Checklist House Keeping
Checklist House Keeping
R.SRINIVASAN
Checklist
ACTIVITY: SAFETY AND HOUSEKEEPING
Location : _______________________________________________ Date : _________
SR.
DESCRIPTION YES N.A. REMARKS
NO.
Is the general status of safety and orderliness in the area
1
maintained?
Are the workers wearing their helmets and safety belts when
2
required?
Are all openings (shafts, doors, balconies) and cut outs safely
3
barricaded or covered?
Is the ladder access area on the floor safely accessible and the
6
ladders checked for damage?
Are all the floor tiles/ granite/ marble properly covered to avoid
7
damages?
Are the debris being cleared on a daily basis and moved out of
9
the site?
R.SRINIVASAN
Checklist
Name Sign Date Name Sign Date
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-EXECUTION CHECKS
POST-EXECUTION CHECKS
R.SRINIVASAN
Checklist
ACTIVITY: EXCAVATION
Location : _______________________________________________ Date : _________
SR.
DESCRIPTION YES N.A. REMARKS
NO.
1 Name, Date and Number of the Drawing
PRE-EXECUTION CHECKS
R.SRINIVASAN
Checklist
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-EXECUTION CHECKS
R.SRINIVASAN
Checklist
SR.
DESCRIPTION YES N.A. REMARKS
NO.
1 Name, Date and Number of the Drawing
PRE-EXECUTION CHECKS
Are the latest "Good for Construction" drawings available?
2
Are the stones wet and free from dust, oil and all forms of
7
contaminations?
POST-EXECUTION CHECKS
Has the curing of masonry been done for atleast 7 days?
20
Checklist : - 6
R.SRINIVASAN
Checklist
Has waterproofing plaster in case of retaining walls done for all
21
external surfaces?
Has a nail been driven to test the strength of joint after 7 days of
22
curing?
Ckecked By; Approved By;
SR.
DESCRIPTION YES N.A. REMARKS
NO.
Is the foam strip around the column starter in place to avoid slurry
8
leakages?
Has the shuttering been checked for proper fixing and sufficient
10
support for concreting ?
Are all the required cut outs and shaft openings in place and
14
checked for correct measurement ?
Have the peripheral areas and cut outs been provided with
15
sufficient cover blocks ?
R.SRINIVASAN
Checklist
Is the deshuttering time as per specification and done in an orderly
17
and safe manner ?
SR.
DESCRIPTION YES N.A. REMARKS
NO.
1 Name, Date and Number of the Drawing
Is the reinforcement free from oil, mud, grease and other forms
9
of contamination?
Are the dowels for columns, beams and slabs in place and
12
checked for proper length ?
Are the required hooks fixed and is the chair height for the upper
13
layer of reinforcement correct ?
Is the lock set properly mixed and the reinforcement turned into
17
the fresh lock set ?
Checklist : - 8
R.SRINIVASAN
Checklist
Has the consultant inspected the reinforcement before the
18
concreting has started?
19 Has adequate lap lengths been provided for all the column bars ?
Is the steel scrap and the rings used for bundling collected in a
20
safe place to avoid any accidents ?
SR.
DESCRIPTION YES N.A. REMARKS
NO.
1 Name, Date and Number of the Drawing
PRE-EXECUTION CHECKS
2 Are the latest "Good for Construction" drawings available ?
Have the required barricading and safety measures been taken?
3
Are the required number of cement bags available on site? (or
4
adequate quantity of RMC been ordered )
5 Are the required tools available at site to ensure correct work ?
6 Have the vibrators been checked before start of the concrete ?
Are calibrated farma available for measurement (weigh batcher
7
in case of weigh batching) .
8 Is the platform and scaffolding material secure ?
Is the necessary shuttering and reinforcement complete and in
9
place?
Has the shuttering material been properly aligned using
10
appropriate equipment?
Are spare hessain cloth or tarpaulin sheet available as
11
protection from the elements ?
