Chapter 3.3 Project Management
Chapter 3.3 Project Management
Projects Projects
JAN FEB MAR APR MAY JUN
Build A • Has a set of pre-defined objectives usually
A Done related to time, cost and performance
Build B
(quality).
B Done
Unique, one-
one-time operations designed to
accomplish a specific set of objectives in a
limited time frame. Involve Planning, cost quality
Scheduling and Control.
1
Project Life Cycle Project Manager
Responsible for:
Gantt
Level 4
2
Work Breakdown Structure (WBS) Planning and Scheduling
• WBS Gantt Chart MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
3
The Network Diagram Advantages
• Path Forces managers to organize
– Sequence of activities that leads from the starting node to
the finishing node Provides graphic display of activities
• Critical path
Identifies
– The longest path; determines expected project duration
• Critical activities – Critical activities
– Activities on the critical path – Slack activities
• Slack
– Allowable slippage for path; the difference the length of – Expected length of project
path and the length of critical path – Length of each path
17-16
4
Critical path and slack time
Project Network: Activity on Node
Order
furniture
Furniture
Locate
facilities
2 setup Critical path
AON The critical path is the path with longest duration
1 6 Move
in
Remodel
5
Slack time (path)
S 7 = duration of critical path – path duration
Hire and
Interview train
3 4
17-17
6 weeks
Critical Path
Deterministic 4
time estimates
8 weeks 2
3 weeks
Path Length Slack
(weeks)
11 weeks Move
in
1-2-3-4-5-6 18 2
1 5 6 1-2-5-6 20 0
1 week
1-3-5-6 14 6
4 weeks
9 weeks
17-19
17-20
5
Example of Network Diagram (AON)
Task Duration Preceding
(days) Task
A 2 -
B 3 A
C 3 A
D 4 B
E 8 C
F 4 C
G 1 D
H 8 E
I 4 F,G,H
Earliest start (ES) = earliest time at which an activity can Perform a Critical Path Analysis
start, assuming all predecessors have Activity Name or
been completed Symbol
Earliest finish (EF) = earliest time at which an activity can be
finished Earliest
A Earliest
ES EF Finish
Latest start (LS) = latest time at which an activity can start Start
so as to not delay the completion time of
the entire project
Latest finish (LF) = latest time by which an activity has to be LS LF Latest
Latest
finished so as to not delay the completion Start Finish
time of the entire project 2
6
EST-EFT
Choose bigger
7
Gantt Chart Assignment
Activity Duration Preceding
DAY
(weeks) Activity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 A 1 -
A B 4 A
B
C 3 A
C
D 7 A,B
D
E E 6 B
F F 2 C,D
G
G 7 E
H
H 9 E,F
I