031 2014 00797 PDF
031 2014 00797 PDF
031 2014 00797 PDF
Blair
OFFICE OF THE CHIEF PORT ADMINISTARTOR,
PORT MANGEMENT BOARD, PORT BLAIR
Page 1 of 33
CONTENTS
Tender Notice 3
3 Proposal 4
6 Deliverables 10
7 Work Schedule 10
8 Schedule of Payment 11
Instruction to Bidders and General
9 12
Terms & Conditions
10 List of Annexures 21
Page 2 of 33
TENDER NOTICE
Page 3 of 33
1 Introduction & Objective
Shipping is the life line of these islands and approx. 150 vessels ply in
the Andaman and Nicobar Islands. Statutory survey and repairs is an
essential requirement of these vessels for which the existing dry docks,
slipways, shore based ship repair infrastructural facilities and expertise
are insufficient. As a result the vessels are not able to comply with the
statutory /mandatory docking schedules.
3 Proposal
The proposed site is a hilly terrain, steeply inclining into the bay between
Chatham and Bamboo flat jetties and facing the bay to the east. Refer
the fig. 1 given below indicating the proposed location. Contour Map &
Bathymetry Chart are also available and provided on request. It is
proposed to install a ship lift & transfer system, dry berths / work
Page 4 of 33
stations with required minimum connected infrastructure like shops,
buildings, roads and facilities for water, power etc. The proposed ship lift
facility shall be of tentative size 140 M (L) and 25 M (W) capable of lifting
6000 T light weight ships. The requirement comprises of work stations
for dry docking of five vessels and afloat repair facility for a minimum of
five vessels. Refer the conceptual plan placed at Annexure: 1 which
details our tentative proposal. Outer side of the Ship-lift jetty and its
extension to South and North are proposed for berthing ships and for
works afloat.
Page 5 of 33
Scope of work for this assignment includes collection of data, its analysis
and all studies required for the preparation of Techno-Economic
Feasibility Study report but not limited to as below:
Page 6 of 33
Consideration and analysis of relevant data provided by PMB,
towards finalization of facilities & layout.
High quality sketches /good for construction drawings shall be
prepared for the proposed developments.
Multiplication
Works completed during the period:
Factor
1st April 2013 to PDD 1.00
Page 9 of 33
Surveyor Diploma in Surveying Two Marine Related
or Certificate in Assignments worth 80
Surveying. crores & above.
6 Deliverables:
The following deliverables shall be submitted as part of Techno-Economic
Feasibility Study:
Site visit notes & Minutes of meetings with PMB officials
Draft TEFS report including drawings– Three hard copies + one soft
copy (both in word & pdf format)
Final TEFS report including drawings– Five hard copies + one soft
copy (both in word & pdf format)
7 Work Schedule:
S no. Description Time Frame
Page 10 of 33
KD4 Submission of Final TEFS Within two weeks after the
Report receipt of PMB‟s comments on
draft TEFS report.
8 Schedule of Payment
a. The Consultant shall be paid the lump sum Consultancy Fees for
providing the services as per the schedule below.
Sl.no Percentage of
Deliverables total consultancy
fees payable
Page 12 of 33
d. Brief Description of Bidding Process:
i. PMB intends to follow Two-part bidding process for selection of
the successful firm for providing Consultancy services for the
preparation of TEFS report:
Part 1: Technical Proposal
Part 2: Financial Proposal
ii. For the purpose of the Part- 1, the Bidders are required to submit
documents listed in Clause # 9, j detailed below as Technical
Proposal.
iii. Under Part-2, the Financial Proposal of Bidders who qualifies in
Part-1 will be opened. The Financial Proposal shall be
submitted as per the format placed at Annexure – III.
e. PMB's Right to Accept or Reject Proposal:
Notwithstanding anything contained in this Proposal Document, PMB
reserves the right to accept or reject any Proposal and to annul the
bidding process and reject all Proposals, at any time without any
liability or any obligation for such acceptance, rejection or annulment,
without assigning any reasons.
PMB reserves the right to reject any Proposal if:
i. at any time, a material misrepresentation is made or uncovered,
or
ii. The Bidder does not respond promptly and thoroughly to requests
for supplemental information required for the evaluation of the
proposal.
f. Contents of Proposal Document:
The Proposal Document shall comprise the contents as mentioned in
this document and would additionally include Addenda if any, issued
in accordance with Clause # 9, c mentioned above.
g. Format of Proposal:
i. Bidders would provide all the information as per this Proposal
Document and in the specified formats. PMB reserves the right to
reject any Proposal that is not in the specified formats.
ii. The bidder shall submit the proposal complete in all respects.
