1.0 Balmer Lawrie & Co. Ltd. invite ONLINE BIDS from experienced, competent and resourceful
Contractors with sound technical and financial capabilities for Supply, Installation, Testing &
Commissioning of Fire Protection System at proposed Central Warehouse at AMTZ, Andhra
Pradesh.
Earnest Money deposit (EMD) is exempted for agencies registered under NSIC or coming
under the definition of Micro and Small Industries and holding valid registration certificates
covering the tendered items/services. Declaration of Udyog Aadhar Memorandum (UAM) by
the MSE parties on Central Public Procurement Portal (CPPP) shall be mandatory. However,
attested/Notarized copy of valid NSIC certificate or “Micro and Small” industry certificate
must be submitted in this regard.
4.1 For the successful bidder, the EMD will be refunded only after completion of the work. No
interest shall be payable towards EMD amount.
4.2 For the unsuccessful bidders, the EMD will be refunded only after the successful bidder has
accepted the work order and the acknowledgment of the same has been received by the
owner.
5.2 The tenderer should have successfully executed Fire Protection Systems during past seven
years ending 31st March, 2018.
Copy of work orders and completion certificates / commissioning report from the owner/
consultant should be enclosed as supportive documents. Order copy issued by the owner to
the consultant shall also be furnished if the completion certificate is issued by the consultant
on behalf of the owner.
5.3 Tenderer should have PAN, GSTIN registration, PF registration, ESI registration (if applicable).
Copy of the same shall be submitted along with techno commercial offer.
For registration and online bid submission tenderer may contact the following officials at the
HELP DESK of M/s C1 India on browsing to the website https://balmerlawrie.eproc.in during
business hours (10:00 a.m. to 06:30 p.m.) from Monday to Friday (Excluding holidays of the
Company):
Escalation Level 1
Mr.Tuhin Ghosh [email protected] +91-8981165071
om
The tenderer shall authenticate the bid with his Digital Certificate for submitting the bid
electronically on e-procurement platform and the bids not authenticated by digital certificate
of the tenderer will not be accepted on the e-procurement platform.
All the tenderers who do not have digital certificates need to obtain Digital Certificate (with
both Signing and Encryption Components). They may contact help desk of M/s C1 India.
The tenderer shall furnish the original Demand Draft for Tender fee and Demand Draft /BG
for EMD to the tender inviting authority so as to reach on or before the due date and time of
the Tender either personally or through courier or by post and the receipt of the same within
the stipulated time shall be the responsibility of tenderer. The Company shall not take any
responsibility for any delay or non-receipt. If any of the documents furnished by the tenderer
is found to be false/fabricated/bogus, the tenderer is liable for black listing, forfeiture of the
EMD, cancellation of work and criminal prosecution. The tenderer is requested to get a
confirmed acknowledgement from the Tender Inviting Authority as a proof of Hardcopies
submission to avoid any discrepancy.
The bidders found defaulting in submission of hard copies of original Demand Draft for Tender
fees and Demand Draft / BG for EMD and other documents to the Tender Inviting Authority
on or before the stipulated time in the Tender will not be permitted to participate in the
Tender.
The bidder is requested to read all the terms and conditions mentioned in the tender
Document and seek clarification if any from if in doubt from Sri A Boral.
The bidder should keep track of any Addendum / Corrigendum / Amendment issued by the
Tender Inviting Authority on time-to-time basis in Company’s website (www.
Balmerlawrie.com) and e-procurement site (https://balmerlawrie.eproc.in). No separate
newspaper advertisement shall be published for such Addendum / Corrigendum /
Amendment etc. The Company calling for tenders shall not be responsible for any
claims/problems arising out of this.
The tenderer should complete all the processes and steps required for bid submission. The
successful bid submission can be ascertained once acknowledgement is given by the system
through bid submission number after completing all the process and steps. M/s C1 India is
not responsible for incomplete bid submission by users. Tenderers may also note that the
incomplete bids will not be saved by the system and are not available for the Tender Inviting
Authority for processing.
Neither the Company (Balmer Lawrie & Co. Ltd.) nor the service provider (M/s C1 India) is
responsible for any failure or non-submission of bids due to failure of internet or other
connectivity problems or reasons thereof.
The hardcopies of the Bid Documents as explained above and also defined in clause no. 2.0 of
Condition of Contract under sealed envelope should reach the office of Head (Technical),
Balmer Lawrie & Co Ltd, Engineering & Projects Department, 21 Netaji Subhas Road, Kolkata
700001, on or before the due date of submission of tender. The Bidders who are submitting
the Bids in person are requested to drop the same in our tender box located at the entrance
of 2nd floor at the above address.
12.0 NON-CONFORMANCE
Tenders not conforming to the above mentioned requirements are liable to be rejected.
(b) The rates should be quoted in the same units as mentioned in the tender schedule of
quantities.
(c) All entries in the tender documents should be in ink / type. Corrections if any should
be attested by full signature of the tenderer.
(d) Every page of the tender document including annexure / enclosures shall be stamped
and signed by the tenderer or his authorized representative thereby indicating that
each and every page has been read and the points noted.
17.2 Bids of any tenderer may be rejected if a conflict of interest between the bidder and Company
(Balmer Lawrie) is detected at any stage.
17.3 All the bids will be evaluated based on Pre-qualification and other criteria as mentioned in
this NIT. Tenders of those bidders who are not meeting the pre-qualification criteria will not
be considered for commercial evaluation.
17.5 Hard copy of Price Bid should not be submitted in the envelope containing Un-priced
documents failing which the bid will be summarily rejected.
17.6 Clarifications /exceptions / deviations to the tender terms & conditions and specifications:
Balmer Lawrie & Co. Ltd. expects Tenderers to confirm compliance to tender terms &
conditions and specifications, failing which the Tenderers are liable to be rejected. Hence all
Tenderers in their own interest are advised to submit their bids in all respects confirming to
all terms & conditions of the bid document.
Bids shall be evaluated based on the information / documents available in the bid. Hence
Tenderers are advised to ensure that they submit appropriate and relevant supporting
documentation alongwith their proposal in the first instance itself. Bids not complying the
requirements of bid documents will be rejected without any further opportunity.
For any Technical clarifications / queries Tenderers are requested to contact from Sri G C Saha, AVP
(E&P), Mob 9748773900, e-mail:[email protected]. (from 10.00AM to 05.00PM, Monday
- Friday).
(A K Basak)
Head (Technical)
CONDITIONS OF CONTRACT
1.0 DEFINITIONS
The following expressions hereunder and elsewhere in the contract documents used shall
have the following meanings respectively assigned to them namely,
1.1 The “Owner/Client” shall mean M/s Balmer Lawrie & Co. Ltd; a company incorporated in India
and having its Registered Office at 21, Netaji Subhas Road, Kolkata - 700 001, and shall include
its successors and assigns.
1.2 The "Project" shall mean “Supply, Installation, Testing & Commissioning of Fire Protection
System” at AMTZ, Visakhapatnam.
1.3 The 'Engineer-In-Charge'/'Engineer' shall mean the Engineer /Officer authorised by the
‘Owner’ for the purpose of the contract for overall Supervision and Co-ordination of site
activity and certification of billing.
(i) Hard copy of Un-priced Tender Document duly filled in, stamped and signed by the
Tenderer as prescribed in different clauses of Tender documents. No hard copy of
priced bid shall be submitted. Priced bid shall only be submitted online. The price bid
file in pdf format shall be downloaded from the website, bidder to fill in their item-
wise rates & amounts on hard copy, stamp, sign, scan and upload the same.
(ii) Earnest money amounting to and in the manner specified along with the Un-priced
bid.
(iii) The Power of Attorney or authorisation, or any other document consisting of adequate
proof of the ability of the signatory to bind the bidder, in original, when the power of
attorney is a special “Power of Attorney” relating to the specific tender of Balmer
Lawrie & Co Ltd only. A notarized true copy of the “Power of Attorney” shall also be
accepted in lieu of the original, if the power of attorney is a general “Power of
Attorney”. However, photocopy of such notarized true copy shall not be accepted.
(iv) Similar work done in past Seven years by the tenderer with copy of work orders and
completion/commissioning certificate from the client/ consultant appointed by the
client.
(a) The tenderer should quote for all items in the Schedule of Rates. Where discrepancy
exists between the two, the rates expressed in words will prevail. Similarly if there is
any discrepancy between unit rate and total amount, the unit rate will prevail.
(b) The rates should be quoted in the same units as mentioned in the tender schedule of
quantities.
(c) All entries in the tender documents should be in ink / type. Corrections if any should
be attested by full signature of the tenderer.
(d) Every page of the tender document including annexure / enclosures shall be stamped
and signed by the tenderer or his authorised representative thereby indicating that
each and every page has been read and the points noted.
The Owner reserves the right to accept or reject any or every tender without assigning any
reason whatsoever / or to negotiate with the tenderer(s) in the manner the Owner considers
suitable. The work may be split up if considered expedient.
(i) On acceptance of the Bid, Bidder shall within fifteen (15) days, deposit with Owner an
Initial Security Deposit of 5% of the Contract value (i.e. order value excluding taxes)
and the same shall be in any of the following form:
a) Bank draft drawn on a Kolkata Branch of any Scheduled Bank in favour of Balmer
Lawrie & Co Ltd.
b) Bank Guarantee executed by any Scheduled Bank as per proforma enclosed and shall
be valid at least sixty days after the completion of work.
(ii) If the Bidder fails to provide the Security Deposit within the period specified, such
failure will constitute a breach of the Contract and Owner shall be entitled to award
the Work elsewhere at Supplier's risk and cost. The EMD of the bidder to whom
Contract was awarded, shall be forfeited
(iv) As and by way of additional security, from every progress bill of Bidder, Security
Deposit in the form of Retention Money (interest free) at the rate of 10% (inclusive of
initial security deposit of 5%) of the Gross value of such bill as determined before
payment shall be retained by the Owner. Owner can permit Bidder to replace the
Security Deposit / Retention Money so retained by Bank Guarantee at his discretion
after successful completion of the work.
(v) Wherever the Security Deposit / Retention Money is furnished by Bidder in any form
other than in cash or Demand Draft, Bidder shall be entirely responsible to keep such
form of security deposit enforceable by extending the validity thereof before one
month of date of expiry and keep them enforceable, until released by Owner after the
Defect Liability Period.
