Estimation of Slab Culvert

This document provides specifications for the construction of a bridge, including: - Dimensions for various structural components of the bridge such as the deck, girders, piers, and abutments. - Quantities of materials needed for the substructure, including excavation requirements and reinforced concrete details. - Reinforcement bar requirements for the foundation. - Dimensions for the independent retaining wall. The document contains detailed specifications to guide construction, ensuring the bridge's structural components are built to proper sizes according to the design plans.

Uploaded by

praloy das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views31 pages

Estimation of Slab Culvert

This document provides specifications for the construction of a bridge, including: - Dimensions for various structural components of the bridge such as the deck, girders, piers, and abutments. - Quantities of materials needed for the substructure, including excavation requirements and reinforced concrete details. - Reinforcement bar requirements for the foundation. - Dimensions for the independent retaining wall. The document contains detailed specifications to guide construction, ensuring the bridge's structural components are built to proper sizes according to the design plans.

Uploaded by

praloy das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 31

BOQ particulars

Approach length
Span Arrangement (c/c of exp) 2x 15 3.50 x 2 = 7.00m 16.5
Total length of bridge 30 0.020 m exp gap each side 30.04
No. of Long. Girders 3
No. of Cross Girders 3
Superstructure Details
Deck Width 8.45 Spacing between Girders= 2.5
Carriageway Width 7.50 Cantilever 1.725
Thickness of deck slab 0.210
Total Depth of Superstructure 1.500
Longitudinal Girder
Length of End Portion 1.000
Length of Tapered Portion 1.500
Length of Mid Portion 9.4
Cross Girder
Length of Cross Girder 5.000 Area of Cross Girder 0.2655

Size of Pedestal 0.700 x 0.700 x 0.300


Depth of Pedestal + Bearing 0.409 / 0.350
Scour level at abt 97.61
Scour level at pier 94.22
Abutment
Abutment Cap(Rec. Portion) 1.24 x 8.70 x 0.40
Abutment Cap(Trap. Portion) 1.02 x 8.70 x 0.40
Abutment Shaft 8.70 x 1.00 x 3.287 SUM
Foundation triangular Portion 1 4.00 x 0.40 x 8.70 6.960
Foundation triangular Portion 2 2.80 x 0.40 x 8.70 4.872
Rectangular potion 1 1.200 x 0.40 x 8.70 4.176
Rectangular potion 2 8.000 x 0.80 x 8.70 55.680
Pier
Pier Cap (Rect.) 6.00 x 2.00 x 0.80
Pier Cap (Trap.) 3.90 x 2.00 x 0.80
Pier Dia 1.60
Foundation tripozoidal portion top area 1.80 x 1.80 SUM
Foundation tripozoidal portion bottom area 8.50 x 8.50 33.971
Rectangular potion 8.500 x 8.50 x 0.90 65.025

Size of Reaction Block (RB1) 0.75 x 0.70 x 0.48


Size of Reaction Block (RB2) 0.75 x 0.40 x 0.67
Size of Reaction Block (RB3) 0.74 x 0.64 x 0.85
size of elastomaric bearing 0.5 0.4 0.096
Independent Retaining Wall (U Shape)
Length of Retaining Wall 2.00
Height of Side Wall 4.98 Depth of Side Wall 0.60
Width of Bottom Slab 8.45 Thickness of Bottom Slab 0.70
Return Wall Thickness of Return Wall @Top 0.30
Length of Return Wall 3.60 hickness of Return Wall @BOTTOM 0.45

Page 1 of 31
Depth/
Sl. SDB MORD Length Width
Item Description Unit Nos Height Quantity
No. Sl. No. Ref No. (m) (m)
(m)
FOUNDATION
1 11.1 300 Excavation for Structures
Earthwork in excavation for structures as per
drawing and technical specifications Clause
305.1 including setting out, construction of
shoring and bracing, removal of stumps and
other deleterious material and disposal upto a
lead of 50 m, dressing of sides and bottom and
backfilling in trenches with excavated suitable
material.

I. Ordinary Soil
i) Upto 3m depth
Abutment Cum 2 9.70 9.00 3.15 549.99
Pier Cum 1 9.50 9.50 3.15 284.29

ii) 3m to 6m depth

Below Retaining wall Cum 4 2.50 9.45 5.83 551.31


Sub-Total = Cum 1,385.59

2 12.39 800 & Providing and laying of PCC M15 levelling


(MoRT 1200 course 100mm thick below foundation
&H) II. PCC Grade M-15 (Levelling Course for
Foundation)
Abutment Cum 2 9.70 9.00 0.150 26.19
Pier Cum 1 9.50 9.50 0.150 13.54
Independent Retaining Wall Cum 4 2.15 8.75 1.200 90.30
Sub-Total = Cum 130.03

3 12.25 1500, R.C.C. grade M 35 in Open Foundation


(MoRT 1700 & complete as per Dwg & Tech Specification.
&H) 2100
Abutment m 2 71.69 143.38
Pier m 1 99.00 99.00
Sub-Total = m 242.37

4 12.38 Cement concrete for reinforced concrete in pile


cap complete as per drawing and Technical
Specification
RCC Grade M35
Using Batching Plant, Transit Mixer and
Concrete Pump
For Abutment Cum 2 0.00 0.40 8.70 0.00
For Pier Cum 1 0.00 1.80 0.00 0.00
Sub-Total = Cum 0.00

4 12.40 1000 & Supplying, fitting and placing HYSD bar


1200 reinforcement in foundation complete as per
drawings and technical specifications Clauses
1000 and 1202
For Abutment Foundation t 2 4.40 8.800
For Abutment Pile t 2 0.00 0.000
For Pier Foundation t 1 8.52 8.520
For Pier Pile t 1 0.00 0.000
Sub-Total = t 17.32

Page 2 of 31
6 12.22 Providing steel liner 10 mm thick for curbs and
6mm thick for steining of wells including
fabricating and setting out as per detailed
drawing
i Abutment or Pier Location t 8.50 0.00 0.15 0.00
Sub-Total = t 0.00
SUBSTRUCTURE
5 13.5 1500, R.C.C. grade M-35 in Substructure complete as
(H) 1700 & per Dwg & Tech Specification
(MoRT 2100
&H) A For Abutments (A1 & A2)
From 5m upto 10m height
(a) Dirt Wall cum 2 8.45 0.3 1.909 9.679
(b) Bracket
(i) Bracket rectangle portion cum 2 7.55 0.30 0.18 0.815
(ii) Bracket triangle portion cum 2 7.55 0.30 0.12 0.272
(c) Pedestals
i) On Edges cum 4 0.70 0.70 0.05 0.098
4x 4 ii) At Centre cum 2 0.70 0.70 0.109 0.107
Sub-Total = cum 10.97
Upto 5m height
(d) Abutment Cap
i) 1st Rect. portion cum 2 1.24 8.700 0.40 8.630
iii) Triangular portion cum 2 1.02 8.70 0.40 3.550
(e) Abutment Shaft cum 2 8.70 1.00 3.287 57.194
Sub-Total = cum 69.37

