock slope failures - their prediction and prevention.
Hong Kong Engineer, vol. 5, no. 7, pp 27-40 (Discussion, vol. 5, no. 9, pp 27-29).
196
Beggs, C.J. (1983). A review of investigation and sampling methods in the recent sediments
in Hong Kong. Proceedings of the Meeting on the Geology of Surficial Deposits in
Hong Kong, Hong Kong, pp 11-18. (Published as Geological Society of Hong Kong,
Bulletin no. 1, edited by W.W.S. Yim, 1984).
Benson, R.P., Murphy, D.K. & McCreath, D.R. (1970). Modulus testing of rock at the
Churchill Falls Underground Powerhouse, Labrador. Proceedings of the Symposium
on Determination of the In Situ Modulus of Deformation of Rock. American Society
for Testing and Materials Special Technical Publication, no. 477, pp 89-116.
Bieniawski, Z.T. (1975). The point load test in geotechnical practice. Engineering Geology,
vol. 9, pp 1-11.
Bishop, A.W. (1948). A new sampling tool for use in cohesionless sands below groundwater
level. Géotechnique, vol. l, pp 125-131.
Bishop, A.W. & Green, P.A. (1973). The development and use of trial embankments.
Proceedings of the Symposium on Field Instrumentation in Geotechnical Engineering,
London, pp 13-37.
Bishop, A.W. & Henkel, D.J. (1976). The Measurement of Soil Properties in the Triaxial Test.
Edward Arnold, London, 227 p.
Bishop, A.W. & Little, A.L. (1967). The influence of the size and orientation of the sample
on the apparent strength of the London Clay at Maldon, Essex. Proceedings of the
Geotechnical Conference on the Shear Strength of Natural Soils and Rocks, Oslo, vol. l,
pp 89-96.
Bjerrum, L. (1973). Problems of soil mechanics and construction on soft clays and
structurally unstable soils (collapsible, expansive and others). Proceedings of the
Eighth International Conference on Soil Mechanics and Foundation Engineering,
Moscow, vol. 2.3, pp 111-159. (Reprinted in Norwegian Geotechnical Institute,
Publication no. 100, 1974, 53 p).
Bjerrum, L. & Anderson, K.H. (1972). Insitu measurement of lateral pressures in clay.
Proceedings of the Fifth European Conference on Soil Mechanics and Foundation
Engineering, Madrid, vol. l, pp 11-20. (Reprinted in Norwegian Geotechnical Institute,
Publication no. 91, 1972, pp 11-20).
Bjerrum, L., Kenney, T.C. & Kjaernsli, B. (1965). Measuring instrumentation for strutted
excavations. Journal of the Soil Mechanics and Foundations Division, American
Society of Civil Engineers, vol. 91, no. SMI, pp 111-114. (Reprinted in Norwegian
Geotechnical Institute, Publication no. 64, 1965, pp 1-17).
197
Bjerrum, L., Nash, J.K.T.L., Kennard, R.M. & Gibson, R.E. (1972). Hydraulic fracturing in
field permeability testing. Géotechnique, vol. 22, pp 319-332. (Reprinted in
Norwegian Geotechnical Institute, Publication no. 94, 1972, pp 1-12).
Blacker, P. & Seaman, J.W. (1985). A review of current nearshore and offshore site
investigation practice in waters around Hong Kong. Proceedings of the Conference on
Geological Aspects of Site Investigation, Hong Kong, pp 41-58. (Published as
Geological Society of Hong Kong, Bulletin no. 2, edited by I. McFeat-Smith, 1985).
Brand, E.W. (1994). Bibliography on the Geology and Geotechnical Engineering of Hong
Kong to May 1994 (GEO Report No. 39). Geotechnical Engineering Office, Hong
Kong, 202 p.
Brand, E.W., Burnett, A.D. & Styles, K.A. (1982). The Geotechnical Area Studies
Programme in Hong Kong. Proceedings of the Seventh Southeast Asian Geotechnical
Conference, Hong Kong, vol. 1, pp 107-123.
Brand, E.W., Hencher, S.R. & Youdan, D.G. (1983a). Rock slope engineering in Hong Kong.
Proceedings of the Fifth International Rock Mechanics Congress, Melbourne, vol. 1,
pp Cl7-C24.
Brand, E.W. & Phillipson, H.B. (1984). Site investigation and geotechnical engineering
practice in Hong Kong. Geotechnical Engineering, vol. 15, no. 2, pp 97-153.
Brand, E.W., Phillipson, H.B., Borrie, G.W. & Clover, A.W. (1983b). Insitu direct shear tests
on Hong Kong residual soils. Proceedings of the International Symposium on Soil and
Rock Investigation by Insitu Testing, Paris, vol. 2, pp 13-17. (Discussion, vol. 3, pp 55-
56).
Brand, E.W. & Premchitt, J. (1980). Shape factors of cylindrical piezometers. Geotechnique,
vol. 30, pp 369-384.
Brenner, R.P. & Phillipson, H.B. (1979). Sampling of residual soils in Hong Kong.
Proceedings of the International Symposium on Soil Sampling, Singapore, pp 109-120.
Brian-Boys, K.C. & Howells, D.J. (1984). Model Specification for Prestressed Ground
Anchors. GCO Publication No. 3/84, Geotechnical Control Office, Hong Kong, 127 p.
[Amd GG2/01/2017]
198
Briaud, J.L. & Gambin, M. (1984). Suggested practice for drilling boreholes for
pressuremeter testing. Geotechnical Testing Journal, vol. 7, pp 36-40.
Broch, E. & Franklin, J.A. (1972). The point load strength test. International Journal of
Rock Mechanics and Mining Sciences, vol. 9, pp 667-697.
Brown, E.T. (Editor) (1981). Rock Characterization Testing and Monitoring: ISRM
Suggested Methods, Pergamon Press, Oxford, 211 p.
[Amd GG2/01/2017]
BSI (1974). Code of Practice for Foundations for Machinery (CP 2012:1974). Part 1 -
Foundations for Reciprocating Machines. British Standards Institution, London, 36 p.
BSI (1986). British Standard Code of Practice for Foundations (BS 8004:1986). British
Standards Institution, London, 150 p.
BSI (1990). Methods of Test for Soils for Civil Engineering Purposes - Parts 1 to 9: (BS 1377,
Parts 1 to 9:1990). British Standards Institution, London, 406 p.
[Amd GG2/01/2017]
BSI (1991). Cathodic Protection - Part 1: Code of Practice for Land and Marine Applications
- (formerly CP 1021) (BS 7361-1:1991). British Standards Institution, London, 122 p.
[Amd GG2/01/2017]
BSI (2004). Eurocode 7: Geotechnical Design - Part1: General Rules (BS EN 1997-1:2004).
British Standards Institution, London, 174 p. [Amd GG2/01/2017]
BSI (2006). Geotechnical Investigation and Testing - Sampling Methods and Groundwater
Measurements - Part 1: Technical Principles for Execution (BS EN ISO 22475-1:2006).
British Standards Institution, London, 134 p. [Amd GG2/01/2017]
BSI (2007). Eurocode 7 - Geotechnical Design - Part 2: Ground Investigation and Testing
(BS EN 1997-2:2007). British Standards Institution, London, 202 p. [Amd GG2/01/2017]
BSI (2008). Safety Precautions and Procedures for the Construction and Descent of Machine-
bored Shafts for Piling and Other Purposes (BS 8008:1996+A1:2008). British
Standards Institution, London, 20 p. [Amd GG2/01/2017]
199
BSI (2009). Code of Practice for Earthworks (BS 6031:2009). British Standards Institution,
London, 128 p. [Amd GG2/01/2017]
BSI (2010). Code of Practice for Site Investigations (BS 5930:1999+A2:2010). British
Standards Institution, London, 206 p. [Amd GG2/01/2017]
BSI (2011a). Geotechnical Investigation and Testing - Field Testing - Part 2: Dynamic
Probing (BS EN ISO 22476-2:2005+A1:2011). British Standards Institution, London,
40 p. [Amd GG2/01/2017]
BSI (2011b). Geotechnical Investigation and Testing - Field Testing - Part 3: Standard
Penetration Test (BS EN ISO 22476-3:2005+A1:2011). British Standards Institution,
London, 26 p. [Amd GG2/01/2017]
BSI (2012a). Geotechnical Investigation and Testing - Geohydraulic Testing - Part 2: Water
Permeability Tests in a Borehole using Open Systems (BS EN ISO 22282-2:2012).
British Standards Institution, London, 36 p. [Amd GG2/01/2017]
BSI (2012b). Geotechnical Investigation and Testing - Geohydraulic Testing - Part 3: Water
Pressure Tests in Rock (BS EN ISO 22282-3:2012). British Standards Institution,
London, 36 p. [Amd GG2/01/2017]
BSI (2012e). Geotechnical Investigation and Testing - Geohydraulic Testing - Part 6: Water
Permeability Tests in a Borehole using Closed Systems (BS EN ISO 22282-6:2012).
British Standards Institution, London, 24 p. [Amd GG2/01/2017]
BSI (2012f). Geotechnical Investigation and Testing - Field Testing, Part 1: Electrical Cone
and Piezocone Penetration Test (BS EN ISO 22476-1:2012). British Standards
Institution, London, 46 p. [Amd GG2/01/2017]
Burland, J.B., Moore, J.F.A. & Smith, P.D.K. (1972). A simple and precise borehole
extensometer. Géotechnique, vol. 22, pp 174-177.
Burnett, A.D. & Styles, K.A. (1982). An approach to urban engineering geological mapping
as used in Hong Kong. Proceedings of the Fourth International Congress of the
International Association of Engineering Geology, New Delhi, vol. 1, pp 167-176.
200
Carter, J.P. & Booker, J.R. (1984). Determination of the deformation modulus of rock from
tunnel and borehole loading tests. Proceedings of the Fourth Australia-New Zealand
Conference on Geomechanics, Perth, vol. 1, pp 509-513.
Chan, M.P. & Lau, S.H. (1986). Drilling in Hong Kong. Contractor (Hong Kong), May
1986, pp 11-14.
Cheffins, D.W. & Chisholm, N.W.T. (1980). Engineering and industrial photogrammetry.
Developments in Close Range Photogrammetry - 1, edited by K.B. Atkinson, pp 149-
180. Applied Science Publishers Ltd, London.
Chiang, Y.C. & Ho, Y.M. (1980). Pressuremeter method for foundation design in Hong Kong.
Proceedings of the Sixth Southeast Asian Conference on Soil Engineering, Taipei, vol. l,
pp 31-42.
Cipullo, A. & Irfan, T.Y. (1984). Discussion on "The determination of the uniaxial
compressive strength of rock material - a review of current practice in Hong Kong" by
T.I. Gamon & P.L. Szeto. Proceedings of the Conference on Geological Aspects of Site
Investigation, Hong Kong, pp 69-71. (Discussion, pp 71-72). (Published as
Geological Society of Hong Kong, Bulletin no. 2, edited by I. McFeat-Smith, 1985).
Clayton, C.R.I. (1984). Sample disturbance and BS 5930. Proceedings of the 20th Regional
Meeting of the Engineering Group of the Geological Society, Guildford, UK, pp 31-41.
(Published as Site Investigation Practice : Assessing BS 5930, edited by A.B. Hawkins,
Geological Society, Engineering Geology Special Publication no. 2, 1986) (Also
published in preprint vol. 2, pp 61-75).
Clayton, C.R.I., Simons, N.E. & Mathews, M.C. (1982). Site Investigation, A Handbook for
Engineers. Grenada, London, 424 p.
Cole, K.W. & Burland, J.B. (1972). Observations of retaining wall movements associated
with a large excavation. Proceedings of the Fifth European Conference on Soil
Mechanics and Foundation Engineering, Madrid, vol. l, pp 445-453.
Craig, D.J. & Gray, I. (1985). Groundwater Lowering by Horizontal Drains. GCO
Publication No. 2/85, Geotechnical Control Office, Hong Kong, 123 p.
Culshaw, M.G. & Waltham, A.C. (1987). Natural and artificial cavities as ground engineering
hazards. Quarterly Journal of Engineering Geology, vol. 20, pp 139-150.
201
Dearman, W.R. & Irfan, T.Y. (1978). Assessment of the degree of weathering in granite using
petrographic and physical index tests. UNESCO International Symposium on
Deterioration and Protection of Stone Monuments, Paris, paper 2.3, 35 p.
Decker, R.S. & Dunnigan, L.P. (1977). Development and use of the Soil Conservation Service
Dispersion Test. Dispersive Clays, Related Piping, and Erosion in Geotechnical
Projects. American Society for Testing and Materials, Special Technical Publication
no. 623, pp 94-109.
Deere, D.W. & Miller, R.P. (1966). Engineering Classification and Index Properties for Intact
Rock. Report AWFL-TR-65-116, Air Force Weapons Laboratory (WLDC), Kirtland
Air Force Base, New Mexico, 273 p.
Delft Soil Mechanics Laboratory (1977). Site Investigations. Delft Soil Mechanics
Laboratory, Delft, the Netherlands, 144 p.
De Mello, V.F.B. (1971). The standard penetration test. Proceedings of the Fourth
Panamerican Conference on Soil Mechanics and Foundation Engineering, San Juan,
Puerto Rico, vol. 1, pp 1-86.
Department of Transport (1976). Department of Transport Specification for Road and Bridge
Works, Clause 2722. Her Majesty's Stationery Office, London, pp 174-175.
DeRuiter, J. (1982). The static cone penetration test, state of the art report. Proceedings of
the Second European Symposium on Penetration Testing, Amsterdam, vol. 2, pp 389-
405.
DiBiagio, E. & Myrvoll, F. (1982). Field instrumentation for soft clay. Soft Clay
Engineering, edited by E.W. Brand & R.P. Brenner, pp 697-736. Elsevier Scientific
Publishing Company, Amsterdam.