The authorization to sign the document must be confirmed by a
written power of attorney accompanying the proposal as per
Annexure – V.
iii. The proposal must contain no interlineations or overwriting
except as necessary to correct errors made by the Consultants
themselves, in which cases such corrections must be initialled
by the person or persons signing the proposal.
iv. Completed technical and financial proposal must be delivered on
or before the time and date stated in proposal document.
Page 13 of 33
h. Sealing and Marking of Proposal.
i. The Bidder shall seal the Technical Proposal and the Financial
Proposal in separate envelopes, duly marking the envelopes as
'PART-I TECHNICAL PROPOSAL' and 'PART -2 FINANCIAL
PROPOSAL'. These envelopes shall then be sealed in an outer
envelope.
ii. The envelopes shall clearly bear the following identification: ”Title
- Proposal for providing Consultancy Services for the Preparation
of Techno-Economic Feasibility Study Report for the setting up
of ship lift facility at Bambooflat, Port Blair.”
iii. The envelope shall be addressed to:
Chief Port Administrator,
Port Management Board, Post Box No. 52, H P O,
Port Blair-744101, A & N Islands.
Phone: 03192-233679 , Fax; 03192-233675
Email: [email protected]
iv. If the envelope is not sealed and marked as instructed above, the
Proposal may be deemed to be non-responsive and would be
liable for rejection. PMB assumes no responsibility for the
misplacement or premature opening of such bids.
Page 14 of 33
in NIT from concerned department and to submit in original to
this board along with the Technical bid.
iv. A forwarding letter confirming validity of the proposal for 90 days
from the due date of submission of proposal and detailing
contents of the proposal including list of enclosed documents.
v. Company profile with legal status, date of establishment,
organization chart and authenticated documents to confirm that
the bidder is in the consulting field for shipyard / port related
facilities for the last 10 years.
vi. Certificate that the Bidder is not under a declaration of
ineligibility issued by Govt. of India / State govt. / Public Sector
Undertakings etc.
vii. Power of Attorney in the name of persons(s) signatories of the
proposal as per Annexure - V.
viii. Credentials to substantiate technical experience of the firm with
respect to the technical capability mentioned at clause # 5, d.
satisfactory documentary evidence to be furnished along with
the offer
ix. Capabilities of consulting firm with respect to personnel. Details
of personnel to be employed / engaged for this project along with
their profile (CVs) as mentioned at clause # 5,e above.
x. The Applicant shall have received a minimum income of Rs.
Three (3) crore towards professional fees on a cumulative basis
during last three Financial years preceding the Proposal Due
Date (i.e. 1st April 2011 to 31st March 2014). Certificate in this
regard shall be submitted as per the format placed at Annexure
– IV.
xi. Declaration for the effect that, on winning the Project
Management Consultancy assignment, the Consultant, it‟s
subsidiaries / affiliates shall not be eligible for bidding in the
implementation assignment of ship lift.
xii. Scope of sub-consultants, if any shall also be detailed with all
their credentials detailing expertise & track record in the
relevant area.
xiii. Approval / Quality certification / Registration with any Govt. /
agency
xiv Financial stability certificate from a nationalized Bank in India
specifically indicating the amount of financial solvency and to
the effect that the tenderer can undertake the work of the
magnitude as contemplated in the tender.
xv The original tender documents (excluding schedule of
price/rates for execution of work) duly signed on each page with
their official stamp.
xvi Exclusions / Deviations, if any
Page 15 of 33
NOTE: BIDDERS MUST NOT INDICATE DIRECTLY OR INDIRECTLY
THEIR FINANCIAL PROPOSAL ANY WHERE IN THE ENVELOPE OF
TECHNICAL PROPOSAL. ANY SUCH DISCLOSURE SHALL RESULT IN
SUMMARILY REJECTION OF WHOLE OF THE PROPOSAL OF THE
CONCERNED BIDDERS.
Page 16 of 33
A non-responsive proposal shall be rejected at this stage and the
second envelope of concerned bidder(s) will not be opened.
t. Security Deposit:
Within fourteen days from the date of receipt of work order/LOA
issued by PMB, the successful bidder shall furnish to PMB, a security
deposit in the form of Bank Guarantee from a Nationalized bank as
per attached format (refer annexure - VII) / FDR / Account Payee DD
drawn in favour of Sr Accounts Officer, Port Management Board for an
amount equivalent to 10% of the order value. The Security Deposit
should remain valid for a period of sixty (60) days beyond the date of
completion of all contractual obligations.