B For Piers
From 5m upto 10m height
(a) Pedestals
i) On Edges cum 4 0.70 0.70 0.05 0.098
ii) At Centre cum 2 0.70 0.70 0.109 0.107
Sub-Total = cum 0.20
Upto 5m height
(b) Pier Cap
i) 1st Rect. portion cum 1 6.00 2.00 0.80 9.600
iii) Trepozoidal portion cum 1 3.90 2.00 0.80 3.120
(c) Pier Shaft (Rounded) cum 1 2.02 2.79 5.64
Sub-Total = cum 18.36

B Return Wall (Upto 5m height) cum 4 3.60 0.38 6.284 33.93

i) Bottom Slab cum 0 2.00 8.45 0.70 0.00


ii) Vertical Wall cum 0 2.00 0.60 4.98 0.00
Sub-Total = cum 33.93
C Reaction Block (From 5m upto 10m height)
i) RB1 cum 8 0.75 0.70 0.48 2.02
ii) RB2 cum 12 0.75 0.40 0.67 2.41
iii) RB3 cum 0 0.74 0.64 0.85 0.00
Sub-Total = cum 4.43

6 12.6 1000 Supplying, fitting and placing HYSD bar


reinforcement (Fe 500) in substructrue complete
as per drawings and technical specification
Clauses 1002, 1005, 1010 & 1202
(i) For abutment t 2 8.62 17.240
(ii) For pier t 1 4.59 4.590
(iii) for pedastal and reaction block@150g/m3 of
t 0.73 0.726
Concrete
Sub-Total = cum 22.56

Page 3 of 31
9 13.16 Supplying, fitting and fixing in position true to
(MoRT line and level POT-PTFE bearing consisting of a
&H) metal piston supported by a disc or unreinforced
elastomer confined within a metal cylinder,
sealing rings, dust seals, PTFE surface sliding
against stainless steel mating surface,
completre assembly to be of cast
steel/fabricated structural steel, metal and
elastomer elements to be as per IRC: 83 part-I &
II respectively and other parts conforming to BS:
5400, section 9.1 & 9.2 and clause 2006 of
MoRTH Specifications complete asper drawing
and approved technical specifications.
Nos 0 - - - - 0

7 13.15 Supplying, fitting and fixing in position true to


(MoRT line and level POT-PTFE bearing conforming to
&H) IRC: 83 (Part-II) section IX and clause 2005 of
MoRTH specifications complete including all MT
accessories as per drawing and Technical
Specifications.

(i) Fixed (1 Nos per Span) No. 2 71.93 143.86


(ii) Free (2 Nos per Span) No. 4 71.93 287.72
(iii) Transverse Guiided (2 Nos per Span) No. 4 71.93 287.72
(iv) Longitudinally Guiided (1 Nos per Span) No. 2 71.93 143.86

8 12.9 600 Providing weepholes in brick masonry/stone


masonry, plain/reinforced concrete abutment,
wing wall, return wall with 100 mm dia AC pipe
extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical
specification Clauses 614, 709, 1204.3.7
Nos 64 - - - - 64

9 12.10 1200 Backfilling behind abutment, wing wall and


return wall complete as per drawings & technical
specification Clause 1204.3.8
With Sandy Material
(i) Behind Abutment cum 2 6.35 3.00 6.28 239.420
(ii) Behind Independent Retaining Wall cum 0 2.00 6.05 6.28 0.000
Sub-Total = cum 239.42

10 12.11 1200 Providing and laying filter media with granular


crushed aggregates as per specification to a
thickness of not less than 600 mm with smaller
size towards the soil and bigger size towards the
wall and providing over the entire surface behind
abutment, wing wall, return wall to the full
height, compacted to firm condition complete as
per drawing and technical specification Clause
1204.3.8

(i) Behind Abutment cum 2 7.55 0.60 6.28 56.933


(ii) Behind Return Wall cum 4 3.00 0.60 6.28 45.245
(iii) Behind Independent Retaining Wall cum 0 2.00 0.60 4.98 0.000
Sub-Total = cum 102.18

Page 4 of 31
SUPERSTRUCTURE
11 13.1 800 Providing and laying reinforced cement concrete
in superstructure complete as per drawing and
technical specifications Clauses 800, 1205.4
and 1205.5.
RCC M-35
i) Longitudinal Girder cum Area Length
(a) End Uniform Section cum 12 0.94 1.000 11.280
(b) Tappered Section cum 12 0.765 1.500 13.770
(c) Mid Uniform Section cum 6 0.59 9.4 33.382
ii) Cross Girder cum
(a) End Cross Girder cum 4 0.2655 5.000 5.310
(b) Intermediate Cross Girder cum 2 0.2655 5.000 2.655
iii) Deck Slab cum 2 2.0394 15 61.182
Sub-Total = cum 127.58

12 13.2 1000 Supplying, fitting and placing HYSD bar


reinforcement (Fe 500) in superstructrue
complete as per drawings and technical
specification Clauses 1002, 1010 & 1202
As per BBS t 2 18.900 37.80
Sub-Total = t 37.80

Providing and laying cement concrete wearing


course M35 grade including reinforcement
13 13.5 800 complete as per drawing and technical
specifications Clauses 800 and 1206.3 Cum 2 15 7.50 0.075 16.875

14 13.6 800 Construction of R.C.C. railing of M 25 grade in


cast-in-situ with 20 mm nominal size aggregate,
true to line and grade, tolerance of vertical
railing post not to exceed 1 in 500, centre-to-
centre spacing between vertical posts not to
exceed 2000 mm as per drawing and technical
specifications Clauses 800, 900 and 1208.3
m 2 37 - - 74.000

15 13.10 1200 Drainage Spouts complete as per drawing and


technical specifications Clause 1209 No 12 12

16 13.11 800 P.C.C. M-15 ordinary grade (1:2.5:5) levelling


course below approach slab complete as per
drawing and technical specificatios Clauses 800
& 1211. cum 2 3.65 7.55 1.200 66.138

17 13.12 800 Reinforced Cement Concrete M-25 grade


approach slab including reinforcement and
formwork complete as per drawing and technical
specifications Clauses 800 and 1211 cum 2 3.5 7.55 0.30 15.855

18 14.22 Strip Seal Expansion Joint (Providing and laying


(MoRT of a strip seal expansion joint catering to
&H) maximum horizontal movement upto 70 mm,
complete as per approved drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation.)
m 3 8.45 25.350

