Testing and Commissioning Method Statement

Table of Content

1. Introduction 02
2. Prerequisites to Procedure 02
3. Reference Documents/Drawings 02
4. Commissioning/Test Procedures 02
5. Documentation 03
6. Demonstration Procedures 04

Public Address System 1


Testing and Commissioning Method Statement

1. Introduction

The Public Address System consists of speakers located in different areas of the
buildings and connected to the music rack in the building control rooms. The rack consists of
music sources, BGM controllers and amplifiers.

The testing & commissioning of the system will consists of checking the proper
coverage and sound distribution of background and paging, zone wise testing, music routing.
The testing of the control room equipment includes checking of the music sources, Control
server, amplifiers etc.

The purpose of this document is to describe the details of all commissioning procedures
for BGM System for the project “Resort” in Abu Dhabi. It includes all necessary requisite
procedures such as prerequisites to Procedure, testing procedures etc.

2. Prerequisites to Procedure

 Obtain and study the latest shop drawings and schematics for the PA/BGM System and
check that all information is complete.

 Check the installation of the speakers and if it is found to be incorrect get the installers
to do the remedial actions to correct the same.
 230 V ac Power supply should be available at all control room/rack locations.
 Termination of all the field speakers to be completed.
 Termination of all cables at the control room equipment to be completed.
 Permit to work at all the locations to be provided by Main Contractor

3. Reference Documents/Drawings
 Specification issued by consultant/client.
 Installation and operation manuals of the system components.
 Single Line Diagram for PA/BGM system

4. Commissioning/Test Procedures

After successful completion of pre-commissioning the system will be ready for


commissioning. Prior to the system testing verifies that equipment’s are not damaged, properly
installed, wired, and connected as per the system requirements and fit for operation. The
entire system will be checked for full functionality as per the approved system design and
requirements as follows.

Public Address System 2


Testing and Commissioning Method Statement