Failure of the successful bidder to submit the required security
deposit shall constitute sufficient grounds for the termination of the
contract. The Security deposit shall remain in force until the
satisfactory completion of the contract and will be discharged
thereafter.
If the consultant abandon the contract or fails to commence or carry
out the work as per the terms and conditions of the work order in
time or suspend the work for long duration (30 days), without valid
reasons acceptable to PMB. PMB will terminate the contract and
arrange the work through other agencies, as may be decided by the
company at the risk and cost of the consultant. In such case, security
deposit will be forfeited.
u. Liquidated Damages:
An amount equal to 1% per day of the contractual amount will be
recovered (unless exempted by the Competent Authority) from the
successful contractor on delay in delivery of Milestones mentioned at
KD2, KD3 and KD4. The maximum LD to be levied will be equal to 10
% of the Contractual Cost and thereafter the work order shall be
cancelled and the Security Deposit submitted by the firm will be
forfeited.
Page 18 of 33
v. Confidentiality:
The Consultant shall treat all the documents and information received
from PMB and all other related documents / communications
including the documents prepared by the Consultant as part of this
consultancy work, in confidence and shall ensure that all who have
access to such material shall also treat them in confidence. The
Consultant shall not divulge any such information unless PMB
authorizes the consultant in advance in writing. Further the
Consultant shall return all the documents received from PMB from
time to time after completion of the Work / Assignment related to
those documents. Also, the Consultant shall not use these documents
for purpose unrelated to this Contract without the prior written
approval of PMB.
Non-disclosure agreement between the consultant and PMB is as
follows:-
Information relating to the TEFS shall not be disclosed to any
agency or any other persons not officially concerned with such
process. The undue use by the consultant of confidential
information related to the process may be treated as breach of
confidentiality and dealt with accordingly. Except with the prior
written consent of the PMB, Consultant or any personnel shall not
at any time communicate to any person or entity any confidential
information acquired in the course of the Contract.
Neither party will disclose to any third party without the prior
written consent of the other party any confidential information
which is received from the other party for the purpose of providing
or receiving Services.
Each party will take measures to protect the confidential
information of the other party, that, in the aggregate are no less
protective than those measures it uses to protect the
confidentiality of its own comparable confidential information, and
in any event, not less than a reasonable degree of protection. Both
parties agree that any confidential information received from the
other party shall only be used for the purpose of providing or
receiving Services under this Contract or any other Contract
between the parties.
w. Conflict of Interest
PMB requires that Consultant must provide professional, objective &
impartial advice and at all times hold the interests paramount, strictly
avoid conflicts with other assignments jobs or their own corporate
interests and act without any consideration for future work. In case
the applicants (consultants) have any subsisting interest, either by
themselves or through their partners, that is likely to conflict the work
specified in the Scope of work, they shall declare such interests as
part of their proposal.
Page 19 of 33
x. Suspension of Work / Assignment
If any of the following events shall have happened and be continuing,
PMB may, by written notice to the Consultant, suspend in whole or in
part, payment due thereafter to the Consultant under the contract:
A default shall have occurred on the part of the Consultant in the
execution of the contract.
Any other condition which makes it unable for either party by
reason of “Force Majeure” as referred to in Clause # 9, aa in this
Section to successfully carry out the Work / Assignment or to
accomplish the purpose of the contract.
y. Termination of work / Assignment by PMB
If any of the following events shall have happened and be continuing,
PMB may, by written notice to the Consultant, terminate the contract”
Any of the conditions referred to under Clause # 9. aa in this
section, shall continue for a period of two weeks after PMB shall
have given written notice to the Consultant of the suspension of
payment to the Consultant under the contract.
In any event, PMB may terminate the contract at any time by
giving not less than four weeks prior notice to the consultants.
z. Termination Procedure
Upon termination of the Contract under Clause # 9. y, in this
Section or receipt of notice of termination, the Consultant
shall take immediate steps to terminate the Work /
Assignment in a prompt and orderly manner and to reduce losses
and to keep further expenditure to a minimum.
Upon termination of the contract (unless such termination shall
have been occasioned by the default of the Consultant), the
Consultant shall be entitled to be reimbursed in full of such costs
as shall have been duly incurred prior to the date of such
termination.