(vi) The Security Deposit / Retention Money shall remain at the entire disposal of Owner
as a security for satisfactory execution and completion of the Work(s). Owner shall be
at liberty to deduct and appropriate from the Security Deposit / Retention Money such
damages (liquidated or otherwise) and other dues and recoveries from Bidder under
this Contract and the amount by which Security Deposit / Retention Money is reduced
by such appropriations, will be made by further deductions from Bidder's subsequent
bills to that extent as to make up the Security Deposit / Retention Money.
(viii) On due and satisfactory performance of all the obligations of Bidder under this
Contract including completion of work in all respects, carrying out the obligations of
Bidder during Defect Liability Period, Retention Money shall be released by Owner
subject to recoveries, deductions and retentions therefrom as provided under the
Contract.
(i) All materials required for the execution of the work should be new and should conform
to applicable standard specification and approved by the Engineer-in-Charge before
actually put to use. Commencement of work without prior approval shall be entirely
at the risk and cost of the Contractor. No delay due to non-availability of the materials,
tools, equipment etc. will be entertained by the Owner. In the case of certain
Machinery / Equipment, the Engineer-in-Charge may inspect the item for approval,
before they are brought to site.
(ii) The Owner shall be entitled at all times at the risk of the Contractor to inspect and/or
test by themselves or through any independent person(s) or agency (ies) appointed by
the owner and/or to direct the Contractor to inspect and/or test all material(s), items
and components whatsoever supplied or proposed for supply, for incorporation in the
work inclusive, during the course of manufacture or fabrication by the Contractor
and/or at the Contractors work or otherwise, such materials or items or components.
The inspection and/or test shall be conducted at the expense of the Contractor and if
conducted by the Contractor may be directed by the Owner to be conducted by agency
(ies) nominated by Owner and/or in the presence of witness (ess) nominated by the
Owner.
(iii) The Contractor shall furnish to the Engineer-in-Charge for approval when requested
or as required by the specification or other contract documents, adequate samples of
material intended for incorporation in the works. Such sample to be submitted before
the work is commenced permitting sufficient time for tests, examination(s) thereto by
the Engineer-in-Charge. All materials furnished and incorporated in the work shall
conform to the sample(s) in all respects.
(iv) The Engineer-in-Charge shall be entitled to reject at any time any defective materials,
item or components, (including special manufactured or fabricated items or
components) supplied by the Contractor for incorporation in the works.
(v) The Contractor shall at all times ensure highest standard of workmanship, relating to
the work to the satisfaction of the Engineer-in-Charge. The Engineer-in-Charge shall
have the power to inspect the work as also to test or instruct the Contractor to test
the works or any structure, material or component thereto at the risk and cost of the
Contractor, either by the Contractor or by any agency(ies) nominated by the Engineer-
in-Charge or Site Engineer on his behalf.
(vi) The Contractor shall provide all facilities, instruments material / labour and
accommodation required for testing the works (including checking the set time out of
work) and shall provide Engineer-in-Charge all assistance necessary to conduct the test
whenever and wherever required.
(vii) The Engineer-in-Charge on inspection or test be not satisfied with the quality or
workmanship of any work, structure, material, component (decision of the Engineer-
in-Charge being final in this behalf), the Contractor shall re-perform, replace, re-install
and / or re-erect as the case may be such work, structure material or component, as
no such rejected work, structure, material, item or component shall be re-used
without the prior permission of Engineer-in-Charge.
(viii) Notwithstanding any provided in the foregoing clauses hereto and notwithstanding
the Engineer-in-Charge/ or his representative has inspected tested and/or approved
any particular work, structure, material or component, such inspection, test or
approval shall not absolve the Contractor of his full responsibilities under the contract
inclusive or relative to the specification, performance guarantee. The said inspection
and test procedure being intended basically for satisfaction of the Owner / prima-facie
erection and/or material and equipment supplied for incorporation in the work is in
order.
(ix) On no account shall the Contractor proceed with the covering up or otherwise placing
beyond reach of inspection or measurement any work before necessary inspection,
entries are filled in the Site Inspection Register by the Engineer-in-Charge or his
authorised representative. Should the Contractor do so the same shall be uncovered
at the Contractor’s risk and expense for carrying out the inspection and measurement.
Measurement of Work shall be recorded as per the direction of Engineer-in-Charge.
(x) If any tests are required to be carried out in connection with the work or materials or
workmanship not supplied by the Contractor, such tests shall be carried out by the
Contractor as per the instructions of Engineer-in-Charge and cost of such tests shall be
reimbursed by the Owner.
(xi) The owner reserve the right to inspect the Equipment at Tenderer’s works by them or
through a third party nominated by the Owner. Tenderer will provide all assistance to
Owner’s inspector in carrying out such inspection at Tenderer’s works free of any
charges.
a) The Contractor shall guarantee that the equipment and workmanship of work done and
any fittings designed / manufactured / supplied by him are as specified in the tender
schedule and wherever there is nothing specifically mentioned shall correspond to the
best available grade and quality as required for the application.
b) The Contractor shall also guarantee that the work done and any fittings designed,
manufactured, supplied, erected shall be as per prevailing relevant standard, codes and
statutory practices / stipulations.
c) The Contractor shall guarantee the work done and any fittings designed, manufactured,
supplied, erected and tested by him against defective materials, poor workmanship,
improper design, operation inadequacies & problems and failure from normal usage, for
a period of 12 (twelve) calendar months after final acceptance of the work by the Owner.
Performance Bank Guarantee shall be issued by any Nationalized / Scheduled Bank on
basic value of material supplied and shall remain valid for above guarantee period.
7.2 Warranty:
The Contractor will repair and/or replace all defective parts, components / fittings,
accessories etc. which shall be notified to them in writing within the Defect Liability Period
Promptly at free of cost. The Contractor will provide similar warranty on the parts,
components, fittings, accessories etc. repaired and/ or replaced.
The intending tenderers shall be deemed to have visited the site and familiarised themselves
thoroughly with the site conditions before submitting the tender. Non-familiarity with the
site conditions will not be considered reason either for extra claims or for not carrying out the
work in strict conformity with the drawings and specifications.
9.01 All materials required for the work shall be supplied by the Contractor. In addition, all
materials required for temporary and enabling work shall be arranged and provided by the
Contractor. All incidental expenses, loading, unloading, transportation, handling etc. shall be
the responsibility of the Contractor and cost towards such expenses should be included in the
finished item rates.
9.02 All other materials, as required to complete the works in all respects according to the contract
rates shall be inclusive of all freights, GST and other taxes, duties, loading, unloading,
transporting, handling and storage charges etc.
Time is the essence of the contract. The tenderer shall submit their plan to complete the
whole work according to the overall time allowed for the execution of work as given in the
Tender Documents and NIT.
10.0.1 The Contractor shall complete in all respects in accordance with the Contract, the entire work
at each job site within the time specified in this behalf in the Time Schedule.
10.0.2 If the Owner so requires, the Progress Schedule in the form of CPM, giving the latest dates of
starting and latest dates of finishing of various operations comprising the work as also the
activities in the critical path and latest dates for achievement of specific milestones in respect
of the work so as to complete in all respects the works (including testing and consequential
operations) within the time provided in the Time Schedule. This Progress Schedule should also
indicate the interlinking of the various activities and bring to light the specific/ critical items
on which the inputs from the owner/ Engineer-in-Charge/ Consultant or other agencies, if
any, would be required, to ensure adherence to the schedule.
10.0.3 If the Contractor shall fail to submit to the Owner/ EIC a Progress Schedule as envisaged above
or if the Owner/EIC and Contractor fail to agree upon the Progress Schedule as envisaged
above, then the Engineer-in-Charge shall prepare the Progress Schedule (the dates of progress
as fixed by the Engineer-in-Charge being final and binding upon the Contractor except as
herein otherwise expressed provided), and shall issue the Progress Schedule so prepared to
the Contractor, which shall then be the Approved Progress Schedule and all the provisions of
clauses 10.0.2 shall apply relative thereto.
10.0.4 Any reference in the Contract Documents to the Approved Progress Schedule” or to the
“Progress Schedule” shall mean the “Approved Progress Schedule” specified in clause 10.0.2
above or the “Progress Schedule” prepared and issued by the Engineer-in-Charge as specified
in clause 10.0.3 above, whichever shall be in existence. In the absence of such approved
Progress Schedule or such Progress Schedule prepared by the Engineer-in-Charge, the
Progress Schedule first prepared by the Contractor (with incorporation of the Owner’s /
Engineer-in-Charge’s comments thereon if any), shall until such approved Progress Schedule
or such Progress Schedule prepared by the Engineer-in-Charge comes into existence, be
deemed to be the Progress Schedule for the purpose of the contract.
10.0.5 Within 7(seven) days of the occurrence of any act, event or omission which, in the opinion of
the Contractor, is likely to lead to delay in the commencement or completion of any particular
work(s or operation(s) or the entire work at any job site(s) and in such as would entitle the
Contractor to an extension of the time specified in this behalf in the Progress Schedule(s), the
Contractor shall inform the site engineer and the Engineer-in-Charge in writing of the
occurrence of the act, event or omission and the date of commencement of such occurrence.
Thereafter, if even upon the cessation of such act or event or the fulfilment of the omission,
the Contractor in his opinion that an extension of the time specified in the Progress Schedule
relative to the particular operation(s) or item(s) or work or the entire work at the job site(s) is
necessary, the Contractor shall within 7 (seven) days after the cessation or fulfilment as
aforesaid make a written request to the Engineer-in-Charge for extension of the relative time
specified in the Progress Schedule and the Engineer-in-Charge may at any time prior to
completion of the work extend the relative time of completion in the Progress Schedule for
such period(s) as he considers necessary, if he is of opinion that such act, event or omission
constitutes a ground for extension of time in terms of the Contract and that such act, event
or omission has in fact resulted in insurmountable delay to the Contractor.
10.0.5.1 The application for extension of time made by the Contractor to the Engineer-in-Charge
should contain full details of-
a) The notice under clause 10.0.5 with a copy each of the notice sent to the Engineer-in-
Charge and Site Engineer.
g) The total extension of time (if any) required/ necessitated for completion, taking the
above into account and after eliminating all overlaps.
10.0.5.2 The opinion/ decision of the Engineer-in-Charge on this behalf and as to the extension of
time necessary shall, subject to the provisions of clause 10.0.6 hereof, be final and binding
upon the Contractor.
