MPR Roads IndGunupur - PAdmapur Road 19.00 To 22.720
MPR Roads IndGunupur - PAdmapur Road 19.00 To 22.720
MPR Roads IndGunupur - PAdmapur Road 19.00 To 22.720
September 2019
Name of the work - “Improvement such as Widening and Strengthening to Gunupur- Padmapur road (MDR) from 19/000 Km to 22/720 Km under KBK (RLTAP)”
3 Widening and Non- Bituminous Base Course (WMM) Km 3.72 3.10 0.62 0.620
Strengthening of
4 Existing road Bituminous Base Course (DBM) Km 3.72 2.50 1.22 1.220
Repair &
8 Major Bridges - Mahanadi River Nos - - - - - -
Rehabilitation
(C) Physical Progress of Other Misc. Work :
Scope of Work Balance Work In
S.No. Section Details of Other Misc. Works UOM Yet to Start Remarks
Work completed Work Progress
1 Toll Plaza location @ Nos - - - - - -
2 Other Works Road Side Drains Rmt. 550 260 290 60 230 -
Road Signs, Marking, Km stones &
3 kms - - - - -
Safety devices & etc.
4 Bus Bays / Passenger Shelters Nos - - - - -
( C) Financial Progress
Target Achieved
Remarks
For the month Cumulative For the month Cumulative
"Rehabilitation and Upgrading to 2 lanes / 2 lane with Paved Shoulders Configuration and Strengthening
1 Name of the work : of Bhojpur- Chhatabar Section (km 131.0 to km 192.0) of NH-200 in the State of Odisha under Phase-I of
National Highways Inter-connectivity Improvement Projects (NHIIP)"
7 Civil Contractor : Sri Durga Condev (P) Ltd.- Shree Balaji Engicon (P) Ltd.-Joint Venture (SDCPL-SBEPL-JV)
8 Contract price of civil works Rs. 218.63 cr
Date of commencement of civil
9 26-10-2015
works.
10 Scheduled date of completion 24-10-2017 (730 days)
Supervision Consultant
11 : LEA Associates South Asia Pvt Ltd.
( Authority's Engineer)
Contract price of Supervision
12 : Rs. 7,82,50,000.00
Consultants (AE)
13 Effective date of assignment of AE : 18-06-2015
Deogarh district: Tree cutting of non foresting area estimate have been obtained by the Ministry vide letter
No.RW/NH-12013/26/6/2010 sp(D)/EAP dt.15.03.2016. Due payment has been deposited to the Forest
18 Tree cutting in non forest area :
Department, Odisha. Tree cutting of 2180 Nos. has been completed so far out of 2422 trees.
Sambalpur district: Tree cutting work of non forestry area of Sambalpur District has been completed.
Stage I clearance: Stage-I clearance approval conveyed by F&E Deptt., Govt of Odisha on dated 12-04-16
20 Forest land diversion :
and for Stage-II, Estimate for NPV, Compensatory afforestation submitted to MoRT&H on dated: 16-06-16
STATUS OF PROJECT UNDER NHIIP PHASE -I as on 15-06-2016 (NH-200)
(i) Electric Pole shifting : Work in Sambalpur District has been completed. Balance work in Deogarh District
recently handed over to EPC Contractor for execution. Route Map of relocation of Electric Poles of Deogarh
21 Shifting of utility :
District was handed over to EPC Contractor during Jan.'2016
(ii) 1.5 Km. of Sec-1 & 6.5 Km. of Sec-II of live water pipe line is yet to be relocated.
Construction camp site completed in Sec-I & Sec-II.The submission of camp lay-out Plan complying to
a) Camp Establishment: :
environmental mitigation plan has been done to AE for review.
b) Laboratory set up: : Set up of lab equipments (100% completed) in Section-I & Section-II.
Existing Batching Plant duly established at Konarajro for Section-I & Rengalibeda for Section-II has been
c) Batching Plant: :
intimated by the EPC Contractor to use for this project corridor.
Existing WMM Plant & Batch type HMP Plant duly established at Badabahal for Section-I is under operation &
d) WMM Plant & Batch type HMP: :
WMM Plant at Rengalibeda for Section-II is under operation.
ROW pillars already established as per schedule. Its painting & lettering confirming to IRC provision is still to
e) ROW :
be complied.
f) Road maintenance Work: : The necessary instruction of PIU & AE has been given for its early regular maintenance
g) Sampling of existing Soil: : Sampling of existing soil of 11 km in Sec-I & 20 km in Sec-II have been completed.
h) Diversion Plan: : Temporary Traffic Diversion Plan for the construction of structures has been Approved.
Status of ESMP (Equipment safety
i) : Being complied & Submitted.
Monitoring plan)
j) Bridge Soil Investigation: : Already Completed.
Source Approval of Manufactured
Source of Admixture, Course Aggregate, Fine Aggregate, Water, Steel, Cement, Hume Pipe have been
k) Materials like (cement,steel,Hume :
approved.
pipes etc)
Aggregate resourse/sampling testing
l) : Approved.
i.e. sand,gravels etc
Quarry for Section-I is at Kusumdih & for section-II is at Khindo. Crusher for Section-I is at Kusumdih &
Section-II is at Chhatripita. The existing crusher plant of Sec-I have been assembled with VSI system & 4.75
m) Quarry & crusher : mm screening facility. The Crusher of Sec-I is under operation. The assembling of VSI system of existing
crusher plant of Sec-II & 4.75 mm screening facility is under progress.
p) Axle load survey : Completed by EPC Contractor and submitted to AE for review.