Page 20 of 33
iii. The term “Force Majeure” as employed herein, shall mean “Act of
God, Strike, Lock-outs or other Industrial Disturbances,
Insurrection, Riots, Epidemics, Land Slides, Earth Quakes,
Storms, Lightening, Floods, Wash Outs, Civil Disturbances,
Explosions and any other similar event not within the control of
either party, and which, by the exercise of due diligence, neither
party is able to overcome.”
ab. Dispute between the Consultant and PMB
This contract is subject to the law of India. Any dispute not resolved
by negotiation shall be settled by the courts of law at India or by
Arbitration Act 1996.
ac. Signing Of Agreement:
Within fourteen days of the date of issue of Letter of Award, the
successful party shall sign the Agreement as per the format placed at
Annexure-VI in non-judicial stamp paper (Rs.100/-).
10 List of Annexures
Annexure – I: Tentative Layout of Ship Repair Facility at Bambooflat.
Annexure – II: Format of Application Letter
Annexure – III: Price Bid Format
Annexure – IV: Format for the Financial capability of Bidder
Annexure – V: Format of Power of Attorney
Annexure - VI: Agreement Format
Annexure – VII: Format of Bank Guarantee for Security Deposit
Annexure – VIII: Format of Bank Guarantee for Advance Payment
Annexure – IX: Format for pre-bid query
-Sd-
Page 21 of 33
Annexure-1
Layout
Page 22 of 33
Annexure – II
APPLICATION LETTER
Letter of Proposal / Bid-Covering letter
(On Applicant‟s letter head)
To
Chief Port Administrator,
Port Management Board,
Post Box No. 52, H P O,
Port Blair-744101, A & N Islands.
Dear Sir,
Thanking you,
Yours faithfully,
Annexure - III
FINANCIAL BID
To
Chief Port Administrator,
Port Management Board,
Post Box No. 52, H P O,
Port Blair-744101, A & N Islands.
Dear Sir,
Sub: Providing Consultancy Services for the Preparation of Techno-Economic
Feasibility Study Report in connection with the setting up of ship lift
facility at Bambooflat, Port Blair, Andaman Islands
Witness:
Signature:
Name : Name:
Address: Designation:
For and on behalf of Address:
Page 24 of 33
Annexure – IV
4 TOTAL
Designation:
Name of firm:
Page 25 of 33
Annexure-V
POWER OF ATTORNEY
Dated: ------------
For………………………………………
Page 26 of 33
Annexure – VI
Whereas the contractor has submitted the quotation for the work of ------
---------------------------vide his quotation (offer No_). -------------------------- dated
------------------- and subsequent letter ---------------------------------------- (
clarification letters if any)-------------------------------------------------------.
AND WHEREAS the PMB, have been pleased to accept the said Bid as
clarified by the subsequent letter and the terms and conditions of (work order
No………………………………………. dt…………………).
1. The contractor shall undertake to carry out the said work according to
the specifications, terms and conditions attached herewith.
2. In case the contractor fails to carry out the said work tendered for by him
within, part or in full, the time provided of or in case the contractor
commits any breach of any of the covenants, stipulations and
agreements herein contained, and on his part to be observed and
performed then and in any such case, it shall be lawful for PMB (if it
shall think fit to do so) by an order in writing to put an end to this
contract, and in case PMB shall have incurred, sustained or been put to
any cost, damages or expenses by reason of this contract having been so
put an end to or in case any differences in price, compensation, loss,
cost, damages, expenses or other moneys shall then or at any time
during the continuance of this contract be payable by the contractor to
PMB under or by virtue of this contract it shall be lawful for the Port
Management Board from and out of any moneys for the time being
payable or owing to the contractor from the Port Management Board,
under or by virtue of this contract or otherwise to pay and reimburse to
the Port Management Board, all such costs, damages and expenses they
may have sustained , incurred or been put to by reason of this contract
having been so put an end to aforesaid and also such differences in
price, compensation, loss, costs, damages, expenses or other moneys
shall for the time being be payable by the contractor aforesaid.
Page 27 of 33
3. All expenses and damages caused to Port Management Board by any
breach of all or any of the terms of this contract by the contractor shall
be paid by the contractor to the Port Management Board and may be
recovered from him. The quotation No. (Offer No.) ----------------------------
---------- and subsequent letter (clarification letters if any)-------------------
------------dt…………and the terms and conditions of the work attached
form an integral part of this agreement.