19 15.13 1900 White Washing of Parapet Walls


White washing two coats on parapet walls and
tree trunks including preparation of surface by
cleaning, scapping, etc. as pre technical
specification Clause 1915
sqm 2 37 1.1 81.400

Page 5 of 31
PROTECTION WORK

20 14.5 1300 Providing and laying boulder pitching on


slopes laid over prepared filter media as per
drawing and technical specifications Clause
1302
(i) Behind Abutment (Quadrate Slope) cum 4 42.70 0.30 51.243
(ii) On Embankment Slope of Approaches cum 4 30 14.06 0.30 506.160
Sub-Total = cum 557.40

21 14.1 1300 Providing and laying filter material underneath


pitching in slopes complete as per drawing and
technical specifications Clause 1302
(i) Behind Abutment (Quadrate Slope) cum 4 42.70 0.15 25.622
(ii) On Embankment Slope of Approaches cum 4 30 14.06 0.15 253.080
Sub-Total = cum 278.70

Page 6 of 31
Detailed Estimate for Construction of 2 x 3.855 m x 1.50 m R.C.C Culvert
Name of Work Construction of Road from Marotolia to Barkrakocha road
SL.
No. DESCRIPTION QTY UNIT RATE AMOUNT

1 Earthwork in Excavation in foundation trenches-do-complete job as per


specification and direction of E/I.

Abutment 2x7.50x2.8x2.35 = 98.700 m3

R/Wall 4x2.5x2.8x2.35 = 65.800 m3

Pier 1x10x2.850x2.35 = 66.975 m3

Cut off C/C Length 2x10.71x1.125x2.4 = 57.834 m3

Floor 2x10.71x2.5x0.30 = 16.065 m3

2x2.6x7.5x0.30 = 11.700

Total = 317.074 m3

a)Ordinary Soil 317.074 m3 190.59 60431.13


2 Providing and laying PCC or RCC M15 foundation-do-complete job as per
specification and direction of E/I.

Abutment 2x8.50x2.8x0.3 = 14.280 m3

R/Wall 4x3.5x2.8x0.3 = 11.760 m3

Pier 1x10x2.850x0.3 = 8.550 m3

Cut off 2x10.71x1.275x0.3 = 8.193 m3

Total = 42.783 m3 42.783 m3 4588.11 196293.11


3 Providing C.R.S.M in CM(1:4) in foundation-do-complete job as per specification
and direction of E/I.

Abutment 2x8.20x(2.5+1.6)/2x2.20 = 73.964 m3

R/Wall 4x3.5x(2.5+1.6)/2x2.20 = 63.140 m3

Pier 6x(9.70+8.75)/2x(2.55+1.65)/2x2.20 = 255.717 m3

Cut off 2x10.71x0.925x0.60 = 11.888 m3

2x10.71x0.725x0.60 = 9.318 m3

2x10.71x0.525x0.60 = 6.747 m3

Total = 420.774 m3 420.774 m3 3101.57 1305060.02


4 Providing C.R.S.M in CM(1:4) in superstructure-do-complete job as per
specification and direction of E/I.

Abutment 2x7.5x(1.5+0.69)/2x2.35 = 38.599 m3

R/Wall 4x(2.5+3.525)/2x(1.5+0.69)/2x3.0 = 39.584 m3

Pier 1x9.0x(1.650+0.750)/2x2.35 = 25.380 m3

1xpi/4x(1.652+0.752)/2x2.375 = 3.065 m3

Total = 106.628 m3 106.628 m3 3226.43 344027.78


5 Providing and laying PCC or RCC M20 in superstructure-do-complete job as per
specification and direction of E/I.

Abutment 2x7.5x0.75x0.3 = 3.375 m3

D/Wall 2x7.50x0.3x0.5 = 2.250 m3

Pier 1x7.5x0.75x0.3 = 10.125 m3

Rounding 1xpix(0.752)/4x0.3x1/2x2 = 0.796 m3


Detailed Estimate for Construction of 2 x 3.855 m x 1.50 m R.C.C Culvert
Name of Work Construction of Road from Marotolia to Barkrakocha road
SL.
No. DESCRIPTION QTY UNIT RATE AMOUNT

R/Wall 4x4.525x0.60x0.075 = 0.815 m3

Total = 17.361 m3 17.361 m3 5424.70 94178.22


6 Providing and laying PCC or RCC M15 in flooring-do-complete job as per
specification and direction of E/I.

Floor 2x7.5x2.6x0.15 = 5.850 m3

2x10.71x3.00x0.15 = 9.639 m3

Total = 15.489 m3 15.489 m3 4588.11 71065.24


7 Providing and laying PCC or RCC M25 in deck slab-do-complete job as per
specification and direction of E/I.

2x7.5x5.325x0.425 = 33.947 m3

Total = 33.947 m3 33.947 m3 6410.00 217600.27


8 Providing and laying PCC or RCC M30 in wearing coat-do-complete job as per
specification and direction of E/I.

1x7.5x10x0.075 = 11.250 m3

Total = 11.250 m3 11.250 m3 10724.29 120648.26


9 Supplying and laying (Properly ae per design and drawing) rip-rap with good
quality of boulders-do-complete job as per specification and direction of E/I.

Under Flooring 2x7.5x2.6x0.15 = 5.850 m3

2x10.71x3.00x0.15 = 9.639 m3

Total = 15.489 m3 15.489 m3 1412.63 21880.23


10 Providing Flush Pointing(1:3)-do-complete job as per specification and direction
of E/I.

Abutment 2x(8.2+7.5)/2x2.5 = 39.250 m3

Pier 6x2x7.5x2.5 = 225.000 m3

Rounding 6xpix(1.65+0.75)/2x2.60 = 58.837 m3

Sides of abutment

R/Wall 2x2x5.3x3.0 = 63.600 m3

4x5.30x0.60 = 12.720 m4

4x(2.025+0.60)/2x3.0 = 15.750 m5

Total = 415.157 m3 415.157 m3 46.56 19329.71


11 Providing weep holes-do-complete job as per specification and direction of E/I.

Abutment 2x4 = 8.000 No.

R/Wall 4x4 = 16.000 No.

Total = 24.000 No. 24.000 No. 109.24 2621.76


12 Providing MS reinforcement(Tor Steel) as per approved design drawing-do-
complete job as per specification and direction of E/I.

