Data 2017-18 Irrigation Data
Data 2017-18 Irrigation Data
LEAD STATEMENT
12 Cement 1 MT At site 0
15 MS Flats 1 MT At site 0
16 6 mm MS rods 1 MT At site 0
17 MS Plate 1 MT At site 0
1. Certified that the leads furnished are correct to the best of my knowledge
2. Certified that the metal and stones are obtained by blasting.
3. Certified that the metal of all sizes are obtained by machine crushing.
N.W:- C & C Kethaverunipadu L.I. Scheme on Krishna River in Chandralapadu Mandal of Krishna
District
COST OF MATERIAL AT SITE OF WORK (SSR - 2017-18) (June 2018 rates)
. Material Unit Lead in Initial Cost Conveyance Conveyance Charges Loading Unloading Total
Km Charges after deducting Charges Charges
contrators profit after after
deducting deducting
contrators contrators
profit profit
1 40 mm HBG Metal Nominal 1 Cum 20 808.00 251.60 221.45 0.00 0.00 1029.45
2 20 mm HBG Metal Nominal 1 Cum 20 1303.00 251.60 221.45 0.00 0.00 1524.45
3 10 mm HBG Metal Nominal 1 Cum 20 894.00 251.60 221.45 0.00 0.00 1115.45
5 10 mm - 4.75 HBG Metal 1 Cum 20 860.00 251.60 221.45 0.00 0.00 1081.45
6 Rough Stone for RR Masonry 1 Cum 40 240.00 464.60 408.92 0.00 0.00 648.92
7 Sand for concrete 1 Cum 10 95.00 135.60 119.35 0.00 0.00 880.00
8 Sand for Filling 1 Cum 10 95.00 135.60 119.35 0.00 0.00 880.00
9 Sand screened for Mortar, 1 Cum 10 170.00 135.60 119.35 0.00 0.00 880.00
plasttering
10 Gravel 1 Cum 6 110.00 89.20 78.51 0.00 0.00 188.51
11 Earth cost or compensation for 1 Cum 0 55.00 0.00 0.00 0.00 0.00 55.00
earth taken frim private land
(excluding seiniorage charges)
13 Bricks Second Class 1000 Nos 25 4628.00 501.50 441.40 48.32 48.32 5166.04
. Material Unit Lead in Initial Cost Conveyance Conveyance Charges Loading Unloading Total
Km Charges after deducting Charges Charges
contrators profit after after
deducting deducting
contrators contrators
profit profit
16 Structural Steel i.e. Angles, 1 MT 0 41300.00 0.00 0.00 0.00 0.00 41300.00
Channels
17 I-sections 1 MT 0 41300.00 0.00 0.00 0.00 0.00 41300.00
21 Rough stone for Revetment 225 1 Cum 40 138.00 464.60 408.92 0.00 0.00 546.92
mm thick
N.W:- C & C Kethaverunipadu L.I. Scheme on Krishna River in Chandralapadu Mandal of Krishna
District
DATA FOR CIVIL WORKS
Index- Sl. No Description Unit Quantity Rate Amount
code
ALLOWANCES
Area Allowance 0%
ABSTRACT
Depth upto 3 m
Unit = cum
A. Materials:
B. Machinery:
C. Labour:
5001.80
Total Rs 18553.40
a) Upto 3 m depth
IRR- Excavation in Ordnary rock without blasting for foundations of canal cross drainage and other
CCDW appurtenant structures and placing the excavated stuff neatly in specified dump area or disposing
-1-4 off the same as directed etc., complete with initial lead upto 50 m and initial lift upto 3 m by
mechanical means. ( Data adopted from MORTH)
Unit = cum
A. Materials:
B. Machinery:
Abstract
Total 17675.40
Upto 3 m depth
Rate as above cum 1.00 111.57 111.57
IRR- Excavation in hard rock requiring blasting including boulders above 0.6 m upto 1.2 m dia. for
CCDW foundations of canal cross drainage and other appurtenant structures and placing the excavated
-1-5 stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial
lead upto 50 m and initial lift upto 3 m.
B. MACHINERY:
C. LABOUR:
28931.40
Area Allowance 0% 28931.40 0.00
ABSTRACT:
A. MATERIALS:
B. MACHINERY:
C. LABOUR:
ABSTRACT:
6 Marshy soil
a) Labour
Mazdoor for dressing sides, bottom and day 2.08 420.00 873.60
back filling (Unskilled)
Crew charges for Hydraulic Excavator hour 0.17 248.30 42.21
Crew charges for Tipper hour 0.45 186.20 83.79
999.60
b) Machinery
Tipper 5.5 cum capacity, 4 trips per hour hour 0.45 346.90 156.11
c) Material
MANUAL MEANS
7 Ordinary soil
a) Upto 3 m depth
Index- Sl. No Description Unit Quantity Rate Amount
code
Unit = cum
a) Labour
b) 3 m to 6 m depth
Unit = cum
Manual Means
a) Labour
Mazdoor (Unskilled) day 4.68 420.00 1965.60
c) Depth above 6 m
Manual Means
Unit = cum
a) Labour
a) Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
Unit = 1 cum
Earth cost or compensation for earth taken cum 1.00 55.00 55.00
frim private land (excluding seiniorage
charges)
Earth work excavation and back filling in cum 1.00 87.83 87.83
ordinary soil by mechanical means
including OH & CP
Lead Charges including OH & CP cum 3.00 54.30
Unit = 1 cum
Earth cost or compensation for earth taken cum 1.00 55.00 55.00
frim private land (excluding seiniorage
charges)
Earth work excavation and back filling in cum 1.00 116.93 116.93
ordinary soil by mechanical means with a
lead of 1Km including CP&OH
1 NIL 0.00
0.00
B. MACHINERY:
in Rs. in Rs.
Index- Sl. No Description Unit Quantity Rate Amount
code
1 Shovel 0.50 cum capacity Hour 8.00 778.70 6229.60
C. LABOUR:
9601.40
ABSTRACT:
A. Cost of Materials Rs: 0.00
10 b Formation of embankment with barrowed earth with a lead of 1Km including earth work
excavation, conveyance, etrc complete- 1 Cum
cost of earth with a lead of 1Km including cum 1.00 80.61 80.61
earth cost or compensation for earth taken
from private land
A. MATERIALS:
1 NIL 0.00
0.00
B. MACHINERY:
C. LABOUR:
9381.40
ABSTRACT:
A. Cost of Materials Rs: 0.00
IRR- 12 Providing compacted embankment for field irrigation channels with gravely soil from approved
CAW- borrow area including sorting out, spreading in layers of 15 cm thickness, breaking clods, watering,
4-6 compacting, dressing sides to required slopes etc.,complete with lead upto 50 m and all lifts.
Output of 1 Crowbarman assumed at 10 cum per day for loosening gravely soil.
Output of 2 mazdoors assumed at 5 cum per day for excavation of gravely soil and loading the
same to transport vehicle at borrow area.
Output of 1 mazdoor assumed at 10 cum loose soil for spreading and levelling.
RATE ANALYSIS UNIT : 25.00 cum
A. MATERIALS:
1 Nill 0.00
0.00
C. LABOUR:
4 mazdoor
5 Cartman with Bullock cart for water Day 1.00 455.00 455.00
7901.10
ABSTRACT:
RBR- 13 Sand Filling in foundation trenches as per drawing and technical specification Clause
FNDN- 305.3.9 MORD & 304 MORTH
2
Unit = 1 cum
a) Labour
b) Material
249.95
b) Bailing out water for earth work cum 1.00 260.00 260.00
excavation /concrete for foundation below
water level. (For building items only) - Other
than sandy soil - 1.0 M to 2.0 M
295.40
c) Bailing out water for earth work cum 1.00 303.00 303.00
excavation /concrete for foundation below
water level. (For building items only) - Other
than sandy soil - 2.0 M to 3.0 M
344.25
BLD- 15 Plain Cement concrete (1:4:8) using 40 mm metal with concrete mixture.
CSTN-
3-5 Unit = 1cum
A. MATERIALS:
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00 41.50 41.50
capacity
Fuel charges hour 1.00 84.90 84.90
C. LABOUR:
863.90
BLD- 16 Plain Cement concrete (M 15) Nominal Mix 1:2.5:5 using 40 mm graded metal with concrete
CSTN- mixer
3-12 Unit : 1cum
i) without water
A. MATERIALS:
Cement Kg 275.000 5.00 1375.00
B. MACHINERY
Index- Sl. No Description Unit Quantity Rate Amount
code
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.000 41.50 41.50
capacity
Fuel charges hour 1.000 84.90 84.90
Total cost of Machinery 126.40
C. LABOUR:
863.90
17 Plain Cement concrete (M 15) Nominal Mix 1:2.5:5 using 20 mm graded metal with concrete
mixer
Unit : 1cum
i) without water
A. MATERIALS:
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.000 41.50 41.50
capacity
Fuel charges hour 1.000 84.90 84.90
C. LABOUR:
863.90
18 Providing High Yeild Strength Deformed steel bars (Fe 415 grade as per IS 1786-1979) of
different diameters, including labour charges for cutting, bending to required sizes and
shapes, placing in position with cover blocks of approved size and tying with binding wire
of 18SWG, forming grills for reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars including all wastages such as overlaps,
couplings, chairs, spacer bars including cost and conveyance of binding wire, cover blocks
and all incidental, operational, labour charges such as cutting, bending, placing in position,
tying including sales and other taxes on all materials etc complete for finished items of
work in all floors (APSS 126).
10450.00
19 R.C.C grade M 20 (Design Mix) using 20 mm Graded Metal (MORTH) for Raft
CASE I : Using Concrete Mixer
Unit = cum
i) without water
(a) Material
(b) Labour
847.32
Area Allowance 0.00 847.32 0.00
(c) Machinery
RBR 20 Reinforced Cement Concrete M20 (Design Mix) using 20 mm graded metal in Well
FNDN Foundation complete as per Drawing and Technical Specification 1200, 1500 & 1700
-12B(II MORTH for well steining for structures where water is not retained.