10.0.6 Subject as elsewhere herein or in the contract documents expressly provided, only the
existence of force majeure circumstances as defined in 10.0.7 hereof shall afford the
Contractor a ground for extension of time for completion of the work or any part of the work
or any operation(s) involved therein, and specifically without prejudice to the generality of
the foregoing, inclement weather, strike, shutdown, third party breach, delay in supply of
material(s) or commercial hardship shall not afford the Contractor a ground for extension of
time or relieve the Contractor of his/its full obligations under the Contract, nor will any forced
shutdown or idleness or other impediment in progress or completion of the work due to any
reason whatsoever afford the Contractor a ground for extension of time or relieve the
Contractor of his/its full obligations under the Contract except and to the extent otherwise
elsewhere herein specifically provided, nor shall any shut down or idle time charges be
payable by the Owner to the Contractor for delay in the commencement, progress or
completion of the work due to any reason whatsoever, including due to the existence of force
majeure circumstances.
10.0.7 The term “Force Majeure” as employed in this contract shall mean wars (declared or
undeclared) or revolutions, civil wars, tidal waves, fires, major floods, earthquakes, epidemics,
quarantine restrictions and freight embargoes and transporters strikes affecting the country
as a whole.
10.0.8 Upon an extension of the time for completion of the work or any part of the work or any
operation(s) involved therein pursuant to clause 10.0.5 hereof, the extended date/time of
completion shall be deemed to be the relative date of completion in the Progress Schedule,
and such extension shall constitute the sole remedy of the Contractor for and/or arising out
of such delays, and the Contractor hereby waives any and all contrary rights.
10.0.9 The mere fact that the Owner shall not have terminated the contract or that the Owner or
Engineer-in-Charge has permitted the Contractor, for the time being to continue with the
work for its completion shall not prejudice the full rights and remedies available to the Owner
under the contract arising out of the delayed completion, including the right of Liquidated
Damages and/or termination. Such permission(s) shall unless specifically stated to be an
extension of time under clause 10.0.5, not be construed as extension(s) of time extension
under clause 10.0.5, and shall merely constitute an indication or intimation, as the case may
be, of the Owner’s willingness, for the time being, to accept the delayed completion, subject
to its rights under the contract.
(i) If the Contractor is unable to complete the jobs specified in the scope of work within
the period specified in NIT, it may request owner for extension of the time with
unconditionally agreeing for payment of LD. Upon receipt of such a request, owner
may at its discretion extend the period of completion and shall recover from the
Contractor’s running account bill, as an ascertained and agreed Liquidated Damages,
a sum equivalent to 0.5% of contract value for each week of delay or part thereof. The
LD shall be limited to 5% of the total contract value (order value excluding taxes).
The parties agree that the sum specified above is not a penalty but a genuine pre-
estimate of the loss/ damage which will be suffered by the owner on account of delay/
breach on the part of the Contractor and the said amount will be payable without
proof of actual loss or damage caused by such delay/breach.
(ii) Notwithstanding what is stated in Clause above, the Owner shall have the right to
employ any other agency to complete the remaining work at the risk and cost of the
Contractor, in the event of his failing to complete the work within the stipulated time
(iii) Then the Engineer-in-Charge upon receiving necessary approval from competent
Authority may in writing make a fair and reasonable extension of time for completion
of the works as per provision of clause no. 10, provided further that the Contractor
shall constantly use his best endeavour to the satisfaction of the Engineer-In-Charge
to proceed with the works. Nothing herein shall prejudice the rights of the Contractor
under clause herein above.
(iv) The Contractor may seek time extension for delay or anticipated delay as per clause
no. 10.0.5 for reasons not attributable to them and in such case time extension may
be given without imposition of LD.
(ii) 60% of the total rate against supply of materials upon receiving of materials at site in
good condition and duly inspected and certified by the Engineer-in-Charge.
(iii) 30% of the total rate against successful installation upon verification and certification
by the Engineer- in-Charge.
(iv) 10% of the total rate against supply successful commissioning and after issuance of
job completion certificate by owner.
(v) On each running account bill 10% of basic order value will be withheld as retention
money. The Contractor shall, within fifteen (15) days, submit to the Owner Initial
Security Deposit equivalent to 5% of the total contract value. During payment of
monthly running account bills, the initial security deposit will be adjusted first against
‘Retention Money’, but in no case total retention including initial security deposit shall
exceed 10% of the executed value of work at any stage. The retention money will be
released after completion and acceptance of work against issue of Bank Guarantee of
the equal amount for defect liability and performance maintenance period, which
shall be twelve (12) months from the date of completion of job. Performance Bank
Guarantee shall be issued by any Nationalized / Scheduled Bank on basic value of
material supplied and shall remain valid for above guarantee period.
(vi) Final payment shall be released based upon the measured installed quantity only.
14.0 ARBITRATION
Any dispute or difference arising under this Contract shall be referred under jurisdiction of
Kolkata to a sole arbitrator to be appointed by the Chairman & Managing Director, Balmer
Lawrie & Co. Limited and the provisions of Arbitration Act, 1996 including any statutory
modifications or enactment thereof shall apply to the Arbitration proceedings. The fees of
the arbitrator, if any, shall be shared equally by both the parties. The award shall be a speaking
award stating reason therefor and is final & binding on the parties. The proceeding shall be
conducted in English language and courts at Kolkata will have exclusive jurisdiction to settle
any dispute arising out of this contract.
During the course of execution of the work, should the Contractor come across items of work
which are not covered under the Schedule of Rate or not included therein, the Contractor
shall draw the attention of the Owner / Engineer-in-Charge to the same and such items of
work shall be treated as extra only with the prior approval of Engineer-in-Charge in writing.
Contractor shall submit a quotation along with the rate analysis for such accepted extra items
before he commences work or purchases the materials in connection with such items.
For extra items, rates shall be derived from similar item rates included in the schedule of work.
Where there is no such similar item available in the schedule, rate shall be analysed as follows:
Rate for extra item = Cost of material including transportation till site (a) + cost of labour
inclusive of all necessary tools, tackles, equipment, machinery and consumable (b) required
to carry out the work + 15% of (a+b) towards profit and overhead + taxes, duties etc.
(i) If the Contractor being an individual or a firm commits any 'Act of Insolvency' or shall
be adjudged as insolvent or being an Incorporated Company shall have an order for
compulsory winding up made against it, or pass an effective resolution for winding up
voluntarily or subject to the supervision of the Court or shall be unable to carry out
and fulfil the contract and to give security therefore, is so required by the Engineer-In-
Charge.
Or shall suffer any payment under this Contract to be attached by or on behalf of any
of the creditors of the Contractor.
Or shall assign or charge, encumber or sublet this contract without the consent in
writing of the Engineer-In-Charge first obtained.
Or shall charge or encumber this contract or any payments due or which may become
due to the Contractor thereunder.
Or if the Engineer-In-Charge shall certify in writing to the Owner that the Contractor -
b) has failed to commence the works, or has without any lawful excuse under
these conditions, suspended the progress of the works for 14 days after
receiving from the Engineer-In-Charge written notice to proceed or
c) has failed to proceed with the works with such due diligence and failed to make
such due progress as would enable the works to be completed within the time
agreed upon or
e) has neglected or failed persistently to observe and perform all or any of the
acts, deeds, matters or things by this Contract to be observed and performed
by the Contractor requiring the Contractor to observe or perform the same, or
(ii) Owner shall, at any time, be entitled to determine and terminate the Contract, if in
the opinion of the Owner the cessation of the Work becomes necessary owing to
paucity of funds or for any other cause whatsoever, in which case the cost of approved
materials at the Site at current market rates as verified and approved by Engineer-In-
Charge and of the value of the Work done to date by the Contractor shall be paid for
in full at the specified in the Contract. A notice in writing from the Owner to the
Contractor of such determination and termination and the reason therefore shall be
the conclusive proof of the fact that the Contract has been so determined and
terminated by the Owner.
(vii) Should the Contract be determined under sub-clause of this clause and the Contractor
claims payment to compensate expenditure incurred by him in the expectation of
completing the Work, the Owner shall consider and admit such claim as are deemed
fair and reasonable and are supported by the vouchers to the satisfaction of the
Engineer-In-charge. The Owner's decision on the necessity and propriety of such
expenditure shall be final and conclusive and binding on the Contractor.
(i) No Labour below the age of eighteen (18) years shall be employed on Work. In case
female workers are engaged, requisite provisions shall be made as per the statute.
(ii) Contractor shall not pay less than what is provided under law to labourers engaged
by him on Work.
(iii) Contractor shall at his expense comply with all labour laws and keep Owner
indemnified in respect thereof.
(v) Contractor shall secure full safety of the workers / employees engaged by him in the
Site premises and shall take at his own cost, insurances and such other safety regulations
for the said purpose.
18.0 INSURANCE
Contractor shall at his own expense carry out and maintain insurance with reputable
companies to the satisfaction of the Owner as follows:
Contractor shall obtain Workmen Compensation policy in his name in respect of contractor’s
employees to be engaged for the work towards compensations as admissible under the
Employee’s Compensation Act, 1923 and Rules framed thereunder upon death/ disablement
and also medical treatment of a worker and the same has to be produced to the Engineer-
in-Charge before start of the work. Owner should be mentioned as the Beneficiary.
If any of the work is sublet, after necessary approval by the Owner, the contractor shall
require the Sub-contractor to provide Employee's Compensation and Liability Insurance for
the Sub-contractor's employees, if such employees are not covered under the Contractor's
Insurance.
Housekeeping
Contractors shall ensure that their work area is kept clean tidy and free from debris. The work
areas must be cleaned on a daily basis. Any disposal of waste shall be done by the Contractor.
All equipment, materials and vehicles shall be stored in an orderly manner. Access to
emergency equipment, exits, telephones, safety showers, eye washes, fire extinguishers, pull
boxes, fire hoses, etc. shall not be blocked or disturbed.
Confined Space
Before commencing Work in a confined space the Contractor must obtain from Owner a
Permit to Work, the Permit to Work will define the requirements to be followed.
a) Confined spaces are kept identified and marked by a sign near the entrance(s).
f) All necessary equipment and support personnel required to enter a Confined
space is provided.