Dunnicliff, C.J. (1971). Equipment for field deformation measurements. Proceedings of the
Fourth Panamerican Conference on Soil Mechanics and Foundation Engineering, San
Juan, Puerto Rico, vol. 2, pp 319-332.
Endicott, L.J. (1984). Site investigations for roads and tunnels in weathered rock.
Proceedings of the Symposium on Geotechnical Aspects of Mass and Material
Transportation, Bangkok, pp 133-151.
Evans, N.C. & Irfan, T.Y. (1991). Landslide Studies 1991 : Blast-induced Rock Slide at Shau
Kei Wan, November 1991. Special Project Report No. SPR 6/91, Geotechnical
Engineering Office, Hong Kong, 115 p. [Amd GG2/01/2017]
202
Evans, G.L., McNicholl, D.P. & Leung, K.W. (1982). Testing in hand dug caissons.
Proceedings of the Seventh Southeast Asian Geotechnical Conference, Hong Kong,
vol. l, pp 317-332.
Flanagan, C.P. & Holmgren, G.G.S. (1977). Field methods for determination of soluble salts
and percent sodium from extract for identifying dispersive clay soils. Dispersive Clays,
Related Piping, and Erosion in Geotechnical Projects. American Society for Testing
and Materials, Special Technical Publication no. 623, pp 121-134.
Foott, R., Koutsoftas, D.C. & Handfelt, L.D. (1987). Test fill at Chek Lap Kok, Hong Kong.
Journal of Geotechnical Engineering, American Society of Civil Engineers, vol. 113,
pp 106-126.
Forth, R.A. & Platt-Higgins, P.M. (1981). Methods of investigation of weathered rocks in
Hong Kong. Proceedings of the International Symposium on Weak Rock, Tokyo, vol. 2,
pp 159-166. (Discussion, vol. 3, p 1387).
Franklin, J.A. (1985). A direct shear machine for testing rock joints. Geotechnical Testing
Journal, vol. 8, pp 25-29.
Franklin, J.A., Broch, E. & Walton, G. (1971). Logging the mechanical character of rock.
Transactions of the Institution of Mining and Metallurgy, vol. 80, pp Al-A9.
Franklin, J.A. & Hoek, E. (1970). Developments in triaxial testing equipment. Rock
Mechanics, vol. 2, pp 223-228.
Froome, K.D. & Bradsell, R.H. (1966). A new method for measurement of distances up to
5 000 ft by means of a modulated light beam. Journal of Scientific Instruments, vol. 43,
pp 129-133.
Frost, R.J. (1973). Some testing experience and characteristic of boulder - gravel fill in earth
dams. Evaluation of Relative Density and Its Role in Geotechnical Projects Involving
Cohesionless Soils. American Society for Testing and Materials, Special Technical
Publication no. 523, pp 207-233.
Fung, A.K.L., Foott, R., Cheung, R.K.H. & Koutsoftas, D.C. (1984). Practical conclusions
from the geotechnical studies on offshore reclamation for the proposed Chek Lap Kok
Airport. Hong Kong Engineer, vol. 12, no. 6, pp 17-26. (Discussion, vol. 6, no. 10,
p. 53 and vol. 7, no. 2, pp 7-8).
Fyffe, S., Reid, W.M. & Summers, J.B. (1986). The push-in pressuremeter: 5 years offshore
experience. The Pressuremeter and Its Marine Applications. American Society for
Testing and Materials, Special Technical Publication no. 950.
Gamon, T.I. (1984a). A comparison between the core orienter and the borehole impression
device. Proceedings of the 20th Regional Meeting of the Engineering Group of the
Geological Society, Guildford, UK, pp 247-251. (Published as Site Investigation
Practice : Assessing BS 5930, edited by A.B. Hawkins, Geological Society, Engineering
203
Geology Special Publication no. 2, 1986) (Also published in preprint vol. 1, pp 228-
231). (Discussion, p 72).
Gamon, T.I. (1984b). The use of the point load test for the determination of strength of
weathered rocks in Hong Kong. Geological Society of Hong Kong Newsletter, vol. 2,
no. 4, pp 9-16.
Gamon, T.I. & Szeto, P.L. (1984). The determination of the uniaxial compressive strength of
rock material - a review of current practice in Hong Kong. Proceedings of the
Conference on Geological Aspects of Site Investigation, Hong Kong, pp 9-19.
(Published as Geological Society of Hong Kong, Bulletin no. 2, edited by I. McFeat-
Smith, 1985).
GCO (1984). Geotechnical Manual for Slopes. (Second edition). Geotechnical Control
Office, Hong Kong, 295 p.
GCO (1986). Hong Kong and Kowloon, Solid and Superficial Geology (1:20 000 map).
Hong Kong Geological Survey Map Series HGM20, Sheet 11. Geotechnical Control
Office, Hong Kong, 1 map.
GCO (1987). Geotechnical Area Studies Programme : Hong Kong and Kowloon. GASP
Report No. 1, Geotechnical Control Office, Hong Kong, 172 p.
GCO (1988). Guide to Rock and Soil Descriptions (Geoguide 3). Geotechnical Control
Office, Hong Kong, 189 p.
GEO (1993). Guide to Retaining Wall Design (Geoguide 1). (Second edition).
Geotechnical Engineering Office, Hong Kong, 267 p.
GEO (2016). Catalogue of Hong Kong Tunnels (up to February 2016). Geotechnical
Engineering Office, Hong Kong.
(http://www.cedd.gov.hk/eng/publications/reference/doc/HK%20Tunnel%20Cat.pdf)
[Amd GG2/01/2017]
GEO (2017a). Model Specification for Soil Testing (Geospec 3). Geotechnical Engineering
Office, Hong Kong, 340 p. [Amd GG2/01/2017]
GEO (2017b). Guide to Reinforced Fill Structure and Slope Design (Geoguide 6).
Geotechnical Engineering Office, Hong Kong, 236 p. [Amd GG2/01/2017]
204
Geological Society (1970). The logging of rock cores for engineering purposes. Geological
Society Engineering Group Working Party Report, Quarterly Journal of Engineering
Geology, vol. 15, pp 265-316.
Geological Society (1972). The preparation of maps and plans in terms of engineering
geology. Geological Society Engineering Group Working Party Report, Quarterly
Journal of Engineering Geology, vol. 5, pp 295-381.
Geological Society (1982). Land surface evaluation for engineering purposes. Geological
Society Engineering Group Working Party Report, Quarterly Journal of Engineering
Geology, vol. 15, pp 265-316.
Gibson, R.E. (1963). An analysis of system flexibility and its effect on timelag in pore-water
pressure measurements. Géotechnique, vol. 13, pp 1-11.
Goodman, R.E., Van, T.K. & Heuze, F.E. (1970). Measurement of rock deformability in
boreholes. Proceedings of the Tenth United States Symposium on Rock Mechanics,
Austin, Texas, pp 523-555.
Government of Hong Kong (1985). Buildings Ordinance (and Building Regulations). Laws
of Hong Kong, Chapter 123, revised edition 1985. Hong Kong Government Printer,
387 p. (Amended from time to time).
Griffiths, D.H. & King, R.F. (1983). Applied Geophysics for Geologists and Engineers : The
Element of Geophysical Prospecting. Pergamon Press, 230 p.
Griffiths, J.S. & Marsh, A.H. (1984). BS 5930 : The role of geomorphological and geological
techniques in a preliminary site investigation. Proceedings of the 20th Regional
Meeting of the Engineering Group of the Geological Society, Guildford, UK, pp 261-
267. (Published as Site Investigation Practice: Assessing BS 5930, edited by A.B.
Hawkins, Geological Society, Engineering Geology Special Publication no. 2, 1986).
(Also published in preprint vol. l, pp 249-259).
Gyenge, M. & Herget, G. (1977). Pit Slope Manual, Supplement 3-2 - Laboratory Tests for
Design Parameters. CANMET (Canada Centre for Mineral and Energy Technology),
CANMET Report 77-26, 74 p.
Haas, C.J. (1983). Proposed new standard test method for dimensional and shape tolerances
of rock core specimens. Geotechnical Testing Journal, vol. 6, pp 226-229.
HCL (2001). Detailed Study of Selected Landslides on Slope No. 11NE-D/C45, Hiu Ming
Street, Kwun Tong. Landslide Study Report No. LSR 7/2001, Geotechnical
Engineering Office, Hong Kong, 96 p. [Amd GG2/01/2017]
Handfelt, L.D., Koutsoftas, D.C. & Foott, R. (1987). Instrumentation for test fill in Hong
Kong. Journal of Geotechnical Engineering, American Society of Civil Engineers, vol.
113, pp 147-160.
205
Handy, R.L. & Fox, N.S. (1967). A soil borehole direct-shear test device. Highway
Research News, USA, no. 27, pp 42-52.
Hansen, A. (1982). Landslide hazard analysis. Slope Instability, edited by D. Brunsden &
D.B. Prior, John Wiley & Sons Ltd, Chichester, pp 523-602.
Head, K.H. (1986). Manual of Soil Laboratory Testing, Volume 3, Effective Stress Tests.
Halsted Press, New York, pp 743-1238.
Hencher, S.R. (1981). Report on Slope Failure at Yip Kan Street (11SW-D/C86) Aberdeen on
12th July 1981. Geotechnical Control Office Report No. GCO 16/81, Geotechnical
Control Office, Hong Kong, 26 p. [Amd GG2/01/2017]
Hencher, S.R. & Martin, R.P. (1982). The description and classification of weathered rocks
in Hong Kong for engineering purposes. Proceedings of the Seventh Southeast Asian
Geotechnical Conference, Hong Kong, vol. l, pp 125-142. (Discussion, vol. 2, pp 167-
168).
Hencher, S.R. & Martin, R.P. (1984). The failure of a cut slope on the Tuen Mun Road in
Hong Kong. Proceedings of the International Conference on Case Histories in
Geotechnical Engineering, St Louis, Missouri, vol. 2, pp 683-688.
Hencher, S.R., Massey, J.B. & Brand, E.W. (1984). Application of back analysis to some
Hong Kong landslides. Proceedings of the Fourth International Symposium on
Landslides, Toronto, vol. l, pp 631-638.
Hencher, S.R. & Richards, L.R. (1982). The basic frictional resistance of sheeting joints in
Hong Kong granite. Hong Kong Engineer, vol. 11, no. 2, pp 21-25.
Heuze, F.E. (1984). Suggested method for estimating the insitu modulus of deformation of
rock using the NX borehole jack. Geotechnical Testing Journal, vol. 7, pp 205-210.
Hilf, J.W. (1975). Compacted fill. Foundation Engineering Handbook, edited by H.F.
Winterkorn & H.Y. Fang, Van Nostrand Reinhold Company, New York, pp 244-311.
HKIE (1981). Guidance Notes on Hand-dug Caissons. Hong Kong Institution of Engineers,
15 p.
Ho, H.Y., King, J.P. & Wallace, M.I. (2006). A Basic Guide to Air Photo Interpretation in
Hong Kong. Applied Geoscience Centre, Department of Earth Sciences, University of
Hong Kong, 115 p. [Amd GG2/01/2017]
Hoek, E. & Bray, W.J. (1981). Rock Slope Engineering. (Third edition). Institution of
Mining and Metallurgy, London, 358 p.
Hoek, E. & Franklin, J.A. (1968). A simple triaxial cell for field and laboratory testing of rock.
Transactions of the Institution of Mining and Metallurgy, Section A, vol. 77, pp 22-26.
Holtz, W.G. (1948). The determination of limits for the control of placement moisture in high
rolled earth dams. Proceedings of the American Society for the Testing of Materials,
Philadelphia, pp 1240-1248.
Horner, P.C. & Sherrell, F.W. (1977). The application of air-flush rotary-percussion
techniques in site investigation. Quarterly Journal of Engineering Geology, vol. 10,
pp 207-221.
Houlsby, A.C. (1976). Routine interpretation of the Lugeon water test. Quarterly Journal
of Engineering Geology, vol. 9, pp 303-313.
Hucka, V. (1965). A rapid method of determining the strength of rocks insitu. International
Journal of Rock Mechanics and Mining Sciences, vol. 2, pp 127-134.
Hudson, J.A. & Ryley, M.D. (1978). Measuring horizontal ground movements. Tunnels and
Tunnelling, vol. 10, no. 2, pp 55-58.
Hvorslev, M.J. (1948). Subsurface Exploration and Sampling of Soils for Civil Engineering
Purposes. US Army Waterways Experiment Station, Vicksburg, Mississippi, 521 p.
Hvorslev, M.J. (1951). Time lag and permeability in groundwater observations. US Army
Waterways Experiment Station, Bulletin no. 36, 50 p.
IAEG (1981). Report of the commission on site investigations. Bulletin of the International
Association of Engineering Geology, no. 24, pp 185-226.
ICE (1976). Manual of Applied Geology for Engineers. Institution of Civil Engineers,
London, 375 p.
ICE (1978). Piling : Model Procedures and Specifications. Institution of Civil Engineers,
London, 161 p.
Idel, K.H., Muhs, H. & Von Soos, P. (1969). Proposal for "quality classes" in soil sampling
and the importance of boring methods and sampling equipment. Proceedings of the
Specialty Session on Site Investigation, Seventh International Conference on Soil
Mechanics and Foundation Engineering, Mexico City, pp 56-61.
207
IMMM (2003). Ground Investigation Working Party - Final Report. Institute of Materials,
Minerals and Mining, Hong Kong Branch, 46 p. [Amd GG2/01/2017]
Ireland, H.O., Moretto, C. & Vargas, M. (1970). The dynamic penetration test : a standard
that is not standardized. Géotechnique, vol. 20, pp 185-192. (Discussion, pp 452-
456).
Irfan, T.Y. & Powell, G.E. (l985). Engineering geological investigations for pile foundations
on a deeply weathered granitic rock in Hong Kong. Bulletin of the International
Association of Engineering Geology, no. 32, pp 67- 80.