I)
Unit = 1 cum
i) without water
Concrete basic Cost of Labour, Material & cum 1.00 5185.92 5185.92
Machinery (a+b+c) as above
d) formwork @ 10 per cent of the cost 10% 5185.92 518.59
of concrete
e&f) Overheads & Contractors Profit 13.615% 5704.51 776.67
BLD- 21 FOOTINGS
CSTN-
3-14 M 20 Design Mix
i) without water
a) Materials
Cement kg 350.00 5.00 1750.00
20mm - 10mm HBG metal (Graded metel) cum 0.80 1391.45 1113.16
b) Labour
3121.78
c) Machinery
i) without water
a) Materials
Cement kg 350.00 5.00 1750.00
20mm - 10mm HBG metal (Graded metel) cum 0.80 1391.45 1113.16
b) Labour
2892.78
c) Machinery
BLD- 23 PEDESTALS
CSTN-
3-14 M 20 Design Mix
i) without water
a) Materials
20mm - 10mm HBG metal (Graded metel) cum 0.80 1391.45 1113.16
b) Labour
3401.78
c) Machinery
i) without water
a) Materials
b) Labour
1st Class Mason day 0.133 500.00 66.50
3789.78
c) Machinery
BLD- 25 COLUMNS
CSTN-
3-15 M 20 Design Mix
i) without water
a) Materials
Index- Sl. No Description Unit Quantity Rate Amount
code
Cement kg 350.00 5.00 1750.00
b) Labour
BLD- 26 LINTELS
CSTN-
3-15 M 20 Design Mix
i) without water
a) Materials
b) Labour
c) Machinery
without water
a) Materials
Cement kg 350.00 5.00 1750.00
b) Labour
1508.89
27 i) Beams without water 1st floor 2nd floor 3rd floor 4th floor 5th floor
Lift charges on Labour @ 10% for each floor 0.00 150.89 301.78 452.67 603.56
Winch Crew charges 0.267 hrs and @10% 0.00 73.72 81.09 88.46 95.83
for each floor
Index- Sl. No Description Unit Quantity Rate Amount
code
Area Allowance 0.00 0.00 0.00 0.00 0.00
Winch Hire charges 0.267 hrs and @10% 0.00 26.81 29.49 32.17 34.85
for each floor
Winch Fuel charges 0.267 hrs and @10% 0.00 37.06 40.77 44.47 48.18
for each floor
Overheads & Contractor's Profit on 335.47 390.00 427.66 465.47 503.13
Centering
Rate for 1 cum 8935.67 9390.68 9704.99 10020.44 10334.75
ii) Beams with water 1st floor 2nd floor 3rd floor 4th floor
28 i) Slab 100 mm thick without water 1st floor 2nd floor 3rd floor 4th floor
Rate per 1 cum as above 6136.20 6136.20 6136.20 6136.20
ii) Slab 100 mm thick with water 1st floor 2nd floor 3rd floor 4th floor
Water charges 1.2 kl/cum for Rural 92.40 92.40 92.40 92.40
29 i) Slab 115 mm thick without water 1st floor 2nd floor 3rd floor 4th floor
Rate per 1 cum as above 6136.20 6136.20 6136.20 6136.20
ii) Roof Slab 115 mm thick with water 1st floor 2nd floor 3rd floor 4th floor
Water charges 1.2 kl/cum for Rural 92.40 92.40 92.40 92.40
30 i) Slab 150 mm thick without water 1st floor 2nd floor 3rd floor 4th floor
Rate per 1 cum as above 6136.20 6136.20 6136.20 6136.20
Winch Hire charges 0.267 hrs and @10% 0.00 26.81 29.49 32.17
for each floor
Winch Fuel charges 0.267 hrs and @10% 0.00 37.06 40.77 44.47
for each floor
Overheads & Contractor's Profit on 419.34 468.60 510.08 448.08
Centering
Rate per cum 9635.54 10046.61 10392.74 9875.38
ii) Slab 150 mm thick with water 1st floor 2nd floor 3rd floor 4th floor
Rate per cum 9635.54 10046.61 10392.74 9875.38
Water charges 1.2 kl/cum for Rural 92.40 92.40 92.40 92.40
31 i) Slab 200 mm thick without water 1st floor 2nd floor 3rd floor 4th floor
Rate per 1 cum as above 6136.20 6136.20 6136.20 6136.20
Winch Hire charges 0.267 hrs and @10% 0.00 26.81 29.49 32.17
for each floor
Winch Fuel charges 0.267 hrs and @10% 0.00 37.06 40.77 44.47
for each floor
Overheads & Contractor's Profit on 195.38 243.50 274.77 306.03
Centering
Rate per cum 7766.58 8168.18 8429.10 8690.00
ii) Slab 200 mm thick with water 1st floor 2nd floor 3rd floor 4th floor
Index- Sl. No Description Unit Quantity Rate Amount
code
Rate per cum 7766.58 8168.18 8429.10 8690.00
Water charges 1.2 kl/cum for Rural 92.40 92.40 92.40 92.40
32 i) Slab 300 mm thick without water 1st floor 2nd floor 3rd floor 4th floor
Rate per 1 cum as above 6136.20 6136.20 6136.20 6136.20
Winch Hire charges 0.267 hrs and @10% 0.00 26.81 29.49 32.17
for each floor
Winch Fuel charges 0.267 hrs and @10% 0.00 37.06 40.77 44.47
for each floor
Overheads & Contractor's Profit on 130.25 175.43 203.74 232.06
Centering
Rate per cum 7223.12 7600.11 7836.40 8072.70
ii) Slab 300 mm thick with water 1st floor 2nd floor 3rd floor 4th floor
Rate per cum 7223.12 7600.11 7836.40 8072.70
Water charges 1.2 kl/cum for Rural 92.40 92.40 92.40 92.40
34 MORTARS
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 420.00 84.00
Total 8208.00
A. MATERIALS:
- Nil - -
C. LABOUR:
A. MATERIALS:
- Nil - -
C. LABOUR:
Index- Sl. No Description Unit Quantity Rate Amount
code
Man mazdoor for mixing mortar day 0.20 420.00 84.00
Total 4608.00
A. MATERIALS:
- Nil - -
C. LABOUR:
A. MATERIALS:
- Nil - - -
C. LABOUR:
Total 2808.00
A. MATERIALS:
- Nil - -
C. LABOUR:
Total 2448.00
A. MATERIALS:
- Nil - -
C. LABOUR:
Total 2208.00
A. MATERIALS:
- Nil - -
C. LABOUR:
Total 1908.00
B. LABOUR:
1171.40
BLD- 36 11.5 cm wide Brick masonry for super-structure on ground floor in cm (1:3) using second
CSTN- class traditional size bricks including cost of all materials, seigniorage charges, labour and
5-11 all operations for constructing half brick masonry, mixing cement mortar, curing etc.,
complete for finished item of work, but excluding conveyance charges of materials.
unit:10sqm
A. MATERIALS:
Country bricks, second class traditional size nos 565.000 5.17 2918.81
23x11x7cm
Cement kg. 106.000 5.00 530.00
B. LABOUR:
Mason 2 class
nd
day 0.600 460.00 276.00
A. MATERIALS:
B. LABOUR:
1440.00
B. LABOUR:
540.80
A. MATERIALS:
Cement kg 28.80 5.00 144.00
B. LABOUR:
540.80
A. MATERIALS:
Cement Mortar (1:3) cum 0.15 3408.00 511.20
B. LABOUR:
Index- Sl. No Description Unit Quantity Rate Amount
code
Mason 1st class day 0.45 500.00 225.00
1884.00
Area Allowance 0% 1884.00 0.00
A. MATERIALS:
B. LABOUR:
1884.00
BLD- 41 Plastering with CM 2 coats, 20 mm thick, base coat in CM (1:5), 16mm thick and top coat in
CSTN- CM (1:4), 4mm thick with Dubara sponze finishing.
8-9
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:5), 16 mm thick
B. LABOUR:
2629.20
Index- Sl. No Description Unit Quantity Rate Amount
code
Area Allowance 0% 2629.20 0.00
BLD- 42 Plastering with CM 2 coats, 12 mm thick, base coat in CM (1:5), 8mm thick and top coat in
CSTN- CM (1:4), 4mm thick with sponze finishing.
8-10 Unit = 10 sqm
A. MATERIALS:
B. LABOUR:
Mason 2 class
nd
day 1.47 460.00 676.20
BLD- 43 Flooring with Cement Concrete 1:4:8, using 40mm metal, 100mm thick and plastered over
CSTN- with 12 mm thick in CM(1:3)
9-15 Unit = 10 sqm
A. MATERIALS:
BLD- 44 Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with
CSTN- 1kg of water proof compound per bag of cement laid over roof when it is green including
10-25 cost of all materials, seigniorage charges, excluding conveyance charges of materials and
including all operational, incidental and labour charges for mixing mortar, laying, rendering
smooth and thread lining, curing, rounding off junctions of wall and slab etc,, complete for
finished item of work
Unit = 10 sqm
A. MATERIALS:
B. LABOUR
Mason 2 class
nd
day 1.540 460.00 708.40
2592.40
BLD- 45 Painting to new walls with 2 coats of ready mixed oil bound wahsable distemper of
CSTN- approved brand and shade over a base coat of appropriate primer of approved brand,
12-1 making 3 coats in all to give an even shade after thourughly brushing the surface to remove
all dirt and remains of loose powdered materials, including cost and conveyance of all
materials to work site and all operational, incidental, labour charges etc. complete for
finished item of work as per SS 911 for internal walls
PRIMARY COAT:
133.80
595.20
BLD- 46 Painting to new walls with 2 coats of water proof cement paint of apporved brand and
CSTN- shade over a base coat of approved cement primer grade I making making 3 coats in all to
12-5 give an even shade after thourughly brushing the surface to remove all dirt and remains of
loose powdered materials, including cost and conveyance of all materials to work site and
all operational, incidental, labour charges etc. complete for finished item of work as per SS
912 for external walls
347.20
878.00
BLD- 47 Painting with Synthetic Enamel paints - Two Coats with Priming Coat on New Iron Work
CSTN-
12-7 & Unit: 10 sqm
12-12
i) Primary Coat
A. MATERIALS :
B. LABOUR
406.00
B. LABOUR
Painter day 1.10 580.00 638.00
638.00
IRR- 48 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N /
CCDW sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
-2-12 aggregates for well kerb including cost of all materials, machinery, labour, formwork, scaffolding,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts.
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement), CA :
0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
i) without water lead
Requirement of materials :
For 1 cum CC:
Coarse aggregates : 0.80 cum
Blending ratio : 65 :35
Fine aggregate : 0.45 cum
Cement content : 350 kg
Super plasticizer : 1.4 kg
RATE ANALYSIS UNIT : 15.00 cum
A. MATERIALS:
B. MACHINERY:
C. LABOUR:
6 mazdoor
25779.90
ABSTRACT:
IRR- 49 Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N / sqmm )
CCDW grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for well
-2-14 bottom plug by tremie or skip box method including cost of all materials, machinery, labour,
batching, mixing, placing in position as per detailed specifications etc., complete with initial lead
upto 50 m and all lifts.
(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),
Requirement of materials :
For placing concrete under water by using tremie the slump of concrete shall be about 150 mm.
Minimum cement content as per IS: 456-2000 Clause-14.2.2 : 350 kg / cum.
Index- Sl. No Description Unit Quantity Rate Amount
code
For 1 cum CC :-
Coarse aggregates : 0.80 cum
Blending ratio : 65 : 35
Fine aggregate : 0.45 cum
Cement content : 350 kg
Super plasticizer : 1.40 kg
A. MATERIALS:
B. MACHINERY:
C. LABOUR:
18373.85
ABSTRACT:
Index- Sl. No Description Unit Quantity Rate Amount
code
A. Cost of Materials including seignorage Rs: 45708.40
charges
B. Hire charges of Machinery Rs: 1057.60
IRR- 50 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than 10
CAW- N /sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
7-13 aggregates for bed and side lining of canal including finishing the junction of bed and sides to
required curveture, cost of all materials, machinery, labour, formwork including supports, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete with initial
lead upto 50 m and all lifts. ( Cement content : 250 kg / cum )
(Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement), CA :
0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Requirement of materials :
For 1 cum CC :-
Coarse aggregates : 0.80 cum
Blending ratio : 65 :35
Fine aggregate : 0.45 cum
Cement content : 250 kg
Super plasticizer : 0.88 kg.
A. MATERIALS:
B. MACHINERY:
C. LABOUR:
8 mazdoor
for batching materials Day 22.00 420.00 9240.00
ABSTRACT:
IRR- 51 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
CAW- N /sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
7-15 aggregates for bed and side lining of canal(100 mm thick) including finishing the junction of bed
and sidesto required curveture, cost of all materials, machinery, labour, formwork including
supports,cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete with initial lead upto 50 m and all lifts.
(Cement content: 300 kg / cum for use of super plasticiser(0.4% by wt. of cement), CA : 0.80
cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Requirement of materials :
Index- Sl. No Description Unit Quantity Rate Amount
code
For 1 cum CC :-
Coarse aggregates : 0.80 cum
Blending ratio : 65 :35
Fine aggregate : 0.45 cum
Cement content : 300 kg
Super plasticizer : 0.96 kg
A. MATERIALS:
B. MACHINERY:
C. LABOUR:
8 mazdoor
34212.45
Area Allowance 0% 34212.45 0.00
ABSTRACT:
IRR- 52 Providing and fixing pre-cast RCC template walls consisting of 0.05 cum M-15 grade concrete
CAW- using 20 mm down size coarse aggregates and 10 kg reinforcement steel moulded as per
7-17 specifications and drawing in CM 1:4 proportion including cost of all materials, machinery, labour,
formwork, fabricating and placing reinforcement steel, mixing, laying, conveying and fixing in
position including necessary excavation for seating, finishing joints in CM 1:4, curing etc.,
complete with initial lead upto 1 km and all lifts.
A. MATERIALS:
B. MACHINERY:
C. LABOUR:
5880.00
ABSTRACT:
IRR- 53 Providing and fixing 20 mm thick 100 mm depth tarfelt expansion joint filler boards for cement
CAW- concrete lining of canal including cost of all materials, labour etc., complete with all leads and lifts.
7-34
A. MATERIALS:
B. MACHINERY:
C. LABOUR:
880.00
ABSTRACT:
A. Cost of Materials Rs: 4890.00
IRR- 54 Providing and constructing 25 cm thick dry rubble stone pitching including cost of all materials,
CAW- labour, hand packing, finishing etc., complete
8-3 ( rubble stones : 0.275 cum/sqm)
Requirement of materials for constructing 100 Sqm pitching :
A. MATERIALS :
C. LABOUR :
ABSTRACT :
Index- Sl. No Description Unit Quantity Rate Amount
code
A. Cost of Material including seignorage Rs. 15040.30
charges
B. Hire Charges of Machinery Rs. 0.00
IRR- 54 a Providing and constructing 225mm thick dry rubble stone pitching including cost of all materials,
CAW- labour, hand packing, finishing etc., complete
8-3 ( rubble stones : 0.247 cum/sqm)
Requirement of materials for constructing 100 Sqm pitching :
A. MATERIALS :
B. MACHINERY :
C. LABOUR :
12925.00
Area Allowance 0% 12925.00 0.00
ABSTRACT :
A. MATERIALS:
B. MACHINERY:
C. LABOUR:
6235.00
ABSTRACT:
56 Supply & fixing of Rolling shutter made sq.m 1.00 2360.00 2360.00 BMT-F.29
of 80 x 1.25 mm machine rolled CRCA
laths, interlocked together through their
entire length and jointed together at the
ends by end-locks, mounted on specially
designed pipe shaft of 50mm di
Contractor’s profit on (a+b+c) 13.615% 2360.00 321.31
Total 2681.31
Labour charges for fixing Iron doors, Iron kg 1.00 4.00 4.00 BMM-V.15
windows and Window grills in position
Area Allowance on labour 0% 28.00 0.00
Contractor’s profit on (a+b+c) 13.615% 71.37 9.72
Total 81.09
Rate for Fabrication of M.S.Items like
Beams and Girders Etc.--1 kg
sundries 0.23
Total 4298.00
59 Supply and fixing of Trash Rack of size
2.00 x1.20 mtrs with frame angle 75x75x6
mm and 16 mm dia rods at 100 mm c/c
on both ways -- Each.