In witness where of the parties here to have been here unto set their hands the
day and year first above written.
In the presence of
Witness: 1.
2.
Witness: 1.
2
Page 28 of 33
Annexure – VII
To,
Chief Port Administrator,
Port Management Board,
Post Box No. 52, H P O,
Port Blair-744101, A & N Islands.
AND WHEREAS it has been stipulated by Port Management Board (The Buyer –
hereinafter called "PMB") in the said contract that the supplier shall furnish
PMB with a Bank Guarantee by a recognized bank for the sum specified
therein as security for compliance with the contractor‟s obligations in
accordance with the Contract.
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee.
NOW THEREFORE we ……………………………………… ………………………………
(Name of the Bank) having its Head Office at
……………………………………………………………………… (Address of Head Office)
and acting through its branch office at …………………………………… (Address of
the executing branch) (hereinafter called "the Bank") hereby affirm that we are
the Guarantor and responsible to PMB, on behalf of the Contractor up to a
total of Rs. ……………………………………………………………….(amount of
Guarantee) (Rupees ………………………………………………………………….Only),
such sum being payable in the types and proportions of currencies in which
the Contract Price is payable and we undertake to pay PMB upon your first
written demand and without cavil or argument, any sum or sums within the
limits of ………………………………………… (amount [1] of guarantee) as
aforesaid without PMB needing to prove or to show grounds or reasons for
PMB‟s demand for the sum specified therein.
We, the Bank, hereby waive the necessity of PMB demanding the said debt
from the Supplier before presenting us with the demand.
Page 29 of 33
We, the Bank, further agree that no change or addition to or other modification
of the terms of the Contract or of the Works to be performed there under or of
any of the Contract documents which may be made between PMB and the
Contractor shall in any way release us from any liability under this guarantee,
and we hereby waive notice of any such change, addition or modification. This
guarantee shall be valid until 28 days from the date of expiry of the Defects
Liability Warranty period.
This Bank Guarantee shall be valid up to (date) and We are liable to pay the
guaranteed amount or any part thereof under this bank guarantee only and
only if PMB serve upon us a written claim or demand on or before
……………………………(date).
Yours truly,
Signature and seal of the guarantor: …………………………….……..
Name of Bank: …………………………………………………………
Address: ………………………………………………………………..
Date: …………………
Page 30 of 33
Annexure - VIII
To,
Chief Port Administrator,
Port Management Board,
Post Box No. 52, H P O,
Port Blair-744101, A & N Islands.
Sir:
In accordance with the Conditions of Contract No.
……………………………… Dated ……………………………………… (hereinafter
called the Contract) for the supply / work of ……………………………………………
…………… (Name of the item / work) , M/s.
……………………………………………………………………………… (Name and
address of Contractor) (hereinafter called the Contractor ) shall deposit with
Port Management Board, Port Blair, a bank guarantee to guarantee his proper
and faithful performance under the Contract an Amount of
Rs.………………………(amount of Guarantee) ………………… ……………… ……(
in words).
We, the Bank, further agree that no change or addition to or other modification
of the terms of the Contract or of Works to be per formed there under or of any
of the Contract documents which may be made between PORT MANAGEMENT
BOARD and the contractor, shall in any way release us from any liability under
this guarantee, and we hereby waive notice of any such change, addition or
modification.
The guarantee shall remain valid and in full effect from the date of the advance
payment under the Contract until PORT MANAGEMENT BOARD receives full
repayment of the same amount from the Contractor.
Page 31 of 33
Notwithstanding anything contained herein:
1. Our liability under this Bank Guarantee shall not exceed Rs …………………
(Rupees only).
2. This Bank Guarantee shall be valid up to (date) and
3. We are liable to pay the guaranteed amount or any part thereof under this
bank guarantee only and only if you serve upon us a written claim or
demand on or before …………………(date) .
Yours truly,
Signature & Seal-----------------------------------------------------
Name of Bank/Financial Institution-------------------------------
Address:---------------------------------------------------------------
Date:-------------------------------------------------------------------
Page 32 of 33
Annexure- IX
To,
Chief Port Administrator,
Port Management Board,
Post Box No. 52, H P O,
Port Blair-744101, A & N Islands.
Fax:
Email:
Points of
Bid
Bid Document Content of RFQ Clarification
Sl. Document
Reference requiring required /
No. number /
section Clarification modifications
page
suggested
1.
2.
Page 33 of 33