ISRM (1978). Suggested methods for the quantitative description of discontinuities in rock
masses. International Journal of Rock Mechanics and Mining Sciences &
Geomechanics Abstracts, vol. 15, pp 319-368.
ISRM (1985). Suggested method for determining point load strength. International Journal
of Rock Mechanics and Mining Sciences & Geomechanics Abstracts, vol. 22, no. 2,
pp 51-60.
Johnson, E.E. (1982). Groundwater and Wells. Johnson Division, Universal Oil Products
Company, St Paul, Minnesota, 440 p.
Kenney, T.C. (1967). Field measurements of insitu stresses in quick clays. Proceedings of
the Geotechnical Conference on the Shear Strength of Natural Soils and Rocks, Oslo,
vol. l, pp 49-55. (Reprinted in Norwegian Geotechnical Institute, Publication no. 76,
1968, pp 19-25).
King, R.A. (1977). A review of soil corrosiveness with particular reference to reinforced earth.
Transport and Road Research Laboratory, Supplementary Report no. 316, Crowthorne,
Berkshire, 27 p.
Kjellman, W., Kallstenius, T. & Wager, O. (1950). Soil sampler with metal foils : device for
taking undisturbed samples of very great length. Proceedings of the Royal Swedish
Geotechnical Institute, no. l, pp 1-75.
Koirala, N.P., Hee, A. & Burnett, A.D. (1986). Geotechnical input to land use planning in
Hong Kong. Proceedings of the Conference on Planning and Engineering Geology
(22nd Regional Conference of the Engineering Group of the Geological Society),
Plymouth, UK, preprint vol., pp 729-739.
208
Koutsoftas, D.C., Foott, R. & Handfelt, L.D. (1987). Geotechnical investigations offshore
Hong Kong. Journal of Geotechnical Engineering, American Society of Civil
Engineers, vol. 113, pp 87-105.
Kruseman, G.P. & DeRidder, N.A. (1980). Analysis and evaluation of pumping test data.
International Institution for Land Reclamation and Improvement, Wageningen, The
Netherlands, Bulletin no. 11, 200 p.
Lambe, T.W. (1951). Soil Testing for Engineers. John Wiley & Sons, Inc., New York, 165 p.
Leach, B. & Herbert, R. (1982). The genesis of a numerical model for the study of the
hydrogeology of a steep hillside in Hong Kong. Quarterly Journal of Engineering
Geology, vol. 15, pp 243-259.
Leróueil, S. & Tavenas, F. (1981). Pitfalls of back analyses. Proceedings of the Tenth
International Conference on Soil Mechanics and Foundation Engineering, Stockholm,
vol. 1, pp 185-190.
Lumb, P. (1983). Engineering properties of fresh and decomposed igneous rocks from Hong
Kong. Engineering Geology, vol. 19, pp 81-94.
Marsland, A. (1971). Large insitu tests to measure the properties of stiff fissured clays.
Proceedings of the First Australia - New Zealand Conference on Geomechanics,
Melbourne, vol. 1, pp 180-189.
Marsland, A. (1972). Clays subjected to insitu plate tests. Ground Engineering, vol. 5, no. 6,
pp 24-31.
Marsland, A. (1973). Instrumentation of flood defense banks along the River Thames.
Proceedings of the Symposium on Field Instrumentation in Geotechnical Engineering,
London, pp 287-303.
Marsland, A. & Eason, B.J. (1973). Measurement of displacements in the ground below
loaded plates in deep boreholes. Proceedings of the Symposium on Field
Instrumentation in Geotechnical Engineering, London, pp 304-317.
Mayes, M. (1985). Which EDM? Land and Mineral Surveying, vol. 3, no. 11, pp 594-595.
McCann, D.M., Jackson, P.D. & Culshaw, M.G. (1987). The use of geophysical surveying
methods in the detection of natural cavities and mineshafts. Quarterly Journal of
Engineering Geology, vol. 20, pp 59-73.
209
McFeat-Smith, I. (1987). Drilling long horizontal boreholes for site investigation purposes.
Contractor (Hong Kong), June 1987, pp 7-12.
McFeat-Smith, I., Nieuwenhuijs, G.K. & Lai, W.C. (1986). Application of seismic surveying,
orientated drilling and rock classification for site investigation of rock tunnels.
Proceedings of the Conference on Rock Engineering and Excavation in an Urban
Environment, Hong Kong, pp 249-261.
McKinlay, D.G. & Anderson, W.F. (1975). Determination of the modulus of deformation of
a till using a pressuremeter. Ground Engineering, vol. 8, no. 6, pp 51-54.
McNicholl, D.P. & Cho, G.W.F. (1985). Surveillance of pore water conditions in large urban
slopes. Proceedings of the 21st Annual Conference of the Engineering Group of the
Geological Society, Sheffield, pp 403-415. (Published as Groundwater in Engineering
Geology, edited by J.C. Cripps et al, Geological Society, Engineering Geology Special
Publication no. 3, 1986) (Also published in preprint volume, pp 445-467).
Meigh, A.C. (1977). Techniques of exploration, sampling and testing, including field tests, in
structurally complex formations. (General Report). Proceedings of the International
Symposium on the Geotechnics of Structurally Complex Formations, Capri, Italy, vol. 2,
pp 238-254.
Meigh, A.C. & Skipp, B.O. (1960). Gamma-ray and neutron methods of measuring soil
density and moisture. Géotechnique, vol. 10, pp 110-126.
Meigh, A.C., Skipp, B.O. & Hobbs, N.B. (1973). Field and laboratory creep tests on weak
rocks. Proceedings of the Eighth International Conference on Soil Mechanics and
Foundation Engineering, Moscow, vol. 1.2, pp 265-271.
Ménard, L. (1965). Regles pour le calcul de la force portante et du tassement des foundations
en fonction des resultats pressiometriques. (Rules for the calculation of bearing
capacity and foundation settlement based on pressuremeter tests). Proceedings of the
Sixth International Conference on Soil Mechanics and Foundations Engineering,
Montreal, vol. 2, pp 295-299.
Moore, J.F.A. (1974). A long-term plate test on Bunter Sandstone. Proceedings of the Third
Congress of the International Society for Rock Mechanics, Denver, vol. 2B, pp 724-732.
Morgan, T.A. & Panek, L.A. (1963). A Method for Determining Stresses in Rock. Report of
Investigations No. 6312, Bureau of Mines, U.S. Department of the Interior.
Naylor, J.A., Rowland, C.D., Young, C.P. & Barber, C. (1978). The investigation of landfill
sites. Water Research Centre, UK, Technical Report TR91, 68 p.
Nixon, I.K. (1982). Standard penetration test : state-of-the-art report. Proceedings of the
Second European Symposium on Penetration Testing, Amsterdam, vol. l, pp 3-24.
210
Norbury, D.R. (1984). The point load test. Proceedings of the 20th Regional Meeting of the
Engineering Group of the Geological Society, Guildford, UK, pp 325-329. (Published
as Site Investigation Practice: Assessing BS 5930, edited by A.B. Hawkins, Geological
Society. Engineering Geology Special Publication no. 2, 1986). (Also published in
preprint vol. l, pp 344-352).
Pang, P.L.R. (1986). A new boundary stress transducer for small soil models in the centrifuge.
Geotechnical Testing Journal, vol. 9, pp 72-79.
Parry, R.G.H. (1971). A simple driven piezometer. Géotechnique, vol. 21, pp 163-167.
Penman, A.D.M. (1960). A study of the response times of various types of piezometers.
Proceedings of the Conference on Pore Pressures and Suction in Soils, London, pp 53-
58.
Penman, A.D.M. (1969). Instrumentation for earth and rockfill dams. BNCOLD News and
Views, May 1969, pp 7-10. (Reprinted in Building Research Establishment, UK,
Current Paper no. 35/69, 6 p).
Penman, A.D.M. (1978). Pore pressure and movement in embankment dams. Water Power
and Dam Construction, vol. 30, no. 4.
Penman, A.D.M. (1986). Field measurement of pore pressures. Proceedings of the Fourth
International Geotechnical Seminar on Field Instrumentation and In-Situ Measurements,
Singapore, pp 163-173.
Penman, A.D.M. & Mitchell, P.B. (1970). Initial behaviour of Scammonden Dam.
Proceedings of the Tenth Conference of the International Commission on Large Dams,
Montreal, pp 723-747. (Reprinted in Building Research Establishment, UK, Current
Paper no. 20/70, 19 p).
Phillipson, H.B. & Brand, E.W. (1985). Sampling and testing of residual soils in Hong Kong.
Sampling and Testing of Residual Soils : A Review of International Practice, edited by
E.W. Brand & H.B. Phillipson, Scorpion Press, Hong Kong, pp 75-82.
Phillipson, H.B. & Chipp, P.N. (1981). High quality core sampling - recent developments in
Hong Kong. Hong Kong Engineer, vol. 9, no. 4, pp 9-15.
Phillipson, H.B. & Chipp, P.N. (1982). Air foam sampling of residual soils in Hong Kong.
Proceedings of the Specialty Conference on Engineering and Construction in Tropical
and Residual Soils, Honolulu, pp 339-356.
Poole, R.W. & Farmer, I.W. (1980). Consistency and repeatability of Schmidt hammer
rebound data during field testing. International Journal of Rock Mechanics and
Mining Sciences & Geomechanics Abstracts, vol. 17, pp 167-171.
211
Pope, R.G., Weeks, R.C. & Chipp, P.N. (1982). Automatic recording of standpipe piezometers.
Proceedings of the Seventh Southeast Asian Geotechnical Conference, Hong Kong,
vol. l, pp 77-89.
Richards, B.G. (1971). Psychometric techniques for field measurements of negative pore
pressure in soils. Proceedings of the First Australia - New Zealand Conference on
Geomechanics, Melbourne, vol. 1, pp 387-394.
Richards, L.R. & Cowland, J.W. (1982). The effect of surface roughness on the field shear
strength of sheeting joints in Hong Kong granite. Hong Kong Engineer, vol. 10, no. 10,
pp 39-43.
Ridley Thomas, W.N. (1982). The application of engineering geophysical techniques to site
investigations in Hong Kong. Proceedings of the Seventh Southeast Asian
Geotechnical Conference, Hong Kong, vol. 1, pp 205-226.
Rigden, W.J., Thorburn, S., Marsland, A. & Quartermain, A. (1982). A dual load range cone
penetrometer. Proceedings of the Second European Symposium on Penetration Testing,
Amsterdam, pp 787-796.
Road Research Laboratory (1952). Soil Mechanics for Road Engineers. Her Majesty's
Stationery Office, London, 565 p.
Rocha, M., Silveira, A. da., Grossmann, N. & Oliveira, E. de. (1966). Determination of the
deformability of rock masses along boreholes. Proceedings of the First Congress of
the International Society for Rock Mechanics, Lisbon, vol. 1, pp 697-704.
Ross-Brown, D.M. & Walton, G. (1975). A portable shear box for testing rock joints. Rock
Mechanics, vol. 7, pp 129-153.
Rowe, P.W. (1972). The relevance of soil fabric to site investigation practice. Géotechnique,
vol. 27, pp 195-300.
Rowe, P.W. & Barden, L. (1966). A new consolidation cell. Géotechnique, vol. 16, pp 162-
170.
Sanglerat, G. (1972). The Penetrometer and Soil Exploration. Elsevier Publishing Co.,
Amsterdam, 464 p.
Serota, S. & Jennings, R.A. (1958). Undisturbed sampling techniques for sands and very soft
clays. Proceedings of the Fourth International Conference on Soil Mechanics and
Foundation Engineering, London, vol. 1, pp 245-248.
212
Sewell, R.J., Campbell, S.D.G., Fletcher, C.J.N., Lai, K.W. & Kirk, P.A. (2000). The Pre-
Quaternary Geology of Hong Kong. Geotechnical Engineering Office, Hong Kong,
181 p. [Amd GG2/01/2017]
Sherwood, D.E. & Child, G.H. (1974). A static dynamic sounding technique. Proceedings
of the European Symposium on Penetration Testing, Stockholm, vol. 2.2, pp 361-366.
Sherard, J.L., Dunnigan, L.P., Decker, R.S. & Steele, E.F. (1976). Pinhole test for identifying
dispersive soils. Journal of the Geotechnical Engineering Division, American Society
of Civil Engineers, vol. 102, pp 69-85.
Siu, K.L. & Wong, K.M. (1984). Concealed marble features at Yuen Long. Proceedings of
the Conference on Geological Aspects of Site Investigation, Hong Kong, pp 75-88.
(Published as Geological Society of Hong Kong, Bulletin no. 2, edited by I. McFeat-
Smith, 1985).
Skempton, A.W. (1986). Standard penetration test procedures and the effects in sands of
overburden pressure, relative density, particle size, ageing and overconsolidation.
Géotechnique, vol. 36, pp 425-447.
Smyth, D.V. & McSweeney, T.V. (1985). Power swivel improves offshore drilling quality.
Contractor (Hong Kong), June 1985, pp 13-15.
Snow, D.T. (1968). Rock fracture spacings, openings, and porosities. Journal of the Soil
Mechanics and Foundations Division, American Society of Civil Engineers, vol. 94,
no. SMI, pp 73-91.
Starr, D.C. & Finn, P.S. (1979). Practical aspects of rock slope stability assessment in Hong
Kong. Hong Kong Engineer, vol. 7, no. 10, pp 49-56.
Stephenson, R.J. (1973). Relative density tests on rockfill at Carters Dam. Evaluation of
Relative Density and Its Role in Geotechnical Projects Involving Cohesionless Soils.
American Society for Testing and Materials, Special Technical Publication no. 523,
pp 234-247.