The Contractor must ensure that all tools & equipment provided for use during the Work is:
b) safe for use, maintained in a safe condition and where necessary inspected to
ensure this remains the case (any inspection must be carried out by a competent
person and records shall be available);
c) Used only by people who have received adequate information, instruction and
d) Provided with Earth leakage circuit breaker (ELCBs) at all times when using
electric power cords. Use of electrical tape for temporary repairs is prohibited.
Working at Height
Any Work undertaken where there is a risk of fall and injury is considered to be working at
height.
For any Contractor Personnel working at height, Contractors shall provide fall prevention
whenever possible and fall protection only when fall prevention is not practicable. Before
commencing Work in a height the Contractor must obtain from Owner a Permit to Work, the
Permit to Work will define the requirements to be followed. Supervisor must be present at all
point of time, to ensure no deviation occur during the course of work.
Fall prevention systems (e.g. fixed guardrails, scaffolds, elevated work platforms) must
provide protection for areas with open sides, including exposed floor openings.
Where fall protection systems are used then the Contractor must ensure the following is
applied:
(ii) Only approved full body harness and two shock-absorbing lanyards are used,
Scaffolding
All scaffolds shall subject to a documented inspection by a competent person and clearly
marked prior to use. The footings or anchorage for scaffolds shall be sound, rigid and capable
of carrying the maximum intended load without settling or displacement. All scaffolding
materials should be of MS tubular type.
Guardrails and toe-boards shall be installed on all open sides and ends of scaffold platforms.
Scaffolds shall be provided with an access ladder or equivalent safe access. Contractor
Personnel shall not climb or work from scaffold handrails, mid-rails or brace members.
Ladders should only be used for light duty, short-term work or access in line with the below
and the Site Requirements.
ii) Ladders will be secured to keep them from shifting, slipping, being knocked or blown
over.
iii) Ladders will never be tied to facility services piping, conduits, or ventilation ducting.
iv) Ladders will be lowered and securely stored at the end of each workday.
v) Ladders shall be maintained free of oil, grease and other slipping hazards
vi) Ladders will be visually inspected by a competent person and approved for use before
being put into service. Each user shall inspect ladders visually before using.
vii)Ladders with structural defects shall be tagged "Do Not Use," immediately taken out
of
service, and removed from the Site by the end of the day.
Lifting Operations
Contractors shall operate and maintain cranes and hoisting equipment in accordance with
manufacturer’s specifications and legal requirements.
Only Contractor Personnel trained in the use of cranes and hoists are permitted to use them.
All lifting equipment / accessories e.g., slings, chains, webbing, chain blocks, winches, jacks
etc shall be indicated with their safe working load have an identification number visible on
the unit and be inspected and tested in accordance with legal requirements.
Damaged equipment / accessories and equipment shall be tagged “out of use” and
immediately removed from Site.
Prior to performing work on machines or equipment, the Contractor shall ensure that it is
familiar with LOTO and Permit to Work procedures and that all of its affected Contractor
Personnel receive the necessary training.
Barricades
Floor openings, stairwells, platforms and walkways, and trenching where a person can fall any
distance shall be adequately barricaded and where necessary, well lit. Where there is a risk of
injury from a fall then rigid barriers must be used.
Barricades must also be used to prevent personnel entering an area where risk of injury is high
e.g., during overhead work activity or electrical testing etc. Such barricading must provide
clear visual warning.
Gas cylinder shall be securely stored and transported, and identified and used in line with the
local requirements. Hose lines shall be inspected and tested for leaks in line with local
requirements. Flash Back arrestor to be used to prevent any explosion due to back fire.
Electrical Safety
Prior to undertaking any work on live electrical equipment the Contractor must obtain a
Permit to Work from Owner. Where ever possible live work should be avoided. Any control
measures highlighted shall be implemented prior to work commencing.
a) Work practices must protect against direct or indirect body contact by means of tools or
materials and be suitable for work conditions and the exposed voltage level.
b) Energized panels will be closed after normal working hours and whenever they are
unattended. Temporary wiring will be de-energized when not in use.
c) Only qualified electrical Contractor Personnel may enter substations and/or transformer
and only after being specifically authorized by Owner.
Hot Works
A Permit to Work must be obtained from Owner prior to any hot works (welding, grinding,
open flame work). Suitable fire extinguishing equipment shall be immediately available.
Objects to be welded, cut or heated shall be moved to a designated safe location, or, if they
cannot be readily moved, all movable fire hazards in the vicinity shall be taken to a safe place.
Personnel working around or below the hot works shall be protected from falling or flying
objects.
Prior to the use of temporary propane or resistance heating devices approval must be
obtained from Owner.
A Permit to Work must be obtained from Owner and all underground lines, equipment and
electrical cables shall be identified and located prior to beginning the work. The Contractor
shall assign a competent Contractor Personnel to all trenching and excavation work.
Safe means of access and egress shall be located in trench excavations. Daily inspections shall
be conducted by a competent Contractor Personnel for evidence of a situation that could
result in possible cave-ins, indications of failure of protective systems or other hazardous
conditions.
Physical barriers shall be placed around or over trenches and excavations. Flashing light
barriers shall be provided at night.
Environmental Requirements
Waste Management
The Contractor is responsible to remove any waste generated by the work being done on the
Site. The Contractor must dispose of the waste in line with the relevant local legislative
requirements. The waste disposal route shall be documented and made available for Owner
to review at any time and may be subject to Owner’s prior approval.
Wastes (includes rinse from washing of equipment, PPE, tools, etc) are not to be poured into
sinks, drains, toilets, or storm sewers, or onto the ground. Solid or liquid wastes that are
hazardous or regulated in any way are not to be disposed of in general site waste receptacles.
Spills
The Contractor is responsible for the provision of adequate spill kits/protection and the clean-
up and disposal costs arising from such spills.
Emissions
The Contractor shall identify and quantify any emission sources associated with the Works.
The control measures associated with these emission shall be subject to the approval of
Owner’s Emissions include but are not limited to noise, dust, fumes, vapours.
To
Balmer Lawrie & Co. Ltd.
Kolkata- 700 001
Whereas …………………….. (Name of the bidder) (hereinafter called “the Bidder”) has submitted its bid
for the ………………….. (purpose) (hereinafter called “the Bid”) against Tender reference No. ………….
dated ………….. M/S. BALMER LAWRIE & CO. LTD., 21 Netaji Subhas Road, Kolkata – 700 001.
The conditions of Tender provide that the Bidder shall pay a sum of Rs………………. (Rupees
……………………….. only) (hereinafter called “the said amount”) as full Earnest Money Deposit in the
forms therein mentioned. The forms of payment of Earnest Money Deposit include guarantee to be
executed by a Scheduled Bank.
The said ………………………. (name and address of the Bidder) have approached us and at their request
and in consideration of the premises we, ……………….. (Name of the Bank) having our office at
……………………………(address of the Bank) have agreed to give such guarantee as herein after
mentioned.
Know All Men by these presents, we, ……………………..(name of the Bank) of ……………….(address of the
Bank) having our office, inter alia, at …………….. (hereinafter called “the Bank”) are bound unto
BALMER LAWRIE & CO. LTD………………(address) (hereinafter called “the Purchaser”) in the sum of Rs.
………………… (Rupees …………………… only) for which payment will truly be made to the Purchaser, the
Bank binds itself, its successors and assigns by these presents this ……. day of ………… 2019.
1. If the Bidder withdraws its Bid during the period of bid validity specified by the Bidder on the
bid form; or
2. If the Bidder, having been notified of the acceptance of its bid by the Purchaser during the
period of bid validity;
b) fails or refuses to furnish the Performance Security, in accordance with the
instructions to Bidders.
Contd….2/-
[2]
We undertake to pay the Purchaser up to the said amount upon receipt of its first written demand,
without the Purchaser having to substantiate their demand, provided that in their demand the
Purchaser shall mention that the amount claimed by them is due owing to the occurrence of one or
both of the two conditions.
This guarantee will remain in force upto ……… (date of expiry) including the ….. days after the period
of the bid validity, and any demand in respect thereof should reach the Bank not later than the above
date.
i) Our liability under the Bank Guarantee shall not exceed Rs. ……… (Rupees …………………………..
only)
iii) We are liable to pay the guaranteed amount or pay part thereof under this Bank Guarantee
only if you serve upon us a written claim or demand on or before ………… (last date of validity)
We, …………………………………… (name of the Bank) undertake not to revoke this guarantee during its
currency except with your previous consent in writing.
We have power to issue this guarantee in your favour under our Memorandum and Articles of
Association and the undersigned has full power to do and execute this Guarantee under the Power
of Attorney dated ……………… day of ……….. 2019 granted to him by the Bank.
Your faithfully,
(Specimen Signature)
BANK GUARANTEE
(PERFORMANCE)
WHEREAS Balmer Lawrie & Co. Ltd. (local address), ……………………………………. an existing company
within the meaning of the Companies Act, 1956 and having its Registered Office at 21, Netaji Subhas
Road, Kolkata – 700 001 (hereinafter referred to as “the Company”) issued a Tender being No.
dated (hereinafter referred to as “the said Tender”) for (set out purpose of the job) and
pursuant thereto Messrs/ Mr. ……………………(set out full name and address of the
Contractor) (hereinafter referred to as “the Contractor” which term or expression wherever the
context so requires shall mean and include the partner or partners of the
Contractor for the time being/his/its heirs, executors, administrators, successors and assigns) (delete
which are not applicable) has accepted the said Tender and field its quotation.
AND WHEREAS the quotation of the Contractor had been accepted by the Company and in pursuance
thereof an Order being No………………. dated ………………. (hereinafter referred to as “the said Order”)
has been placed by the Company on the Contractor for (set out purpose of the job).
AND WHEREAS under the terms of the said Order the Contractor is required to furnish the Company
at their/his/its own costs and expenses a Bank Guarantee for Rs………………………….(Rupees
……………………………….. only) as performance guarantee for the fulfilment of the terms and conditions
of the said Tender and to do execute and perform the obligations of the Contractor under the
Agreement dated the …………….. day of …………………….. (hereinafter referred to as “the Agreement “)
entered into by and between the Company of the one part and the Contractor of the other part, the
terms of the said Tender and the terms contained in the said Order which expression shall include all
amendments and/or modifications/or variation thereto.
AND WHEREAS the Contractor had agreed to provide to the Company a Bank Guarantee as security
for the due performance of their/his/its obligations truly and faithfully as hereinbefore mentioned.