Have the dimensions and orientation of the excavated pit been
12
checked ?
13 Has the pit been cleaned by removing all the loose materials ?
R.SRINIVASAN
Checklist
23 Has the levelling and finishing of P.C.C done ?
POST-EXECUTION CHECKS
Has it been ensured that hessain cloth is provided and curing
24
done?
Has it been ensured that no loose earth has fallen on the P.C.C
25
bed ?
Ckecked By; Approved By;
SR.
DESCRIPTION YES N.A. REMARKS
NO.
1 Name, Date and Number of the Drawing
PRE-EXECUTION CHECKS
2 Are the latest "Good for Construction" drawings available ?
Have the required barricading and safety measures been taken?
3
Are the required number of cement bags available on site? (or
4
adequate quantity of RMC been ordered )
5 Are the required tools available at site to ensure correct work ?
6 Have the vibrators been checked before start of the concrete ?
Are calibrated farma available for measurement (weigh batcher
7
in case of weigh batching) .
8 Is the platform and scaffolding material secure ?
Is the necessary shuttering and reinforcement complete and in
9
place?
Has the shuttering material been properly aligned using
10
appropriate equipment?
11 Is the dimensional accuracy of shuttering material correct?
Have the dimensions and orientation of the excavated pit been
12
checked ?
13 Is the test report of cement and steel available at site office ?
14 Has the aggregate been checked? (In case of Site – Mix)
Has the diameter and spacing of reinforcement been checked?
15
Have inserts through columns, if required been placed?
16
Has the verticality of properly supported column box been
17
checked ?
Are spare hessain cloth or tarpaulin sheet available as
18
protection from the elements?
Has the sequence of concreting been planned and sufficient
19
labour deployed ?
R.SRINIVASAN
Checklist
If the depth to be concreted is more than 500 mm, then is
22
concreting being done in layers?
Is the right grade of cement and water-cement ratio been
23 followed?
Are the markings on the column dowels done and a line dori
24
being used to maintain correct concrete level?
Have the admixtures, if any been added?
25
Has the slump cone test been conducted on fresh concrete?
26
Have test cubes been cast (site lab)?
27
POST-EXECUTION CHECKS
28 Is curing been ensured?
Has deshuttering been done carefully without damaging the
29
concrete surface?
Ckecked By; Approved By;
SR.
DESCRIPTION YES N.A. REMARKS
NO.
1 Name, Date and Number of the Drawing
PRE-EXECUTION CHECKS
2 Are the latest "Good for Construction" drawings available ?
Have the required barricading and safety measures been taken?
3
Are the required number of cement bags available on site? (or
4
adequate quantity of RMC been ordered )
5 Are the required tools available at site to ensure correct work ?
6 Have the vibrators been checked before start of the concrete ?
Are calibrated farma available for measurement (weigh batcher in
7
case of weigh batching) .
8 Is the platform and scaffolding material secure ?
Is the necessary shuttering and reinforcement complete and in
9
place?
Has the shuttering material been properly aligned using appropriate
10
equipment?
11 Is the dimensional accuracy of shuttering material correct?
Have markings been made on the column dowels for concrete
12
level ?
13 Is the test report of cement and steel available at site office ?
14 Has the aggregate been checked? (In case of Site – Mix)
Has the diameter and spacing of reinforcement been checked?
15
16 In case of screed-concrete, have bull marks been installed
Are spare hessain cloth or tarpaulin sheet available as protection
17
from the elements ?
Has the sequence of concreting been planned and sufficient labour
18
deployed ?
R.SRINIVASAN
Checklist
Is the concrete been properly compacted with a vibrator or manually
20
?
If the depth to be concreted is more than 500 mm, then is concreting
21
being done in layers?
Is the right grade of cement and water-cement ratio been followed?
22
Are the markings on the column dowels done and a line dori being
23
used to maintain correct concrete level?
Have the admixtures, if any been added?