Strange, P.J. (1986). Urban geological mapping - techniques used in Kowloon and Hong
Kong. Proceedings of the Symposium on the Role of Geology in Urban Development
in Southeast Asia, (Landplan III), Hong Kong, pp 181-189. (Published as Geological
Society of Hong Kong, Bulletin no. 3, edited by P.G.D. Whiteside, 1987). (Abstract in
Geological Society of Hong Kong Abstracts, no. 4, 1986, pp 14)
Strange, P.J. & Shaw, R. (1986). Geology of Hong Kong Island and Kowloon, 1:20 000 Sheets
11 and 15. Hong Kong Geological Survey Memoir No. 2, Geotechnical Control Office,
Hong Kong, 136 p.
213
Sweeney, D.J. (1982). Some insitu soil suction measurements in Hong Kong's residual soil
slopes. Proceedings of the Seventh Southeast Asian Geotechnical Conference, Hong
Kong, vol. 1, pp 91-106. (Discussion, vol. 2, pp 93-96).
Sweeney, D.J. & Ho, C.S. (1982). Deep foundation design using plate load tests.
Proceedings of the Seventh Southeast Asian Geotechnical Conference, Hong Kong,
vol. 1, pp 439-452.
USACE (1997). Engineer Manual 1110-2-2901 Engineering and Design - Tunnels and Shafts
in Rock. US Army Corps of Engineers.
(http://140.194.76.129/publications/eng-manuals/em1110-2-2901/toc.htm)
[Amd GG2/01/2017]
USBR (1974). Earth Manual. (Second edition). United States Bureau of Reclamation, US
Government Printer, Washington D.C., 810 p.
Van Zuidam, R.A. & Van Zuidam-Cancelado, F.I. (1979). Terrain analysis and classification
using aerial photographs : A geomorphological approach. ITC Textbook of Photo-
Interpretation Volume VII - Use of Aerial Detection in Geomorphology and
Geographical Landscape Analysis, International Institute of Aerial Survey and Earth
Sciences (ITC), Enschede, The Netherlands, 333 p.
Vaughan, P.R. (1974). The measurement of pore pressure with piezometers. Proceedings of
the Symposium on Field Instrumentation in Geotechnical Engineering, London, pp 411-
422.
Verstappen, H.T. & Van Zuidam, R.A. (1968). ITC Textbook of Photo-interpretation. ITC,
Delft. The Netherlands. 7 vols.
Wallace, G.B. Slebir, E.J. & Anderson, F.J. (1970). Insitu methods for determining
deformation modulus used by the Bureau of Reclamation. Determination of the In Situ
Modulus of Deformation of Rock, American Society for Testing and Materials, Special
Technical Publication no. 477, pp 3-26.
Walton, W.C. (1962). Selected analytical methods for well and aquifer evaluation. Illinois
State Water Survey, Urbana, Illinois, Bulletin no. 49, 81 p.
Ward, W.H., Burland, J.B. & Gallois, R.W. (1968). Geotechnical assessment of a site at
Munford, Norfolk, for a large proton accelerator. Géotechnique, vol. 18, pp 399-431.
Way, D.S. (1978). Terrain Analysis - A Guide to Site Selection Using Aerial Photographic
Interpretation. (Second edition). McGraw Hill, New York, 438 p.
214
Weltman, A.J. & Head, J.M. (1983). Site investigation manual. Construction Industry
Research & Information Association Special Publication no. 25 / PSA Civil Engineering
Technical Guide no. 35, 144 p.
Whiteside, P.G.D. (1986). Horizontal plate loading tests in completely decomposed granite.
Hong Kong Engineer, vol. 14, no. 10, pp 7-14. (Discussion, vol. 14, no. 10, p. 14 and
vol. 15, no. 2, pp 37-39, 48).
Whyte, I.L. (1984). The quality of U100 sampling. Proceedings of the 20th Regional
Meeting of the Engineering Group of the Geological Society, Guildford, UK, pp 419-
423. (Published as Site Investigation Practice : Assessing BS 5930, edited by A.B.
Hawkins, Geological Society, Engineering Geology Special Publication no. 2, 1986).
(Also published in preprint vol. 1, pp 485-494).
Wilson, N.E. (1963). Laboratory vane shear tests and the influence of pore water stresses.
Laboratory Shear Testing of Soils. American Society of Testing and Materials, Special
Technical Publication no. 361, pp 377-385.
Windle, D. & Wroth, C.P. (1977). The use of a self-boring pressuremeter to determine the
undrained properties of clays. Ground Engineering, vol. 10, no. 6, pp 37-46.
Tables
216
List of Tables
Table Page
No. No.
Table 1 - Selected Maps, Plans and Aerial Photographs Available from the
Lands Department
Legend:
# See Figure 3 for full programme of the new geological survey
* See Table 2 for further details
218
Approximate
Year Scale(s) Coverage (%) Remarks
HKI K NT
Note: Colour aerial photographs have also been taken routinely since 1993.
219
Approximate
Year Scale(s) Coverage (%) Remarks
HKI K NT
Notes: (1) This Table is intended to provide general guidance only. It should be read in conjunction with
Table 4. Each situation must be assessed on its own merits to decide on the appropriate scope
of the S.I. More or less intensive S.I. than that recommended may be required, depending on
the particular site conditions.
(2) Irrespective of the above S.I. class boundaries, the least stringent S.I. class for different risk
categories should be Class 1 for 'High' risk, Class 2 for 'Low' risk and Class 3 for 'Negligible'
risk. The risk categories are those given in the Geotechnical Manual for Slopes (GCO, 1984)
and should be assessed with reference to both the present use and the development potential of
the site.
221
Nominal
Nominal Diameter Rod Coupling
Diameter
Design Design Design OD ID Design
Core Hole Core Hole OD ID ID
TNW 61 76 NMLC 52 76 NW 89 76 BW 54 44 19
T2-76 62 76 HW 115 101 NW 67 57 35
222
PW 140 126 HW 89 80 60
T6-101 79 101
Mazier* 74 101
PW 140 126 NW 67 57 35
3C-MLC** 76 111
Legend:
* With retractor shoe OD Outer Diameter
** With or without retractor shoe ID Inner Diameter
Notes: (1) This list is not exhaustive and should not imply the exclusion of other recognised core barrels and casing / rods systems.
(2) For additional information, reference can be made to BS EN ISO 22475-1:2006 (BSI, 2006). [Amd GG2/01/2017]
(3) All dimensions are in millimetres.
223
Mass of Sample
Purpose of Sample Soil Type
Required
Soil identification. including Clay, silt, sand 1 kg
Atterberg limits, sieve analysis,
Fine and medium gravel 5 kg
moisture content and sulphate content
tests Coarse gravel 30 kg
Compaction tests All 25 kg to 60 kg
Clay, silt, sand 100 kg
Comprehensive examination of
construction materials, including soil Fine and medium gravel 130 kg
stabilization
Coarse gravel 160 kg
Note: Table taken from BS 5930 (BSI, 2010). [Amd GG2/01/2017]
224
Expected
Material Type Typical Composition of Materials Sampling Procedure Quality
Class
Soils derived from Composition of soils varies depending Block sample from dry excavation 1
insitu rock on the nature of parent rock material. Large diameter triple-tube core-barrel 1
weathering Soils derived from granitic rock are (102 mm diameter cores) with retractor
usually silty and clayey sands; soils shoe, air-foam flush
derived from volcanic rock are usually
Triple-tube core-barrel (≥ 74 mm 1/2
sandy and clayey silts.
diameter cores) with retractor shoe
U100 sampler 2/4
SPT split barrel sampler with or without 3/4
liner
Bulk samples and jar samples from dry 3/4
open excavation
Light percussion shell and chisel for 5
boulders
Colluvium Fresh or variably decomposed rock The sampling procedures for soils derived
fragments (boulders, cobbles and from insitu rock weathering apply.
gravels) within a matrix of varying
proportions of sand, silt and clay
Alluvial and marine The following materials can be found :
deposits (a) Granular soils (sands, silty sands or Piston sampler or compressed air sand 2/3
sandy silts) sampler
U100 sampler (with core-catcher) 4
SPT split barrel sampler 4
Light percussion shell 5
(b) Very soft to soft cohesive soils Piston sampler 1
(sandy clays, silty clays or clays) Thin-walled sampler 1/2
U100 sampler 2/3
Delft continuous sampler 2/3
Light percussion clay cutter (dry 4/5
boreholes) or shell (wet boreholes)
(c) Firm to very stiff cohesive soils Triple-tube core-barrel with retractor shoe 1/2
U100 sampler 2/3
Light percussion clay cutter 5
(d) Cohesive and granular soils The sampling procedures for soils derived
containing boulders, cobbles or gravel from insitu rock weathering apply.
Fill Variable material, which can include See sampling procedures for relevant soil
compacted or uncompacted soil, rock type and composition under 'Alluvial and
fragments and building debris mixtures Marine Deposits' above.
Rock All rock types found in Hong Kong, Diamond core drilling with double or N/A
including boulders in colluvium triple-tube core-barrel. The latter
generally causes less disturbance and
gives better core recovery, especially in
highly fractured or jointed rocks.
Notes: (1) The typical composition of materials should only be taken as a general guide.
(2) The quality classes are defined in Table 9.
(3) The expected quality classes given should only be taken as a guide, as sample quality is highly
dependent on workmanship and on the compactness (or consistency) and grading of the soil.
225
Class 4 Classification
Notes: (1) Large diameter class 1 and class 2 samples are often sufficient to allow
the 'fabric' of the soil to be examined. Sometimes this may also be done
using class 3 and class 4 samples.
(2) Remoulded properties can be obtained using class 1 to class 4 samples.
(3) Table adapted from BS EN 1997-2:2007 (BSI, 2007). [Amd GG2/01/2017]
Table 10 - Evaluation of Piezometer Types
Remote Other
Pressure
Closed-
-1 atmosphere permeability As above; very regular
hydraulic (High Can be Useful for measuring small
226
to any positive Moderate Yes As above measurements in low de-airing required when
air entry de-aired suctions.
pressure permeability soil are measuring suctions.
pressure)
possible.
Cannot be Only suitable when tip almost
Yes, some head No method of checking
Any positive de-aired; Moderate to poor, but very little Fairly cheap; no gauge always below groundwater
Pneumatic Rapid loss over long if pore water or pore air
pressure only partially long term experience available house required. level and no large suctions
distance pressure is measured.
self de-airing occur.
Signal quality degenerates with
As above; expensive;
Electric time; instrument life about ten
Any positive Yes, but special zero reading liable to
vibrating wire Rapid As above years, but reliability of - Not generally recommended.
pressure cable required drift and cannot be
type instrument that cannot be
checked.
checked is always suspect
Yes, but with
Electric Any positive care because of
Rapid As above poor - As above Not recommended.
resistance type pressure transmission
losses
-1 atmosphere Vandal damage often
Moderate Can be Cheap, simple to read First choice for measuring
Tensiometer to positive Yes Good irreparable; regular de-
to rapid de-aired and maintain. pore suction.
(Suction)
Negative
Seismic direct Determination of material properties of the ground (sonic Uphole, downhole and crosshole surveys are carried out. Data are indirect
methods wave velocities, dynamic moduli and rock-mass quality). and represent averages, and may be affected by other mass characteristics.
Location of geological features.
Electrical Mapping of subsurface material interfaces (including Variable weathering patterns often complicate interpretation. Water table
resistivity saltwater boundaries). Estimation of soil resistivity (hence location often limits the depth for practical study as conductivity rises sharply
corrosivity). Location of geological features and in saturated materials & makes differentiation between horizons impossible.
underground cavities, e.g. disused tunnels.
227
Gravimetric Location of geological features. Normally used only to locate cavities, e.g. in karst terrain.
Magnetic Location of buried metalliferous man-made objects (e.g.
Large scale surveys are generally carried out from an aircraft.
cables and pipelines) and geological features.
Seismic reflection Mapping of the seabed and material interfaces below the Long continuous traces can be obtained. Background 'noise', solid waste on
seabed. the seabed, gas bubbles trapped within sediments, and variable weathering
patterns often complicate interpretation. Does not provide sound velocities.
Computation of depths to interfaces requires velocity data obtained by other
Marine Investigations
Category
Name of Test Recommended References Remarks
of Test
Geospec 3 (GEO, 2017a)
Clause 5; Frequently used in the determination of soil properties, e.g. dry density, degree of saturation.
Moisture content Geotechnical Manual for Slopes Soils containing halloysitic clays, gypsum or calcite can lose water of crystallisation when heated, and should
(GCO, 1984), Section 3.2.2 be dried at various temperatures to assess the effect on determination of moisture content.
[Amd GG2/01/2017]
Geotechnical Manual for Slopes, Frequently used in the determination of other properties, e.g. void ratio, particle size distribution by
Specific gravity
228
Section 3.2.4; sedimentation.
Lambe (1951) Chapter 2
[Amd GG2/01/2017]
Particle size distribution: Wide application in Hong Kong in the classification of soils.
(a) Sieving (a) Geospec 3 (GEO, 2017a) (a) Sieving gives the grading of soil coarser than silt. Cave is required with soils derived from insitu rock
Clause 8; weathering, to avoid crushing of soil grains during disaggregation. Dispersant should be excluded when
Geotechnical Manual for determining particle size distribution for certain applications, e.g. for designing filters, and in selecting
Slopes, Section 4.6; fill for reinforced fill structures. [Amd GG2/01/2017]
Brian-Boys et al (1986)
Clause 5.1
[Amd GG2/01/2017]
(b) Sedimentation (b) Geospec 3 (GEO, 2017a) (b) The proportion of the soil passing the finest sieve (63 µm) represents the combined silt and clay fraction.
Clause 8; The relative proportions of silt and clay can only be determined by sedimentation.
Geotechnical Manual for
Slopes, Section 3.2.5
[Amd GG2/01/2017]
Laboratory vane shear Wilson (1963) A useful test for classifying silts and clays in term of consistency. See also Geoguide 3 (GCO, 1988).