Contd….2/-
[2]
2. We, ……………………………. (set out full name of the Bank) do hereby undertake to pay to the
Company without any deduction whatsoever a sum not exceeding Rs………………… (Rupees
…………………………. only) without any protest, demur or proof or condition on receipt of a
written demand from the Company stating that the amount claimed is due by way of loss and
damage caused to or would be caused to or suffered by the Company due to bad
workmanship or by reason of breach of any of the terms and conditions of the Agreement,
the said Tender and the said Order hereinbefore mentioned.
3. The Guarantee is issued as security against due performance of the obligations of the
Contractor or under the Agreement aforesaid and the said Tender and the said Order
hereinbefore mentioned and subject to the conditions that our liabilities under this Guarantee
is limited to a maximum sum of Rs………………. (Rupees ………………………………………………………….
only) or the amount of loss or damage suffered or to be suffered by the Company in its opinion
at any period of time, whichever is lower.
4. We, ………………………………….. (set out full name of the Bank) further agree that the undertaking
herein contained shall remain in full force for a period of months from the date of the
satisfactory execution of the Contract.
5. This Guarantee shall not be affected by any amendment or change in the Agreement or
change in the constitution of the Bank and/or the Company and/or the Contractor.
6. We ………………………………….. (set out full name of the Bank) undertake not to revoke this
Agreement during its currency except with the previous consent of the Company in writing.
7. All claim under this Guarantee must be presented to us within the time stipulated after which
date the Company’s claim/right under this Guarantee shall be forfeited and we,
………………………………….(set out full name of the Bank) shall be released and discharged from
all liabilities hereunder.
Contd….3/-
[3]
8. This instrument shall be returned upon its expiry or settlement of claim(s) if any, thereunder.
9. Notwithstanding anything contained hereinbefore our total liabilities under this Guarantee
shall not exceed a sum of Rs……………….. (Rupees ………………………………………………… only) and
unless a demand or claim in writing under this Guarantee reaches us on or before the date of
……………………. (last date of claim) and if no claim is received by us by that date all rights and
claims of the Company under this Guarantee shall be forfeited and we,
………………………………(set out full name of the Bank) shall be released and discharged of all our
liabilities under this Guarantee thereafter.
10. We have power to issue this guarantee in your favour under our Memorandum and Articles
of Association and the undersigned has full power to execute this Guarantee under Power of
Attorney dated the …………… day of ……………………… granted to him by the Bank.
Place :
Date :
Dear Sir,
That Messrs/Mr. ………………..(set out full name and address and constitution of the Contractor)
(hereinafter referred to as “the Contractor”) filed their/his/its quotation against your Tender being
Tender No. ………………….. dated …………….. (hereinafter referred as “the said Tender”) for the work
……………………………………………………….. (set out the purpose of the job) and in pursuance thereto an
Order being No. …………….. dated ……….. (hereinafter to as “the Order”) was issued by you to the
Contractor.
The conditions of the said Tender, inter alia, requires that the Contractor shall pay a sum of
Rs………………………. only) as full security deposit (hereinafter referred to as “the security deposit”) in
the form therein mentioned. The form of payment of security deposit includes a guarantee to be
executed by a Scheduled Bank.
The said Messrs/Mr. ……………………… (set out full name of the Contractor) have/has approached us
and at their/his/its request and in consideration of the premises We ……………………….. (set out full
name of the Bank) having our office, inter alia at ……………………… (state the address of the Bank) have
agreed to give such guarantee in the manner following :
3 We, ………………………. (set out full name of the Bank), hereby undertake with you if default is
made by Messrs/Mr. ………………….. (set out full name of the Contractor) in performing any of
the terms and conditions of the Tender and/or in payment of the security deposit or any other
or in payment of money payable to you. We, ………………………….. (set out full name of the Bank)
shall merely on demand from you without demur or protest shall pay you the said amount of
Rs……………… (Rupees ……………………. only) or such portion thereof not exceeding the said sum
as you may demand from time to time.
2. We, ………………………….. (set out full name of the Bank), further agree with you that you
hereunder to adopt any mode for realisation of your dues from the Contractor and/or to
vary any of the Terms and Conditions of your Contract with the said Messrs/Mr. …………………
(set out full name of the Contractor), or to extend time of performance by Contractor from
time to time or to postpone for any time or from time to time any of the powers exercisable
by you against Contractor and to forbear or enforce any of the terms and conditions relating
to the Contract and we, ………………………………. (set out full name of the Bank) shall not be
relieved from our liability by reason of any such variation, or any indulgence to be given by
you to the Contractor or by any such matter or thing whatsoever which under the law
relating to sureties would but for this provision have effect of so releasing us.
Contd……2/-
[2]
3. Your right to recover the said sum of Rs……………….. (Rupees ……………………………… only) from
us in the manner aforesaid will not be affected or suspended by reason of the fact that any
dispute or disputes is/are pending before any Officer, tribunal, court or any other authority
or authorities.
6. Our guarantee shall remain in force and effect until ……………….. (set out the date of expiry)
and unless a claim or demand in writing is made against us under this guarantee before the
expiry of six months from the aforesaid date i.e. ………………………. (set out last date of Claim
period), the said Guarantee all your rights under this guarantee shall be forfeited and we,
………………………… (set out full name of the Bank) shall be relieved and discharged from all
liabilities thereunder.
7. We , …………………………….. (set out full name of the Bank) undertake not to revoke this
Guarantee during its currency except with your previous consent in writing.
8. We, …………………………………….. (set out full name of the Bank) have power to issue this
Guarantee in your favour under our Memorandum and Articles of Association and the
undersigned has full power to execute/sign this Guarantee under the Power of the Attorney
dated the ……………. day of Two Thousand and Eighteen granted by the Bank.
Yours faithfully,
TECHNICAL
SPECIFICATION
FOR
SUPPLY, INSTALLATION, TESTING & COMMISSIONING
OF FIRE PROTECTION SYSTEM
FOR
1.0.0 GENERAL
1.1.0 Intent of Specification
1.1.1 This specification is intended to cover residual engineering, supply, fabrication, erection,
testing and commissioning of the fire-protection system, as per enclosed Schedule of Work,
drawings and tender terms & conditions inclusive of the supply of all labour, supervision,
tools, equipment and erection materials as necessary.
1.1.2 The specification shall be read in conjunction with the Conditions of Contract, Schedule of
Work/Bill of Quantity as enclosed with this Specification. However, in the event of any
conflict between Schedule of Work/Bill of Quantity and Technical Specification or data
sheets, item description mentioned in Schedule of Work/Bill of Quantity shall prevail.
All fire-protection equipment and installation work shall also conform to National Building
Code and local Fire Department. Fire Department and Fire Insurance Regulations as regards
safety, earthing and other essential provisions specified therein for installation and operation
of the systems.
Nothing in this specification shall be construed to relieve the CONTRACTOR of this
responsibility.
2.1.2 All relevant drawings, technical data sheets and technical leaflets/catalogues, Test Certificates
of major items shall be submitted.
2.1.3 Furnishing of all labour, skilled and unskilled, supervisory personnel, tools and tackles for
fabrication/erection, testing equipment, implements, supplies, consumables and hardware
for timely and efficient execution of the site work.
2.1.4 The item of work to be performed on all equipment and materials shall include but not be
limited to the following:
Receiving, unloading of the materials at site
Opening, inspection and reporting all damages and short supply of items.
Arranging to repair and/or re-order all damaged and short supply items.
Storing at site with suitable all weather protection.
Side-Shifting of materials as directed by Engineer-in Charge
Assembly, erection and complete installation.
Necessary co-ordination between works done by the other contractors.
Final check-up, testing and commissioning in presence of owner's representative.
Trial run for seven days, rectification of defects, if any and adjustment as necessary.
2.1.5 Field modification carried out shall be marked up red on one set of drawing. Based on the
mark up, as built drawing will be prepared.
2.1.6 Preparation of cable schedule for Fire Detection & Alarm System
2.1.7 Preparation of AS BUILT DRAWINGS and submission of the same in soft copies (in Auto cad
2004 / Microsoft Word/excel format) as well as in hard copies.
2.1.8 Reference shall be drawn to the "Schedule of Work” for quantity of major items.
2.1.9 Contractor will be given a place (only) for storing his materials, tools, tackles. Contractor shall
construct a store (at his own cost) at that designated place to keep his materials, tools &
tackles. Contractor shall make proper security arrangement for his materials till the
installation is taken over by the owner. Owner will not be responsible for any theft/loss of
materials.
2.1.10 Construction power and water: Contractor shall arrange for water and construction power at
his own cost. However, if power is available during execution same may be provide to the
contractor on chargeable basis.
3.0.0 TESTS
3.1.0 Pre-commissioning Tests at site
3.1.1 The installation work shall be tested by the contractor after completion of his
erection/installation work with an advance notice to the engineer so that he or his authorized
representative may witness the same also.
The contractor shall carry out Test as per relevant codes & standards and record the same in
proper format. All piping after installation shall be tested for a hydrostatic test pressure of 16
Kg/Sq cm maintained for 24 hours. All joints and valves shall be checked for leaks and rectified
and retested. During testing all valves except drain & air valves shall be kept fully open. After
completion of the tests, the recorded test results shall be submitted to the owner for his
approval and acceptance.
3.1.2 The test result of any installation or equipment or its part, if considered not satisfactory to
the engineer, the concerned installation / equipment and its accessories shall be properly
rectified by the contractor and shall be tested again to the satisfaction of the engineer by the
contractor at his own cost.
4.1.2 However, as the plot allotted to BL is located at the furthest corner, an online booster pump
have been considered for increasing the water pressure. However, this booster pump will only
be installed after confirming the pressure from AMTZ Authority.
4.1.3 Open Area: Around the periphery of the warehouse along the Boundary wall, hydrant network
has been considered with SH hydrant at 30 mtr. interval. Water Monitors have been
considered at two corner location of the plot.
4.1.4 Warehouse:
a) Inside the warehouse, beam smoke detectors have been considered as it is impractical,
inappropriate and not cost effective to use traditional point-type detectors for this type of
warehouse.
b) Manual alarm call points along with Hooters are proposed near rolling shutter location for
the purpose of raising an alarm manually once verification of a fire or emergency condition
exists.
c) Fire Escape Hydrants with Hose Box and Hose Reel has been are provided for fighting fire.
4.1.6 Hooter cum strobes will be installed such as to alert people uniformly all over the area covered
under FDA system in case detection of fire.
