Construction Engineering Formula Sheet
Construction Engineering Formula Sheet
Construction Engineering Formula Sheet
Basic Conversions
Economic Haul Distance; Large Dozer up to 3000 ft; Scraper 3000 – 5000 ft; Trucks > 5000 ft
1 liter = 1 kg
Pyramid Method = V = AL / 3
Conical Spoil Pile = Vol = (Ab x H) / 3; D = (7.64V / tan )1/3; H = (D/2) tan ;where Ab=base area;
Triangular Spoil Bank = Vol = Cross section Area x L ; B = (4V/(L x tan )1/3 ; H = (B x tan ) / 2 ; V=
pile volume; B= base width ; H = pile ht; L = pile length ; = angle of repose (deg)
(γdry)=(γwater * Gs)/(1+e)
Specific Gravity = S * e = Gs * w
DL = Dry Loose unit wt (pcf) ; DB = Dry Bank unit wt (pcf) ; DC = Dry compacted unit wt(pcf)
Trigonometric Leveling Elevation at unknown location = elevation at known + HI + (slope distance sin
Traverse Area: Method of Coordinates; The area is A = ½ (Sum of full line products – Sum of broken line
products)
Rising section = cut; Falling section = fill; zero slope = moving from cut to fill or vice versa
Estimating Quantities and Cost
Trenching: Be careful to fully understand what the dimensions represent, Use horizontal In-In and Vertical
Out-Out
Estimating # bricks in wall : net wall (sf) = Gross surface Area of Wall (sf) – Area of open surface (sf)
then find surface area of brick with mortar (sf) (net wall / SA of one brick) x # rows = bricks in
wall
Volume of mortar per brick = (mortar thickness)(brick width)(length + height + mortar thickness)
Rebar = When finding the number of rebar bars in wall = # rebar = (the length of wall / spacing of bars) +
Engineering economics
Depreciation:
Solve for Center of Gravity: Ax = (A1)(x1) + (A2)(x2) + … + (An)(xn) ; where A= Total Area
x = distance to the CoG in the x direction, A1 and A2 = Area/Volume or Mass; x1 and x2 = distance to the CoG
Crane selection erection and stability
Crane Stability: Factor of Safety against toppling = Resisting moment / Toppling moment
Resisting Moment = = (Weight of Counter Weight (WC)) x (Distance from toppling pt to Counterweight)
Equipment Production
Dozer: Total Time = Q / (P x N) : Q = Quantity of material to be moved; P = hourly production rate per
Grader: Total Time = (P x D) / (S x E): P= number of passes required; D = distance traveled in each pass,
in miles or feet; S = speed of grader, in mph or fpm (multiply mph by 88 to convert to fpm; E = efficiency
factor
Scraper: Total time (hours) = Q / P x N Q = total volume to move(BCY), P = hourly production rate
Loader: Maximum production rate (LCY per hour) = heaped bucket capacity x bucket fill factor x 60
Net production rate (LCY per hour) = maximum production rate (LCY per hour) x efficiency factor
Excavator: q = ((3600 sec/hour x B x E x P)/ C) x Volume Correction q = Volume of soil excavated and
dumped in a truck by the excavator (CY/hr), B = Bucket struck capacity (CY), E = Bucket efficiency factor, P
= Productivity factor, C = Cycle time for 90 degree angle and optimum depth
Compactor: Production (CCY per hour) = (16.3 x W x S x L x E) / N W = compacted width per pass (in
required
Compactor: Compactors required = FD x SCF / CP FD = amount of fill delivered (LCY per hour), SCF =
Dump Truck: Number of trucks required = 1 + truck cycle time (minutes) / loader cycle time (minutes)
Scheduling
CPM Network Analysis
TF = LS – ES = LS – (EF – D) = LS – EF + D
Independent Float = Early start of successor – Late finish of predecessor – duration of Activity
Early Finish = Early Start + Duration ; Early Start = Early Finish – Duration
c = pessimistic estimate
Cost Slope = (crash cost – normal cost) / (normal time – crash time)
Air Content (%) = Volume of Air (cf) / Total Volume of Concrete (cf)
Volume of material (cf) = Weight of material (lbs) / ( 62.4 x specific gravity of material)
Temporary Structures
Construction Loads
Cp = Lo (.25 + 15/sqrt(AI)) Cp = reduced design uniformly distributed Personnel and Equipment load per
sf, Lo = is the unreduced uniformly distributed P&E per sf; A I = is the influence area, sf
P&E on slope roof; R = 1.2 –0.5F where F = slope of the roof (in/ft); R = Reduction Factor (.6 < R < 1.0)
Formwork
Lateral pressure of concrete(p) = wh or ρgh p = lateral pressure, lb/ft2 ; w = unit weight of concrete,
lb/ft3; ρ = density of concrete (kg/m3); g = gravitational constant, 9.81 N/kg ; h = depth of fluid or plastic
Columns: For slump 7in or less to depth of 4ft or less: pmax = CwCc[150 + 9000 R/T]
Walls: rate of placement (R) less than 7ft/h and height not exceeding 14 ft: pmax = CwCc[150 + 9000 R/T]
Walls: R is 7ft/hr to 15ft/hr and height not exceeding 14 ft: pmax = CwCc[150 + 43,400/T +2800R/T]
R = rate of placement(ft/hr), T = temperature of concrete during placing, oF, Cw = unit weight coefficient, Cc
= chemistry coefficient
Shoring and Reshoring
Bracing
Anchorage
The force required to pull the concrete apart = Force (lbs) = material cohesion (lbs/in2) x Surface Area of
failure
F1 = wh12 / 2 ; F2 = wh22 / 2 ; w = unit weight of water ; h1 = outside water height ; h2 = inside water
height
buoyancy force
OSHA Incident Rate = (# of Injuries & Illness * 200,000) / Total hrs all employees