75x75x6 mm angles =
43.52 kgs
((2x1.20)+(2x2.00))x6.80
16 mm Rods = (((120/10)x2.00)+
75.84 kgs
((200/10)x1.20))x1.58
75x75x6 mm angles =
48.96 kgs
((2x1.20)+(2x2.40))x6.80
16 mm Rods = (((120/10)x2.00)+
83.42 kgs
((240/10)x1.20))x1.58
144.00 kgs
Cost of material 81.09 kg 11677.28
sundries 0.72
11678.00
60 Supply and fixing of Trash Rack of size
1.20 x 1.20 mtrs with frame angle
75x75x6 mm and 16 mm dia rods at 100
mm c/c on both ways -- Each.
sundries 0.95
Total 3650.00
62 Supply and fixing of Gate of size 3.00
x1.50 m in two leaves frame made with
75x75x6 mm angles alround and welded
with 16 mm dia rods at 100 mm c/c on
both ways including handle and hold
fasts.etc complete.
Aldrops 300mm long (MS Powder coated) 1.00 each 149.00 149.00 BMT-G.45
Sundries 0.01
Total 18820.00
9500.00
64 Spreading of 40 MM HBG metal
Cost of 40 mm HBG metal 1.00 Cum 1029.45 1029.45
Labour for spreading 1.10 day 420.00 462.00
Area Allowance on labour 0% 462.00 0.00
Add for contractor's profit and overheads 13.615% 1491.45 203.06
Total 1694.51
65 Spreading of gravel
Cost of Gravel 1.00 Cum 188.51 188.51
Un skilled labour 1.10 day 420.00 462.00
Area Allowance on labour 0% 462.00 0.00
Add for contractor's profit and overheads 13.615% 650.51 88.57
Total 739.08
67 Hot dipped Galvanised Iron Chain link Sq.m 1.00 394.00 394.00 BMT-F.20
mesh 8 gauge - (4.0 mm) as per IS: 2721-
1979: 2"x2" (50 mm x 50 mm) - 8 Gauge
68 MS Windows
Windows: Double shutter 3'-0" x 4'-0" 1 Sqm 1.00 5684.00 5684.00 BMT-P.10
(914.4mm x 1219.2mm) outer frame section
size of 46 x 52 mm shutter framesection
size of 46 x 46 mm Mullion section size of
46 x 70 mm
Sundries 7.70
70 Hand railing
Index- Sl. No Description Unit Quantity Rate Amount
code
Supply & fixing of 30x6mm MS flat including 1 RMT 1.41 81.09 114.58
fixing labour charges
0.03x0.006x1x7850
Supply & fixing 12mm dia rod at 0.15m c/c 1 RMT 7.11 81.09 576.55
to be welded in between 50mm dia MS pipe
and 30mm flat with a height 0.90m each
(1.00/0.15 = 6.77 say 7Nos x0.90= 6.30m )
and Horizontal rod i.e. 1.00m , total 7.30m
say 8m
8xIIx0.0122/4x7850
Supply & fixing of 50mm nominal bore GI 1 RMT 1.00 404.00 404.00 BMW
pipe light grade properties and weight as F-77
per ISI 1239 ISI mark with GI fitting
including cost of pipe and its fitting labour
charges
BLD- 71 Supplying and fixing galvanised steel barbed wire (IS : 278-1962 Type I) weighing 9.38 Kg
CSTN- per 100 metres (min.), Straining and fixing to any type of standard, rails, straining bolts,
15-7 including securing with and provision of galvanised mild steel wire, stapples or steel pins,
etc., as directed (Posts and struts of wood, concrete, steel, etc.) and straining bolts shall be
paid for separately).
Labour :-
For fixing & stretching wire
300.00
A. MATERIALS:
B. MACHINERY:
C. LABOUR:
2111.30
Sundries 0.87
Total cost of MS windows 4823.00
b) Fabrication, supply and fixing of M.S windows of size 1.20 M
x1.20M with 3 leaves
1 Window frame with 40x40x5mm MS angle 14.4
at 3.0kg/m
2 4X1.2mX3.00
Shutter frame with 35x35x5mm MS angle at 24.96
2.60Kg/m
6X1.20+6X.40=9.60mx2.60kg
3 20x5mm MS flat 1.92
2x1.20x0.80
4 Safity rods10 mm 12.17
13x1.20mx0.78 kg
5 16guage sheet 18.09
1.20x1.20x0.0016x7850
71.54 81.09 5801.18
MS Hold fasts100mm long 4nos 4 25.00 100.00
Tower bolts100 mm long 6nos 6 21.00 126.00
Hinges100 mm 6nos 6 19.00 114.00
Wind appliences 3nos 3 41.00 123.00
MS power coated handles 125 mm long 3nos 3 28.00 84.00
Index- Sl. No Description Unit Quantity Rate Amount
code
6348.18
Add for contractor's profit and overheads 13.615% 547.00 74.47
6422.65
Sundries 0.35
Total cost of MS windows 6423.00
343.00
75 Formation of Ring Bund duly laying the sand bags in the stipulated places 8.50
including cost of the empty cement bag, sand, thread, stitching charges &
labour charges with overhead charges including contractor profit
Unit = cum
Taking out put = 360cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 2.08 420.00 873.60
Crew charges for excavator hour 3.60 248.30 893.88
Crew charges for tipper hour 15.00 186.20 2793.00
Area Allowance 0% 4560.48 0.00
b) Machinery
22706.94
c&d) Overheads & Contractors Profit 13.615% 22706.94 3091.55
Excavation of trenches for Infiltration galleries, syphon lines and connecting mains in all
77 soils under water including all leads, lifts, shoring, strutting, bailing out of water and
removal of shoring and strutting materials after completion of pipeline work
Unit- 10 cum
IRR- 77 Providing homogeneous embankment using soil from approved borrow area in
PMW- layers of 25 to 30 cm before compaction including cost of all materials, machinery,
3-22 labour, all operations such as excavation, sorting out, transportation, spreading soil
New5 - in layer of specified thickness, breaking clods,sectioning,etc.,complete with initial
lead upto 1 km and all lifts.
RATE ANALYSIS
A. MATERIALS: 807.00 cum
Sl Particulars Unit Quantity Rate Amount
No
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Add seigniorage charges for soil (As per G.O.Ms.No.198 807.00 0.00 0.00
,dt:13.08.09)
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl Description Unit Quantity Rate Amount
No
in Rs. in Rs
Index- Sl. No Description Unit Quantity Rate Amount
code
1 Angle dozer 90 hp Hour 2.70 1331.80 3595.86
Fuel / Energy charges Hour 2.70 653.10 1763.37
2 Shovel 0.85 cum capacity Hour 8.00 1324.90 10599.20
Fuel / Energy charges Hour 8.00 933.70 7469.60
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 346.90 13876.00
Fuel / Energy charges Hour 40.00 320.80 12832.00
Total hire charges of Machinery Rs: 50136.03
C. LABOUR:
Sl Description Unit Quantity Rate Amount
No
in Rs. in Rs
1 Crew for Dozer Hour 2.70 248.30 670.41
2 Crew for Shovel Hour 8.00 248.30 1986.40
3 Crew for Tipper Hour 40.00 186.20 7448.00
4 work inspector Day 1.00 475.00 475.00
5 mazdoor Day 2.00 420.00 840.00
Total cost of Labour Rs: 11419.81
ABSTRACT:
A. Cost of Materials including seigniorage charges Rs: 0.00
B. Hire charges of Machinery Rs: 50136.03
C. Cost of Labour Rs: 11419.81
Total Rs: 61555.84
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 8380.83
Total cost for 807 cum Rs: 69936.67
Rate per cum (A+B+C+D Rs: 86.70
)/807
IRR- 78 Providing homogeneous embankment using soil from approved borrow area in
PMW- layers of 25 to 30 cm before compaction including cost of all materials, machinery,
3-23 labour, all operations such as watering, compacting to density control of not less
New6 - than 95 percent or as stipulated using 8T roller etc., complete with initial lead upto
1 km and all lifts.
RATE ANALYSIS
A. MATERIALS: UNIT : 807.00 cum
Sl Particulars Unit Quantity Rate Amount
No
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Add seigniorage charges for soil 807.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl Description Unit Quantity Rate Amount
No
in Rs. in Rs
1 Angle dozer 90 hp Hour 2.70 1331.80 3595.86
Fuel / Energy charges Hour 2.70 653.10 1763.37
2 Pump 5 hp ( ele ) Hour 4.00 2.30 9.20
Fuel / Energy charges Hour 4.00 28.30 113.20
3 Water tanker 8000 ltr Hour 8.00 342.60 2740.80
Fuel / Energy charges Hour 8.00 320.80 2566.40
4 Vibratory pad foot roller 8 tonne Hour 6.40 1042.00 6668.80
Fuel / Energy charges Hour 6.40 1103.40 7061.76
5 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 24579.39
C. LABOUR:
Sl Description Unit Quantity Rate Amount
No
in Rs. in Rs
1 Crew for Dozer Hour 2.70 248.30 670.41
4 Crew for Pump Hour 4.00 87.00 348.00
5 Crew for Water tanker Hour 8.00 186.20 1489.60
6 Crew for Roller Hour 6.40 276.10 1767.04
Index- Sl. No Description Unit Quantity Rate Amount
code
7 work inspector Day 1.00 475.00 475.00
8 mazdoor Day 2.00 420.00 840.00
Total cost of Labour Rs: 5590.05
ABSTRACT:
A. Cost of Materials including seigniorage Rs: 0.00
charges
B. Hire charges of Machinery Rs: 24579.39
C. Cost of Labour Rs: 5590.05
Total Rs: 30169.44
D.Add for contractor's profit and overheads 13.615% Rs. 4107.57
on (A+B+C)
Total cost for 807.00 cum Rs: 34277.01
RATE ANALYSIS
A. MATERIALS: UNIT : 807.00 cum
Sl Particulars Unit Quantity Rate Amount
No
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Add seigniorage charges for soil 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl Description Unit Quantity Rate Amount
No
in Rs. in Rs
1 Tractor with 2T Roller Hour 10.00 345.00 3450.00
2 Sundries LS 2.00 30.00 60.00
Total hire charges of Machinery Rs: 3510.00
C. LABOUR:
ABSTRACT:
A. Cost of Materials including seigniorage Rs: 0.00
charges
B. Hire charges of Machinery Rs: 3510.00
C. Cost of Labour Rs: 1077.50
Total Rs: 4587.50
D.Add for contractor's profit and overheads on 14% Rs. 624.59
(A+B+C) Total cost for 807.00 cum Rs: 5212.09
Rate per cum (A+B+C+D Rs: 6.50
)/807
Earth cost for compensation for earth taken cum 1.00 55.00 55.00
from private land excluding seigniorage
charges
85 Augoring and boring of holes in site for Bored cast-in-situ RCC piles for builfing foundations in
loamy, clayey soils like black cotton soils and ordinary soils without under reams as per IS 2911-
1980 as per approved designs including all operations, incidental, labour charges, hire charges of
machinery, augur bore drill and shell equipment etc complete for all depths and for finished item of
work for piles of following diameters
a Up to 300mm dia
Total cost for 1 RM
A). MATERIALS
NIL
B). LABOUR
Mazdoor Day 0.526 420.00 220.92
C) Labour allowance 0% 220.92 0.00
D) Overheads and contractor's profit 13.615% 220.92 30.08
Total 251.00
b 350mm dia to 450mm dia
Total cost for 1 RM
A). MATERIALS
NIL
B). LABOUR
Mazdoor Day 0.631 420.00 265.02
C) Labour allowance 0% 265.02 0.00
D) Overheads and contractor's profit 13.615% 265.02 36.08
Total 301.10
c 500mm dia to 700mm dia
Total cost for 1 RM
A). MATERIALS
NIL
B). LABOUR
Mazdoor Day 0.789 420.00 331.38
C) Labour allowance 0% 331.38 0.00
D) Overheads and contractor's profit 13.615% 331.38 45.12
Total 376.50
86 Under reaming for Bored cast-in-situ RCC piles for builfing foundations in loamy, clayey soils like
black cotton soils and ordinary soils with Augoring and boring equipment in site as per IS 2911-
1980 as per approved designs including all operations, incidental, labour charges, hire charges of
machinery, augur bore drill and shell equipment etc complete for all depths and for finished item of
work for piles of following diameters
Unit = 1cum
(a) Material
(b) Labour
1591.00
kgs 38.00
sundries 7.72
Data
Capacity of shovel bucket : 0.85 cum
B. MACHINERY:
C. LABOUR:
D. Add for contractor's profit and overheads on A+B+C 13.615% 65892.20 Rs. 8971.22
B. MACHINERY:
2 Dumpers 5 cum capacity 4 Nos. Fuel / Energy Hour 32.00 450.90 14428.80
charges
4 Air compressor 8.5 cmm ( ele ) 2 Nos Fuel / Hour 13.00 132.60 1723.80
Energy charges
5 Jack hammers 4 Nos. Fuel / Energy charges Hour 26.00 15.40 400.40
D. Add for contractor's profit and overheads on A+B+C 13.615% 33481.40 Rs. 4558.49
5 a) EW in Hard rock requiring blasting up to 50m lead up to 3 depth including 1 Cum Err:509
1.50m depth in hard rock
b) EW in Hard rock requiring blasting up to 1 Km lead up to 3 depth including 1 Cum 428.95
1.50m depth in hard rock
6 EW in Marshy soil Including Refilling with selected earth conveyed from 1000 M 1 Cum 222.58
lead through Tractor Trally.