24
Has the slump cone test been conducted on fresh concrete?
25
Have test cubes been cast (site lab) ?
26
POST-EXECUTION CHECKS
27 Is curing been ensured ?
Has deshuttering been done carefully without damaging the
28
concrete surface ?
Have high pressure water cleaners been used to clean the beam
29
bottoms of inverted beams ?
Ckecked By; Approved By;
SR.
DESCRIPTION YES N.A. REMARKS
NO.
1 Name, Date and Number of the Drawing
PRE-EXECUTION CHECKS
R.SRINIVASAN
Checklist
Are the markings on the column dowels done and a line dori
21
being used to maintain correct concrete level?
Have the admixtures, if any been added?
22
Have test cubes been cast (site lab) ?
23
POST-EXECUTION CHECKS
24 Is curing been ensured ?
Has deshuttering been done carefully without damaging the
25
concrete surface ?
Ckecked By; Approved By;
SR.
DESCRIPTION YES N.A. REMARKS
NO.
1 Name, Date and Number of the Drawing
PRE-EXECUTION CHECKS
2 Are the latest "Good for Construction" drawings available ?
Are the required number of blocks available? (both load bearing
3
and non-load bearing)
Surface preparation:
Has the hacking at contact surfaces of column & beam been
4
done ?
Has cement mortar slurry been applied over the hacked surface
5
and cured for 3 days ?
R.SRINIVASAN
Checklist
POST-EXECUTION CHECKS
23 Has the curing of blockwork done for atleast 7 days?
Has a nail been driven to test the strength of joint after 7 days of
25
curing ?
Ckecked By; Approved By;
ACTIVITY: HACKING
Location : _______________________________________________ Date : _________
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-EXECUTION CHECKS
2 Is the surface cleaned off from dried mortar and loose particles ?
POST-EXECUTION CHECKS
Checklist : - 14
R.SRINIVASAN
Checklist
Has hacking been done on concrete columns,beams,ceiling and
6
all contact surfaces of blockwork ?
Ckecked By; Approved By;
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-EXECUTION CHECKS
R.SRINIVASAN
Checklist
Is the mesh provided throughtout the length of the
9
wall ?
POST-EXECUTION CHECKS
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-EXECUTION CHECKS
R.SRINIVASAN
Checklist
Is the mesh provided throughtout the length of the wall ?Is the
9 packing between corner beads and blockwork done with rich
cement mortar 1:2 ?
POST-EXECUTION CHECKS
10 Is the button mark and corner beads in line and at right angles?
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-EXECUTION CHECKS
Has it been ensured that only rubber lubricant is used for joining
2
SWR pipes & fittings ?
Has provision been made for expansion joints, air vents and
3
proper anchorage for laying of big pipelines ?
Has heavy-duty solvent cement used for large diameter and
4
higher class pipes (6 kg / cm2 and above) ?
R.SRINIVASAN
Checklist
Has it been ensured that cutting pipes are cut square and
7 chamfered at the end cut to an angle of 15 degree with a
medium file ?
POST-EXECUTION CHECKS
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-EXECUTION CHECKS
Has it been ensured that the spigot end and inside of the socket
4
is clean and the sealing ring is placed evenly in the socket?
Checklist : - 18
R.SRINIVASAN
Checklist
POST-EXECUTION CHECKS
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-EXECUTION CHECKS
Checklist : - 19
R.SRINIVASAN
Checklist
Have all the sewer pipes, traps and other fittings free from
2 cracks, holes and burrs etc., and is checked before being put
into use?
POST-EXECUTION CHECKS
Has it been ensured that the spigot end and inside of the socket
is clean and the sealing ring is placed evenly in the socket?Are
4
the spacing of inspection chambers and manholes such that
cleaning of sewer lines can be done easily?
Have the joints of sewer pipes been plugged with cotton yarn
7
(packing rassi) before applying cement slurry over joints ?
SR.
DESCRIPTION YES N.A. REMARKS
NO.