Table 12 - Tests on Soils and Groundwater (Sheet 2 of 4)
Category
Name of Test Recommended References Remarks
of Test
Sulphate content :
(a) Total sulphate content (a) Geospec 3 (GEO, 2017a)
of soil Clause 9.3
[Amd GG2/01/2017] These tests assess the aggressiveness of soil and groundwater to buried concrete and steel. Local experience
Chemical and Corrosivity Tests and Groundwater
indicates that sulphate content of Hong Kong soils is generally low. Therefore Geospec 3 (GEO, 2001)
(b) Sulphate ion content (b) Geospec 3 (GEO, 2017a) Clause 9.3 is normally adequate. [Amd GG2/01/2017]
of groundwater and Clause 9.3
aqueous soil extracts [Amd GG2/01/2017]
229
Total sulphide content of
American Public Health
groundwater and Assesses the aggressiveness of soil and groundwater to buried steel.
Association (1985) Part 427
aqueous soil extracts
Assesses:
Department of Transport (1976)
Chloride ion content (i) the aggressiveness of soil to buried concrete and steel;
Clause 2722
(ii) the suitability of fine aggregate for use in concrete.
Resistivity BS 1377-9 (BSI, 1990) Assesses the potential for electrochemical corrosion of buried steel. The quoted reference gives a test
Section 5.1 [Amd GG2/01/2017] method for compacted fill, as opposed to field measurement using the four electrode method (see
Section 33.2.1). Corrosion of steel in soils is discussed in BS 8004 (BSI, 1986) and King (1977).
Assesses the likelihood of sulphate reducing bacteria being present, which promote microbiological corrosion
BS 1377-9 (BSI, 1990)
Redox potential of buried steel. The quoted reference gives a test method for compacted fill, as opposed to field
Section 5.2 [Amd GG2/01/2017]
measurement, which is described in BS 1377-9 (BSI, 1990). [Amd GG2/01/2017]
Table 12 - Tests on Soils and Groundwater (Sheet 3 of 4)
Category
Name of Test Recommended References Remarks
of Test
Triaxial compression tests: The quick undrained test gives undrained shear strength in terms of total stresses, and has application to
(a) Quick undrained (a) Geospec 3 (GEO, 2017a) short-term stability and bearing capacity analyses. Effective stress analysis is relevant to most soils and
Clause 15 engineering applications in Hong Kong; consequently the consolidated drained test or consolidated
(b) Consolidated drained undrained test with measurement of pore water pressure should generally be used. Tests should be carried
[Amd GG2/01/2017]
(c) Consolidated undrained out in the stress range appropriate to the analysis.
(b) Bishop & Henkel (1976)
with measurement of pore For saturated clays with undrained shear strength less than about 75 kPa, the insitu penetration vane test
Soil Strength Tests
water pressure (c) Geotechnical Manual for (see Section 21.3), used in conjunction with the cone penetration test (see Section 23.3), will normally be
Slopes, Sections 3.7 and the best method for measuring undrained shear strength.
3.8; Head (1986) A number of other triaxial tests are possible, e.g. failure by increasing pore pressure, decreasing σ3 etc.
Triaxial tests can also be used to find K0.
Direct shear test Akroyd (1969); ASTM (1985i); A useful and practical alternative to the consolidated drained triaxial test for shear strength measurements
Geotechnical Manual for on fill, colluvium and soils derived from weathering of rock insitu. The test specimen can be oriented to
Slopes, Sections 3.7 and 3.9; measure shear strength on a pre-determined plane. The major limitation of the test is the specimen
thickness, which governs the maximum particle size that can be tested. Common specimen sizes are
230
Head (1986)
60 mm and 100 mm square by 20 mm thick. The less common 60 mm diameter by 20 mm thick and
300 mm square by 160 mm thick direct shear boxes have also been used in Hong Kong
Consolidation: These tests yield soil parameters from which the amount and time scale of settlements can be calculated.
(a) One-dimensional (a) Geospec 3 (GEO, 2017a) The simple oedometer test is the one in general use. Although reasonable assessment of settlement can be
consolidation Clause 14 made from the results of the test, estimates of the time scale have been found to be extremely inaccurate for
[Amd GG2/01/2017] some soils. This is particularly true for clay soils containing layers and partings of silt and sand, where the
(oedometer test)
Soil Deformation Tests
horizontal permeability is much greater than the vertical. In these cases, more reliable data may be
(b) Triaxial consolidation obtained from tests in the Rowe cell, which is available in sizes up to 250 mm diameter and where a larger
(b) Bishop & Henkel (1976)
(c) Rowe cell and potentially more representative sample of soil can be tested (see Section 12.5). Another alternative is
(c) Rowe & Barden (1966); to obtain values of permeability, k from insitu permeability tests, and combine them with coefficients of
Head (1986) volume decrease, mv obtained from the simple oedometer test.
Values of the modulus of deformation of soil can be obtained from the stress-strain curves from triaxial
compression tests, where the test specimens have been consolidated under effective stresses corresponding
Modulus of deformation Head (1986) to those in the field. However, values obtained in this way frequently do not correlate well with insitu
observations. It is now generally considered that the plate test (see Section 21.6), the pressuremeter (see
Section 21.7) and back analysis of existing structures yield more reliable results.
Table 12 - Tests on Soils and Groundwater (Sheet 4 of 4)
Category
Name of Test Recommended References Remarks
of Test
Permeability: The constant head test is suited only to soils of permeability roughly within the range 10-4 m/s to
(a) Constant head permeability (a) Akroyd (1969) 10-2 m/s. For soils of lower permeability the falling head test is applicable. For various reasons,
Soil Permeability
test principally sample size and ground variability, laboratory permeability tests often yield results of
(b) Falling head permeability (b) Akroyd (1969) limited value, and insitu tests should generally yield more representative data (see Section 21.4).
Tests
test The Rowe cell allows the direct measurement of permeability by a constant head, with a back
(c) Triaxial permeability test (c) Bishop & Henkel (1976); pressure and confining pressures more closely consistent with the field state, and by both vertical
Head (1986) and radial flow.
(d) Rowe cell (d) Head (1986); Rowe &
Barden (1966)
Dry density / moisture content Geospec 3 (GEO, 2017a) Indicates the degree of compaction that can be achieved at different moisture contents and with
Compaction
relationship Clause 10 [Amd GG2/01/2017] different compactive effort. It is carried out in conjunction with determinations of insitu dry density
Tests
(ASTM, 1985b; ASTM, 1985e; ASTM, 1985h; Geospec 3 (GEO, 2017a) Clause 11; see also
Soil
231
California bearing ratio (CBR) Akroyd (1969); GEO (2017a) This is on empirical test used in the design of flexible pavements. The test can also be carried out
Pavement
Design
Clause 12 insitu (see Section 29.4), but the results may be substantially different from the laboratory test due
Tests
[Amd GG2/01/2017] to the difference in the confining condition, especially for sands.
Double oedometer test Hilf (1975); Holtz (1948) Assesses the potential for soils to collapse on wetting.
Potential
Collapse
Tests
Soil
Double hydrometer test Decker & Dunnigan (1977) Used to identify dispersive soils, in order to assess the potential for dispersive piping and internal
(dispersion test) erosion to occur in slopes and earth structures. The different tests may not give consistent
Soil Dispersion
Exchangeable sodium Flanagan & Holmgren (1977) indications of dispersion, consequently it is advisable to use more than one test method.
Tests
percentage test
Emerson crumb test (turbidity Standards Association of
test) Australia (1980)
Pinhole test Sherard et al (1976)
Table 13 - Outline of Engineering Consideration and SI Techniques for Rock Tunnels (based on IMMM, 2003)
[Amd GG2/01/2017]
Major Engineering Approach to Investigation Testing Survey / Monitoring
Key Points for SI
Considerations Investigation Methods Insitu Testing Instrument Types
Blasting design Nature of soil and/or rock at tunnel level Geological mapping of surface rock Impression packer test, televiewer Piezometers for monitoring pore
(invert and crown) and around the tunnels, exposures water pressures at various
Machineability (suitability for and around/within the shafts Packer permeability test and possibly hydrogeological response zones
TBM) Aerial photograph interpretation to pumping test
Rock mass weathering (including presence identify photolineaments Settlement gauges
Soil and rock mass excavation and of corestones and mixed ground) and Insitu stress measurement (e.g. by
support design (possibility of strength Geophysical surveys to identify hydrofracturing)
presence of mixed face conditions, anomalies and low seismic velocity
fractured ground, and weak, Distribution, orientation and characteristics zones Soil permeability test and response
compressible and/or permeable of discontinuities test in piezometer
zones) Boreholes – vertical holes needed for
Rock mass permeability sampling and downhole tests. Unless
Water pressures acting on lining surface materials need to be
/retaining structures for their design Insitu stress characterised for assessment of effects Laboratory Testing/Analysis Survey / Monitoring
of the tunnel works, boreholes can be Unconfined Compressive Strength Location survey of physical
Potential water inflow into the Presence of fault zones, dykes, contact zones wash-bored down to the zone of interest Young’s Modulus constraints and sensitive receivers
shafts and along the tunnels. between geological units, etc. Sub-horizontal/inclined holes from the Poisson’s Ratio
tunnel portal and/or shaft locations to Point Load Strength Complete annual cycle needs to be
Assessment of tunnels/shafts Hydrogeology, including permanent examine variations of ground conditions Rock joint characteristics monitored to indicate groundwater
232
drainage and pumping groundwater table, perched water tables, along the tunnel drive Abrasivity pressure response to rainfall and
requirements permeable zones feeding water to the Hardness seasonal fluctuation, and to
tunnels, etc. Inclined holes to intercept faults, dykes Geological thin sections recharge from the sea
Effects of the tunnel works on land and contact zones at tunnel level
stability, e.g. ground Potential recharge in response to rainfall and Probing ahead during tunnelling Classification and consolidation creep Baseline ground movement and
collapse/landslide due to the sea, and hydraulic boundary conditions operation tests for settlement-susceptible near- vibration survey and condition
inadequate support, hydraulic surface materials survey of sensitive receivers (e.g.
failure, blow-out failure, etc. Dewatering effects of the tunnels, and the Directional coring (for deep tunnels) cracks on existing structures) over
tunnel works damming subsurface Salinity testing to assess the effects of a sufficiently long period to
Ground settlement, heave and groundwater flow Sampling groundwater on tunnelling equipment establish trends
lateral movement and distortion of Rock coring through proposed tunnel and lining
sensitive receivers as a result of Nature of surface materials, in particular, levels (including all alternative
construction-induced ground loss, strength, permeability, compressibility and alignments) and covering sufficient
ground deformation/vibration and consolidation and creep characteristics ground above crown and below invert
groundwater inflow/drawdown
As-built records and site history, in Undisturbed soil samples for near-
Design of tunnel portal slopes particular, effects of past and on-going surface materials, potentially affected by
construction activities that could affect the the tunnel and shaft construction
Lining/retaining structure tunnels/shafts and the sensitive receivers
durability design
Ground and groundwater chemistry
Effects of blasting on
surface/subsurface facilities and
slopes
NB: Reference should also be made to the ground investigation guidelines for deep excavations and rock tunnels produced by AGS (HK) (2004a & b; 2005).
233
Figures
234
List of Figures
Figure Page
No. No.
Figure Page
No. No.
Figure Page
No. No.
Notes : (1) The open-tube sampler may also be attached to drill rods and driven or
pushed into the ground by the drilling rig or SPT hammer.
(2) Two sample tubes may be coupled together to provide a longer sample or
additional overdrive space.
(3) The vents in the sampler head should have a minimum collective cross
sectional area of 600 mm2 to allow free exit ot air and water above the
sample.
(4) A core-catcher device (not shown) may also be included with the cutting
shoe.
(5) Samplers smaller in diameter than the U100 are available which are of
similar design.
Note : Figures based on BS 5930 (BSI, 2010) and Penman (1986). [Amd GG2/01/2017]
Notes : (1) Figure based on BS EN ISO 22476-3 (BSI, 2011b). [Amd GG2/01/2017]
(2) A slightly enlarged inner diameter of the split barrel is permitted, provided
removable liners are always used which have an inside diameter of
35 mm.
(3) A ball valve in the base of the coupling as shown in ASTM (1985a) is also
permitted.
(4) All dimensions are in millimetres.
Notes : (1) Expressions come from Hvorslev (1951); figure based on BS 5930 (BSI, 2010).
[Amd GG2/01/2017]
(2) Values are primarily for tests carried out through the open ends of boreholes.
Case (d) may be used for tests carried out using piezometer tips, but more
accurate results will be obtained by using Figure 29 especially for values of
L/D > 2.
(3) Cases (e) and (f) assume the permeability of the soil in the casing to be the same
as that below it. Where this is not so, see Hvorslev (1951).
(4) Cases (a) and (b) tend to measure the mean permeability of the soil; (c) and (d)
the vertical permeability; (e) and (f) the horizontal permeability. Where the
horizontal permeability is much greater than the vertical permeability, all tests
will tend to measure the former.
Notes : (1) (a) after BS EN ISO 22476-1 (BSI, 2012f), (b) & (c) after Delft Soil
Mechanics Laboratory (1977). [Amd GG2/01/2017]
Note : Figure adopted from Brown (1981) and BS 5930 (BSI, 2010).[Amd GG2/01/2017]
Plates
285
List of Plates
Plate Page
No. No.
Appendices
299
Appendix A
Information Required for Desk Study
300
Contents
Page
No.
Contents 300
A.1 General
A desk study involves the collection and review of information required for the planning
of the project and of the site investigation.
Topographic maps and plans are useful for studying the general features of the site, and
for identifying ground features of engineering significance, e.g. slopes, retaining structures,
streams, tunnels, burial grounds and obstructions such as transmission lines and towers. They
are also useful for the assessment of the effect of the proposed works on adjacent properties and
structures, and for the identification of works areas, storage areas and access, including
temporary access for construction purposes.