7 a) EW by manual means in Ordinary soil up to 3m depth 1 Cum 173.70
8 EW by manual means in Ordinary rock (not requiring blasting) above 6m depth 1 Cum 248.14
10 a) EW in all kinds of soil including boulders upto 0.30 m dia for field channels up 1 Cum 51.40
to 50m lead & 3m lift
b) Embankment with barrowed earth with a lead of 1Km including earth work 1 Cum 98.00
excavation
11 EW in ordinary rock without blasting including boulders above 0.3 m upto 0.60 1 Cum 84.40
m dia. for field channels up to 50m lead & 3m lift
12 Embankment for field irrigation channels with gravely soil from approved borrow 1 Cum 363.30
areawith lead upto 50 m and all lifts.
13 Sand filling 1 Cum 1147.74
15 PCC(1:4:8) using 40mm HBG metal with concrete mixer up to 3m delift 1 Cum 3547.98
16 PCC (M15) Nominal mix(1:2.5:5) using 40mm HBG metal with concrete mixer 1 Cum 4380.53
Sl No Description Unit Rate
17 PCC (M15) Nominal mix(1:2.5:5) using 20mm HBG metal with concrete mixer 1 Cum 4558.76
b) Labour
1st Class Mason day 0.133 500.00 66.50
2nd Class Mason day 0.267 460.00 122.82
Mazdoor (Both Men & Women) day 4.600 420.00 1932.00
Crew charges for Concrete Mixer h 1.333 230.10 306.72
Crew charges for Vibrator h 1.333 165.60 220.74
2648.78
Area Allowance 0% 2648.78 0.00
Total cost of Labour 2648.78
c) Machinery
Weigh Batcher Hire charges (Machine h 1.333 41.50 55.32
mixing) charges
Fuel charges h 1.333 84.90 113.17
Vibrator Hire charges h 1.333 5.90 7.86
Fuel charges h 1.333 19.70 26.26
Total cost of Machinery 202.61
Total a+b+c 6696.55
Centering charges @ Rs 1171 per sqm cum 1.00 7806.67 7806.67
i.e. Rs 1171/0.15 = Rs7806.67 per cum
Total 14503.22
Total 12551.55
Total 10599.88
Total 9624.05
Total 9298.77
Total 9038.55
Total 8648.22
Total 12829.88
Total 11296.55
Total 9763.22
Total 8740.99
Total 8536.55
Total 8229.88
33365.86
Cost per kg 96.47
N.W:- C & C Kethaverunipadu L.I. Scheme on Krishna River in Chandralapadu Mandal of Krishna District
DATA FOR SLUICE VALVES, NON RETURN VALVES, AIR CUSHION VALVES, AIR VALVES & ZERO VELOCITY VALVES
Labour charges for laying in position S&S or flanged C.I. specials such as tees, bends, collars tapers and caps etc
(a) Labour
Diameter in mm Initial Rate E.D. + Edn VAT @ 5% on Conveyance, Weight of Labour charges CP & OH @ 14% Sundries Say
Cess @ cost of valve, Loading & valve for lowering & on cost of valve,
12.36% on ED&Edn cess Unloading keeping in Conv., Fixing
cost of valve position
Sluice Valves with Hand wheel
PN - 1.0
100 11898.00 1189.80 47.10 123.50 1849.58 0.12 15061
PN - 1.6
100 7147.00 714.70 47.10 123.50 1117.93 0.87 9104
125 8934.00 893.40 61.77 161.97 1398.51 0.12 11388
PN - 1.6
100 4696.00 469.60 47.10 123.50 740.47 0.43 6030
10 kg/cm 2
100 61203.00 6120.30 212.00 9454.94 0.76 76991
20Kg/cm2
100 77422.00 7742.20 212.00 11952.67 0.13 97329
150 117655.00 11765.50 362.00 18169.55 0.95 147953
25Kg/cm2
100 85161.00 8516.10 212.00 13144.47 0.43 107034
Sl No Dia in mm Thickness in Weight per meter Cost as per Variation on cost Revised Cost
mm of pipe in Kgs SSR 2017-18 due to change in
(Wm) cost of MS plate
(M2-M1)/1000 x
Wm
1 500 8 98.69 8033.00 715.5 8748.50
DATA FOR MS Pipes confirming to IS 3589/2001 including in lining with CM(1:2) 15mm thick using 4 Nos of
6mm dia MS Rings at each end of the pipes and out coating with CM(1:3) 30mm thick by shortcreting or
gunetting duly providing wire mesh of size 50x50x3mm
Diameter in Thickness Cost of pipe Laying & CP & OH Sundries Total
mm in mm Jointing charges charges @
13.615% on
cost of pipe,
Conv, L&J
DATA FOR SLUICE VALVES, NON RETURN VALVES, AIR CUSHION VALVES, AIR VALVES & ZERO VELOCITY
VALVES
Labour charges for laying in position S&S or flanged C.I. specials such as tees, bends, collars tapers and caps etc
10 No. Tees of 200x150mm dia
Weight = 10x70kgs = 700 kgs
(a) Labour
Plumber 1st class day 0.465 625.00 290.63
Plumber 2nd class day 1.094 460.00 503.24
Man mazdoor day 2.480 420.00 1041.60
Cost for 700 kgs 1835.47
Total for 700 kgs 1835.47
Cost for 1kg 2.62
Diameter in Initial Rate Conveyance, Weight of Labour CP & OH @ Sundries Total
mm Loading & valve charges for 13.615% on
Unloading lowering & cost of valve,
keeping in Conv., Fixing
position
With by-pass
With by-pass
15 kg/cm 2
100 81294.00 4064.70 274.00 11658.89 0.41 97292.00
20Kg/cm2
100 89422.00 4471.10 274.00 12820.85 0.05 106988.00
25Kg/cm2
100 98361.00 4918.05 274.00 14098.75 0.20 117652.00
13 110 6 Kgs/cm ² 233.00 1.90 236.00 13.09 33.91 283.00 0.00 283.00
14 110 10 Kgs/cm ² 374.00 3.06 378.83 13.09 53.36 445.28 0.72 446.00
16 125 4 Kgs/cm ² 213.00 1.72 215.72 14.88 31.39 261.98 0.02 262.00
17 125 6 Kgs/cm ² 297.00 2.51 300.96 14.88 43.00 358.83 0.17 359.00
18 125 10 Kgs/cm ² 489.00 3.93 495.20 14.88 69.45 579.52 0.48 580.00
20 140 4 Kgs/cm ² 266.00 2.14 269.38 16.66 38.94 324.98 0.02 325.00
21 140 6 Kgs/cm ² 383.00 3.12 387.91 16.66 55.08 459.65 0.35 460.00
22 140 10 Kgs/cm ² 607.00 4.91 614.74 16.66 85.96 717.36 0.64 718.00
24 160 4 Kgs/cm ² 350.00 2.80 354.41 19.04 50.85 424.30 0.70 425.00
25 160 6 Kgs/cm ² 496.00 4.01 502.33 19.04 70.98 592.35 0.65 593.00
26 160 10 Kgs/cm ² 795.00 6.41 805.11 19.04 112.21 936.36 0.64 937.00
28 180 4 Kgs/cm ² 446.00 3.58 451.65 21.42 64.41 537.48 0.52 538.00
29 180 6 Kgs/cm ² 640.00 5.13 648.10 21.42 91.15 760.67 0.33 761.00
30 180 10 Kgs/cm ² 1,018.00 8.09 1,030.76 21.42 143.25 1,195.43 0.57 1196.00
32 200 4 Kgs/cm ² 543.00 4.33 549.83 23.80 78.10 651.73 0.27 652.00
33 200 6 Kgs/cm ² 778.00 6.35 788.02 23.80 110.53 922.35 0.65 923.00
34 200 10 Kgs/cm ² 1240.00 10.00 1,255.77 23.80 174.21 1,453.78 0.22 1454.00
36 225 4 Kgs/cm ² 727.00 5.51 735.69 26.78 103.81 866.28 0.72 867.00
37 225 6 Kgs/cm ² 1,050.00 7.98 1,062.58 26.78 148.32 1,237.67 0.33 1238.00
38 225 10 Kgs/cm ² 1,670.00 12.68 1,689.99 26.78 233.74 1,950.50 0.50 1951.00
40 250 4 Kgs/cm ² 842.00 6.67 852.52 29.75 120.12 1,002.39 0.61 1003.00
41 250 6 Kgs/cm ² 1,284.00 9.89 1,299.59 29.75 180.99 1,510.33 0.67 1511.00
42 250 10 Kgs/cm ² 2,025.00 15.67 2,049.71 29.75 283.12 2,362.58 0.42 2363.00
44 280 4 Kgs/cm ² 1,103.00 8.45 1,116.33 33.32 156.52 1,306.17 0.83 1307.00
Sl.N Description Basic cost Weight of Revised Laying & CP & OH Total Sund Total cost
o in SSR pipe in basic cost Jointing charges ries per
2017-18 Kgs/metre @ meter.