Main Bar 20mm-2x62Nosx5.50M=682x2.50 = 1705.000 kg

Dist:16mm-2x44nosx7.45 M=655.60x1.58 = 1035.848 kg


Detailed Estimate for Construction of 2 x 3.855 m x 1.50 m R.C.C Culvert
Name of Work Construction of Road from Marotolia to Barkrakocha road
SL.
No. DESCRIPTION QTY UNIT RATE AMOUNT

Chairs:16mm:60nos x7.5 M=120 Mx1.58 = 189.600 kg

Total 16MM = 1225.448 Kg

S Steel long 10mm:2x26 nosx5.30M = 275.600 kg


Trans 10mm :2x19 Nos x7.45 M = 283.100 kg
Cap & Dirt Wall:
10mm dia main 2x8 Nosx7.45 M = 119.200 kg
10mm dia main 2x12 Nosx7.45 M = 178.800 kg
10mm dia strirrups 2x39 Nosx3.1 M = 241.800 kg
2x39 Nosx1.9 M = 148.200 kg
Total 10MM = 1246.700 Kg

1526.05 M x0.62 = 946.151 kg


Total MS Rod = 5123.299 kg

Total MS Rod = 5.123 MT 5.123 MT 60438.27 309643.33


Total 2762779.06
Depth/
Sl. Length Width
Item Description Unit Nos Height Quantity
No. (m) (m)
(m)
FOUNDATION
1 Excavation for Structures

Ordinary Soil

Abutment Cum 2 9.45 3.80 1.60 114.91

Pier Cum 1 9.45 3.80 1.60 57.46

Below Wing wall Cum 4 1.50 1.70 3.13 31.88

Cut Off Wall Cum 2 7.00 2.95 1.95 80.54

Flooring Cum 1 4.40 9.75 0.30 12.87

Sub-Total = Cum 297.65

Providing and laying of PCC M15 levelling


2
course 100mm thick below foundation

Abutment Cum 2 8.75 2.65 0.15 6.96

Pier Cum 1 8.75 2.80 0.15 3.68

Independent Retaining Wall Cum 4 1.15 0.70 0.15 0.48

Cut Off Wall Cum 2 7.00 1.95 0.15 4.10

Sub-Total = Cum 15.21

R.C.C. grade M 35 in Open Foundation


3 complete as per Dwg & Tech Specification.

Abutment m 2 25.12 50.24


Pier m 1 25.12 25.12

Sub-Total = m 75.35

4 Supplying, fitting and placing HYSD bar


reinforcement in foundation complete as per
drawings and technical specifications
Clauses 1000 and 1202

For Abutment Foundation t 2 4.40 8.80

For Pier Foundation t 1 8.52 8.52

Sub-Total = t 17.32

5
Providing and laying PCC M15 in Flooring Cum 1 4.40 8.45 0.15 1.27

Providing and laying Stone Pitching in


6 Cum 1 4.40 8.45 0.15 1.27
Flooring
1 Excavation for Structures

Ordinary Soil

SUBSTRUCTURE
7
R.C.C. grade M-35 in Substructure complete
as per Dwg & Tech Specification

For Abutments (A1 & A2)

Abutment Cap
i) 1st Portion Cum 2 8.45 0.40 0.30 2.03

ii) 2nd portion Cum 2 8.45 0.70 0.20 1.18

Abutment Shaft Cum 2 8.45 1.15 1.28 24.78

Sub-Total = Cum 27.99

For Piers

Pier Cap Cum 1 8.45 0.65 0.50 2.75

Cum
Pier Shaft Cum 1 8.45 1.58 1.28 10.77

Sub-Total = Cum 13.52

Return Wall Cum 4 3.50 0.38 1.78 9.32

Sub-Total = Cum 13.52

Cut Off Wall Cum 2 7.00 1.71 23.94

Sub-Total = Cum 23.94

8 Supplying, fitting and placing HYSD bar


reinforcement (Fe 500) in substructrue
complete as per drawings and technical
specification Clauses 1002, 1005, 1010 &
1202

For abutment t 2 8.62 17.24

For pier t 1 4.59 4.59


Sub-Total = Cum 21.83
1 Excavation for Structures

Ordinary Soil
9 Providing weepholes in brick masonry/stone
masonry, plain/reinforced concrete abutment,
wing wall, return wall with 100 mm dia AC
pipe extending through the full width of the
structures with slope of 1(V):20(H) towards
drawing face complete as per drawing and
technical specification Clauses 614, 709,
1204.3.7

Abutment Nos 4 - - - - 4.00

Retaining Wall Nos 16 - - - - 16.00

10 Backfilling behind abutment, wing wall


and
With return
Sandy wall complete as per drawings
Material
& technical specification Clause 1204.3.8
Behind Abutment Cum 2 6.35 2.90 3.23 118.78
Sub-Total = Cum 118.78

11 Providing and laying filter media with granular


crushed aggregates as per specification to a
thickness of not less than 600 mm with
smaller size towards the soil and bigger size
towards the wall and providing over the entire
surface behind abutment, wing wall, return
wall to the full height, compacted to firm
condition complete as per drawing and
technical specification Clause 1204.3.8

Behind Abutment Cum 2 7.55 0.60 3.23 29.22

Behind Return Wall Cum 4 2.90 0.60 3.23 22.45


Behind Independent Retaining Wall cum 0 2.05 0.60 0.00 0.00
Sub-Total = Cum 51.66
1 Excavation for Structures

Ordinary Soil

SUPERSTRUCTURE
12 Providing and laying reinforced cement
concrete in superstructure complete as per
drawing and technical specifications Clauses
800, 1205.4 and 1205.5.
RCC M-35
Deck Slab Cum 2 8.45 3.00 0.30 15.21
Sub-Total = Cum 15.21

13 Supplying, fitting and placing HYSD bar


reinforcement (Fe 500) in superstructrue
complete as per drawings and technical
specification Clauses 1002, 1010 & 1202
As per BBS t 2 18.90 37.80
Sub-Total = t 37.80

Providing and laying cement concrete


wearing course M35 grade including
14 reinforcement complete as per drawing and Cum 2 3.00 7.50 0.08 3.38
technical specifications Clauses 800 and
1206.3

15 Parapet Wall Cum 2 13.00 0.40 0.60 6.24

16 Drainage Spouts complete as per drawing


and technical specifications Clause 1209 No 2 2.00

17 P.C.C. M-15 ordinary grade (1:2.5:5) levelling


course below approach slab complete as per
drawing and technical specificatios Clauses Cum 2 3.65 8.45 0.30 18.51
800 & 1211.