For works to be carried out in a marine environment (e.g. seawalls and piers), Admiralty
charts and tide tables should also be referred to.
In some cases, old maps may be useful, e.g. to check the location and extent of an old
seawall or a buried stream course. Archaeological maps may also be required to establish the
boundaries of an archaeological site.
The following information should be referred to for a preliminary study of the ground
conditions :
Local rainfall records should be collected where the proposed works require slope and
drainage design. Hydrological information, where available, is useful in drainage studies,
including the assessment of flooding risk and the influence of the proposed works on the local
and downstream drainage regimes.
Past construction records, for both the site and for adjacent properties, should be
obtained where appropriate, to provide information on the following :
Records of past failure, flooding and settlement of ground and structures should also be
noted and studied where necessary.
Details and locations of existing services and utilities, including stormwater drains,
sewers, fresh and salt water mains, fire fighting mains, electrical cables, gas mains and
telephone ducts, should be referred to for the following purposes :
Except where an investigation is being planned for a site that has not been allocated to
the project (e.g. an investigation that is for the purpose of selecting sites or establishing the
suitability of a site), there should be available a set of lease conditions or engineering conditions,
depending on whether the proposed project is to be undertaken privately or by Government.
It is essential that these conditions are studied thoroughly during the desk study or as soon as
they become available.
Engineering conditions are issued by the appropriate District Lands Office of the Lands
Department, and lease conditions are normally issued by the Registrar General/Land Officer.
These conditions govern the use of the site. They also set down the requirements and
restrictions on development, and define the responsibilities of the related parties and authorities.
The following items are normally covered :
(i) maintaining both the stability of the land and its surface
condition, within, and where appropriate, adjacent to
the site,
(ii) interference with or damage to roads, services, drains,
channels, etc.,
(iii) water supply,
(iv) connections to sewers and stormwater drains,
304
(v) drainage.
In some cases, special clauses may also be present in the lease conditions. For example,
a geotechnical clause may be used to indicate that a site is considered to be geotechnically
difficult to develop, hence forewarning a developer that a high degree of skilled geotechnical
engineering input will be required.
In planning a ground investigation, the effect of the proposed works on the ground, on
adjacent properties and structures and on existing services and utilities, should be thoroughly
examined. For example, the effect of flushing water from drilling on existing slopes and
retaining walls should be considered.
Requirements and restrictions imposed by local statutes should be studied and observed
in the planning and execution of the investigation. For example, the Summary Offences
Ordinance (Government of Hong Kong, 1981b) restricts the use of powered mechanical
equipment between 7 p.m. and 7 a.m., and on any public holiday, including Sundays. This
Ordinance also controls the general level of noise at night, i.e. from 11 p.m. to 6 a.m., even if
powered mechanical equipment is not being used. Statutes governing safety, health and
welfare of workmen are given in Appendix E.
Land matters should be dealt with well in advance of the required date of commencement
of investigations. For this purpose, the appropriate District Lands Office of the Lands
Department, and, where appropriate, the relevant District Office, should be consulted, so as to
305
arrange for unhindered access for transporting equipment to site, and to enable work to be
carried out on site. The land matters should include :
It is important that the exact locations of site boundaries of private and Government land,
and of allocated works areas and storage areas, should be ascertained from the appropriate
District Lands Office. The appropriate District Survey Office of the same Department may
also have to be consulted for information on delineation of the ground, especially in the New
Territories where land demarcation has not been carried out to a high standard in the past.
The District Lands Office should also be consulted on matters relating to 'fung shui' and
burial grounds.
Where trees need to be felled or removed, prior permission should be obtained from the
appropriate District Lands Office, who will consult the Agriculture & Fisheries Department,
Urban Services Department or Regional Services Department, as appropriate. Whenever
possible, permission should be sought twelve months in advance, so that the root system of any
tree suitable for transplanting may be prepared for the move.
The approval of the Buildings Ordinance Office, must be obtained for site investigation
work that falls within the Mid-levels Scheduled Area. Plans showing the boundary of the Mid-
levels Scheduled Area may be viewed in the Buildings Ordinance Office and the Geotechnical
Engineering Office. Pumping test proposals for private developments must also be submitted
to the Buildings Ordinance Office for approval.
Information on the as-built alignment of the Mass Transit Railway and its "protection
boundary" may be obtained from the Mass Transit Railway Corporation, whose advice must be
sought where the proposed ground investigation work falls within the protection boundary.
If it is intended to use explosives, for example in a seismic survey, the prior permission
of the Commissioner of Mines at the Civil Engineering Department must be obtained.
In the case of marine investigations, the Marine Department must be notified of the
details of the proposals, so that notices to mariners can be issued. Special restrictions may be
imposed by Director of Marine where works is to be carried out in close proximity to fairways,
channels, typhoon shelter entrances, terminals and piers. There may be circumstances where
contractors vessels will need to provide mooring arrangements outside typhoon shelters for
their vessels during the passage of typhoons. Where investigations are proposed close to the
runway of Kai Tak Airport, permission must first be obtained from the Civil Aviation
Department. Similarly, permission must be obtained from the Mass Transit Railway
Corporation, the Cross Harbour Tunnel Co. Ltd, the Water Supplies Department, or the various
public utility companies, if investigations are proposed near submerged tunnels, pipelines or
utilities.
Where the proposed ground investigation works fall within a gazetted historical site,
permission must be obtained from the Antiquities & Monuments Office of the Government
Secretariat before commencement of any work. The Antiquities & Monuments Office should
also be consulted before any historical site is entered, even if it is not gazetted.
A.9 References
Government of Hong Kong (1981a). Fire Services Ordinance (and Fire Services Regulation).
Laws of Hong Kong, Chapter 95, revised edition 1981. Hong Kong Government
Printer, 45 p. (Amended from time to time).
Government of Hong Kong (1983). Dangerous Goods Ordinance (and Dangerous Goods
Regulations). Laws of Hong Kong, Chapter 295, revised edition 1983. Hong Kong
Government Printer, 278 p. (Amended from time to time).
Government of Hong Kong (1985). Buildings Ordinance (and Building Regulations). Laws
of Hong Kong, Chapter 123, revised edition 1985. Hong Kong Government Printer,
387 p. (Amended from time to time).
307
Appendix B
Sources of Information
[Amd GG2/01/2017]
308
Contents
Page
No.
Contents 308
Page
No.
B.10 Scheduled and Designated Areas and Other Concerned Areas 318
B.10.1 Mid-levels Scheduled Area 318
B.10.2 North-western New Territories and Ma On Shan Areas 318
B.10.3 Mass Transit Railway Areas 318
B.10.4 Sewage Tunnel Protection Areas 319
B.10.5 Designated Area of Northshore Lantau 319
B.10.6 Water Gathering Grounds (WGG) 319
B.10.7 Marine Ground Investigation in Difficult Ground Areas 320
B.1 Generals
This document gives important sources of information for the planning of site
investigation in Hong Kong, in addition to the publications and guidance documents prepared
by the GEO. A complete list of GEO publications and a list of TGNs, which are continually
updated, can be found at the website http://www.cedd.gov.hk. Other information that could
be useful for planning, design, construction and maintenance of geotechnical works can be
found at the Hong Kong Slope Safety Website http://hkss.cedd.gov.hk.
The SIS is a geographical information system developed by the GEO to enable on-line
examination and analysis of information on slopes and the surrounding ground. It contains
computerised information including the catalogue of slopes (see Section B.2.2 below), slope
maps, locations of previous landslide incidents reported to GEO and ground investigation
stations, geology, natural terrain landslides and selected geotechnical information for the
various districts in Hong Kong. The SIS can be accessed through the SIS terminals in the
Civil Engineering and Development Building and also via the Hong Kong Slope Safety Website
(http://hkss.cedd.gov.hk). The GEO Slope Safety Division can be contacted for up-to-date
information on the development of the SIS.
The SMRIS, which is maintained by the Lands Department, systematically identifies the
maintenance responsibility of all man-made slopes registered in the Catalogue of Slopes. The
most up-to-date information of maintenance responsibility can be accessed via the Lands
Department or at the Lands Department’s Website (http://www.landsd.gov.hk). Where the
land status of a slope is not available in SMRIS, the Systematic Identification of Maintenance
Responsibility of Slopes (SIMAR) Unit or the respective DLO of Lands Department should be
consulted.
311
The GEO in collaboration with the Hong Kong Observatory (HKO) has established and
maintains a network of automatic raingauges throughout Hong Kong. Rainfall data have been
recorded at 5-minute intervals at these raingauges since 1984. In 1999, the GEO automatic
raingauge system was upgraded and expanded to include 86 GEO raingauges (Pang et al, 2000).
Verified rainfall data are available either from the HKO or the GEO Standards and Testing
Division.
An Incident Report contains information on the date, time (where known) and location
of the incident, the type, size, possible causes contributing to and consequence of the failure,
the advice given, evidence of past instabilities, photographs taken of the failure, etc. If the
failure mass exceeds 50 m3 or where a fatality is involved, a Landslip Card, which contains
more detailed information, is also prepared and is available for inspection in the Public Section
of the Civil Engineering Library (CEL) (Section B.12.1). A computerised landslide database
containing data from the Incident Reports and Landslip Cards is available and is accessible via
the SIS. The database is maintained and updated by the GEO Landslip Preventive Measures
Division 1.
The ENTLI contains information on over 105,000 landslides occurred on natural terrain.
Comprehensive information is recorded in Geographical Information System for each landslide
record including the dates of the aerial photographs when the landslide was first observed, width
and length of the landslide scar, slope gradient, and nature of vegetation cover across the
landslide source. The ENTLI is available for inspection as 1:5 000 scale map sheet paper
copies in the CEL and the digital copy of the data is held in the GEO Planning Division.
A series of fifteen 1:20 000 scale boulder field inventory maps covering the Hong Kong
Special Administrative Region (HKSAR) is available for viewing in GEO Planning Division
and the CEL and a digitised version is available in the SIS. A multiple attribute mapping
technique was adopted to present the results. Four attributes were mapped-percentage area
covered by boulders, boulder type, boulder size and boulder shape.
In this study, covering the whole of Hong Kong, a geomorphological interpretation was
conducted to identify features thought to be landslides with sources areas greater than 20 m
wide (Scott Wilson (Hong Kong) Ltd., 1999a, 1999b). The 1:5 000 scale maps containing the
features are available for viewing in the GEO Planning Division.
312
The Survey & Mapping Office (SMO) of the Lands Department provides maps and plans
in various scales and for various purposes in both digital and paper forms. A list of the
currently available plans and maps, and their coverage, is given in Table B1.
The Land Information Centre of the SMO operates a Computerised Land Information
System (CLIS) and maintains the topographic mapping database covering the whole territory
of Hong Kong. Many utility companies, engineering consultants, computing system
consultants and education institutes have established their own automated mapping, facilities
management, customer support and geographic information systems using the digital maps
provided by the SMO as their common reference. The digital map data are available in four
different formats, namely E00, DGN, DXF and DWG, to suit applications in different platforms.
Services offered by the SMO include the supply of photographic copies of available
maps, plans and aerial photographs, as well as producing enlargements and reductions.
Updated information on map products and related publications, data map products and map
price catalogue, etc., can also be found at the Lands Department Website
(http://www.landsd.gov.hk/mapping/ en/pro&ser/products.htm).
(a) Early maps of Hong Kong are held for reference by the
Survey & Mapping Office and the Government Records
Service (GRS).
The availability of vertical aerial photographs is summarised in Tables B.2a and B.2b.
In general the aerial photograph scales range from 1:2 500 down to 1:50 000. The low altitude
aerial photographs, mainly in the range of 1:6 000 to 1:10 000, are the most useful scale for the
majority of aerial photograph interpretation undertaken.
The GEO Aerial Photograph Library contains over 280,000 aerial photographs including
oblique aerial photographs. They can be borrowed by GEO staff as well as consultants
working on Government projects. A GIS-based computerised aerial photograph retrieval
system is now available for users to identify the photograph collection at a workstation in the
Library. The Library, which is housed in the GEO Planning Division on the 11th Floor of the
Civil Engineering and Development Building, is accessible by staff of the HKSAR Government
and also non-Government staff engaged in Government projects.
A similar system for searching aerial photographs is also available in the SIS.
Aerial photographs can be purchased directly from the Map Publications Centres of the
Lands Department.
Geological surveying in Hong Kong is carried out by the Hong Kong Geological Survey
(HKGS) of the GEO. Thirty-four maps and six sheet reports have been published to date and
the Sheet Reports are available (free of charge) either from the GEO Planning Division or
downloaded from the CEDD Website (http://www.cedd.gov.hk). In 2003, the HKGS
embarked on a programme to update the 1:20 000 scale geological maps and to release them in
digital form. The coverage of the maps, memoirs and reports is shown in Figure B1. The
maps and memoirs (except those which are free of charge) can be obtained from the Map
Publications Centres of the Survey and Mapping Office while the memoirs are also available
from the online Government Bookstore at http://www.bookstore.gov.hk.
A series of eleven 1:20 000 scale terrain classification maps (TCM) covering the whole
of the HKSAR was produced by the GEO in the 1980s. Each map covers an irregular area
based on catchment boundaries. Derivative maps and accompanying reports have been
published for each area as the Geotechnical Area Studies Programme (GASP) series. The
series contains 12 volumes, of which Volume XII is a summary report for the whole of the
HKSAR. They are available for viewing in the Geotechnical Information Unit (GIU) of the
CEL. Limited copies are available for sale at the Map Publications Centres of the Survey and
Mapping Office, and online Government Bookstore.
Nine catchments with extensive colluvial deposits were also identified for GAS mapping
at 1:2 500 scale. These maps contain details of old landslide scars. In 1990, a 1:5 000 scale
314
terrain classification mapping exercise was carried out for eleven 1:5 000 scale map sheets in
North Lantau. These are available for viewing in the CEL and have been incorporated into
three Engineering Geology Reports on the North Lantau Area (Franks, 1991, 1992; Woods,
1992).