13.615%
on Cost
of pipe,
L&J
1 2 3 4 5 8 9 10 11 12
45 280 6 Kgs/cm ² 1,622.00 12.40 1,641.56 33.32 228.04 1,902.92 0.08 1903.00
46 280 10 Kgs/cm ² 2,564.00 19.62 2,594.93 33.32 357.84 2,986.09 0.91 2987.00
48 315 4 Kgs/cm ² 1,396.00 10.68 1,412.85 37.49 197.46 1,647.79 0.21 1648.00
49 315 6 Kgs/cm ² 2,039.00 15.72 2,063.80 37.49 286.09 2,387.37 0.63 2388.00
50 315 10 Kgs/cm ² 3,237.00 24.73 3,276.00 37.49 451.13 3,764.62 0.38 3765.00
51 355 4 Kgs/cm ² 1,828.00 13.60 1,849.44 42.25 257.55 2,149.24 0.76 2150.00
52 355 6 Kgs/cm ² 2,654.00 21.11 2,687.29 42.25 371.63 3,101.17 0.83 3102.00
53 400 4 Kgs/cm ² 2,305.00 17.16 2,332.06 47.60 323.99 2,703.65 0.35 2704.00
54 400 6 Kgs/cm ² 3,376.00 25.17 3,415.69 47.60 471.53 3,934.82 0.18 3935.00
N.W:- C & C Kethaverunipadu L.I. Scheme on Krishna River in Chandralapadu Mandal of Krishna District
350 mm 143.85
400 mm 143.85
450 mm 176.40
500 mm 187.95
600 mm 210.00
700 mm 342.30
800 mm 342.30
900 mm 342.30
1000 mm 551.25
1100 mm 551.25
1200 mm 1058.40
1300 mm 1069.95
1400 mm 1069.95
1500 mm 1069.95
1600 mm 1202.25
1700 mm 1202.25
1800 mm 1224.30
1900 mm 1278.90
2000 mm 1278.90
NP 2 Class
150 221.45 33.72 94.24 47.57 0.02 397.00
200 272.35 62.92 101.66 59.49 0.58 497.00
225 295.89 64.03 127.45 66.36 0.27 554.00
250 314.69 132.13 133.16 78.96 0.06 659.00
300 444.47 152.85 141.58 100.60 0.50 840.00
350 571.90 170.15 157.92 122.53 0.50 1023.00
400 629.24 196.15 175.23 136.23 0.15 1137.00
450 784.33 219.08 193.20 162.92 0.47 1360.00
500 904.23 237.38 221.17 185.54 0.68 1549.00
600 1269.01 395.41 255.29 261.37 0.92 2182.00
700 1644.01 432.43 343.00 329.41 0.15 2749.00
800 2110.53 653.48 412.00 432.41 0.58 3609.00
900 2680.78 1148.17 494.00 588.57 0.48 4912.00
1000 3276.43 1164.71 592.00 685.26 0.60 5719.00
1100 3799.48 1208.35 690.00 775.76 0.41 6474.00
1200 4290.20 1225.99 788.00 858.32 0.49 7163.00
1400 6155.33 1267.89 886.00 1131.30 0.48 9441.00
1600 7616.99 1333.58 984.00 1352.59 0.84 11288.00
1800 8483.09 1394.21 1082.00 1492.11 0.59 12452.00
6 kg/cm2
350 2532.11 143.85 251.00 398.51 0.53 3326.00
400 2720.01 143.85 271.00 426.81 0.33 3562.00
450 2873.47 176.40 314.00 457.99 0.14 3822.00
500 3119.17 187.95 333.00 495.60 0.28 4136.00
600 3581.37 210.00 409.00 571.88 0.75 4773.00
700 4072.00 342.30 481.00 666.50 0.20 5562.00
800 4935.25 342.30 543.00 792.47 0.98 6614.00
900 5677.44 342.30 595.00 900.60 0.66 7516.00
1000 6701.70 551.25 688.00 1081.16 0.89 9023.00
1100 7547.76 551.25 772.00 1207.79 0.20 10079.00
1200 8492.48 1058.40 856.00 1416.90 0.22 11824.00
1300 9679.30 1069.95 970.00 1595.58 0.17 13315.00
1400 11226.35 1069.95 1097.00 1823.50 0.20 15217.00
1500 12713.87 1069.95 1190.00 2038.69 0.49 17013.00
1600 14322.89 1202.25 1333.00 2295.24 0.62 19154.00
1700 15437.93 1202.25 1451.00 2463.11 0.71 20555.00
1800 17102.98 1224.30 1536.00 2704.39 0.33 22568.00
1900 18274.46 1278.90 1621.00 2882.89 0.75 24058.00
2000 20077.77 1278.90 1707.00 3140.12 0.21 26204.00
Diameter Cost of pipe Conveyance Laying & CP & OH Sundries Total
charges Jointing charges @
charges 13.615% on
cost of pipe,
Conv, L&J
8 kg/cm2
350 2540.11 143.85 251.00 399.59 0.45 3335.00
400 2739.70 143.85 271.00 429.49 0.96 3585.00
450 2895.38 176.40 314.00 460.97 0.25 3847.00
500 3131.95 187.95 333.00 497.34 0.76 4151.00
600 3606.36 210.00 409.00 575.28 0.36 4801.00
700 4133.90 342.30 481.00 674.92 0.88 5633.00
800 5066.81 342.30 543.00 810.38 0.51 6763.00
900 5851.17 342.30 595.00 924.25 0.28 7713.00
1000 6916.76 551.25 688.00 1110.44 0.55 9267.00
1100 7783.23 551.25 772.00 1239.85 0.67 10347.00
1200 8828.85 1058.40 856.00 1462.69 0.06 12206.00
1300 10046.74 1069.95 970.00 1645.60 0.71 13733.00
1400 11665.18 1069.95 1097.00 1883.24 0.63 15716.00
1500 13224.53 1069.95 1190.00 2108.21 0.31 17593.00
1600 14875.49 1202.25 1333.00 2370.47 0.79 19782.00
1700 16071.19 1202.25 1451.00 2549.33 0.23 21274.00
1800 18187.61 1224.30 1536.00 2852.06 0.03 23800.00
1900 19274.01 1278.90 1621.00 3018.98 0.11 25193.00
2000 21325.96 1278.90 1707.00 3310.06 0.08 27622.00
Diameter Cost of pipe Conveyance Laying & CP & OH Sundries Total
charges Jointing charges @
charges 13.615% on
cost of pipe,
Conv, L&J
10 kg/cm2
350 2551.15 143.85 251.00 401.10 0.90 3348.00
400 2769.61 143.85 271.00 433.56 0.98 3619.00
450 2927.16 176.40 314.00 465.30 0.14 3883.00
500 3155.50 187.95 333.00 500.55 0.00 4177.00
600 3640.22 210.00 409.00 579.89 0.89 4840.00
700 4256.93 342.30 481.00 691.67 0.10 5772.00
800 5190.62 342.30 543.00 827.24 0.84 6904.00
900 6014.98 342.30 595.00 946.55 0.17 7899.00
1000 7140.90 551.25 688.00 1140.96 0.89 9522.00
1100 8058.98 551.25 772.00 1277.39 0.38 10660.00
1200 9135.63 1058.40 856.00 1504.46 0.51 12555.00
1300 10414.50 1069.95 970.00 1695.67 0.88 14151.00
1400 12094.62 1069.95 1097.00 1941.71 0.72 16204.00
1500 13705.61 1069.95 1190.00 2173.71 0.73 18140.00
1600 15426.57 1202.25 1333.00 2445.50 0.68 20408.00
1700 16703.45 1202.25 1451.00 2635.41 0.89 21993.00
1800 19152.22 1224.30 1536.00 2983.39 0.09 24896.00
1900 20936.39 1278.90 1621.00 3245.31 0.40 27082.00
2000 22413.08 1278.90 1707.00 3458.07 0.95 28858.00
Diameter Cost of pipe Conveyance Laying & CP & OH Sundries Total
charges Jointing charges @
charges 13.615% on
cost of pipe,
Conv, L&J
12 kg/cm2
350 2562.14 143.85 251.00 402.59 0.42 3360.00
400 2803.34 143.85 271.00 438.16 0.65 3657.00
450 2981.54 176.40 314.00 472.70 0.36 3945.00
500 3219.84 187.95 333.00 509.31 0.90 4251.00
600 3751.99 210.00 409.00 595.11 0.90 4967.00
700 4390.47 342.30 481.00 709.85 0.38 5924.00
800 5374.49 342.30 543.00 852.27 0.94 7113.00
900 6291.16 342.30 595.00 984.15 0.39 8213.00
1000 7367.34 551.25 688.00 1171.79 0.62 9779.00
1100 8334.61 551.25 772.00 1314.92 0.22 10973.00
1200 9342.61 1058.40 856.00 1532.64 0.35 12790.00
1300 10772.79 1069.95 970.00 1744.45 0.81 14558.00
1400 12819.47 1069.95 1097.00 2040.40 0.18 17027.00
1500 14982.31 1069.95 1190.00 2347.53 0.21 19590.00
1600 16956.39 1202.25 1333.00 2653.79 0.57 22146.00
1700 18303.73 1202.25 1451.00 2853.29 0.73 23811.00
1800 21032.32 1224.30 1536.00 3239.37 0.01 27032.00
1900 22133.83 1278.90 1621.00 3408.34 0.93 28443.00
2000 24606.93 1278.90 1707.00 3756.76 0.41 31350.00
Diameter Cost of pipe Conveyance Laying & CP & OH Sundries Total
charges Jointing charges @
charges 13.615% on
cost of pipe,
Conv, L&J
14 kg/cm2
350 2614.05 143.85 251.00 409.66 0.44 3419.00
400 2853.81 143.85 271.00 445.03 0.31 3714.00
450 3058.57 176.40 314.00 483.19 0.84 4033.00
500 3285.35 187.95 333.00 518.23 0.47 4325.00
600 3871.02 210.00 409.00 611.32 0.66 5102.00
700 4523.24 342.30 481.00 727.93 0.53 6075.00
800 5547.24 342.30 543.00 875.79 0.67 7309.00
900 6525.32 342.30 595.00 1016.04 0.34 8479.00
1000 7612.04 551.25 688.00 1205.10 0.61 10057.00
1100 8615.20 551.25 772.00 1353.12 0.43 11292.00
1200 10012.94 1058.40 856.00 1623.91 0.75 13552.00
1300 11846.33 1069.95 970.00 1890.62 0.10 15777.00
1400 13714.78 1069.95 1097.00 2162.30 0.97 18045.00
1500 15568.15 1069.95 1190.00 2427.30 0.60 20256.00
1600 17644.56 1202.25 1333.00 2747.48 0.71 22928.00
1700 20320.85 1202.25 1451.00 3127.92 0.98 26103.00
1800 21969.97 1224.30 1536.00 3367.03 0.70 28098.00
1900 24054.46 1278.90 1621.00 3669.84 0.80 30625.00
2000 27711.53 1278.90 1707.00 4179.46 0.11 34877.00
16 kg/cm2
350 2704.05 143.85 251.00 421.92 0.18 3521.00
400 2895.28 143.85 271.00 450.67 0.20 3761.00
450 3123.52 176.40 314.00 492.04 0.04 4106.00
500 3382.99 187.95 333.00 531.52 0.54 4436.00
600 3986.26 210.00 409.00 627.01 0.73 5233.00
700 4729.74 342.30 481.00 756.05 0.91 6310.00
800 5892.30 342.30 543.00 922.77 0.63 7701.00
900 7042.94 342.30 595.00 1086.51 0.25 9067.00
1000 8241.25 551.25 688.00 1290.77 0.73 10772.00
1100 9370.84 551.25 772.00 1456.00 0.91 12151.00
1200 10842.01 1058.40 856.00 1736.79 0.80 14494.00
1300 12345.88 1069.95 970.00 1958.63 0.54 16345.00
1400 14364.47 1069.95 1097.00 2250.75 0.83 18783.00
1500 17459.97 1069.95 1190.00 2684.87 0.21 22405.00
1600 19448.79 1202.25 1333.00 2993.13 0.83 24978.00
1700 21346.64 1202.25 1451.00 3267.59 0.52 27268.00
1800 24376.38 1224.30 1536.00 3694.66 0.66 30832.00
1900 26568.25 1278.90 1621.00 4012.09 0.76 33481.00
2000 28906.74 1278.90 1707.00 4342.18 0.18 36235.00
Cost of Machine End Pair (Socket+Spigot) for Providing MS Specials on PSC Pipe Lines excluding Cost of
MS Special including cost and Conveyance to site etc., complete
Diameter Cost including Contractor Total Sundries Total
Conveyance to profit &
site overhead
charges @14%
6 kg/cm2 on basic cost,
350 11000.00 conveyance
1497.65 12497.65 0.35 12498.00
400 12600.00 1715.49 14315.49 0.51 14316.00
450 14200.00 1933.33 16133.33 0.67 16134.00
500 15870.00 2160.70 18030.70 0.30 18031.00
600 19000.00 2586.85 21586.85 0.15 21587.00
700 22283.00 3033.83 25316.83 0.17 25317.00
800 25500.00 3471.83 28971.83 0.17 28972.00
900 28760.00 3915.67 32675.67 0.33 32676.00
1000 31700.00 4315.96 36015.96 0.04 36016.00
1100 34979.00 4762.39 39741.39 0.61 39742.00
1200 38200.00 5200.93 43400.93 0.07 43401.00
1300 41198.00 5609.11 46807.11 0.89 46808.00
1400 48582.00 6614.44 55196.44 0.56 55197.00
1500 57000.00 7760.55 64760.55 0.45 64761.00
1600 63481.00 8642.94 72123.94 0.06 72124.00
1700 71200.00 9693.88 80893.88 0.12 80894.00
1800 81400.00 11082.61 92482.61 0.39 92483.00
1900 94100.00 12811.72 106911.72 0.28 106912.00
2000 113200.00 15412.18 128612.18 0.82 128613.00
N.W:- C & C Kethaverunipadu L.I. Scheme on Krishna River in Chandralapadu
Mandal of Krishna District
COST OF RCC S/S PIPES PER METRE FOR THE YEAR 2017-18
Dia in mm NP-2 Class NP-3 Class P-1 Class P-2 Class P-3 Class
150 213.00 337.00 435.00 538.00
200 262.00 391.00 562.00 742.00
225 284.00 439.00 638.00 824.00
250 302.00 481.00 678.00 858.00
300 425.00 1074.00 644.00 972.00 1205.00
350 548.00 1313.00 803.00 1359.00 1747.00
400 602.00 1456.00 954.00 1807.00 2319.00
450 751.00 1605.00 1006.00 2142.00 2838.00