18 Reinforced Cement Concrete M-25 grade


approach slab including reinforcement and
formwork complete as per drawing and Cum 2 3.50 8.45 0.30 17.75
technical specifications Clauses 800 and
1211

19 White Washing of Parapet Walls


White washing two coats on parapet walls
and tree trunks including preparation of Sqm 2 13.00 1.10 28.60
surface by cleaning, scapping, etc. as pre
technical specification Clause 1915

CEMENT PLASTER

20 Cement Plaster (1:4)

1. Wing Wall Sqm 4 2.40 3.13 30.00

2. Wing Wall Top Sqm 4 1.00 0.40 1.60

3. Abutment Sqm 2 21.10 3.23 136.10


1 Excavation for Structures

Ordinary Soil

4. Pier Sqm 1 21.90 3.38 73.91

5. Slab Sides Sqm 2 3.00 0.30 1.80

6. Slab Bottoms Sqm 2 8.45 3.00 50.70

7. Parapet Walls Sides Sqm 2 26.80 0.60 32.16

8. Parapet Walls Top Sqm 2 13.00 0.40 10.40

Sub-Total = Sqm 336.6675


483147000.xlsx Vol Calc

#REF!

Computation of Volume Computation of Pitching


#REF! #REF!
Average
Length of Area of
Area Volume Chainage Length of
Chainage Pitching Pitching
Pitching
FILL CUT FILL CUT 00+100 0.773
00+000 0.000 3.897 0.000 0.000 00+110 0.762 0.767 7.674
00+010 0.000 3.701 0.000 37.990 00+120 2.024 1.393 13.929
00+020 0.000 2.955 0.000 71.270 00+130 1.159 1.591 15.912
00+030 0.000 1.772 0.000 94.905 00+140 1.037 1.098 10.979
00+040 0.573 0.290 2.865 105.215 Total : 48.495
00+050 0.765 0.080 9.555 107.065
00+060 0.875 0.145 17.755 108.190 Total Area: 48.49 sqm
00+070 1.000 0.175 27.130 109.790
00+080 2.147 0.000 42.865 110.665
00+090 2.558 0.000 66.390 110.665
00+100 3.534 0.000 96.850 110.665
00+110 6.729 0.000 148.165 110.665
00+120 12.184 0.000 242.730 110.665
00+130 14.986 0.000 378.580 110.665
00+140 21.900 0.000 563.010 110.665

#REF! Computation of Pitching


Area Volume #REF!
Average
Chainage Length of Area of
FILL CUT FILL CUT Chainage Length of
Pitching Pitching
Pitching
00+300 23.780 0.000 0.000 0.000 00+300 2.491
00+310 15.432 0.000 196.060 0.000 00+310 2.491 2.491 24.914
00+320 8.668 0.000 316.560 0.000 00+320 2.491 2.491 24.914
00+330 2.699 0.000 373.395 0.000 00+330 2.828 2.660 26.597
00+340 0.066 0.888 387.220 4.440 Total : 76.43
00+350 0.025 1.353 387.675 15.645 Total Area: 76.43 sqm
00+360 0.042 1.504 388.010 29.930
00+370 0.028 1.911 388.360 47.005
00+380 0.000 2.348 388.500 68.300
00+390 0.002 2.008 388.510 90.080
00+400 0.000 2.332 388.520 111.780
00+410 0.000 1.859 388.520 132.735
00+420 0.000 2.173 388.520 152.895
00+430 0.082 1.895 388.930 173.235
00+440 0.000 1.894 389.340 192.180
00+450 0.318 1.770 390.930 210.500
00+460 0.121 1.789 393.125 228.295
00+470 0.000 2.497 393.730 249.725
00+480 0.154 2.256 394.500 273.490
00+490 0.069 2.455 395.615 297.045
00+500 0.236 2.496 397.140 321.800
00+510 0.289 2.451 399.765 346.535
00+520 0.020 3.022 401.310 373.900
00+530 0.000 3.887 401.410 408.445

Abstract
Remark FILL CUT Total
#REF! 563.01 110.67 673.68
#REF! 401.41 408.45 809.86

Smeatons Project Pvt. Ltd., Ranchi


483147000.xlsx Retaining Wall

#REF!

QUANTITY CALCULATION

SL. NH Sch.
DESCRIPTION UNIT No. Length Breadth Height L×B×H QTY
No. Item
D No. RETAINING WALL
47 Excavation for structures in ordinary
soil (Earth work in excavation of
foundation of structures as per
drawing and technical specification,
12.1 (I) including setting out, construction of
B shoring and bracing, removal of
stumps and other deleterious matter,
dressing of sides and bottom and
bockfilling with approved material)
Mechanical means
#REF!
6 m Height Retaining Wall cum 2 10.8 6.1 2.1 138.35 276.7

4 m Height Retaining Wall cum 2 10.8 3.80 2.1 86.18 172.4

#REF!
6 m Height Retaining Wall cum 2 10.8 6.1 2.1 138.35 276.7
4 m Height Retaining Wall cum 2 10.8 3.80 2.1 86.18 172.4

Total 0.0

48 12.8 A Plain/Reinforced cement concrete in


Foundation complete as per drawing
and technical specification, (PCC
Grade M15 using Concrete Mixer)

#REF!

6 m Height Retaining Wall cum 2 10.2 5.5 0.1 5.61 11.2

4 m Height Retaining Wall cum 2 10.2 3.20 0.1 3.26 6.5

#REF!

6 m Height Retaining Wall cum 2 10.2 5.5 0.1 5.61 11.2

4 m Height Retaining Wall cum 2 10.2 3.20 0.1 3.26 6.5

Total 0.0

49 12.8 E Plain/Reinforced cement concrete in


Foundation complete as per drawing
and technical specification, (RCC
Grade M25 using Concrete Mixer)

#REF!
6 m Height Retaining Wall

Foundation Straight cum 2 10 5.30 0.6 31.8 63.6

Foundation Tapered cum 2 10 1.220 1.0 12.2 24.4

Shaft cum 2 10 0.700 1.0 7 14.0

4 m Height Retaining Wall

Foundation Straight cum 2 10 3.00 0.6 18 36.0

Foundation Tapered cum 2 10 0.700 1.0 7 14.0

Smeatons Project Pvt Ltd., Ranchi


483147000.xlsx Retaining Wall

Shaft cum 2 10 0.433 1.0 4.33 8.7

#REF!
6 m Height Retaining Wall

Foundation Straight cum 2 10 5.30 0.6 31.8 63.6

Foundation Tapered cum 2 10 1.37 1.0 13.7 27.4

Shaft cum 2 10 0.7 1.0 7 14.0

4 m Height Retaining Wall

Foundation Straight cum 2 10 3.00 0.6 18 36.0

Foundation Tapered cum 2 10 0.78 1.0 7.8 15.6

Shaft cum 2 10 0.433 1.0 4.33 8.7

Total 0.0

50 13.5 F Plain /Reinforced Cement Concrete in


Sub-Structure complete as per
(p) Case
drawing and technical specifications
I (RCC M 25 using concrete mixer)
#REF!

6 m Height Retaining Wall cum 2 10 0.500 4.0 20 40.0

4 m Height Retaining Wall cum 2 10 0.367 2.0 7.34 14.7

#REF!