4.1.7 Manual Call point will be placed at suitable locations
4.1.8 Portable Fire Extinguishers (CO2, ABC , DCP Type) as per IS: 15683 has been considered.
4.1.9 Fire Notice Boards, Signages will be displayed as required.
4.1.10 Fire Brigade inlet connection has been provided near entry gate to overcome emergency
situation.
5.1.6 Pipes and fittings shall be fixed to walls and ceilings by suitable clamps at intervals specified.
Only approved types of anchor fasteners shall be used for RCC ceilings and walls.
5.1.7 Pipes and fittings shall be fixed truly vertical, horizontal or in slopes as required in a neat
manner. The pipes shall be supported by structural steel fabricated (like, channel / angle / flat
/ plate etc.) supports with suitable anchor fasteners / suspended thread rods not less than
M16 in size.
5.1.8 Valves and other appurtenances shall be as located that they are easily accessible for
operation, repairs and maintenance. Valves / other equipment fitted above the false ceiling
shall be provided with trap / access doors.
5.1.9 Pipes for wet risers within the Building shall be M.S. tubes conforming to IS 1239
(Heavy 'C' class) with flanged/welded joints.
5.1.10 Fittings for steel pipes shall be malleable iron or forged iron fittings with screwed / welded
joints.
5.2.0 PIPING
All pipes inside the building and where specified, outside the building shall be M.S. conforming to IS:
1239 - Heavy. Pipes 200 mm dia. and above shall be M.S. as per IS: 3589 with minimum 6 mm wall
thick & fittings shall be fabricated from pipes confirming to IS 3589. Pipes shall be carefully laid to
the alignment, levels and gradients and great care shall be taken to prevent any sand, earth or other
matter from entering the pipes during laying. Pipes shall be kept thoroughly clean during the course
of laying. The ends of pipes shall be blocked with wooden plugs wedged home, at the end of each
days work to prevent dirt and rodents, insects etc., entering the pipe.
Pipes up to 50mmdia, tapered screwed / Socket welded / Butt welded type jointing shall be adopted,
while for pipes above 50mmdia welded or flanged connections shall be used. Flanged joints shall be
made with 3 mm thick insertion rubber washer / Gaskets. All bolt holes in flanges shall be drilled &
making hole by using gas cutting is not acceptable. The drilling of each flange shall be in accordance
with relevant Standards provided in Data Sheet.
Flanged joints shall be used for connections to vessel, equipment, flanged valves and also on suitable
straight lengths of pipeline at strategic points to facilitate erection and subsequent maintenance
work. The Bolts /Nuts / Washers used in the system shall be in accordance with relevant Standards
provided in Data Sheet.
5.3.0 VALVES
5.3.1 BUTTERFLY VALVES
Butterfly valves shall be as per BS 5155 & provided for pipes 50mmdia and above on downstream
(delivery side) of the pumps. The valves shall be CI construction, seat shall be black nitrile rubber
with in situ molding. The valves shall be PN 1.2 rating. All valves shall be connected with supervisory
switch for monitoring at Fire alarm panel. Cabling shall be measured and paid under Fire alarm
system.
Upon actuation of an automatic detector, visual and acoustic signaling at the main fire alarm
control panel shall indicate the address where acknowledgement by the operator shall cancel
the acoustic signal only. Two types of alarm sound shall be required.
The evacuation signal should be continuous and the alert signal should be intermittent.
Provisions shall be made for changing the “Alert” signal to “Evacuation” signal in any sector
panel manually.
After an alarm has been initiated it should continue until normal conditions have been
restored. Manually operating silencing devices shall be provided for transferring or limiting
the alarm to a control sounder. The operation of the silencing device should not cancel the
visual indication until a reset operation is provided after the alarm condition has been
restored. Automatic silencing of alarm shall not be used. The complete system shall be
suitable for operation a 24 V, DC supply with all necessary batteries, battery charger, etc. All
parts, components and accessories necessary for the complete installation shall be provided.
The wiring for the Fire Alarm System with the building shall be with armoured copper cables
with all necessary terminations and wiring accessories. The number of junction boxes shall be
kept to the minimum. Where junction boxes are required, equivalent insulating material
sleeves shall be used for the wiring in the junction boxes. PVC cables shall be rated at 1100 V
as per the latest IS.
The Main Fire Alarm Panel shall work on 230 Volts A.C. 50 Hz, 1 phase. The Main Fire Alarm
Panel shall be capable of working on batteries also i.e., (24 Volts D.C.) maintenance free
batteries of specified make. The FACP shall have its own Battery Backup of a minimum of 48
hours in normal run and then 30 minutes in alarm condition. The back up time calculation
shall be done as per IS 2189 standards. The Battery shall be 2*12V (24V) DC and of sealed lead
acid rechargeable maintenance free type. Whenever the A.C. Power fails, the batteries shall
automatically take over the system, thus operating the system 24 hrs. a day. There shall be 2
Nos. of 12 Volts batteries supplied along with the panel and shall be accommodated in a
proper enclosure.
The Main Fire Alarm Panel shall sound whenever fire/ fault occur. Whenever ‘Fire’ Signal
comes, panel hooter shall sound with wailing sound and whenever ‘Fault’ signal comes the
panel shall sound continuously i.e., the audio sound produced shall be differentiated between
Fire / Fault signal.
The panel shall be capable of handling multiple alarms with alarms in queue displayed. The
panel shall have multi-character LCD display interface to display all events, menu driven
software to program the zone details of sector panels and a programmable keypad to enter
the zone description. Any Fire / Fault in any zone of the sector panel shall be annunciated in
English language description of the event with date, time, panel number, zone number &
description of alarm/trouble and zone details.
It shall be capable of being networked with the sector panels located at different part of the
premises through a single multi-drop RS485 data bus.
Detectors shall be provided with blinking bi-colour LED to visually indicate the healthiness of
the detector / alarm condition. Detectors shall be suitable for an operating temperature -30º
C to 70º C and relative humidity of 0% to 95 %( non-condensing). The detector shall have
inbuilt intelligence to detect the fire conditions via the inbuilt algorithms in the
microprocessor, as well shall have the inbuilt intelligence to detect software and hardware
faults or malfunction as well if double addressing is assigned by mistake on the loop.
PEDs shall be with In-built short circuit isolator in each device for avoiding multi-device
failures in case of short circuit in loop cable. The detector can support independent output
from the base which can be used for Remote LED, which can be assigned from the Fire Alarm
Control Panel. Each detector will be complete with an interchangeable mounting base that
includes a terminal box into which the detector can be plugged in. Also there shall be an
external terminal box to terminate the field cable. The base for the detector shall be from the
same manufacturer of the detector and should be imported. This detectors/base shall be
traceable to manufacturer’s batch certificate. Detectors shall be suitable for a supply voltage
of 15 to 40 V DC without affecting the sensitivity.
6.5.0 Hooters
The Electronic Hooters shall be housed in MS enclosure of 1.5mm sheet metal. The Hooters
shall be with built on oscillator & amplifier. The Hooters shall give two tones, wailing sound
whenever it receives 24 V supply from panel on receipt of Fire signal. The range of Hooter
shall be 85db approx. at 1 mtr. The MS box shall be painted with Fire Red (Powder Coated).
Hooter shall be of wall / ceiling mounted to suit the interiors.
Alarm receiving and alarm signaling circuits shall be of two wire system and the system shall
be partly with armoured cu cable.
10 Hydrant valve & water :GEI / Newage / Shah Bhogilal / ASCO/Fire Shield/Sh
monitor, Branch Pipe with Nozzle Fire(E.A.M)
Besides above mentioned make equivalent approved make (EAM) may also be used. The Contractor
shall also obtain prior approval from Owner for the ‘Make’ and ‘Rating’ of any other major item not
mentioned above.
AMTZ/FPS/12 Sprinklers
TITLE :
TECHNICAL DATA SHEET FOR BRANCH PIPE &
NOZZLES DOC NO. AMTZ/FPS/01
PACKAGE: FIRE PROTECTION SYSTEM REV. 0 DATE: 04-06-2019
PROJECT: Central Warehouse at AMTZ, Vizag SHEET 1 OF 1
Inlet : 63 mm dia
Outlet : 20 mm dia
3.4 Quick coupling end / Hose coupling : Fire Hose Coupling (By Hose Supplier)
8 Size : 63 mm x 15 M long
13 Marking : IS:14933-2001
Year of Manufacturer
Manufcturers name of trademark
8.0 Painting (Inside & Outside) : powder coated finish of red out side & white
1.0 Manufacturer GEI / Newage / Shah Bhogilal / Fire Shield / Sha Engg
/Equivalent
6.0 Flow : 54 m3 / Hr at 7
4 Size Barrel/Nozzle : 63 mm
8 Rotation
Horizontal- 360 deg
8.1 Horizontal : 360 Deg. In eiher direction
13 Anti Corrossive Treatment Hot Dip Galvanising for ferrous items & all
items with 3 coats of fire red colour as per IS : 5
Stamp & Signature of the Tenderer Shade no. 536
Tender No. EP/AMTZ/CWH/FPS/04 Page 57 of 77
Engineering & Projects SBU-LI
2.0 PIPING (UNDERGROUND / ABOVE GROUND / IN TRENCHES) (NORMALLY FILLED WITH WATER)
2.1 Standard : IS : 1239 (Part-I), IS : 3589, Gr 330
2.2 Type : ERW / Spiral Weld
2.3 Class & Grade :
a.Up to 150NB MS Black Heavy grade to IS : 1239 (Part-1)
b 200 NB TO 400 NB M S Black to IS : 3589 Grade 410
7.60 Bolts and nuts & Washers Machine Bolts, For Size M 16 & Below IS : 1367 Gr. 8.8. &
For Size M 20 & Above IS : 1367 Gr. 6.8.
Heavy Hexagonal Nut For Size M 16 & Below IS : 1367 Gr.
8.0. & For Size M 20 & Above IS : 1367 Gr. 6.0. All nut, bolt
& washers shall be galvanised.