500 867.00 1836.00 1358.00 2306.00 3210.00
600 1214.00 2578.00 1860.00 3445.00 4430.00
700 1572.00 3300.00 2488.00 4518.00 5595.00
800 2026.00 4374.00 3109.00 5319.00 6726.00
900 2574.00 5500.00 3741.00 6220.00
1000 3148.00 6160.00 4763.00 7097.00
1100 3647.00 7278.00 5729.00
1200 4110.00 8597.00 6678.00
1400 5924.00 11383.00
1600 7333.00 14800.00
1800 8122.00 19657.00
LATEST COST OF RCC S/S PIPES PER METRE FOR THE YEAR 2017-18
400 mm 249.40
450 mm 249.40
500 mm 361.20
600 mm 406.35
700 mm 655.75
800 mm 655.75
900 mm 655.75
1000 mm 1038.45
1100 mm 1038.45
1200 mm 2031.75
1300 mm 2031.75
1400 mm 2031.75
1500 mm 2031.75
1600 mm 2031.75
1700 mm 2461.75
1800 mm 2461.75
1900 mm 2461.75
2000 mm 2597.20
DATA FOR PCCP PIPES
Diameter Cost of pipe Conveyance Laying & CP & OH Sundries Total
charges Jointing charges charges @
13.615% on
cost of pipe,
Conv, L&J
4 kg/cm2
400 4809.87 249.40 528.00 760.71 0.02 6348.00
450 5135.97 249.40 622.00 817.90 0.73 6826.00
500 5462.07 361.20 677.00 885.01 0.72 7386.00
600 6266.32 406.35 792.00 1016.31 0.02 8481.00
700 7136.70 655.75 903.00 1183.89 0.66 9880.00
800 8397.76 655.75 1036.00 1373.69 0.80 11464.00
900 9547.78 655.75 1167.00 1548.10 0.37 12919.00
1000 11480.20 1038.45 1279.00 1878.55 0.80 15677.00
1100 12746.37 1038.45 1450.00 2074.22 0.96 17310.00
1200 14174.56 2031.75 1582.00 2421.88 0.81 20211.00
1300 15520.20 2031.75 1694.00 2620.34 0.71 21867.00
1400 17766.79 2031.75 1865.00 2949.49 0.97 24614.00
1500 20874.21 2031.75 2069.00 3400.34 0.70 28376.00
1600 23747.16 2031.75 2240.00 3814.77 0.32 31834.00
1700 25498.07 2461.75 2522.00 4150.10 0.08 34632.00
1800 30202.00 2461.75 2674.00 4811.23 0.02 40149.00
1900 32423.10 2461.75 2916.00 5146.59 0.56 42948.00
2000 34227.05 2597.20 3105.00 5436.37 0.38 45366.00
Diameter Cost of pipe Conveyance Laying & CP & OH Sundries Total
charges Jointing charges charges @
13.615% on
cost of pipe,
Conv, L&J
6 kg/cm2
400 4809.87 249.40 528.00 760.71 0.02 6348.00
450 5135.97 249.40 622.00 817.90 0.73 6826.00
500 5462.15 361.20 677.00 885.02 0.63 7386.00
600 6348.04 406.35 792.00 1027.44 0.17 8574.00
700 7236.36 655.75 903.00 1197.45 0.44 9993.00
800 8507.15 655.75 1036.00 1388.58 0.52 11588.00
900 9696.42 655.75 1167.00 1568.33 0.50 13088.00
1000 11667.52 1038.45 1279.00 1904.05 0.98 15890.00
1100 12973.70 1038.45 1450.00 2105.17 0.68 17568.00
1200 14440.00 2031.75 1582.00 2458.02 0.23 20512.00
1300 16206.38 2031.75 1694.00 2713.76 0.11 22646.00
1400 18172.11 2031.75 1865.00 3004.68 0.46 25074.00
1500 21306.59 2031.75 2069.00 3459.21 0.45 28867.00
1600 24238.77 2031.75 2240.00 3881.71 0.77 32393.00
1700 26056.86 2461.75 2522.00 4226.18 0.21 35267.00
1800 30821.10 2461.75 2674.00 4895.53 0.62 40853.00
1900 33120.84 2461.75 2916.00 5241.58 0.83 43741.00
2000 35503.65 2597.20 3105.00 5610.18 0.97 46817.00
Diameter Cost of pipe Conveyance Laying & CP & OH Sundries Total
charges Jointing charges charges @
13.615% on
cost of pipe,
Conv, L&J
8 kg/cm2
400 4809.87 249.40 528.00 760.71 0.02 6348.00
450 5096.79 249.40 622.00 812.57 0.24 6781.00
500 5513.65 361.20 677.00 892.03 0.12 7444.00
600 6416.51 406.35 792.00 1036.76 0.38 8652.00
700 7324.98 655.75 903.00 1209.52 0.75 10094.00
800 8624.12 655.75 1036.00 1404.51 0.62 11721.00
900 9852.94 655.75 1167.00 1589.65 0.66 13266.00
1000 11853.92 1038.45 1279.00 1929.43 0.20 16101.00
1100 13199.06 1038.45 1450.00 2135.85 0.64 17824.00
1200 14714.61 2031.75 1582.00 2495.41 0.23 20824.00
1300 16530.53 2031.75 1694.00 2757.89 0.83 23015.00
1400 18586.54 2031.75 1865.00 3061.10 0.61 25545.00
1500 21739.00 2031.75 2069.00 3518.08 0.17 29358.00
1600 24729.33 2031.75 2240.00 3948.50 0.42 32950.00
1700 26614.69 2461.75 2522.00 4302.13 0.43 35901.00
1800 31904.54 2461.75 2674.00 5043.04 0.67 42084.00
1900 34331.57 2461.75 2916.00 5406.42 0.26 45116.00
2000 36357.03 2597.20 3105.00 5726.36 0.41 47786.00
Diameter Cost of pipe Conveyance Laying & CP & OH Sundries Total
charges Jointing charges charges @
13.615% on
cost of pipe,
Conv, L&J
10 kg/cm2
400 4831.09 249.40 528.00 763.60 0.91 6373.00
450 5196.83 249.40 622.00 826.19 0.58 6895.00
500 5572.14 361.20 677.00 900.00 0.66 7511.00
600 6485.98 406.35 792.00 1046.22 0.45 8731.00
700 7422.64 655.75 903.00 1222.82 0.79 10205.00
800 8742.09 655.75 1036.00 1420.57 0.59 11855.00
900 10000.67 655.75 1167.00 1609.76 0.82 13434.00
1000 12040.44 1038.45 1279.00 1954.83 0.28 16313.00
1100 13424.54 1038.45 1450.00 2166.55 0.46 18080.00
1200 14988.35 2031.75 1582.00 2532.68 0.22 21135.00
1300 16853.71 2031.75 1694.00 2801.89 0.65 23382.00
1400 19042.98 2031.75 1865.00 3123.24 0.03 26063.00
1500 22170.54 2031.75 2069.00 3576.84 0.87 29849.00
1600 25630.49 2031.75 2240.00 4071.19 0.57 33974.00
1700 27643.99 2461.75 2522.00 4442.27 0.99 37071.00
1800 32588.95 2461.75 2674.00 5136.22 0.08 42861.00
1900 35110.91 2461.75 2916.00 5512.53 0.81 46002.00
2000 37209.62 2597.20 3105.00 5842.44 0.74 48755.00
Diameter Cost of pipe Conveyance Laying & CP & OH Sundries Total
charges Jointing charges charges @
13.615% on
cost of pipe,
Conv, L&J
12 kg/cm2
400 4882.09 249.40 528.00 770.54 0.97 6431.00
450 5236.96 249.40 622.00 831.65 0.99 6941.00
500 5622.84 361.20 677.00 906.90 0.06 7568.00
600 6555.50 406.35 792.00 1055.69 0.46 8810.00
700 7511.30 655.75 903.00 1234.89 0.06 10305.00
800 8859.18 655.75 1036.00 1436.51 0.56 11988.00
900 10157.27 655.75 1167.00 1631.08 0.90 13612.00
1000 12236.96 1038.45 1279.00 1981.58 0.01 16536.00
1100 13660.15 1038.45 1450.00 2198.63 0.77 18348.00
1200 15264.08 2031.75 1582.00 2570.22 0.95 21449.00
1300 17178.02 2031.75 1694.00 2846.05 0.18 23750.00
1400 19888.85 2031.75 1865.00 3238.41 0.99 27025.00
1500 23002.56 2031.75 2069.00 3690.12 0.57 30794.00
1600 26180.87 2031.75 2240.00 4146.12 0.26 34599.00
1700 28250.80 2461.75 2522.00 4524.88 0.57 37760.00
1800 33283.65 2461.75 2674.00 5230.80 0.80 43651.00
1900 36674.79 2461.75 2916.00 5725.45 0.01 47778.00
2000 38926.53 2597.20 3105.00 6076.20 0.07 50705.00
Diameter Cost of pipe Conveyance Laying & CP & OH Sundries Total
charges Jointing charges charges @
13.615% on
cost of pipe,
Conv, L&J
14 kg/cm2
400 4912.01 249.40 528.00 774.61 0.98 6465.00
450 5296.82 249.40 622.00 839.80 0.98 7009.00
500 5681.94 361.20 677.00 914.95 0.91 7636.00
600 6624.06 406.35 792.00 1065.02 0.57 8888.00
700 7623.04 655.75 903.00 1250.10 0.11 10432.00
800 8988.31 655.75 1036.00 1454.09 0.85 12135.00
900 10316.03 655.75 1167.00 1652.69 0.53 13792.00
1000 12424.53 1038.45 1279.00 2007.12 0.90 16750.00
1100 13897.71 1038.45 1450.00 2230.98 0.86 18618.00
1200 15539.81 2031.75 1582.00 2607.76 0.68 21762.00
1300 17829.57 2031.75 1694.00 2934.76 0.92 24491.00
1400 20383.35 2031.75 1865.00 3305.74 0.16 27586.00
1500 23483.55 2031.75 2069.00 3755.60 0.10 31340.00
1600 26802.61 2031.75 2240.00 4230.77 0.87 35306.00
1700 29555.57 2461.75 2522.00 4702.53 0.15 39242.00
1800 34743.08 2461.75 2674.00 5429.50 0.67 45309.00
1900 37528.35 2461.75 2916.00 5841.67 0.23 48748.00
2000 39888.83 2597.20 3105.00 6207.22 0.75 51799.00
Diameter Cost of pipe Conveyance Laying & CP & OH Sundries Total
charges Jointing charges charges @
13.615% on
cost of pipe,
Conv, L&J
16 kg/cm2
400 4970.63 249.40 528.00 782.59 0.38 6531.00
450 5366.42 249.40 622.00 849.28 0.90 7088.00
500 5762.87 361.20 677.00 925.97 0.96 7728.00
600 6741.94 406.35 792.00 1081.07 0.64 9022.00
700 7770.97 655.75 903.00 1270.24 0.04 10600.00
800 9166.89 655.75 1036.00 1478.40 0.96 12338.00
900 10753.29 655.75 1167.00 1712.23 0.73 14289.00
1000 13006.48 1038.45 1279.00 2086.35 0.72 17411.00
1100 14602.84 1038.45 1450.00 2326.98 0.73 19419.00
1200 16389.56 2031.75 1582.00 2723.45 0.24 22727.00
1300 18481.22 2031.75 1694.00 3023.48 0.55 25231.00
1400 21170.40 2031.75 1865.00 3412.89 0.96 28481.00
1500 24106.21 2031.75 2069.00 3840.38 0.66 32048.00
1600 27851.79 2031.75 2240.00 4373.62 0.84 36498.00
1700 30224.12 2461.75 2522.00 4793.55 0.58 40002.00
1800 35490.64 2461.75 2674.00 5531.28 0.33 46158.00
1900 40966.41 2461.75 2916.00 6309.76 0.08 52654.00
2000 40806.34 2597.20 3105.00 6332.14 0.32 52841.00
Diameter Cost of pipe Conveyance Laying & CP & OH Sundries Total
charges Jointing charges charges @
13.615% on
cost of pipe,
Conv, L&J
18 kg/cm2
400 5010.59 249.40 528.00 788.03 0.98 6577.00
450 5414.54 249.40 622.00 855.83 0.23 7142.00
500 5830.05 361.20 677.00 935.11 0.64 7804.00
600 6840.52 406.35 792.00 1094.49 0.64 9134.00
700 7876.12 655.75 903.00 1284.56 0.57 10720.00
800 9325.02 655.75 1036.00 1499.93 0.30 12517.00
900 10958.67 655.75 1167.00 1740.19 0.39 14522.00
1000 13283.09 1038.45 1279.00 2124.01 0.45 17725.00
1100 14908.80 1038.45 1450.00 2368.64 0.11 19766.00
1200 16756.44 2031.75 1582.00 2773.40 0.41 23144.00
1300 18971.13 2031.75 1694.00 3090.18 0.94 25788.00
1400 21399.45 2031.75 1865.00 3444.08 0.72 28741.00
1500 25072.17 2031.75 2069.00 3971.89 0.19 33145.00
1600 28458.34 2031.75 2240.00 4456.20 0.71 37187.00
1700 30922.88 2461.75 2522.00 4888.69 0.68 40796.00
1800 36271.61 2461.75 2674.00 5637.61 0.03 47045.00
1900 41939.67 2461.75 2916.00 6442.27 0.31 53760.00
2000 41773.30 2597.20 3105.00 6463.79 0.71 53940.00
Diameter Cost of pipe Conveyance Laying & CP & OH Sundries Total
charges Jointing charges charges @
13.615% on
cost of pipe,
Conv, L&J
20 kg/cm2
400 5048.60 249.40 528.00 793.21 0.79 6620.00
450 5453.71 249.40 622.00 861.16 0.73 7187.00
500 5889.20 361.20 677.00 943.17 0.43 7871.00
600 6898.16 406.35 792.00 1102.34 0.15 9199.00
700 8005.45 655.75 903.00 1302.17 0.63 10867.00
800 9469.09 655.75 1036.00 1519.55 0.61 12681.00
900 11207.89 655.75 1167.00 1774.12 0.24 14805.00
1000 13569.95 1038.45 1279.00 2163.07 0.53 18051.00
1100 15244.41 1038.45 1450.00 2414.33 0.81 20148.00
1200 17135.57 2031.75 1582.00 2825.02 0.66 23575.00
1300 19490.00 2031.75 1694.00 3160.82 0.43 26377.00
1400 22259.46 2031.75 1865.00 3561.17 0.62 29718.00
1500 25611.57 2031.75 2069.00 4045.33 0.35 33758.00