6 m Height Retaining Wall cum 2 10 0.500 4.0 20 40.0

4 m Height Retaining Wall cum 2 10 0.367 2.0 7.34 14.7

Total 0.0

51 12.40 Supplying , fitting and placing un- tonne Foundation 14.39 0.0
coated HYSD bar reinforcement in
foundation complete as per drawing
and technical specifications
52 13.6 Supplying , fitting and placing HYSD tonne Substructure 14.31 0.0
bar reinforcement in sub-structure
complete as per drawing and technical
specifications
53 15.5 Providing and laying Filter material

under pitching in slopes complete as

per drawing and technical specification


#REF!

6 m Height Retaining Wall cum 2 10 0.6 5.0 30 60.0

4 m Height Retaining Wall cum 2 10 0.6 3.0 18 36.0

#REF!

6 m Height Retaining Wall cum 2 10 0.6 5.0 30 60.0

4 m Height Retaining Wall cum 2 10 0.6 3.0 18 36.0

Total cum 0.0

54 13.8 Providing weep hole in Brick, Each 360 0.0


masonary/Plain/Reinforced Cement
Concrete abutment, wing
wall/returnwall with 100mm dia AC
pipe, extending through the full widt
of the structure with slope of 1V:20H
towards drawing foce. Complete as
per drawing and Technical
specification.

Smeatons Project Pvt Ltd., Ranchi


483147000.xlsx BOQ Retaining Wall

#REF!

BILLS OF QUANTITIES

SL. NH Sch. DESCRIPTION UNIT QTY RATE AMOUNT

No. Item No.


D RETAINING WALL

47 12.1 (I) B Excavation for structures in ordinary soil cum 0 63 0


(Earth work in excavation of foundation
of structures as per drawing and technical
specification, including setting out,
construction of shoring and bracing,
removal of stumps and other deleterious
matter, dressing of sides and bottom and
backfilling with approved material)
Mechanical means
48 12.8 A Plain/Reinforced cement concrete in cum 0 3852 0
Foundation complete as per drawing and
technical specification, (PCC Grade M15
using Concrete Mixer)

49 12.8 E Plain/Reinforced cement concrete in cum 0 4710 0


Foundation complete as per drawing and
technical specification, (RCC Grade M25
using Concrete Mixer)

50 13.5 F (p) Plain /Reinforced Cement Concrete in cum 0 4994 0


Sub-Structure complete as per drawing
and technical specifications (RCC M 25
Case I using concrete mixer)
51 12.40 Supplying , fitting and placing un-coated tonne 0 67578 0
HYSD bar reinforcement in foundation
complete as per drawing and technical
specifications
52 13.6 Supplying , fitting and placing HYSD bar tonne 0 67721 0
reinforcement in sub-structure complete
as per drawing and technical
specifications
53 15.5 Providing and laying Filter material under cum 0 1459 0
pitching in slopes complete as per
drawing and technical specification
54 13.8 Providing weep hole in Brick, Each 0 128 0
masonary/Plain/Reinforced Cement
Concrete abutment, wing wall/returnwall
with 100mm dia AC pipe, extending
through the full widt of the structure with
slope of 1V:20H towards drawing foce.
Complete as per drawing and Technical
specification.
Sub Total D: 0

Smeatons Project Pvt ltd., Ranchi


483147000.xlsx Steel Retaining Wall

#REF!

STEEL CALCULATION
Foundation Sub-Structure

Structure Sub Total Sub Total


(Kg) (Kg)
Retaining wall Shrirampur Side

6 m Height Retaining Wall 4383.2 4336

4 m Height Retaining Wall 2814.2 2818.8

Retaining wall Fatehpur Side

6 m Height Retaining Wall 4383.2 4336

4 m Height Retaining Wall 2814.2 2818.8

Total 14394.80 14309.60

Smeatons project Pvt Ltd., Ranchi


483147000.xlsx Sch. reif

#REF!

"RETAINING WALL 6m height "

0.30

5.00 6.00

0.40
1.00 0.60

1.50 0.80 3.00

5.30
Typical Diagram of Retaining Wall

Reinforcement Schedule for Retaining Wall of Height 6 m

SL. Spacing
Bar Marked as Dia (mm)
No. (mm)

1 a 10 200 10T @ 200mm c/c

2 b 10 200 10T @ 200mm c/c

3 c 16 125 16T @ 125mm c/c

4 d 10 150 10T @ 150mm c/c

5 e 16 125 16T @ 125mm c/c

6 g 10 200 10T @ 200mm c/c

7 k -earth face 16 125 16T @ 125mm c/c

8 L- remote face 16 125 16T @ 125mm c/c

9 m 10 150 10T @ 150mm c/c

10 n 10 150 10T @ 150mm c/c

Smeatons Project Pvt. Ltd., Ranchi


483147000.xlsx Sch. reif

"RETAINING WALL 4m height "

0.30

3.00 4.00

0.40
1.00 0.60

1.00 0.50 1.50

3.00
Typical Diagram of Retaining Wall

Reinforcement Schedule for Retaining Wall of Height 4 m

SL. Spacing
Bar Marked as Dia (mm)
No. (mm)
1 a 10 200 10T @ 200mm c/c

2 b 10 200 10T @ 200mm c/c

3 c 16 125 16T @ 125mm c/c

4 d 10 150 10T @ 150mm c/c

5 e 16 125 16T @ 125mm c/c

6 g 10 200 10T @ 200mm c/c

7 k -earth face 16 125 16T @ 125mm c/c

8 L- remote face 16 125 16T @ 125mm c/c

9 m 10 150 10T @ 150mm c/c

10 n 10 150 10T @ 150mm c/c

Smeatons Project Pvt. Ltd., Ranchi


#REF!

Bar Bending Schedule for per meter of 6 m Height Retaining Wall

Mark Bar Length in Width in


Clear Cutting Total Unit Total
Location Design Diameter Spacing Longitudinal Transverse Shape Remarks
Cover Length Number Weight Weight
ation d Direction Direction L B

(mm) (mm) (mm) (mm) (mm) (mm) (mm) (m) (Kg) (Kg)

B Bottom
Foundation a 10 200 3800 1000 75 4225 450 4.68 6 0.62 17.31 Longitudinal
L Heel

B Bottom
Foundation c 16 125 2300 1000 75 2725 450 3.18 8 1.58 40.14 Longitudinal
L in Toe

B B Bottom
Foundation b 10 200 1000 3800 75 1000 450 1.90 20 0.62 23.46 Transverse
L Heel

B B Bottom
Foundation d 10 150 1000 2300 75 1000 450 1.90 17 0.62 19.94 Transverse
L Toe

Heel Top
Foundation e 16 125 3827 1000 75 4252 450 4.70 8 1.58 59.44
Longitudinal