1 Name, Date and Number of the Drawing
PRE-EXECUTION CHECKS
Has the line on walls done by chalk in proper alignment, plumb and as
2
per the heights mentioned in plumbing drawings ?
R.SRINIVASAN
Checklist
Alignment and straightness should be considered
Height for all fittings should be as per given drawing
4 Has the check for class / specifications of materials done?
Has it been ensured that the groove chasing does not exceed 30 mm
5 after rough plaster for cold water supply line and cold feed line and 50
mm for hot water supply lines ?
6 Are the required tools available ?
7 Are there any specific requirements of the client?
Has the pipe-skeleton been prepared and the joints checked for proper
8
tightness ?
Is the skeleton, including fittings covered with good quality Hessian cloth
9
and tied properly for cold water pipe work ?
Is the skeleton fixed in wall using 40 mm plumbing nails at a
10
distance of 230 mm on alternate side ?
Are proper sized wooden plugs inserted in the pipe end and then has
11
the threading carried out ?
POST-EXECUTION CHECKS
Are the internal pipe works in toilets and kitchen concealed and carried
12
out as per working drawings ?
Are the sharp edges of gripping vice and other handling tools
13
muffed with a suitable packing to prevent damage of pipe surface ?
Are the joints made with hand tightening of the fitting over pipe and
14
covered with proper layer of Teflon tape ?
Has special care been taken while connecting UPVC pipe with G.I.
15
Fittings ?
Has water tightness of line been checked using pressure testing
16
equipment ?
17 Has bitumen paint been applied over the G.I pipe work ?
Has it been ensured that the bore pieces projecting out should be of
18
minimum 200 mm from plastered surface ?
Has a gap of 10 mm been kept between all pipes and fittings to
19 accommodate thermal expansion and contraction of pipes for longer life
of the system?
Are all the horizontal lines within bathrooms cement encased and
20 tested before compacting of sunken floor to avoid any accidental
damages ?
21 Has curing been done over the plaster for at least 7 days ?
Ckecked By; Approved By;
SR.
DESCRIPTION YES N.A. REMARKS
NO.
1 Name, Date and Number of the Drawing
PRE-EXECUTION CHECKS
R.SRINIVASAN
Checklist
Have all the loose particles,dirt and dust been scrubbed off from
3
the surface?
Has the second coat of lime applied after the first coat been
10
completely dried ?
POST-EXECUTION CHECKS
ACTIVITY: PUNNING
Location : _______________________________________________ Date : _________
SR.
DESCRIPTION YES N.A. REMARKS
NO.
1 Name, Date and Number of the Drawing
PRE-EXECUTION CHECKS
2 Has the area been prepared for executing the work ?
Checklist : - 22
R.SRINIVASAN
Checklist
POST-EXECUTION CHECKS
15 Is the surface horizontally and vertically perfect ?
SR.
DESCRIPTION YES N.A. REMARKS
NO.
1 Name, Date and Number of the Drawing
Checklist : - 23
R.SRINIVASAN
Checklist
PRE-PLASTERING CHECKS
2 Is the latest "Good for Construction" drawings available ?
Is sufficient place available for starting plastering?
3
POST-PLASTERING CHECKS
Is curing carried out for a min.of 10 days, with the date of
15
plastering on wall with permanent marker
16 Has lime been properly applied, if required ?
17 Has all mortar spillage been cleaned ?
SR.
DESCRIPTION YES N.A. REMARKS
NO.
Checklist : - 24
R.SRINIVASAN
Checklist
1 Name, Date and Number of the Drawing
PRE-PLASTERING CHECKS
2 Is the latest "Good for Construction" drawings available ?
3 Is access available for starting plastering?
4 Has the required barricading and safety measures been taken?
Is the concrete surface beam/column hacked with a minimum of 80
5
hackings/sq.ft?