1600 29077.09 2031.75 2240.00 4540.44 0.72 37890.00
1700 31622.60 2461.75 2522.00 4983.95 0.70 41591.00
1800 37052.78 2461.75 2674.00 5743.97 0.50 47933.00
1900 42915.13 2461.75 2916.00 6575.08 0.04 54868.00
2000 42747.51 2597.20 3105.00 6596.43 0.86 55047.00
N.W:- C & C Kethaverunipadu L.I. Scheme on Krishna River in Chandralapadu Mandal of Krishna District
COST OF PRESTRESSED (CYLINDER) CONRETE PIPES PER METRE FOR THE YEAR 2017-18
Dia in mm 4 Kg/cm2 6 Kg/cm2 8 Kg/cm2 10 Kg/cm2 12 Kg/cm2 14 Kg/cm2 16 Kg/cm2 18 Kg/cm2
R 2017-18
20 Kg/cm2
4955.00
5348.00
5770.00
6752.00
7828.00
9259.00
10946.00
13250.00
14876.00
16715.00
19001.00
21687.00
25059.00
28454.00
30928.00
36238.00
42010.00
41760.00
20 Kg/cm2
5048.60
5453.71
5889.20
6898.16
8005.45
9469.09
11207.89
13569.95
15244.41
17135.57
19490.00
22259.46
25611.57
29077.09
31622.60
37052.78
42915.13
42747.51
MATERIALS
Gelatin 80% 57 kg
Detonator Electric 9 each
Ordinary Detonator 5 each
Explosive small dia (kelvex-220) 54 kg
Binding wire 55 kg
Coarse aggregate 10-4.75 mm 860 cum
Coarse aggregate 20-10 mm 1170 cum
Coarse aggregate 40-20 mm 1122 cum
Coarse aggregate 40 mm nominal size 808 cum
Coarse aggregate 20 mm nominal size 1303 cum
Coarse aggregate 10 mm nominal size 894 cum
Empty cement bag 5.00 each
Sand unscreened for concrete & Filtering items 95 cum
Sand unscreened for filling 95 cum
Sand screened for plastering 170 cum
GI pipe 100 mm 'B' class 622 m
Hemp yarn 61 kg
MS bolts/nuts/washers 68 kg
Murrum 185 cum
Super plasticizer (conplast RP-264) 43 kg
Tar felt joint filler board 12 mm 322 sqm
Tar felt joint filler board 20 mm 489 sqm
Uncoursed Rubble stone at quarry 303 cum
Rough Stone for Revetment 225 mm 138 cum
Welding electrodes 4 mm dia 11 each
Diesel 61.73 litre
Lubricants 220 litre
Petrol 71.68 litre
Structural steel fabrication 24 kg
Sand for filling 95 cum
Gravel / Quarry spall 110 cum
Barbed wire 68 kg
Earth cost or compensation for earth taken from 55 cum
private land
Earth cost or compensation for earth taken from 80.61 cum
private land with 1 km lead excluding CP & OH
Rough stone for RR Masonry 240 cum
Sand bags (cost of sand and empty bag) 8.5 each
Selected earth 55 cum
Water Charges (Urban) 103 kilo litre
Water Charges (Rural) 77 kilo litre
Chain link mesh 8 gauge (4 mm) 50x50 mm 394 sqm
Rolling shutter 2360 sqm
Water based Cement primer of interior Grade-1 120 kg
Water based Cement primer of Exterior Grade-2 153 kg
Impervious water proofing compound 0 kg Deleted in SSR
2015-16
Red oxide primer paint for iron works Grade-1 104 litre
Dry powder distemper 34 kg
Oil bound washable distemper 66 kg
Water proof cement paint 39 kg
Anti corrosive bitumen paint 415 litre
Synthetic enamel paint 201 litre
Aldrops 300mm long (MS Powder coated) 149 each
MS Hold fasts100mm long 25 each approx local
rate
MS power coated Tower bolts100 mm long 21 each
MS power coated butt Hinges100 mm 19 each
MS power coated door stoppers 41 each
MS power coated door handles 125 mm long 28 each
Anti corrosion CRPPC (Corrosion Resistant) 293 litre BMT-H.07
inhibitive admixture
Prepainted steel windows double shutter 3-0" x 5684 sqm BMT-P.02
4'0"
GI pipe 50mm dia light grade 404 RM
GI bolts/Nuts/Washers 85 Kg
Rubber packing 93 Kg
Bailing out water
EWE/Concrete 0 to 1 m 220 cum
EWE/Concrete 1 to 2 m 260 cum
EWE/Concrete 2 to 3 m 303 cum
Labour charges for fabricating Doors & 24 kg
Windows
Labour charges for fixing Doors & Windows in 4 kg
position
Fabrication charges for trusses, beams and 21 kg
girders
Labour charges for fixing girders in position 19 kg
Lead charges for Earth for 1 km excluding 25.61 cum
contractors profit and OH
Acetylene Gas 284 cum
Oxygen Gas 36 cum
Fabrication charges for structural steel 24 kg
Anti corrosion CRPPC (Corrosion Resistant) 350 litre
inhibitive admixture
Fuse Coil 7 RM
Delifting charges
0 to 3 m 0 cum
3 to 4m 45.00 cum
4 to 5 m 90.00 cum
5 to 6 m 135.00 cum
6 to 7 m 180.00 cum
7 to 8 m 225.00 cum
8 to 9 m 270.00 cum
9 to 10 m 315.00 cum
10 to 11 m 360.00 cum
11 to 12 m 405.00 cum
12 to 13 m 450.00 cum
13 to 14 m 495.00 cum
14 to 15 m 540.00 cum
15 to 16 m 585.00 cum
16 to 17 m 630.00 cum
17 to 18 m 675.00 cum
18 to 19 m 720.00 cum
19 to 20 m 765.00 cum
20 to 21 m 810.00 cum
21 to 22 m 855.00 cum
22 to 23 m 900.00 cum
23 to 24 m 945.00 cum
24 to 25 m 990.00 cum
25 to 26 m 1035.00 cum
LABOUR CHARGES
Mazdoor 420 day
Blaster/Plumber class I/ Pipe fitter 625 day
Welder/ Gas cutter 465 day
Black smith 1st class 500 day
Fitter Cl-I 500 day
Strucural steel fabricator 580 day
Mason Cl-1/ Brick layer Cl-1 500 day ***
Well sinker 480 day ***
Driller 535 day ***
Bar bender 625 day ***
Painter 1st class 580 day
Crowbar man / Mason Class II / Fitter Cl-II 460 day
/Erector shuttering / Carpenter Cl II
Painter 2nd class / Plumber 2nd class 460 day
Cartman with bullock cart / Bullock drawn roller 455 day
for rolling
Loading & Unloading charges for earth by 26.27 cum
Manual means (Idle hire charges of trucks are
not added)
Work Inspector 475 day
Helper Blasting 420 day
Crowbarman / Jumper man 420 day
Stone breaker / Hammer man 420 day
MACHINERY CHARGES
Hire Fuel Crew charges Total
charges charges
Hydraulic Excavator 1 cum capacity ( Shovel 1324.90 933.70 248.30 2506.90
0.85 cum 110 HP )
Air compressor 210 cfm/250 cfm (7cmm) 187.30 763.90 220.90 1172.10
(diesel)
Air compressor 210 cfm/250 cfm (8.50 cmm) 213.90 954.90 220.90 1389.70
(diesel)
Jack hammer 15.40 0.00 345.20 360.60
Tipper 5 cum 346.90 320.80 186.20 853.90
Shovel 0.50 cum 778.70 509.30 248.30 1536.30
5 HP pump (diesel) 7.90 84.90 116.10 208.90
Stationery derrick crane 66.80 0.00 0.00 66.80
Diesel Generating set 30 KVA 51.10 679.00 138.10 868.20
Set of helmets & Air circulating pipes/valves 0.00
Concrete Mixer 300/200 (diesel) 41.50 84.90 230.10 356.50
Winch 35HP (Electric) 100.40 138.80 276.10 515.30
Needle Vibrator 40 mm (petrol) 5.90 19.70 165.60 191.20
Upright Drilling Machine 17.40 28.30 208.70 254.40
Concrete Mixer 600/400 (diesel) 72.00 169.80 230.10 471.90
Water Tanker 8000 litres 342.60 320.80 186.20 849.60
Concrete Hand Mixer 45/30 Litres 4.30 0.00 0.00 4.30
Bending Machine 3000x12 mm 36.00 85.00 138.10 259.10
Welding set 13.50 68.00 0.00 81.50
Air compressor 8.5cmm (diesel) 213.90 954.90 220.90 1389.70
Angle Dozer 90 HP 1331.80 653.10 248.30 2233.20
5 HP pump (electric) 2.30 28.30 87.00 117.60
Vibratory Pad Foot Roller 8T 1042.00 1103.40 276.10 2421.50
Tractor with 2 T Roller 345.00
Dumper 4.5 cum 450.90 427.80 238.40 1117.10
Air compressor 8.5 cmm ( electric) 132.60 318.70 172.60 623.90
CENTERING & SCOFFOLDING CHARGES
Material Labour Total
charges charges
Footings 277.00 473.00 750.00
Bed blocks, Bands 61.00 244.00 305.00
Pedestals, pile caps 315.00 753.00 1068.00
Plinth Beams 1335.00 1141.00 2476.00
Columns for 1st floor 355.00 2495.00 2850.00
Columns for 2nd floor 355.00 2722.00 3077.00
Columns for 3rd floor 355.00 1606.00 1961.00
Columns for 4th floor 355.00 1739.00 2094.00
Columns for 5th floor 355.00 1873.00 2228.00
Columns for 6th floor 355.00 2007.00 2362.00
Columns for 7th floor 355.00 2141.00 2496.00
Columns for 8th floor 355.00 2275.00 2630.00
Columns for 9th floor 355.00 2408.00 2763.00
Columns for 10th floor 355.00 2542.00 2897.00
Columns for 11th floor 355.00 2676.00 3031.00
Columns for 12th floor 355.00 2810.00 3165.00
Columns for 13th floor 355.00 2944.00 3299.00
Columns for 14th floor 355.00 3077.00 3432.00
Columns for 15th floor 355.00 3211.00 3566.00
Scaffolding Charges
Brick Masonry/ Stone masonry 1st floor 9.93 61.83 71.76
Brick Masonry/ Stone masonry 2nd floor 9.93 87.78 97.71
Brick Masonry/ Stone masonry 3rd floor 9.93 113.74 123.67
Plastering 1st floor 0.99 6.18 7.17
Plastering 2nd floor 0.99 8.78 9.77
Plastering 3rd floor 0.99 11.37 12.36
Sundries 30
Seigniorage charges for earth excluding 26.4 cum
contract profit
Laying of sand bags including empty cement 8.50 bag
bag, sand, thread, stiching charges and CP &
OH
Centering charges for RCC Vertical walls of 920 1 Sqm of
plane surface centering
area
Centering charges for RCC Vertical walls of 1171 1 Sqm of
circular faces centering
area
Common burnt clay bricks 23cm x11cm x7cm 4628 1000 Nos
Brick bat 675.00 BMT-H.05
Lead charges for earth including OH&CP 29.10 1 cum
Excavation of trenches for Infiltration galleries, syphon lines and connecting mains in all soils under
water
0 to 1m deep under water 11671 per 10 cum
1 to 2m deep under water 16717 per 10 cum
2 to 5m deep under water 25092 per 10 cum
DATA FOR WELL SINKING
Index-code Sl. Description Unit Quantity Rate
No
Well sinking in sandy and other loose soils under water either by manual labour, divers or
dredgers weighting the top of staining to assist sinking etc., including dewatering and
PHE-
other incidental charges such as hire charges for mechanical equipment etc., complete
WSNP-28
upto 4.0 m dia (For non perennial rivers)
(a) Labour
(a) Labour
b) Machinery
(a) Labour
b) Machinery
(a) Labour
b) Machinery
(a) Labour
b) Machinery
c) Total
5m dia II/4x5x5/II/4x4x4 =
6m dia II/4x6x6/II/4x4x4 =
7m dia II/4x7x7/II/4x4x4 =
8m dia II/4x8x8/II/4x4x4 =
9m dia II/4x9x9/II/4x4x4 =
44100.00
0.00
6004.22
50104.22
25052.11
29400.00
16800.00
46200.00
0.00
46200.00
1068.80
10488.80
2861.60
4321.10
18740.30
8841.62
73781.92
Amount
36890.96
23520.00
16800.00
40320.00
0.00
40320.00
3740.80
10488.80
2861.60
6481.65
23572.85
8699.01
72591.86
36295.93
23520.00
16800.00
40320.00
0.00
40320.00
3740.80
Amount
10488.80
2861.60
8642.20
25733.40
8993.17
75046.57
37523.29
26880.00
19200.00
46080.00
0.00
46080.00
4275.20
11987.20
3270.40
8642.20
28175.00
10109.82
84364.82
42182.41
Amount
1.5625
2.2500
3.0625
4.0000
5.0625
6.2500
7.5625
9.0000
8 m internal dia
100208.44
147563.84
145183.72
150093.16
168729.64
12 m internal
dia
225468.99
332018.64
326663.37
337709.61
379641.69
DATA FOR LAYING JOINTING & TESTING OF RCC & PSC PIPES
Index- S No Description Unit Quantity Rate Rs.