Toe Top
Foundation g 10 200 2352 1000 75 2777 450 3.23 6 0.62 11.95
Longitudinal

B B
Heel Top
Foundation d 10 150 1000 3827 75 1000 450 1.90 27 0.62 31.67
Transeverse
L

B B
Toe Top
Foundation b 10 200 1000 2352 75 1000 450 1.90 13 0.62 15.25
Transeverse
L
Abutment
k B B Shaft Earth
Shaft -earth 16 125 6000 1000 75 5850 650 6.50 8 1.58 82.17
L Face,
face
Vertical

Abutment
L-
B B Shaft Water
Shaft remote 16 125 6000 1000 75 5850 650 6.50 8 1.58 82.17
L Face,
face
Vertical

Abutment
B B Shaft Earth
Shaft m 10 150 1000 5000 75 850 400 1.25 34 0.62 26.23
L Face,
Transverse
Abutment
B B Shaft Water
Shaft n 10 150 1000 5000 75 850 400 1.25 34 0.62 26.23
L Face,
Transverse

Total per m = 435.96 kg

Foundation per m = 219 kg

Substructure per m = 216.80 kg


#REF!

Bar Bending Schedule for per meter of 4m Height Retaining Wall


Length in Width in
Mark Bar
Longitudin Transver Clear Cutting Total Unit Total
Location Design Diameter Spacing Shape Remarks
al se Cover Length Number Weight Weight
ation d L B
Direction Direction

(mm) (mm) (mm) (mm) (mm) (mm) (mm) (m) (Kg) (Kg)

B Bottom
Foundation a 10 200 2000 1000 75 2425 450 2.88 6 0.62 10.65 Longitudinal
L Heel

B Bottom
Foundation c 16 125 1500 1000 75 1925 450 2.38 8 1.58 30.02 Longitudinal
L in Toe

B B Bottom
Foundation b 10 200 1000 2000 75 1000 450 1.90 11 0.62 12.90 Transverse
L Heel

B B Bottom
Foundation d 10 150 1000 1500 75 1000 450 1.90 11 0.62 12.90 Transverse
L Toe

Heel Top
Foundation e 16 125 2052 1000 75 2477 450 2.93 8 1.58 37.01
Longitudinal

Toe Top
Foundation g 10 200 1577 1000 75 2002 450 2.45 6 0.62 9.08
Longitudinal

B B
Heel Top
Foundation d 10 150 1000 2052 75 1000 450 1.90 15 0.62 17.59
Transeverse
L
B B
Toe Top
Foundation b 10 200 1000 1577 75 1000 450 1.90 9 0.62 10.56
Transeverse
L

k B B Abutment
RE wall -earth 16 125 4000 1000 75 3850 650 4.50 8 1.58 56.89 Shaft Earth
face L Face, Vertical

L- Abutment
RE wall remote 16 125 4000 1000 75 B B 3850 650 4.50 8 1.58 56.89 Shaft Water
face L Face, Vertical

Abutment
B B Shaft Earth
RE wall m 10 150 1000 3000.00 75 850 250 1.10 20 0.62 13.58
L Face,
Transverse

Abutment
B B Shaft Water
RE wall n 10 150 1000 3000 75 850 250 1.10 20 0.62 13.58
L Face,
Transverse

Total per m = 281.65 kg

Foundation per m = 140.71 kg

Substructure per m = 140.94 kg


483147000.xlsx QTY H.P

#REF!

QUANTITY CALCULATION
SL. NH Sch.
DESCRIPTION UNIT No. Length Breadth Height L×B×H QTY
No. Item No.
D HUME PIPE CULVERT

Excavation for structures in ordinary soil (Earth work


in excavation of foundation of structures as per drawing
and technical specification, including setting out,
construction of shoring and bracing, removal of stumps
55 12.1 (I) A (i) and other deleterious matter, dressing of sides and
bottom and backfilling with approved material)
Mechanical means.

Head Wall cum 4 6.90 1.75 0.900 10.87 43.48

Bedding cum 2 15.20 1.70 0.520 13.44 26.88

Total cum 0.00

PCC 1:3:6 in foundation (Plain Cement Concrete


1:3:6 nominal mix with crushed stone aggregate
40mm nominal size mechanically mixed, placed in
56 9.1 foudation and compacted by vibration including curing
for 14 days.) (Grade M-10)

Head Wall cum 4 6.55 1.40 0.150 1.38 5.52

Bedding cum 2 15.20 1.60 0.160 3.89 7.78

Total cum 0.00


Providing and laying Filter material under pitching in
57 15.5 slopes complete as per drawing and technical cum 4 3.61 4.60 0.15 2.49 0.00
specification
Providing and laying Pitching on slopes laid over
prepared filter media including boulder apron laid dry in
58 15.4 A front of toe of embankment complete as per drawing cum 2 4.50 6.40 0.30 8.64 0.00
and technical specifications. (Stone / Boulder )

Plain/Reinforced cement concrete in Foundation


complete as per drawing and technical specification,
59 12.8 C (RCC Grade M20 using Concrete Mixer)

Head Wall cum 4 6.40 0.90 2.45 14.11 56.450

Bedding cum 2 15.20 1.70 1.600 41.34 82.68

Less for Pipe cum 2 17.85 3.77 1.00 17.85 35.700

Total 0.000
Supplying , fitting and placing un-coated HYSD bar
reinforcement in foundation complete as per drawing
60 12.40 and technical specifications tonne 2 Hume Pipe 0.126 0.000

Laying Reinforced Cement Concrete Pipe


61 9.2 NP4/prestressed concrete pipe on first class bedding in
single row

A 1000 mm dia No 6 2.50 1.00 1 2.50 0.00

###

Smeatons Project Pvt . Ltd , Ranchi


483147000.xlsx BOQ H.P

#REF!

PIPE CULVERT PART


SL. NH Sch.
DESCRIPTION UNIT QTY RATE AMOUNT
No. Item No.
55 12.1 (I) A Excavation for structures in ordinary soil (Earth
work in excavation of foundation of structures
as per drawing and technical specification,
including setting out, construction of shoring
cum 0.00 63 0
and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom
and backfilling with approved material)
(i) Mechanical means.
56 9.1 PCC 1:3:6 in foundation (Plain Cement Concrete
1:3:6 nominal mix with crushed stone
aggregate 40mm nominal size mechanically
mixed, placed in foudation and compacted by cum 0.00 3099 0
vibration including curing for 14 days.) (Grade
M-10)

57 15.5 Providing and laying Filter material under


pitching in slopes complete as per drawing and cum 0.00 1459 0
technical specification
58 15.4 A Providing and laying Pitching on slopes laid over
prepared filter media including boulder apron
laid dry in front of toe of embankment complete cum 0.00 1031 0
as per drawing and technical specifications.
(Stone / Boulder )
59 12.8 C Plain/Reinforced cement concrete in Foundation
complete as per drawing and technical
cum 0 4337 0
specification, (RCC Grade M20 using Concrete
Mixer)
60 12.40 Supplying , fitting and placing un-coated HYSD
bar reinforcement in foundation complete as per cum 0 67578 0
drawing and technical specifications
61 9.2 A Laying Reinforced Cement Concrete Pipe
NP4/prestressed concrete pipe on first class cum 0.00 5935 0
bedding in single row
SUB TOTAL 0

Smeatons Project Pvt Ltd., Ranchi


483147000.xlsx QTY Box Culvert

#REF!