7.70 Gaskets Champion AF 120 - 3 mm Thk. Non Asbestos
Note : FLANGES AND BOLTS & NUTS FOR G.I. PIPE LINES SHALL BE GALVANISED AS PER IS : 4736
Stamp & Signature of the Tenderer Tender No. EP/AMTZ/CWH/FPS/04 Page 59 of 77
Engineering & Projects SBU-LI
6.11 Counter flange IS:2062 drilled to ANSI B 16.5 # 150 (By others)
10.0 Spur gear reduction unit Provided (For size 350 & above
11.0 Accessories provided
11.1 Position indicator Provided
11.2 Locking arrangement As required
7.0 End connection : Flanged to ANSI B 16.5 (CI 150 Flat Face)
a) Body 24 Kg/cm2
b) Seat 16 Kg/cm2
9.2 Disc Facing Ring : Rubber to IS : 638 Type A
9.4 Indication for direction flow : Permanently marked arrow on the valve body
5.2 Length : 10 m
1.0 GENERAL
2.1 All external or exposed surface of mechanical & electrical equipment, vessels, tanks,
ducts, piping, valves, accessories and surfaces of all structures, platforms, galleries
etc. shall be provided with required primer and finish painting after necessary
surface preparation.
2.2 Quality of primer shall be chosen that they are suitable for withstanding maximum
expected surface temperature and they type of atmosphere it is exposed to.
2.3 Application of primer and finish paints shall be done at site of far as possible except
for finished machine and equipment such as diesel engine, pumps, compressor etc
. For such finished equipment and components there of, the painting may be
completed at shop and transported to site with paint duly protected. For items such
as structures, plates, tank shells, pipe pieces etc. shop coat of protective paint shall
be given before dispatch to site.
However, touch-up paints shall be done at site after erection and commission as per
the instruction of the purchaser.
2.4 The Bidder shall follow the provisions of TAC, Indian Standards or equivalent
approved other National Standards in selection of paints, application and surface
preparation
3.1 The scheme of painting to be followed for various equipment are furnished in
Appendix. The Bidder may suggest any alternative painting scheme if the same is
superior to the suggested scheme. The final scheme of painting to adopted shall be
subjected to purchaser’s approval.
3.2 When material or paint is specified or described by the name of a particular brand,
manufacturer or vendor, the specific time mentioned shall be understood as
indicating the function and quality desired. Other manufacturer’s product shall be
approved provided specific information is given to allow the purchaser to evaluate
the product proposed.
4.2 COATS
A. Prime Coat
B. Finish Coat
2- coats of synthetic enamel paint (Minimum 50 microns dry DFT per coat).
13 Cover Tamper Switch Standard with ULC Models , Optional for UL Models
TENDER DRAWING
List of Drawings
Sl.No. Title Drawing No. Revision Date
LAYOUT PLAN OF AMTZ CENTRAL DRG.NO.
1 Rev. No. 1 18-05-2019
WAREHOUSE EP/CWH/AMTZ/01
%$<#0&& 0
785%29(17
9(17,/$7,21
1
0:,'(52$'
(*
*877(5
56
$/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56 $/80,180),;('/289(56
6287+:(67(/(9$7,21
127(,QWKHVFKHGXOHH[WUDTXDQWLWLHV
KDYHEHHQFRQVLGHUHGWRWDNHFDUHRI
*877(5
TXDQWLW\YDULDWLRQZKLOHH[HFXWLRQDVSHUVLWH
X X
FRQGLWLRQ
),5(/(*(1'6
&<&/(67$1'
6<0 '(6&5,37,21 47<
+<'5$179$/9(
56 56
+26(5((/'580075
7252$' 7252$'
&$53$5.,1* +26(%2;:,7++26(6$1'%3
0:,'(52$'
%($0'(7(&72575$160,77(5
)5217(/(9$7,21 %($0'(7(&7255(&,9(5
0$18$/&$//32,17
785%29(17
+227(5
9(17,/$7,21
:$7(5021,7(5
56 56
($9(6+(,*+7
72 72
52$' ))/ ))/ ))/ 52$'
%$<#0&& 0
6/
$5($67$7(0(17
12
56 &2/'6725$*(0;0
0:,'(52$'
5(&(37,2152200;0
$&&2817652200;0
0:,'(52$'
3/$170$1$*(552200;0
&21)(5(1&(52200;0
56
*$7(2)),&(0;0
0:,'(52$'$07=
0(7(552200;0
2876,'(572,/(70;0
6
.9$'*:,7+$&2867,&(1&/2685(
6 6
5,'*(/,1(
6
&2/' &2/'
6
&+$0%(5 6
&+$0%(5
6 ,7(0 47< :,'7+ +(,*+7 '(6&5,37,21
6 6
0 0
6 56 &+$,17<3(0(&+$1,&$/*($5
56 56 56 56 23(5$7('
56 &+$,17<3(+$1'23(5$7('
/2$',1*81/2$',1*%$< /2$',1*81/2$',1*%$< 56 &+$,17<3(+$1'23(5$7('
6* $8720$7('6/,',1**$7(
&$123<
(* '28%/(/($)6:,1*7<3(
:* 6,1*/(/($):,&.(7*$7(
:*
6* 6* 3/27$5($ $&5(6
'(/,9(5<
&211(&7,1* &211(&76
72 72
(;,6,67,1* 1(:
/,1( /,1(
785%29(17 6.</,*+73$1(/7<3 ($9(6/,1( 7(1'(5385326(21/<
7DSSLQJIURP5,1*0$,1ZLOOEH 9(17,/$7,21
SURYLGHGE\$07=$XWKRULW\ 522)3/$1
0:,'(52$'$07=
352-(&76352326('&(175$/:$5(+286($7
$07=9,=$*
NOTES:
1.0 Details of the items under this Schedule shall be read in conjunction with the corresponding
Specifications, Drawings and other Tender Documents.
2.0 The work shall be carried out as per approved drawings, Specifications and the description of
the items in this Schedule and/or Engineer's instructions. Drawings enclosed with these
documents are only for providing some preliminary of the work involved.
3.0 Items of work provided in this Schedule but not covered in the Specifications shall be executed
strictly as per instructions of the Engineer-In-Charge.
4.0 Unless specifically mentioned otherwise in the Contract, the Tenderer shall quote for the
finished items and shall provide for the complete cost towards power, fuel, tools, tackles,
equipment, Constructional Plant, Temporary Work, labour, materials, levies, taxes, transport,
layout, re-pairs, rectification, maintenance till handing over, supervisions, colonies, shops,
establishments, services, temporary roads, revenue expenses, contingencies, overheads,
profits and all incidental items not specifically mentioned but reasonably implied and
necessary to complete the work according to the contract.
5.0 The Quantities of the various items mentioned in the Schedule of Items are approximate and
may vary or may be deleted altogether. The Contractor, in his own interest, should get an
indication of the probable extent of the work to be executed under any particular item in this
Schedule before undertaking any preliminary and enabling work or purchasing bought out
components related to the work.
6.0 Rates shall be quoted both in figures and in words in clear legible writing. No over writing is
allowed. All scoring and cancellations should be countersigned by the Tenderer. In case of
illegibility, the rates written in word will be considered final. All entries shall be in English
language.
7.0 Engineer's decision shall be final and binding on the Contractor regarding clarification of items
in this Schedule with respect to the other sections of the Contract.
8.0 For extra items, rates shall be derived from similar item rates included in the schedule of work.
Where there is no such similar item available in the schedule, rate shall be analyzed as follows:
Rate for extra item = Cost of material including transportation for delivery upto site (a) + cost
of labour inclusive of all necessary tools, tackles, equipment, machinery and consumable (b)
required to carry out the work + 15% of (a+b) towards profit and overhead + taxes, duties etc.
as applicable.
Schedule of Work
Supply, Installation, Testing and Commissioning of Fire Protection System for Central Warehouse
at AMTZ, Andhra Pradesh
Tender No EP / AMTZ / CWH / FPS / 04
Sl. Description Unit Qty Unit Rate (Rs) Amount (Rs)
No.
Supply, Installation, Testing & Commissioning (SITC) of
1.0 Electrical motor driven online Booster pump of monoblock type capable to deliver 1600- Set 1
LPM (96 Cum/ Hr) at 45 MWC. The pump shall be coupled to TEFC motor of suitable HP
Rating with speed of 2900RPM and complete set shall mounted on common base frame.
The installation shall be complete with necessary pressure gauge with gun metal shut off
cock on suction & delivery side. The quoted rate shall includes providing & fixing of anti
vibration pad and suitable size of metal expansion bellows at suction & delivery side of
the pumps and Foundation bolts etc. Hydrant Tapping will be available from central Do not quote
rainm main laid by AMTZ Authoritiy.This item along with item no 2 & 3 will be executed
as per requirement at site only if the pressure available at tapping point/battery limit is here
low. As the pump will be installed outside, suitable canopy to be provided on the motor.
2.0 Suitable outdoor duty starter (Star-Delta type) electrical panel with all protection and Set 1
Amp Meter / Volt Meter / Auto Manual selector etc. for the above mentioned pump.
3.0 Cabling of suitable size (along with termination) from Electrical Starter to Motor for Lot 1
commissioning of the pump. However, incoming supply to starter is not included in the
scope. Earthing of the Pump and panel from the nearest earthpit shall be included in this
item.
4.0 Dial type glycerine filled pressure gauge with 150 mm dial and range of 0-14 Kg./sq.cm. NoƐ 1
together along with ball valve of 15 mm and GI Barrel Nipples.
5.0 Supplying, laying, testing and commissioning of above-ground piping carried out of MS
Class "C" ERW pipes as per IS : 1239 for pipes upto 150 mm NB and as per IS:3589 (
6.35mm thick ) with all online Pipe Fittings, flanges (ASA 150 class), nuts,bolts
(Galvanised),gaskets,washers, 'U' clamp and tapping for gauges/instruments including
cutting, welding, fixing in / on walls, ceiling by using suitable supports etc,. The quoted
rate shall also include for chasing / chipping walls, making bore holes in walls / floor and
making them good with filler material etc. The item rate shall also include surface
preparation of pipes by wire brushing, application of 2 coat red-oxide primer and 2 coat of
synthetic enamel finish paint. complete. Steel work for supports shall be paid under
separate item.
a 150mm nominal dia Rmt 900
6 Supplying and laying underground buried piping (or road crossing) together with Rmt 40
protective wrapping and coating for MS pipe as per IS : 1239 carried out of MS class "C"
piping for pipes up to 150mm NB and as per IS : 3589 for pipes 200mm NB and above
together with fittings and accessories as under : Rates shall include Excavation & Back
filling in soft soil/murrum and application of 4mm thick wrapping & coating material over
under ground piping.