The GEO Planning Division is the repository for geological records for the HKSAR.
These include the field observations embodied in the geological maps and memoirs, manuscript
geological maps, and offshore data. Requests for information should be directed to the Chief
Geotechnical Engineer of the Planning Division. The GEO also holds a collection of
representative rock types and thin sections. These are available for inspection by arrangement.
An on-line version of the geology of Hong Kong, based on the two memoirs but with additions
from the current map updating programme now underway, has been published on the internet
(Lee & Sewell, 2007). The on-line geological memoir of Hong Kong can be accessed at
http://www.cedd.gov.hk/eng/about/organisation/ org_geo_pln_map.htm. A summary of the
nature and occurrence of Hong Kong rocks and superficial deposits is also given in Appendix A
of Geoguide 3 (GEO, 2017).
The Hydrographic Office of the Marine Department complies and publishes paper charts
and electronic navigational charts. Further information on the products and services of the
Hydrographic Office can be found at the website http://www.mardep.gov.hk.
Marine Department Notices are issued as and when required concerning information
relating to navigational safety and other marine activities in Hong Kong waters. Copies of the
Notices can be downloaded from the website http://www.mardep.gov.hk.
The Hong Kong Observatory (HKO) collects and publishes meteorological information
in Hong Kong. It issues daily weather reports and forecasts as well as warnings on tropical
cyclone, thunderstorm, rainstorm, landslip, strong monsoon, fire danger, frost, tsunami, cold
and very hot weather. Rainfall records are published monthly and annually. The HKO also
maintains a local seismological network to monitor earthquakes near Hong Kong.
Predicted tide levels at selected locations are published annually in ‘Tide Tables for
Hong Kong’ which are available at the online Government Bookstore.
Further information on the services of the HKO can be found at the website
http://www.hko.gov.hk.
315
The Drainage Services Department and Water Supplies Department operate and
maintain separate systems of stream/river gauging stations in the main catchment areas of the
HKSAR.
The GIU of the GEO holds reports of previous ground investigation, which usually
include borehole logs and sometimes results from geophysical surveys and laboratory testing
of soils, rocks and sediments. Digital Geotechnical Information Unit (DGIU) system is also
available for fast retrieval of these reports in the CEL.
The GIU also contains a large amount of other information of direct relevance to site
investigation, and this is described in Section B.12.1.
For example, each Government Department retains its own files on projects that are
carried out under its control. Copies of design reports and record drawings of completed
projects are also kept.
Department Record/Information
Drainage Services Department Records of sewerage tunnels (see also Section B.10.4)
Since 1984, the GEO has compiled annual reports to document information on rainfall
and landslides occurring in the HKSAR. GEO has also prepared detailed/forensic
investigation reports on some selected major landslide incidents and incidents involving
casualties. Since 1997, GEO has started engaging consultants to carry out investigation of
some selected landslides and to prepare landslide study reports. The annual reports,
detailed/forensic investigation reports and landslide study reports are either published as GEO
Reports or produced as GEO internal reports. GEO Reports can be purchased from the online
Government Bookstore or downloaded from the CEDD Website http://www.cedd.gov.hk.
317
GEO internal reports can be viewed in the CEL. Summary of findings of selected landslide
studies are also uploaded onto the Hong Kong Slope Safety Website http://hkss.cedd.gov.hk for
viewing.
The GRS is the central repository for the permanent archives and selected official
publications of the HKSAR Government. It maintains catalogued collections of maps and
photographs dating from 1860, together with almost complete collections of the Hong Kong
Government Gazette, Blue Books, Sessional Papers, Administrative Reports, Historical &
Statistical Abstracts of Hong Kong, Legislative Council Minutes, Annual Departmental Reports,
Ordinances and Regulations, Hong Kong Hansard and a comprehensive newspaper collection.
In November 2002, GRS introduced an integrated information access system to facilitate online
searching of all catalogues and access to selected visual images via the Internet.
(http://www.grs.gov.hk/ws/english/es_online_cata.htm)
The Photo Library of the Information Services Department has in place some old
photographs which may be reproduced for use by members of the public.
Lists of declared monuments and deemed monuments as well as archaeological sites are
maintained by the Antiquities & Monuments Office (AMO) of the Leisure and Cultural Services
Department (see also Section B.3.2).
For private development, the general requirements for carrying out ground investigation
works, including the site supervision requirements, are given in PNAP APP-49 which can be
downloaded from Buildings Department Website http://www.bd.gov.hk. For public
development, the requirements are given in WBTC No. 13/90. Ground Investigation Note No.
1/2008, which can be downloaded from CEDD Website http://www.cedd.gov.hk gives the
details of procurement of ground investigation and laboratory testing services provided by
CEDD for Government projects. Guidance on specific aspects of site investigation for tunnel
works in Hong Kong are given in Sections 10.9, 16.5 and 40.4 of this Geoguide.
318
For private development, the requirements on the special geotechnical control for
ground investigation works in the Mid-levels Scheduled Area are given in PNAP APP-30. For
public development, the requirements are specified in ETWB TC (Works) No. 29/2002A.
The designated areas in North-western New Territories and Ma On Shan are specified
as Area Numbers 2 and 4 respectively of the Scheduled Areas in the Fifth Schedule of the
Buildings Ordinance. The plans illustrating the exact extent of these Areas are on display in
the Buildings Department and in the GIU.
For private development, the requirements on the special geotechnical control for
ground investigation works in these Scheduled Areas are given in PNAP APP-61. For public
development, the requirements are specified in ETWB TC (Works) No. 4/2004.
To safeguard the safety and stability of the Mass Transit Railway (MTR) structures
operated and maintained by the MTR Corporation Limited (MTRCL), a “protection boundary”
for the railways has been drawn on plans or determined by a figure and a set of
building/engineering guidelines produced. The areas within the “protection boundary” are
commonly known as the railway protection areas.
The MTR operates a network of railways. Amongst the railway protection areas, some
areas are designated as Scheduled Area No. 3 in the Fifth Schedule of the Buildings Ordinance
319
(Scheduled Area No. 3). The areas within the “protection boundary” have been designated as
Scheduled Area No. 3. The plans illustrating the extent of these areas are available for
inspection in the Buildings Department (BD) and the MTRCL. Information on the “alignment
of the railways as constructed” may be obtained direct from MTRCL. For private
development, the additional requirements for ground investigation works within Scheduled
Area No. 3 are given in PNAP APP-24 and PNAP APP-131. WB Technical Circular No.
19/2002, ETWB Technical Circular (Works) Nos. 33/2003 and 2/2005 shall be referred to for
guidance on ground investigation works near the MTR and liaison with the Railway Protection
& Land Survey Manager of the MTRCL.
The Survey and Mapping Office of Lands Department maintains a set of digital land
records covering the whole territory of Hong Kong. Useful information, e.g. lot boundaries,
the railway reserves and others, is recorded in this database.
The sewage tunnel protection areas are designated as Area Number 5 of the Scheduled
Areas in the Fifth Schedule of the Buildings Ordinance (Scheduled Area No. 5). The plans
illustrating the extent of these areas are available for inspection in the Buildings Department
and the Drainage Services Department. For private development, the additional requirements
for ground investigation work within Scheduled Area No. 5 are given in PNAP APP-62. For
ground investigation works proposals of Government Departments in the vicinity of the sewage
tunnels, the project proponents shall refer to ETWB Technical Circular (Works) No. 28/2003
for the procedures for forwarding proposals to Drainage Services Department and GEO for
comment/agreement.
The Designated Area is underlain by locally complex geological conditions that require
due attention to be given to the potential problems associated with high-rise buildings and other
structures involving deep foundations. Technical recommendations and the plan illustrating
the exact extent of the area are given in GEO TGN No. 12.
For private development, administrative procedures and general guidance for ground
investigation work in the Designated Area are given in PNAP APP-134. For public
development, the requirements are specified in ETWB TC(W) No. 4/2004.
Information on the limits of the WGG and the required conditions for protection of the
WGG against pollution should be obtained from the relevant regional office of the Water
Supplies Department. Maps showing WGG are also held by the relevant District Lands
Offices of the Lands Department.
320
Difficult ground conditions generally refer to the existence of unfavourable subsoil strata
on site. Technical guidelines on the areas and the plan illustrating the extent of the areas are
given in Port Works Design Manual issued by CEDD.
Information on the locations of water mains, water tunnels, reservoirs and other
waterwork facilities maintained by the Water Supplies Department (WSD) should be sought
from the Department. Application forms and further information on the customer services of
the WSD can be found at the website http://www.wsd.gov.hk.
As-built records of public stormwater drains and foul sewers should be sought from the
Drainage Services Department (DSD). Similar records for private lots can be obtained from
the Buildings Department. As-built records of exclusive road drainage should be sought from
the Highways Department.
The CEL is the central reference library of the Civil Engineering and Development
Department. The CEL contains over 150,000 documents, including periodicals, books,
conference proceedings, manuals, standards, codes of practice, geotechnical reports, maps,
documents submitted to GEO in support of private developments, and documents produced by
or for Government Departments.
The GIU forms part of the CEL and comprises a collection of geotechnical data from
ground investigations throughout the HKSAR. The following GIU materials are among those
available for inspection within the Public Section of the CEL.
Members of the public are free to view documents held within the Public Section of the
CEL and search for library materials using the Online Public Access Catalogue (OPAC) – V
Lib computer terminals. Retrieval of ground investigation and laboratory testing reports can
be accessed by the Digital Geotechnical Information Unit (DGIU) system. A user’s manual
for DGIU is provided in the CEL. Photocopying and printing facilities are available.
Further information on the services of the CEL and GIU can be found under the Public
Services Section of the CEDD Website http://www.cedd.gov.hk/eng/services/library/ index.htm.
The City Hall Public Library, the Hong Kong Central Library and the Kowloon Public
Library each houses a reference section which contains a number of published documents on
the geology and geotechnical engineering of Hong Kong, together with some unpublished
reports. They also house Hong Kong Collections of considerable interest. Direct access is
permitted to the shelved items, and bibliographic information of the items can be accessed
through the Online Public Access Catalogue. Photocopying facilities are available for public
use.
The University of Hong Kong, the Chinese University of Hong Kong, the Hong Kong
Polytechnic University, the Hong Kong University of Science and Technology and the City
University of Hong Kong each has a large library which contains a collection of general
geological and geotechnical information. The first three, however, can only be accessed by
special permission, although for bona fide visitors this is usually not difficult to obtain. The
University of Hong Kong maintains the Hong Kong Collection, which contains considerable
unpublished information, as well as master and doctoral degree theses on geological and
geotechnical topics.
322
Hong Kong Polytechnic University Library, Hong Kong University of Science &
Pao Yue-kong Library, Technology Library,
Yuk Choi Road, Clear Water Bay,
Hung Hom, Kowloon. Kowloon.
(Tel.: 2766 6863) (Tel.: 2358 6762)
(Website: http://www.lib.polyu.edu.hk) (Website: http://library.ust.hk)
Leisure and Cultural Services Department, Map Publications Centre (Hong Kong),
1-3 Pai Tau Street, Survey and Mapping Office
Sha Tin, Lands Department
New Territories. 23rd Floor, North Point Government
(Tel.: 2603 4567) Offices,
(Website: http://www.lcsd.gov.hk) 333 Java Road, North Point, Hong Kong.
(Tel.: 2231 3187)
(E-mail: [email protected])
Standards and Testing Division, GEO, The University of Hong Kong Library,
12th Floor, Civil Engineering and Development Pokfulam Road,
Building, Hong Kong.
101 Princess Margaret Road, (Tel.: 2859 2203)
Homantin, Kowloon. (Website: http://lib.hku.hk)
(Tel.: 2762 5345)
(E-mail: [email protected])
B.14 References
Allen, P.M. & Stephens, E.A. (1971). Report on the Geological Survey of Hong Kong, 1967-
1969. Hong Kong Government Press, 116 p, plus 2 maps.
Fyfe, J.A., Shaw, R., Campbell, S.D.G., Lai, K.W. & Kirk, P.A. (2000). The Quaternary
Geology of Hong Kong. Geotechnical Engineering Office, Hong Kong, 208 p. plus 6
maps.
Franks, C.A.M. (1991). Engineering Geology of North Lantau: Tsing Chau Tsai Peninsula to
Ta Pang Po (Special Project Report SPR 4/91). Geotechnical Engineering Office,
Hong Kong, 148 p. plus 9 drgs.
Franks, C.A.M. (1992). Engineering Geology of North Lantau: Ta Pang Po to Tai Ho Wan
(Special Project Report SPR 2/92). Geotechnical Engineering Office, Hong Kong,
109 p. plus 5 drgs.
GCO (1982). Mid-levels Study: Report on Geology, Hydrology and Soil Properties (1982).
Geotechnical Control Office, Hong Kong, 265 p. plus 54 drgs.
GEO (1998), GEO Emergency Manual, Geotechnical Engineering Office, Hong Kong
(Amended from time to time)
GEO (2003) Guide to Slope Maintenance (Geoguide 5). (Third Edition) Geotechnical
Engineering Office, Hong Kong, 132 p
GEO (2017). Guide to Rock and Soil Descriptions (Geoguide 3). (Continuously Updated E-
Version released on 29 August 2017). Geotechnical Engineering Office, Civil
Engineering and Development Department, HKSAR Government, 171 p.
King, J.P. (1999). Natural Terrain Landslide Study, the Natural Terrain Landslide Inventory
(GEO Report No. 74). Geotechnical Engineering Office, Hong Kong, 127 p.
326
Lee, C.W. & Sewell, R.J. (2007). On-line Geological Memoir of Hong Kong. Episodes,
vol. 30, no.1, 62 p.
