Unit - I: Topics: Introduction To Distribution Systems, Load Modelling and Characteristics
Unit - I: Topics: Introduction To Distribution Systems, Load Modelling and Characteristics
INTRODUCTION
(i) Demand: The demand of an installation or system is the load at the receiving
terminals averaged over a specified interval of time. Here, the load may be given in
kilowatts, kilovars, kilovoltamperes, kiloamperes, or amperes.
(ii)Demand interval: It is the period over which the load is averaged. This selected Δt
period may be 15 min, 30 min, 1 h, or even longer. Of course, there may be situations
where the 15 and 30 min demands are identical.
(v) Demand Factor: It is the ratio of the maximum demand of a system to the total
connected load of the system.
The demand factor(DF) is
(vi)Connected load: It is the sum of the continuous ratings of the load consuming
apparatus connected to the system or any part thereof.
(vii)Utilization factor: It is “the ratio of the maximum demand of a system to the rated
capacity of the system”. Therefore, the utilization factor (Fu) is
The utilization factor can also be found for a part of the system.
(viii)Plant factor: It is the ratio of the total actual energy produced or served over a
designated period of time to the energy that would have been produced or served if the
plant (or unit) had operated continuously at maximum rating. It is also known as the
capacity factor or the use factor.
(ix) Load factor: It is “the ratio of the average load over a designated period of time to
the peak load occurring on that period”. Therefore
where T is the time, in days, weeks, months, or years. The longer the period T, the
smaller the resultant factor. It is less than or equal to 1.0.
(x) Diversity factor: It is “the ratio of the sum of the individual maximum demands of
the various subdivisions of a system to the maximum demand of the whole system”.
Therefore, the diversity factor (FD) is
The diversity factor can be equal to or greater than 1.0.
We know,
(xii)Load diversity: It is “the difference between the sum of the peaks of two or more
individual loads and the peak of the combined load”. Therefore, the load diversity (LD)
is
(xiii)Contribution factor: The contribution factor of the ith load to the group
maximum demand. It is given in per unit of the individual maximum demand of the ith
load.
Therefore,
(xiv)Loss factor: It is “the ratio of the average power loss to the peak-load power loss
during a specified period of time”. Therefore, the loss factor (FLS) is
The above equation is applicable for the copper losses of the system not for the iron
losses.
LOAD CUVRE & LOAD DURATION CURVES
(I) LOAD CURVE:
In a power system, a load curve or load profile is a chart illustrating the variation
in demand/electrical load over a specific time. Generation companies use this
information to plan how much power they will need to generate at any given time.
A graphical plot showing the variation in demand for energy of the consumers on
a source of supply with respect to time is known as the load curve. If this curve is
plotted over a time period of 24 hours, it is known as daily load curve. If it is plotted for
a week, month, or a year, then it is named as the weekly, monthly or yearly load curve
respectively.
A typical load curve is shown in the following fig.
CLASSIFICATION OF LOADS
A load or power requirement (also KVA) of a consumer varies widely. A broad
classification for the loads is
(i) Domestic and residential loads
(ii) Only lighting loads (such as for street lights etc.)
(iii) Commercial loads (shops, business establishments, hospitals)
(iv) Industrial loads
(v) Agricultural loads and other rural loads
(iii)Industrial Loads:
Industrial loads are of greater importance in distribution systems with demand
factor 0.7 to 0.8 and load factor 0.6 to 0.7. For heavy industries demand factor may be
0.9 and load factor 0.7 to 0.8.
Typical power range for various loads:
Cottage and small-scale industries : 3 to 20 kW.
Medium industries (like rice mills, oil mills, workshops, etc.) : 25 to 100 kW
Large industries connected to distribution feeders (33 kV and below) : 100 to 500 kW
The DLC of a week day of this type of load in terms of peak load is as shown in
the fig.
2) A generating station supplies the following loads 15000 kW, 12000 kW, 8500
kW, 6000 kW, 450 W. The station has a maximum demand of 22000 kW. The annual
load factor of the station is 48 %. Calculate i) The number of units supplied annually ii)
The diversity factor iii) The demand factor.
SOL:
3) The supply system has following types of loads:
What are connected load of each category if the demand factor for domestic, commercial
and industrial loads are 50, 60 and 80 percent respectively? Find i) Maximum demand
ii) Daily energy consumption iii) Load factor.
SOL:
4) A generating station has the following daily load cycle.
Draw the load curve and find i) Maximum demand ii) Units generated per day iii)
Average load iv) Load factor
SOL:
5) The maximum demand of a power station is 96000 kW and daily load curve is
described as follows: