Client Ref
CAUSE & EFFECT DIAGRAM OF TARFA#2 EMCO Ref AR1810.00-PRO-LST-002
Rev 00
Date 30/11/2018
Project: Elaboration of FEED documents for the provision of the water injection system
'GENERAL NOTES:
ESD Level 1 : Emergency shutdown of all pocess units within the plant
The level 1 shutdown shall be initiated only by an emergency push button located in the CPF control room, or by confirmed fire detection in process areas, or by confirmed gas, or by loss of electrical power, or a major process trip.
The Level 1 shutdown will shutdown the entire process unit by :
•Isolation of all process units and initiate an automatic blowdown of all hydrocarbon inventory
• Tripping of all electrical equipment within unit
• Initiation of audible and visual alarms at the CCR and in the area local to the unit
2-Blowdown philosophy
The blowdown is initiated as follows:
- Automatically following level 0 shutdown,
- Manually following level 1 or 2 or shutdown.
page 2 de 5
TAG NO
- Abbreviation
ESD
ESD
Level 1
Level 0
Level
Shutdown
CAUSE
LEVEL 1 ESD
LEVEL 0 ESD
-
-
SERVICE
Project: Elaboration of FEED documents for the provision of the water injection system.
P&ID
-
-
EFFECT
4
3
2
1
X
X
X
X
X
X
page 3 de 5
Client Ref
CAUSE & EFFECT DIAGRAM OF TARFA#2 EMCO Ref AR1810.00-PRO-LST-002
Rev 00
Date 30/11/2018
Project: Elaboration of FEED documents for the provision of the water injection system.
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
P&ID
-
EFFECT
Close of SDV-1201
Close of SDV-1200
Close SDV-1000
Close SDV-1500
SDV-1200
SDV-1201
SDV-1200
SDV-1000
SDV-1500
PBE-4000
TAG
-
CAUSE
ACTION
INSTRUMENT Shutdown
FUNCTION SERVICE P&ID
ALARM
ALARM
ALARM
ALARM
ALARM
ALARM
11 ALARM
12 ALARM
17 ALARM
18 ALARM
20 ALARM
21 ALARM
16 START
CLOSE
CLOSE
CLOSE
10 CLOSE
13 CLOSE
TAG NO Level
15 STOP
19 STOP
1
9
Water Skimmer MBD-1200 1
PSHL-1200 ESD Level 3 High Pressure in MBD-1200 AR1810.00-PRO-DRW-002-sht 3 of 3 2 X X X
PSHL-1200 ESD Level 3 Low Pressure in MBD-1200 AR1810.00-PRO-DRW-002-sht 3 of 3 3 X X X
LSHH-1200 ESD Level 3 High High water level in MBD-1200 AR1810.00-PRO-DRW-002-sht 3 of 3 4 X X X
LSH-1200 ESD Level 3 High oil level in MBD-1200 AR1810.00-PRO-DRW-002-sht 3 of 3 5 X X
LSL-1200 ESD Level 3 Low Oil level in MBD-1200 AR1810.00-PRO-DRW-002-sht 3 of 3 6 X X
LSL-1201 ESD Level 3 Low water level in MBD-1200 AR1810.00-PRO-DRW-002-sht 3 of 3 7 X
Water injection Tank ABJ-1000 8
LSH-1000 ESD Level 3 High water Level in ABJ-1000 AR1810.00-PRO-DRW-002-sht 3 of 3 9 X X
LSL-1000 ESD Level 3 Low water Level in ABJ-1000 AR1810.00-PRO-DRW-002-sht 3 of 3 10 X X
page 4 de 5
Client Ref
CAUSE & EFFECT DIAGRAM OF TARFA#2 EMCO Ref AR1810.00-PRO-LST-002
Rev 00
Date 30/11/2018
Project: Elaboration of FEED documents for the provision of the water injection system.
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
AR1810.00-PRO-DRW-002-sht 3 of 3
P&ID
EFFECT
DESCRIPTION
PAH-5000
PAH-5100
PAH-5200
FCV-5000
FCV-5100
FCV-5200
PBA-5000
PBA-5100
PBA-5200
PAL-4500
PAL-5000
PAL-5100
PAL-5200
PBE-4500
TAG
-
CAUSE
ACTION
INSTRUMENT Shutdown
FUNCTION SERVICE P&ID
ALARM
ALARM
ALARM
ALARM
ALARM
ALARM
11 ALARM
12 ALARM
15 ALARM
TAG NO Level
OPEN
10 OPEN
14 OPEN
STOP
STOP
STOP
13 STOP
1
9
Booster Pump PBE-4500 1
PSH-4500 ESD Level 3 High Pressure downstream PBE-4500 AR1810.00-PRO-DRW-002-sht 3 of 3 2 X X
PSL-4500 ESD Level 3 Low Pressure upstream PBE-4500 AR1810.00-PRO-DRW-002-sht 3 of 3 3 X X
Triplex pump PBA-5000 4
PSH-5000 ESD Level 3 High Pressure downstream PBA-5000 AR1810.00-PRO-DRW-002-sht 3 of 3 5 X X
PSH-5001 ESD Level 3 High Pressure upstream TRF #6 AR1810.00-PRO-DRW-002-sht 3 of 3 6 X X
PSL-5000 ESD Level 3 Low Pressure downstream PBA-5000 AR1810.00-PRO-DRW-002-sht 3 of 3 7 X X X
PSH-5001 ESD Level 3 Low Pressure upstream TRF #6 AR1810.00-PRO-DRW-002-sht 3 of 3 8 X X X
Triplex pump PBA-5100 9
PSH-5100 ESD Level 3 High Pressure downstream PBA-5100 AR1810.00-PRO-DRW-002-sht 3 of 3 10 X X
PSH-5001 ESD Level 3 High Pressure upstream TRF #6 AR1810.00-PRO-DRW-002-sht 3 of 3 11 X X
PSL-5100 ESD Level 3 Low Pressure downstream PBA-5100 AR1810.00-PRO-DRW-002-sht 3 of 3 12 X X X
PSH-5001 ESD Level 3 Low Pressure upstream TRF #6 AR1810.00-PRO-DRW-002-sht 3 of 3 13 X X X
Triplex pump PBA-5200 14
PSH-5200 ESD Level 3 High Pressure downstream PBA-5200 AR1810.00-PRO-DRW-002-sht 3 of 3 15 X X
PSH-5001 ESD Level 3 High Pressure upstream TRF #6 AR1810.00-PRO-DRW-002-sht 3 of 3 16 X X
PSL-5200 ESD Level 3 Low Pressure downstream PBA-5200 AR1810.00-PRO-DRW-002-sht 3 of 3 17 X X X
PSH-5001 ESD Level 3 Low Pressure upstream TRF #6 AR1810.00-PRO-DRW-002-sht 3 of 3 18 X X X
page 5 de 5