7 Supplying, Installing, testing and commissioning of C.I. butterfly valves conforming to BS
5155 (PN 1.6) slim seal standard lever operated type with required flanges, nuts, bolts etc.
complete.
a 150mm nominal dia NoƐ 4
8 Cast Iron Gate Valve -Rising Spindle type (IS : 14846 ) with companion Flanges, Bolts, Nuts
and Gaskets
a 150mm nominal dia NoƐ 2
9 Supplying, installing, testing and commissioning of C.I. Non-return valves as per IS:5312
reflux swing check type with required flanges, nuts, bolts and gaskets etc. complete.
a 150 mm nominal dia NoƐ 4
Schedule of Work
Supply, Installation, Testing and Commissioning of Fire Protection System for Central Warehouse
at AMTZ, Andhra Pradesh
Tender No EP / AMTZ / CWH / FPS / 04
Sl. Description Unit Qty Unit Rate (Rs) Amount (Rs)
No.
10 Stand Post type Water Monitor made of C.S Body having 63/32 mm nozzle size with flow NoƐ 2
capacity of 1750lpm@7Kg/Cm2 as per IS:- 8442 Type- “I”, ISI marked.-Refer data sheet.
11 Single headed oblique type ground faced hydrant valve conforming to IS 5290, made of NoƐ. 28
gunmetal with 63 mm dia instantaneous outlet of 80 mm dia fanged inelt ,Blank caps ,
chain and CI hand wheels etc complete.
12 15 M long, 63mm dia RRL hose conforming to IS 636 Type A with instantaneous couplings NoƐ. 56
Do not quote
and Hoses shall be stored inside the hose cabinet.
13 Gun metal short branch pipe with nozzle conforming to IS 903. NoƐ. 28
here
14 M.S. Hose cabinet (with canopy) stand mounted type fabricated out of M.S. sheet of 16 NoƐ. 28
swg. with glass fronted (4mm thick glass with rubber beeding) door, lock and key suitable
for 1 branch pipe and 2 hoses and size of the cabinet shall be 600mm x 750 mm x 250
mm. Quoted rate shall be includes suitable stand for mounting, all fasteners etc, and
cabinet shall be powder coated of approved colour both inside and outside. (Structural
work shall be paid separately).
15 First aid fire Hose reel drum of MS powder coated with fire red colour, 180° swinging type NoƐ 12
with 19mm dia Rubber braided hose of 30 m length with 25 mm dia Ball Valve and 6mm
diameter Shut off nozzle, complete. Hose reel shall be fixed on wall.
16 Fire brigade inlet siamese connection (4way) manifold including valves and check valve of Nos 1
size 150mm size having gunmetal 4 nos. 63mm dia Gun Metal instantaneous inlet
arrangements to the main header complete with required flanges, bolt, nut and
washer,cap and chain etc. It shall be as per IS 5131 with built in check valve and
150mmdia outlet connection to the fire main grid with 150mm dia Butterfly valve and
non – return valve. Butteryfly valve & NRV shall paid under seprate item as mentioned
above.
17 Supplying and fixing approved make of 25mm dia automatic air release valve of single ball Nos 2
or spring loaded type complete with unions etc. complete.
18 Supplying, installing, testing and commissioning of Gun metal chrome finished Ball valves
with fittings of screwed end type.
a 25mm nominal dia Nos 3
19 Supply, fabrication, erection, alignment and fixing in position, true to line and level, Kg 1,000
structural steel work for structural supports etc. made out of rolled steel angles, plates,
steel tubes etc., including splicing, cutting, bending, drilling, welding, riveting, bolting etc.,
with all tools and tackles, plant and machinery including preparation of detailed shop
drawings as per design drawings and specifications, wire brushing to remove mill scales
etc and painting. Quoted rate shall be inclusive of two coat of primer and two coat of
synthetic enamel paint of approved shade.
20 Flow Switches to indicate and transfer signal to Fire Alarm Panel regarding the flow of the NoƐ 1
water in respective brusting of sprinkler
21 Supplying, installing, testing and commissioning K 80 conventional Sprinkler quartzoid
bulb type of standard coverage and standard response with 15 mm screwed end
connection of 68 deg. C. temperature rating and orifice shall not be less than 12.7mm.
Sprinklers shall be UL Listed / FM approved with Chrome finished.
22 Stainless steel corrugated flexible pipe(hose) for dropping sprinklers below false ceiling, NoƐ 6
pipe shall be 16 bar pressure rating and 1500 mm long 25 mm dia with union / reducer
collar, clamps etc. as required.
23 Supply & fixing of approved type rosette plates (Surface mounted type, in two piece) for NoƐ 6
Sprinklers below false ceiling area.
24 Supply, installing, testing and commissioning of analogue addressable Fire Alarm Control NoƐ 1
panel with 48 hrs battery back up.The Panel Shall be single loop capacity. The control
panel, battery charger etc, The panel shall consisting with 80 character LCD display and
RS 485 for networking.
25 Supply, installing, testing and commissiong of Analogue beam detector NoƐ 12
Schedule of Work
Supply, Installation, Testing and Commissioning of Fire Protection System for Central Warehouse
at AMTZ, Andhra Pradesh
Tender No EP / AMTZ / CWH / FPS / 04
Sl. Description Unit Qty Unit Rate (Rs) Amount (Rs)
No.
26 Supply, Installation, Testing and Commissioning of Intelligent Addressable Photo Electric NoƐ 6
Type Smoke Detectors - Below False Ceiling with indicating lamp, mounting base and all
other mounting accessories complete as required.
27 Supply, installing, testing and commissiong of Analogue Addressable I/O Module . NoƐ 6
30 Monitor Module: Supply, Installation, testing and commissioning of Addressable Monitor NoƐ 1
Modules for Interfacing PFC/Dry Inputs of Sprinkler Line Flow Switch Status in Faire Alarm
Panel integration with all the mounting accessories complete as required.
Do not quote
31 Supplying, installing, testing and commissioning of 2 core x 1.5 sq. mm, annealed tin
copper conductor, armoured FRLS outer sheathed PVC insulated Cable confirming to IS
Rmt 1700 here
1554 Part-1. with Ferrules, Lugs, saddles, saddles base, conduits (if required) & other
accessories complete as required. Whereever the cable is laid inside the office, it shall be
concealed as per the direction of Engineer-in-Charge. The job includes chipping of walls
and making it good for
concealed wiring.
32 Supply, installation, transportation of Fire Extinguishers including supply of nuts, bolts,
brackets etc. including making good of wall, wherever required, after installation and
supply of all related material all complete as per codes, standards, specifications,
documents and direction of Engineer-in-Charge.
a) CO2 type Fire Extinguisher -4.5 KG as per IS 15683 NoƐ 10.0
c) DCP type Fire Extinguisher -25 Kg as per IS 10658, Trolley type NoƐ 2.0
33 MS Fire Water buckets fillled with sand including the structure of fixing- 3 buckets on MS Nos 1.0
fabricated stand. The stand shall be painted with red oxide or zinc chromate primer and
synthetic enamel paint thereafter.
34 Self Illuminated Signages-Fire Exit, Fire Extinguishers, Danger, Fire Bucket and No NoƐ 22
Smoking, Size 300 x 150 mm approx
35 Self Illuminated Fire EXIT Signages 10 '' X 12 '' NoƐ 6
36 Supply & fixing of Signboard-Aluminimum Composite Panel Board of 3mm with Sq. 75
ecosolvent printing with Lamination and Radium Stickers of differenerti sizes such as 12 ft
inch X 6 inch, 8 inch X 4 inch or any other sizes
37 Sign-writing/Letter writing with 'Post Office Red' paint or any other shade (as directed by Sq. 2
Engineer-in-Charge) on sing-boards or on the wall like '''Fire Extinguisher",Fire Bucket"', m.
"Danger", numbering of extingusihers etc.
38 S.I.T.C of 1.5 HP single stage, high speed, horizontal, centrifugal, open well Submersible NoƐ 2
pump (Kirsokar KOS N or euiavlent model of other approved make) to be installed in
RCC water reservoir along with standard length suitable size power supply cable suitable
for operation on Three phase,415 volts, 50 Hz, A.C Supply etc.complete as reqd. as per
specifications below. Pump shall generate flow of 7.5 Cum/Hr at head of 20 mtr. The
scope shall include suppply and fixing GI pipe line with necessary fiitings at pump delivery
with connection to CPVC water line laid by other contractor. The scope also covers supply
and installation of sutiable IP-54 DOL starter for the mentioned pump with contactors,
overload realys, on-off switches etc.(L&T or approved equivalent make). (1 No Pump -
Work + 1 No Pump- Stand By)
39 Supply, installation, testing & commissioning of C-PVC Sch 40 Brass Threaded end Ball Nos 2.0
valve of 2 Inches
40 Supply, installation, testing & commissioning of C-PVC Sch 40 Brass Threaded end Ball Nos 2.0
valve of 1 1/2 Inches
Schedule of Work
Supply, Installation, Testing and Commissioning of Fire Protection System for Central Warehouse
at AMTZ, Andhra Pradesh
Tender No EP / AMTZ / CWH / FPS / 04
Sl. Description Unit Qty Unit Rate (Rs) Amount (Rs)
No.
41 Supply, installation, testing & commissioning of C-PVC Sch 40 Brass Threaded end Ball Nos 2.0
valve of 1 Inches
42 Supply, installation, testing & commissioning of C-PVC Sch 40 Brass Threaded end Ball Nos 1.0
valve of 1/2 Inches
43 Supply & fixing of 1 1/2 inch brass gate valve with CI wheel NoƐ 1.0
44 Supplying and Fixing of 40 mm dia. Gun Metal vertical threading type non return valve , Nos 2.0
including cutting , threading etc. as reqd..
45 Supply and installation of Brass mechanical type flange end flowmeter for AMTZ inlet of Nos 1.0
50NB
46 Excavation and back filling work with all materials, labour, tools and tackles complete as CuM 8.0
Do not quote
per direction of Engineer-In-Charge.
47 P.C.C. work with shuttering, all materials, labour, tools and tackles complete as per CuM 4.0
here
direction of Engineer-In-Charge
48 R.C.C. work (inclding shuttering & reinforcement @ max. 100 kg per Cum of concrete) CuM 2.0
with all materials,labour, tools and tackles complete as per direction of Engineer-In-
Charge for the supports.
A TOTAL (BASIC)