Pang, P.L.R., Evans, N.C., Lam, T.W.K., Au, D. & Man, K.S. (2000). Upgrading of an
automatic raingauge system. Proceedings of the Symposium on Slope Hazards and
their Prevention, Hong Kong, pp 297-302.
Scott Wilson (Hong Kong) Ltd (1999a). Specialist API Services for the Natural Terrain
Landslide Study – Task B Factual Report. Report to Geotechnical Engineering Office,
Hong Kong, 9 p. plus 4 Appendices.
Scott Wilson (Hong Kong) Ltd (1999b). Specialist API Services for the Natural Terrain
Landslide Study – Interpretive Report. Report to Geotechnical Engineering Office,
Hong Kong, 32 p. plus 6 Appendices.
Sewell, R.J., Campbell, S.D.G., Fletcher, C.J.N., Lai, K.W. & Kirk, P.A. (2000). The Pre-
Quaternary Geology of Hong Kong. Geotechnical Engineering Office, Hong Kong,
181 p. plus 4 maps
Woods, N.W. (1992). Engineering Geology of North Lantau: Tung Chung, Vol. I & II
(Special Project Report SPR 1/93). Geotechnical Engineering Office, Hong Kong,
94 p. plus 8 drgs.
327
Topographic Maps
1. 1:1 000 Full HPIC 750 x 850 3254 B&W B1000 3254
2. 1:5 000 Full HP5C 750 x 850 166 B&W B5000 189
3. 1:10 000
Full SM10C 685 x 980 59 B&W B10000 57
(Street Map)
4. 1:20 000 Full HM20C 685 x 980 16 Colour B20000 16
5. 1:50 000 Full HM50CL 1010 x 690 2 Colour N.A. N.A.
6. 1:100 000 Full HM100CL 655 x 850 1 Colour N.A. N.A.
7. 1:200 000 Full HM200CL 327 x 425 1 Colour N.A. N.A.
8. 1:300 000
(Hong Kong in As per
HM300C 610 x 860 1 Colour N.A. N.A.
its regional title
setting)
Digital Orthophotos / Orthophoto Maps
1. 1:5 000 Full N.A. N.A. N.A. N.A. DOP5000 189
2. 1:10 000 Full N.A. N.A. N.A. N.A. DOP10000 55
3. 1:50 000 Full OPM50 1080 x 1400 1 Colour N.A. N.A.
4. 1:100 000 Full OPM100 600 x 770 1 Colour N.A. N.A.
B&W/
Aerial Photos Full# N.A. 250 x 250 Numerous DAP numerous
Colour
Geological Maps
Selective
1. 1:5 000* HGP5, 5A, 5B 760 x 1000 34 Colour N.A. N.A.
Areas
2. 1:20 000* Full HGM20 & 20S 775 x 1000 14 & 1 Colour N.A. N.A.
2a. 1:20 000 Full HGM20 700 x 1000 1 Colour N.A. N.A.
3. 1:100 000 Full HGM100 660 x 1000 1 Colour N.A. N.A.
Town Planning
Plan by Planning N.A. 471 Various Various B&W N.A. N.A.
Department
Legend:
* See Figure B1 for area coverage
# See Table B2 for further details
328
Approximate
Year Scale(s) Coverage (%) Remarks
HKI K NT
Note: Colour aerial photographs have also been taken routinely since 1993.
329
Approximate
Year Scale(s) Coverage (%) Remarks
HKI K NT
Map Coverage
Sheet Report Nos. Area of Coverage
1:5 000 Sheet Nos.
SW-A
6 Tung Chung and Northshore Lantau Island 9-SE-A, 9-SE-B and 5 offshore part
map sheets
Appendix C
Contents
Page
No.
Contents 332
C.1 General
The purpose of the site reconnaissance is to confirm and supplement the information
collected during the desk study (see Section 4.2). The site reconnaissance may include both
site inspection and local enquiries concerning existing and proposed features on and adjacent
to the site.
Although site reconnaissance is normally carried out after completion of a thorough desk
study (see Section 4.2 and Appendix A), an early site visit/reconnaissance preceding the desk
study may sometimes be very useful.
Prior to undertaking the site reconnaissance, the following preparations should be made :
(b) The site plan, topographic and geological maps and the
necessary equipment should be available; for example,
notebook, pencil, large clip board, camera, measuring tape,
geological compass (compass and clinometer), geological
hammer, penknife and hand lens (x10). For large sites, a
range finder and binoculars may also be useful. Any
equipment necessary to ensure the safety of field personnel
should also be included.
(g) Water levels, direction and rate of flow in nullahs and streams,
and also flood levels and tidal and other fluctuations, should
be noted where relevant.
Data on and relating to ground conditions should be gathered and recorded, as follows :
(d) The surface drainage pattern and any evidence of active soil
erosion from surface water (e.g. gullies) should be noted.
A supplementary site visit will often be necessary just prior to commencement of the
actual ground investigations. Where appropriate, this should include the following activities :
Appendix D
Contents
Page
No.
Contents 337
D.1 General
In addition to the determination of ground conditions at the site, which are considered
elsewhere in this Geoguide, other information that may be required for design and construction
is briefly summarised in the following sections.
The items listed in this Appendix are by no means exhaustive, and relevant guidance
documents on the information requirements for design and construction should be consulted for
additional advice. Time constraints may limit the extent of detailed study that can be given to
the project, in which case allowance should be made in the design, e.g. by adopting conservative
assumptions for design parameters.
A detailed survey of the site and its boundaries, showing means of access, utilities and
services, easements and drainage networks, will be necessary. Survey coordinates should be
referenced to the 1980 Hong Kong Metric Grid and levels to the Hong Kong Principal Datum.
Exact locations of site boundaries should be ascertained from the appropriate District Lands
Office (see Appendix A.8). The following may also be required :
(e) Locations of survey markers and bench marks near the site,
with accompanying details; documentation of site markers
and bench marks.
The design of structures in, adjoining or near the sea, nullahs or streams may require
information on the following :
339
Sources of materials for construction may need to be located and proven, including:
(e) water,
Sites for disposal of wastes or surplus materials may need to be located, and methods of
disposal resolved, for such materials as :
Access to controlled tips and public dumping areas must be determined, as well as
transport requirements and environmental controls.
341
Appendix E
Safety Precautions
342
Contents
Page
No.
Contents 342
E.1 General
The prime factors required to ensure safe working conditions are supervision by a
competent person and the engagement of a suitably experienced contractor who possesses
adequate resources for the project in hand.
Reference should always be made to relevant Ordinances and Safety Regulations, and
to the British Standards and Codes of Practice for advice on the manufacture and use of
equipment.
A comprehensive set of regulations exists in Hong Kong governing the safety, health
and welfare of personnel employed in construction works. For construction sites generally,
the principal statutory requirements are given in the Factories and Industrial Undertaking
Ordinance and its subsidiary Regulations (Government of Hong Kong, 1985), and the
Construction Sites (Safety) Regulations (Government of Hong Kong, 1983a). These statutes
cover general as well as specific areas of construction works, including :
(c) Use of lifting appliances and lifting gears, dealt with under
Parts II, III and V of the Construction Sites (Safety)
Regulations.
The use of explosives and compressed gas (for example, in seismic surveys) is dealt with
under the Dangerous Goods Ordinance and its subsidiary Regulations (Government of Hong
Kong, 1983b).
The use of equipment incorporating radioactive sources is dealt with under the Radiation
Ordinance and its subsidiary Regulations (Government of Hong Kong, 1982). Such
equipment should always be used fully in accordance with the manufacturers' recommendations.
344
In urban areas, significant hazards may be encountered from underground services such
as electricity and gas. Particular attention should be paid to the hazards resulting from damage
to high voltage power cables, gas pipelines and associated installations. Before any trial pits,
probes or boreholes are commenced in areas where there may be underground services, hand-
excavated inspection pits should be used to establish the presence or otherwise of all such
services. Hand-operated power tools may be necessary in inspection pits to assist excavation
through hard materials, but should be used with extreme care.
For works on or adjacent to public roads and pavements, the requirements of the Road
Traffic (Traffic Control) Regulations (Government of Hong Kong, 1983c) must be complied
with. Reference should also be made to the Code of Practice for the Lighting, Signing &
Guarding of Road Works (Highways Office, 1984).
345
E.5 References
[Amd GG2/01/2017]
BSI (2008). Safety Precautions and Procedures for the Construction and Descent of Machine-
bored Shafts for Piling and Other Purposes (BS 8008:1996+A1:2008). British
Standards Institution, London, 20 p. [Amd GG2/01/2017]
Government of Hong Kong (1983a). Construction Sites (Safety) Regulations. Laws of Hong
Kong, Chapter 59, revised edition 1983. Hong Kong Government Printer, 58 p.
(Amended from time to time).
Government of Hong Kong (1983b). Dangerous Goods Ordinance (and Dangerous Goods
Regulations). Laws of Hong Kong, Chapter 295, revised edition 1983. Hong Kong
Government Printer, 278 p. (Amended from time to time).
Government of Hong Kong (1983c). Road Traffic (Traffic Control) Regulations. Laws of
Hong Kong, Chapter 374, revised edition 1983. Hong Kong Government Printer,
134 p. (Amended from time to time).
Government of Hong Kong (1985). Factories and Industrial Undertakings Ordinance (and
Subsidiary Legislation). Laws of Hong Kong, Chapter 59, revised edition 1985.
Hong Kong Government Printer, 270 p. (Amended from time to time).
Highways Office (1984). Code of Practice for the Lighting, Signing & Guarding of Road
Works. Hong Kong Government Printer, 41 p.
HKIE (1981). Guidance Notes on Hand-dug Caissons. Hong Kong Institution of Engineers,
15 p.
Labour Department (1985). A Guide to the Construction Sites (Safety) Regulations. Hong
Kong Government Printer, 48 p.
Labour Department (1986). Reference Manual for Construction Sites Inspection Report.
Hong Kong Government Printer, 24 p.
346
Appendix F
Contents
Page
No.
Contents 347
F.1 Geophysics
Magnetic surveys to identify faults have been successful in offshore areas in Hong Kong
(Sewell et al, 2000 and references therein). Confirmatory boreholes and insitu testing should
be carried out to verify the interpretation obtained from the survey.
Although vertical boreholes are the most commonly used method of ground
investigation, the samples and logging obtained may only indicate very localised characteristics
of the ground along a tunnel alignment.
Inclined boreholes may give comparatively more information along the tunnel alignment
than vertical boreholes. Where the orientation of suspected subvertical fault zones or other
significant geological features is known, targeting an inclined borehole in a direction roughly
perpendicular to the feature may give a useful indication of the location, overall thickness and
engineering properties of the feature.
The relative inclinations of the borehole and the feature being investigated govern the
success of the inclined borehole. Faults in Hong Kong are commonly discontinuous and
typically have variable dip, dip direction, width and weathering characteristics. These factors
may affect the effectiveness of inclined boreholes.
Drilling of horizontal boreholes can be carried out either from the excavation face, an
intermediate shaft or from the other end of the tunnel to investigate the ground conditions, in
particular to check whether suspected features of poor ground are present and if so their nature
and extent.
There are limitations to the maximum length that the horizontal borehole can be driven,
depending on the ground conditions, the size of the hole and the power of the drilling rig. 'N'
and 'H' size cores have been obtained from an 800 m long hole in Hong Kong.
Drilling of a horizontal borehole during the planning and design stage is often not
feasible due to lack of access to the tunnel level; usually, for deep tunnels, the construction of
vertical access shafts will not have commenced at this stage.
349
During the construction stage, drilling of horizontal boreholes from the tunnel face can
affect the rate of progress of the excavation; hence alternative access points should be
investigated and the cost-effectiveness of the operation needs to be carefully assessed in the
light of the adequacy of ground data for the design and risk management.
Directional coring techniques are now available to drill from ground level to great depth
and then along a horizontal alignment. This method does not require provision of working
space at the tunnel level and can be very useful for investigating deep tunnels.
There may be limitations as to the maximum depth and length that a directional corehole
can reach as well as the type of core samples that can be taken and the type of geotechnical tests
that can be performed. These matters, as well as drilling location accuracy, cost, mobilisation
considerations and drilling rate should be examined as early as possible in a tunnel project.
To avoid creating preferential flow paths and obstructions in the ground that could pose
hazards to the tunnel excavation, for boreholes that are close to or intercept the tunnel, the
person supervising the ground investigation should ensure that all metal casings are removed
and the boreholes are properly grouted after completion of sampling and testing.
For long boreholes, probe holes and core holes, the position of which could impact on
the design and construction, the specification should require the orientation (dip and dip
direction) and the position of the holes to be checked regularly as drilling progresses to ensure
that they follow the intended alignment.
GEO PUBLICATIONS AND ORDERING INFORMATION
土力工程處刊物及訂購資料
Writing to 書面訂購
Publications Sales Unit, 香港北角渣華道333號
Information Services Department, 北角政府合署6樓626室
Room 626, 6th Floor, 政府新聞處
North Point Government Offices,
333 Java Road, North Point, Hong Kong. 刊物銷售組
or 或
Calling the Publications Sales Section of Information Services 致電政府新聞處刊物銷售小組訂購 (電話:(852) 2537 1910)
Department (ISD) at (852) 2537 1910
進入網上「政府書店」選購,網址為
Visiting the online Government Bookstore at
http:// www.bookstore.gov.hk http://www.bookstore.gov.hk
Downloading the order form from the ISD website at 透過政府新聞處的網站 (http://www.isd.gov.hk) 於網上遞交
http://www.isd.gov.hk and submitting the order online or by 訂購表格,或將表格傳真至刊物銷售小組 (傳真:(852) 2523
fax to (852) 2523 7195 7195)
Placing order with ISD by e-mail at [email protected] 以電郵方式訂購 (電郵地址:[email protected])
1:100 000, 1:20 000 and 1:5 000 geological maps can be 讀者可於下列地點購買1:100 000、1:20 000及1:5 000地質圖:
purchased from: