Assignment Solutions #4
Assignment Solutions #4
2. Figure.1 shows the network diagram indicating the activity and its duration. Based on the
description, choose the correct option which maps the delay to the corresponding critical path(s).
Figure. 1
Assuming the critical activities are on time, match the following:
i. Delayed early start of B by 2 days (I) ABD is the critical path
ii. Delayed early start of B by 3 days (II) ACD and ABD are critical paths
iii. Delayed early start of B by 4 days (III) ACD is the critical path
a. i-I, ii-II, iii-III
b. i - III, ii- II, iii- I
c. i- II, ii- I, iii- III
d. i- III, ii- I, iii- II
6. The critical path is the _____ path in the project and delaying the critical path will delay the
______.
a. Shortest, Activity duration
b. Longest, Project
c. Earliest, Early start of the activity
d. Latest, Slack of an activity
Q7 - 15: The table.1 given below has a high-level breakdown of twenty work items for the gas processing
plant construction project. (Source: High-level integrated deterministic, stochastic and fuzzy cost-duration
analysis aids project planning and monitoring, focusing on uncertainties and earned value metrics by
David Wood 2017).
Table. 1
Activity
No. Activity Predecessors Duration (days)
1 Select Site/Market Survey - 75
2 Process design/engineering 1 80
3 Project planning & consents 2 90
4 Tender & select contractors 2 80
5 Build Process A building 3,4 150
6 Install Process A Plant 5 60
7 Select/train Process A Staff 6 40
8 Build Process B building 3,4 180
9 Install Process B Plant 8 75
10 Select/train Process B Staff 6,9,12 50
11 Build Process C building 3,4 125
12 Install Process C Plant 11 50
13 Select/train Process C Staff 12 30
14 Install Plant Control System 6,9,12,18 90
15 Test Systems/Procedures 7,10,13,14 30
16 Plant HAZOP 15,19 20
17 Build Storage Facilities 3,4 90
18 Build Loading Facilities 17 60
19 Contract Transportation 18 60
20 Commission Plant 16 40
Soln:
9. If Build Process A building utilizes 60% of its total float, what is the remaining total float?.
a. 45 days
b. 27 days
c. 35 days
d. 18 days
Soln: 0.6*45 =27 utilised. Remaining is 45-27= 18 days
10. Free float and Interfering float of Select/ Train Process A staff are____and___.
a. 95 days & 0 days
b. 55 days & 40 days
c. 45 days & 50days
d. 40 days & 55 days
Soln: Activity 7 's successor is Activity 15 . 590-495 = 95 days free float. Total float = 95
therefore Interfering float = 0
12. The early finish and late finish of Select/train Process B Staff activity are___and___.
a. 500 and 540
b. 500 and 550
c. 550 and 590
d. 540 and 590
Soln: Network diagram
14. If the Build Process C building gets delayed by 45 days (from ES schedule) and Install Process C
Plant gets delayed by 30 days (from ES schedule), the critical path now and duration are
____and___.
a. 1-2-3-8-9-14-15-16-20 ; 680 days
b. 1-2-3-5-6-14-15-16-20 ; 635 days
c. 1-2-3-17-18-19-16-20 ; 515 days
d. 1-2-3-11-12-14-15-16-20 ; 600 days
Sol. It's the same because the sum of delays = 75 <80(shared float)