6 Are Button marks placed at appropriate intervals?
7 Has the GI mesh been nailed between all RCC & masonry members
17 Is the surface wet & free from dust, oil & all forms of contamination?
27 Are the edges of window frames & door frames perfectly vertical?
POST-PLASTERING CHECKS
Is curing been carried out for a minimum of 10 days, with the date of
32
plastering on the wall?
33 Are grooves, drip mould and mortar bands given as per design?
34 Has all mortar spillage been cleaned?
R.SRINIVASAN
Checklist
SR.
DESCRIPTION YES N.A. REMARKS
NO.
1 Name, Date and Number of the Drawing
PRE-PLASTERING CHECKS
2 Is the latest "Good for Construction" drawings available ?
3 Is sufficient place available for starting plastering?
4 Has the required barricading and safety measures been taken?
7
Has the GI mesh been nailed between all RCC & masonry members?
8 Are the corner beadings in place and plumb?
15
Are the
Is the A/c works,
blockwork access
cured control 7and
for atleast fire alarms systems in place ?
days?
16
17 Is the surface wet & free from dust, oil & all forms of contaminations?
25
Is the wall being plastered to given specifications, to plumb and even?
26 Is plastering done above & below all platforms and lofts?
27
Are the edges of window frames & door frames perfectly vertical ?
28 Are all corners in line and finished properly ?
29 Are switch boxes in position and properly finished?
30 Is the plaster surface cut properly for skirting?
31 Has the kind of finishing required been achieved?
Normal sponge finish (for POP application) ?
Rough finish (tile application/first coat)?
Smooth, even finish (textured coatings)?
POST-PLASTERING CHECKS
Is curing been carried out for a minimum of 10 days, with the date of
32
plastering on the wall with permanent marker ?
33 Are grooves, drip mould and mortar bands given as per design?
34 Has lime been properly applied, if required ?
35 Has all mortar spillage been cleaned?
Ckecked By; Approved By;
R.SRINIVASAN
Checklist
Location : _______________________________________________ Date : _________
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-EXECUTION CHECKS
POST-EXECUTION CHECKS
R.SRINIVASAN
Checklist
ACTIVITY: WATERPROOFING
Location : _______________________________________________ Date : _________
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-EXECUTION CHECKS
POST-EXECUTION CHECKS
Has the masking tape been removed?
16
R.SRINIVASAN
Checklist
Name Sign Date Name Sign Date
ACTIVITY: WATERPROOFING
SR.
DESCRIPTION YES N.A. REMARKS
NO.
SLOPED ROOFS:
PRE-EXECUTION CHECKS
POST-EXECUTION CHECKS
R.SRINIVASAN
Checklist
ACTIVITY: WATERPROOFING
SR.
DESCRIPTION YES N.A. REMARKS
NO.
FLAT ROOFS:
PRE-EXECUTION CHECKS
Have the upturns and pipe outlets been reinforced with fibre mat
6
between two coats ?
POST-EXECUTION CHECKS
R.SRINIVASAN
Checklist
ACTIVITY: WATERPROOFING
SR.
DESCRIPTION YES N.A. REMARKS
NO.
SUNKEN AREAS:
PRE-EXECUTION CHECKS
POST-EXECUTION CHECKS
R.SRINIVASAN
Checklist
Ckecked By; Approved By;
ACTIVITY: PAINTING
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-PAINTING CHECKS
Has the shade, type of paint been approved by the architect and
2
duly certified ?
Has it been ensured that wall and ceiling surfaces are
3
completely dry ?
Have all the loose particles, dirt and dust been scrubbed off from
4
the surface ?
Has proper scaffolding arrangement been done With safety
5
measures ?
6 Are the required tools available?
7 Are there any specific requirements of the client ?
Has the 2nd coat of putty been applied after the 1st coat has
10
completely dried ?
11 Have all undulations been covered using putty?
Has sanding of the surfaces been done properly to render a
12
smooth surface?
Has the dust from the surface been thoroughly Wiped off after
13
sanding the puttied surface?
