POUR CARD New Format
POUR CARD New Format
POUR CARD New Format
BEFORE CONCRETING
POST CONCRETING
SL no Item description
A. Form Wroks
1 Check for form works shuttering release agent applied
2 Check for stop / drop form work
3 Check for form works slaid to the correct dimensions including line,level
4 Check for tightness and rigidity
5 Check for cleanliness for formwork
6 Check for formwork scaffolding / staging
B. REINFORCEMENT WORK
1 Check for approved BBS and structual drawing
2 Check for bar laps,chair & cover blocks provided for reinforcement
3 Check for sufficent length & no of rebars dowels if any,laid for future/further
C General and Concreteworks
1 Check for box out/pipe sieeves etc. laid as per drawing/ requirement
2 Check for embedded items / electrical conduits laid as per drawing
3 Check for qulity of bulk material / RMC
4 Check for plastisizer / additives
5 Check for expansion joints provision if any
6 Check for existing concrete hacking and cleaning
7 Check for concrete top level marked at required places
8 Check for sufficent no of vibrators/required equipment for concreting
9 Check for concrete height / depth / width requirements
10 Check for task lighting,if any
D EHS
1 Check for overall safty is ensured during the pour
CLEARANCE FOR CONCRETING
MCL ENGINEER: SMC ENGINEER:
FOR CONTRACTOR
SIGNATURE
NAME
DATE
EERA CONSTRUCTION LTD.
OR CONCRETE WORKS (POUR CARD)
Clearance date:
Clearance Time:
OK/NOT OK Remarks
SIGNATURE
NAME
DATE