code
PHE- 2A Sub Analysis : (Basic Data)
LCIF-2A OBSERVED DATA FOR TESTING OF 450 MM DIA PSC MAIN : Pumping main to
Hydralic field test pressure including transportation of Water with minimum lead
of 500 M
(Length = 500 Mts) taking out put / 500 Mts. Unit = 1 Rmt.
Labour
Fitters (2 x 3 days)
Machinery
Hire charges for Hydralic field test pressure days 3.000 1200.00
testing including transportation of water @
Rs. 1200/- (1000+200) / day
Materials
Specials Ls 30.00
a) Labour
b) Material
c) Testing
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 9.60
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 10.80
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 12.00
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 14.40
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 16.80
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 19.20
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 21.60
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 24.00
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 28.80
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
Total
(b) Material
Add for Water charges at 1% on Labour & Lt
Testing
a) Labour
b) Material
c) Testing
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 16.80
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 19.20
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 21.60
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 24.00
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
a) Labour
b) Material
c) Testing
Testing of Pipelines with required pressure as rm 100.000 28.80
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
Unit= 1 rmt
Taking out put 100 rmt
iii 150 mm dia
a) Labour
Mason 1st class day 1.170 500.00
Mason 2nd class day 2.730 460.00
Man mazdoor day 7.800 420.00
Woman mazdoor(water carrier) day 1.600 420.00
b) Material
Rubber rings conforming BIS 5382/1985 each 50.000 57.00
c) Testing
Testing of Pipelines with required pressure as rm 100.000 7.20
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour &
Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit 0%
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
Index- S No Description Unit Quantity Rate Rs.
code
iv 200 mm dia
a) Labour
Mason 1st class day 1.170 500.00
Mason 2nd class day 2.730 460.00
Man mazdoor day 7.800 420.00
Woman mazdoor(water carrier) day 1.600 420.00
b) Material
Rubber rings conforming BIS 5382/1985 each 50.000 67.00
c) Testing
Testing of Pipelines with required pressure as rm 100.000 9.60
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour &
Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit 0%
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
Index- S No Description Unit Quantity Rate Rs.
code
v 225 mm dia
a) Labour
Mason 1st class day 1.620 500.00
Mason 2nd class day 3.780 460.00
Man mazdoor day 10.500 420.00
Woman mazdoor(water carrier) day 2.300 420.00
b) Material
Rubber rings conforming BIS 5382/1985 each 50.000 75.00
c) Testing
Testing of Pipelines with required pressure as rm 100.000 10.80
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour &
Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit 0%
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
Index- S No Description Unit Quantity Rate Rs.
code
vi 250 mm dia
a) Labour
Mason 1st class day 1.620 500.00
Mason 2nd class day 3.780 460.00
Man mazdoor day 10.500 420.00
Woman mazdoor(water carrier) day 2.300 420.00
b) Material
Rubber rings conforming BIS 5382/1985 each 50.000 85.00
c) Testing
Testing of Pipelines with required pressure as rm 100.000 12.00
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour &
Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit 0%
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
Index- S No Description Unit Quantity Rate Rs.
code
vii 300 mm dia
a) Labour
Mason 1st class day 1.750 500.00
Mason 2nd class day 4.140 460.00
Man mazdoor day 11.600 420.00
Woman mazdoor(water carrier) day 2.300 420.00
b) Material
Rubber rings conforming BIS 5382/1985 each 40.000 106.00
c) Testing
Testing of Pipelines with required pressure as rm 100.000 14.40
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour &
Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit 0%
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
Index- S No Description Unit Quantity Rate Rs.
code
viii 350 mm dia
a) Labour
Mason 1st class day 1.900 500.00
Mason 2nd class day 4.500 460.00
Man mazdoor day 12.700 420.00
Woman mazdoor(water carrier) day 2.400 420.00
b) Material
Rubber rings conforming BIS 5382/1985 each 40.000 132.00
c) Testing
Testing of Pipelines with required pressure as rm 100.000 16.80
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour &
Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit 0%
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
Index- S No Description Unit Quantity Rate Rs.
code
ix 400 mm dia
a) Labour
Mason 1st class day 2.100 500.00
Mason 2nd class day 4.900 460.00
Man mazdoor day 13.900 420.00
Woman mazdoor(water carrier) day 2.900 420.00
b) Material
Rubber rings conforming BIS 5382/1985 each 40.000 175.00
c) Testing
Testing of Pipelines with required pressure as rm 100.000 19.20
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour &
Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit 0%
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
Index- S No Description Unit Quantity Rate Rs.
code
x 450 mm dia
a) Labour
Mason 1st class day 2.250 500.00
Mason 2nd class day 5.250 460.00
Man mazdoor day 15.000 420.00
Woman mazdoor(water carrier) day 3.300 420.00
b) Material
Rubber rings conforming BIS 5382/1985 each 40.000 200.00
c) Testing
Testing of Pipelines with required pressure as rm 100.000 21.60
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour &
Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit 0%
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
Index- S No Description Unit Quantity Rate Rs.
code
xi 500 mm dia
a) Labour
Mason 1st class day 2.430 500.00
Mason 2nd class day 5.670 460.00
Man mazdoor day 16.200 420.00
Woman mazdoor(water carrier) day 3.300 420.00
b) Material
Rubber rings conforming BIS 5382/1985 each 40.000 227.00
c) Testing
Testing of Pipelines with required pressure as rm 100.000 24.00
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour &
Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit 0%
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
Index- S No Description Unit Quantity Rate Rs.
code
xii 600 mm dia
a) Labour
Mason 1st class day 2.750 500.00
Mason 2nd class day 6.450 460.00
Man mazdoor day 16.300 420.00
Woman mazdoor(water carrier) day 3.300 420.00
b) Material
Rubber rings conforming BIS 5382/1985 each 40.000 280.00
c) Testing
Testing of Pipelines with required pressure as rm 100.000 28.80
per relevant IS Specification including filling
with water with a water lead upto 500 M,
including hire charges of testing equipment,
labour and Materials needed for testing (as
per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour &
Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit 0%
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
SC PIPES
Amt Rs.
t.
1500.00
1380.00
3600.00
62.50
438.00
30.00
6.00
3703.80
10720.30
21.44
0.48
585.00
1255.80
3276.00
672.00
5788.80
2850.00
720.00
9358.80
65.09
9423.89
0.00
9423.89
94.24
Amt Rs.
585.00
1255.80
3276.00
672.00
5788.80
3350.00
960.00
10098.80
67.49
10166.29
0.00
10166.29
101.66
Amt Rs.
810.00
1738.80
4410.00
966.00
7924.80
3650.00
1080.00
12654.80
90.05
12744.85
0.00
12744.85
127.45
Amt Rs.
810.00
1738.80
4410.00
966.00
7924.80
4100.00
1200.00
13224.80
91.25
13316.05
0.00
13316.05
133.16
Amt Rs.
875.00
1904.40
4872.00
966.00
8617.40
4000.00
1440.00
14057.40
100.57
14157.97
0.00
14157.97
141.58
Amt Rs.
950.00
2070.00
5334.00
1008.00
9362.00
4640.00
1680.00
15682.00
110.42
15792.42
0.00
15792.42
157.92
Amt Rs.
1050.00
2254.00
5838.00
1218.00
10360.00
5120.00
1920.00
17400.00
122.80
17522.80
0.00
17522.80
175.23
Amt Rs.
1125.00
2415.00
6300.00
1386.00
11226.00
5800.00
2160.00
19186.00
133.86
19319.86
0.00
19319.86
193.20
Amt Rs.
1215.00
2608.20
6804.00
1386.00
12013.20
7560.00
2400.00
21973.20
144.13
22117.33
0.00
22117.33
221.17
Amt Rs.
1375.00
2967.00
6846.00
1386.00
12574.00
9920.00
2880.00
25374.00
154.54
25528.54
0.00
25528.54
255.29
Amt Rs.
2940.00
1000.00
1680.00
0.00
3840.00
9460.00
94.60
0.00
9554.60
19.11
1.19
Amt Rs.
875.00
1904.40
4872.00
966.00
8617.40
5160.00
1440.00
15217.40
100.57
15317.97
0.00
15317.97
153.18
Amt Rs.
950.00
2070.00
5334.00
1008.00
9362.00
6160.00
1680.00
17202.00
110.42
17312.42
0.00
17312.42
173.12
Amt Rs.
1050.00
2254.00
5838.00
1218.00
10360.00
7000.00
1920.00
19280.00
122.80
19402.80
0.00
19402.80
194.03
Amt Rs.
1125.00
2415.00
6300.00
1386.00
11226.00
7920.00
2160.00
21306.00
133.86
21439.86
0.00
21439.86
214.40
Amt Rs.
1215.00
2608.20
6804.00
1386.00
12013.20
9080.00
2400.00
23493.20
144.13
23637.33
0.00
23637.33
236.37
Amt Rs.
1375.00
2967.00
6846.00
1386.00
12574.00
13160.00
2880.00
28614.00
154.54
28768.54
0.00
28768.54
287.69
Amt Rs.
585.00
1255.80
3276.00
672.00
5788.80
2850.00
720.00
9358.80
65.09
9423.89
0.00
9423.89
94.24
Amt Rs.
585.00
1255.80
3276.00
672.00
5788.80
3350.00
960.00
10098.80
67.49
10166.29
0.00
10166.29
101.66
Amt Rs.
810.00
1738.80
4410.00
966.00
7924.80
3750.00
1080.00
12754.80
90.05
12844.85
0.00
12844.85
128.45
Amt Rs.
810.00
1738.80
4410.00
966.00
7924.80
4250.00
1200.00
13374.80
91.25
13466.05
0.00
13466.05
134.66
Amt Rs.
875.00
1904.40
4872.00
966.00
8617.40
4240.00
1440.00
14297.40
100.57
14397.97
0.00
14397.97
143.98
Amt Rs.
950.00
2070.00
5334.00
1008.00
9362.00
5280.00
1680.00
16322.00
110.42
16432.42
0.00
16432.42
164.32
Amt Rs.
1050.00
2254.00
5838.00
1218.00
10360.00
7000.00
1920.00
19280.00
122.80
19402.80
0.00
19402.80
194.03
Amt Rs.
1125.00
2415.00
6300.00
1386.00
11226.00
8000.00
2160.00
21386.00
133.86
21519.86
0.00
21519.86
215.20
Amt Rs.
1215.00
2608.20
6804.00
1386.00
12013.20
9080.00
2400.00
23493.20
144.13
23637.33
0.00
23637.33
236.37
Amt Rs.
1375.00
2967.00
6846.00
1386.00
12574.00
11200.00
2880.00
26654.00
154.54
26808.54
0.00
26808.54
268.09