Has it been ensured that the first coat of paint is applied and
14
finished with roller?
Has it been ensured that the final coat is applied after 4 to 6
15
hours of first coat?
POST-PAINTING CHECKS
R.SRINIVASAN
Checklist
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-TILING CHECKS
6 If tiles are used, have they been soaked for atleast 30 minutes ?
14 Have the tiles been gently tapped after laying on the motar bed?
POST-TILING CHECKS
R.SRINIVASAN
Checklist
Has the area been barricaded so as not to allow foot
21
movement?
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-TILING CHECKS
POST-TILING CHECKS
R.SRINIVASAN
Checklist
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-TILING CHECKS
14 Is the floor moist and provided with cement slurry for bonding ?
POST-TILING CHECKS
R.SRINIVASAN
Checklist
21 Is the finished floor level ?
22 Are all the laid floor surfaces properly covered ?
Has it been ensured that grouting is done after 24hrs of laying of
23
tiles ?
Has the area been barricaded so as not to allow foot
24
movement ?
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-EXECUTION CHECKS
Are proper electrical connections and working platform
available, in case of on-site fabrication
Are the required tools and safety equipments(scaffolding)
available?
POST-EXECUTION CHECKS
R.SRINIVASAN
Checklist
SR.
DESCRIPTION YES N.A. REMARKS
NO.
Are the door frames and architraves of the required size and
5
matching grains and colour available on-site?
Is the provided openings in confirmation with the drawings
6
provided?
If the door is to be set on Gypsum partition, is there gap for the
7
plywood inner frame?
Is there sufficient gap between the door frame and civil finished
8
surface to fill with worth glue? (recommended -10 mm gap)
POST-EXECUTION CHECKS
R.SRINIVASAN
Checklist
SR.
DESCRIPTION YES N.A. REMARKS
NO.
PRE-VDF CHECKS
R.SRINIVASAN
Checklist
POST-VDF CHECKS
SR.
DESCRIPTION YES N.A. REMARKS
NO.
Structural Glazing
1 Frame Work
1.1 Are the latest "Good for Construction" drawings available?
Is the site ready with all civil openings duly plastered and
1.2
painted before starting the frame
1.3 Are adequate quantity of materials available at site?
Have safety measures required for the frame work been taken
1.4
care?
1.5 Are the required tools available?
Have the frame work materials viz. mullions, transoms etc.
1.6
been properly protected before
Have the MS brackets used to anchor the mullions properly
1.7
been surface treated?
Have the specified anchor bolts properly grouted to support the
1.8
mullions in RCC/PCC only?
Are all the mullions in true plumb (in case of vertical glazing) or
1.11 in the same angle (in case of inclined glazing) and all the
transoms in the water level after installation?
R.SRINIVASAN
Checklist
2 Glazed Panel Installation
Is a proper register for bonding of glass showing the date of
2.1
bonding maintained in bonding area?
Are the glass and glass processing in compliance with the
2.2
specification?
Is the processed glass free from all distortions?
2.3
Is the glass/ACP properly bonded with structural silicone
2.4
sealant to the glass frame?
Is the silicone sealant bite as per the design requirement?
2.5
Has the bonded panel been installed on the frame work with
2.7
glass clip and specified SS
Ckecked By; Approved By;
SR.
DESCRIPTION YES N.A. REMARKS
NO.
Has the sealant been applied in the gap between the glazed
2.8 panels with uniform width horizontally & vertically by placing
suitable backer rod in the gap for weather proofing?
Has the glass been cleaned with proper cleaning tools and mild
2.9 soap solution with no dirt,stains, scratches etc, on the glass?
Has the flashing, if required been taken care after the glazing?
2.10
R.SRINIVASAN
Checklist
Has the gap between the adjacent panels been filled with
3.7 weather sealant backed on a suitable backer rod for weather
proofing?
Has the protection sheet been removed after installation as
3.8
specified by the manufacturer?