1)The soft copy of final review report the P & P of balance 30 Km. from Km.142+000 to Km.172+000, 106
Nos. of Box Culverts, 10 Nos. of Minor Bridges, Pavement Design of Sec-I from Km.131+000 to Km.142+000
Pavement Design, Plan Profile and has been handed over to the EPC Contractor on 10.04.2016 for formal submission to AE for final review.
q) :
Work Programme: 2) (i) The Design and GAD of Major Bridge, (ii) Working drawing and detail co-ordinates of major and minor
junctions, (iii) Bus lay bye & Truck lay-bye, (iv) Drainage Plan of the entire Project Cooridor, (v) Pavement
design of Sec-I from Km.142+000 to Km.156+447 is yet to be completed and submitted by the EPC
28 Mobilisation of Man power : Mobilized as per requirement in Sec-II. However, it is inadequate in Sec-I to achieve the month's target.
The Mobilization of AE has been completed except the Resident Engineer as per direction of Chief Engineer,
NH Division, Odisha. The obligations in respect of reporting & deliveries is being complied in time in
confirmity to consultancy Aggrement. The Assistance & supporting guidance in technical & contractual
29 Activities performed by AE :
matters are being provided always to the Authority in all respect. The site supervision & Monitoring of Project
Progress keeping in mind for the achievement of the Monthly target as well as 2 nd Milestone is also being
expedited by Authority's Engineer.
STATUS OF PROJECT UNDER NHIIP PHASE -I as on 24-06-16 (NH-217)
Supervision Consultant M/s. EPTISA Servicios de Ingenieria S.L in cooperation with Eptisa India Private
11 :
(Construction Supervision Consultant) Limited
Micro plan for non title holders and CPRs sanctioned by MoTH&H on 08-03-16.
21 Rehabilitation & Resettlement
1st installment disbursed 50% of PAPs.
22 Status of Drawings
Box Culverts 41 39 39
Minor Bridges 6 6 6
Major Bridge 1 Repair & Rehabilitation
b) Plan & Profiles Submitted by Approved
Chainage
Contractor by CSC
00/00 to 07/00
12/19/2014 12/30/2014
11/00 to 12/00
133/0 to 134/0
6/25/2015 7/13/2015
136/0 to 137/0
a) Camp Establishment: : Camp construction work completed and situated at km 139/350 RHS on NH-353
d) WMM Plant & Batch type HMP: : WMM Plant & HMP mobilized and functioning
24 Mobilization of Man power : Not yet fully mobilized by the Civil Works Contractor
1) The Monthly progress Report upto May-2016 and quarterly progress report for
the period Jan'16-Mar'16 is furnished.
2) The Monthly progress Report for Environmental Monitoring Reports for the
month of Apr-2015 and quarterly progress report for the same for period Jan'16-
25 Activities performed by CSC :
Mar'16 is furnished.
3) Profile checking of all 68 Km is completed.
STATUS REPORT OF EPC PROEJCTS UNDER IMPLEMENTATION BY NH WING Dated. 18.06.2016
Rehabilitation and upgrading to 2-lanes/2-lane with paved shoulders configuration strengthening of Nabarangpur-
1 Name of the work : Koksara Section from 25/0 to 80/0 Km. of N.H. 201 in the state of Odisha under phase -1 of NHIIP-OD-201-09
dated.27.05.2015.
Supervision Consultant
11 : M/s Euroestudios S.L(Spain) & Theme Engineering Service Pvt Ltd ( JV)
( Authority's Engineer)
14 Mobilization Advance to EPC contractor: : 1st Mobilization of Rs4,58,81,300/- & 2nd Mobilization of Rs 6,88,21,950/- has been paid to EPC contractor.
Mile stone
15 Financial Targets for Mile Stone Amount (Cr) Physical
Target date
Balance to
Target Achievement Achievement
Achieved
Earthwork 14.00 Km
GSB 11.25 KM
DBM 6.0 Km
Major Bridge
16 Tree cutting in non forest area : Cutting & felling of road side trees has been completed up to 200 nos out of 224 and others are in pogress.
Permission granted for Stage-I clearance vide letter No. (CONST) 319-18885/2015 dated.28.10.2015 of Joint Secretary to
17 Forest land diversion :
Government F&E Department, Bhubaneswar. NPV & CA deposited to concerned DFOs for Stage-II Clearance.
Electric shifting work completed & estimate for water supply pipe line shifting work has been sanctioned by RO, BBSR on dated:
18 Shifting of utility :
25-05-16
19 Physical Activity by the agency at site :
a) Camp Establishment: : Camp construction work near 47/500 Km.(At Semela) is completed.
b) Laboratory set up: : The Agency has set up the Laboratory at Semela camp.
e) ROW : 98% ROW handed over on appointed date i.e. 02.11.2015.& balance 2% was handed over on 28/01/2016
m) Quarry & crusher : lease taken up at 48/500Km. At Ushigoan crusher and production is in progress.