BOX CULVERT (2.00M x 2.00M)

SL. NH Sch.
DESCRIPTION No. Length Breadth Height L×B×H QTY
No. Item No.
62 Excavation for structures in ordinary
soil (Earth work in excavation of foundation
of structures as per drawing and technical
12.1 (I) A specification, including setting out,
(i) construction of shoring and bracing, removal
of stumps and other deleterious matter,
dressing of sides and bottom and backfilling
with approved material) Mechanical means.
i) Curtain Wall (Type I) 1 7.4 2.45 2.65 48.04 48.04
ii) Curtain Wall (Type II) 1 7.4 2.1 2.15 33.41 33.41
iii) Apron 1 7.4 9 1.05 69.93 69.93
iv) Wing Wall
4 3.82 2.810 6.84 73.42 293.68

Total 0.00
63 12.8A Plain/Reinforced cement concrete in open
foundation complete as per drawing and
technical specification, (PCC Grade M15)

i) Box Culvert
1 3.6 8.45 0.15 4.56 4.56

ii) Apron Floor


11.43
AS PER STD. SHEET ATTACHED FOR BOX
iii) Curtain Wall CULVERT
3.7
iv) Wing Wall 4 5.51 2.52 0.15 2.08 8.32
Total 0
64 12.8 C Plain/Reinforced cement concrete in open
foundation complete as per drawing and
technical specification, (RCC Grade M 20
using Concrete Mixer)

Smeatons Project Pvt Ltd., Ranchi


483147000.xlsx QTY Box Culvert

ii) Wing Wall 47.1


AS PER STD. SHEET ATTACHED FOR BOX
iii) Box Culvert CULVERT
54
Total 0.00
65 14.10 PCC M-15 Grade Levelling Course below
Approach Slab complete as per drawing and 2 3.5 8.45 0.15 4.44 0
Technical specification
66 14.11 Approach Slab (M30 Grade) including
reinforcement and formwork complete as 2 3.5 8.45 0.3 8.87 0
per drawing and Technical specification.
67 14.7 Construction of railing of M30 grade in-
situ with 20mm nominal size aggregate,
true to line and grade, tolurence of vertical
RCC post not to exceed 1 in 500, centre to
centre spacing between vertical post not to 2 10.2 10.2 0
exceed 2000 mm, leaving adequate space
between vertical post for expansion,
complete as per approved drawings and
technical specificatoins.
68 13.8 Providing weep holes in Brick masonry/
Plain/ Reinforced concrete abutment, wing
wall/ return wall with 100 mm dia AC pipe,
extending through the full width of the 4 12 0
structure with slope of 1V:20H towards
drawing face. Complete as per drawing and
technical specification.
69 14.9 Providing drainage spout complete as per
1 4 0
drawing and technical specification
70 15.4A Providing and laying Pitching on slopes
laid over prepared filter media including
AS PER STD. SHEET ATTACHED FOR BOX
boulder apron laid dry in front of toe of 0
CULVERT
embankment complete as per drawing and
technical specifications (Stone/Boulder)
71 15.5 Providing and laying Filter material under
pitching in slopes complete as per drawing
4 3.82 0.6 0.925 2.12 0
and technical specification
In Wing Wall
72 13.6 Supplying , fitting and placing HYSD bar
AS PER STD. SHEET ATTACHED FOR BOX
reinforcement in sub-structure complete 0
CULVERT
as per drawing and technical specifications

Smeatons Project Pvt Ltd., Ranchi


483147000.xlsx BOQ Box Culvert

#REF!
BOX CULVERT (2.00M x 2.00M)
SL. NH Sch.
DESCRIPTION UNIT QTY RATE AMOUNT
No. Item No.
62 Excavation for structures in Ordinary soil
(Earth work in excavation of foundation of
structures as per drawing and technical
12.1 (I) A specification, including setting out,
cum 0.00 63 0
(i) construction of shoring and bracing, removal
of stumps and other deleterious matter,
dressing of sides and bottom and backfilling
with approved material) Mechanical means.
63 12.8A Plain/Reinforced cement concrete in open
foundation complete as per drawing and cum 0.00 3852 0
technical specification, (PCC Grade M15)
64 12.8 C Plain/Reinforced cement concrete in open
foundation complete as per drawing and
cum 0.00 4337 0
technical specification, (RCC Grade M 20
using Concrete Mixer)
65 14.10 PCC M-15 Grade Levelling Course below
Approach Slab complete as per drawing and cum 0.00 3706 0
Technical specification
66 14.11 Approach Slab (M30 Grade) including
reinforcement and formwork complete as per cum 0.00 7952 0
drawing and Technical specification.
67 14.7 Construction of railing of M30 grade in-situ
with 20mm nominal size aggregate, true to
line and grade, tolurence of vertical RCC post
not to exceed 1 in 500, centre to centre
spacing between vertical post not to exceed metre 0.00 1664 0
2000 mm, leaving adequate space between
vertical post for expansion, complete as per
approved drawings and technical
specificatoins.
68 13.8 Providing weep holes in Brick masonry/ Plain/
Reinforced concrete abutment, wing wall/
return wall with 100 mm dia AC pipe,
extending through the full width of the Each 0.00 128 0
structure with slope of 1V:20H towards
drawing face. Complete as per drawing and
technical specification.
69 14.9 Providing drainage spout complete as per
Each 0.00 885 0
drawing and technical specification
70 15.4A Providing and laying Pitching on slopes laid
over prepared filter media including boulder
apron laid dry in front of toe of embankment cum 0.00 1031 0
complete as per drawing and technical
specifications (Stone/Boulder)
71 15.5 Providing and laying Filter material under
pitching in slopes complete as per drawing
cum 0.00 1459 0
and technical specification
In Wing Wall
72 13.6 Supplying , fitting and placing HYSD bar
reinforcement in sub-structure complete as tonne 0.00 67721 0
per drawing and technical specifications

Smeatons Project Pvt Ltd., Ranchi


483147000.xlsx BOQ Box Culvert

SUB TOTAL
0.00

Smeatons Project Pvt Ltd., Ranchi