Manual On Monitoring Infrastructure Projects by A Practitioner
Manual On Monitoring Infrastructure Projects by A Practitioner
on Monitoring
Infrastructure
Projects
by a Practitioner
by the
© 2010 by the Concerned Citizens of Abra for Good Government and the Affiliated Network
for Social Accountability in East Asia and the Pacific (ANSA-EAP). This is a release edition,
published January 2010.
This material may be copied and used for research, educational, scholarly or non-profit
purposes without permission of either ANSA-EAP or CCAGG. We request that ANSA-
EAP and CCAGG be cited as the source of the information and that any photo credits or
bylines be similarly credited to the photographer or author or ANSA-EAP or CCAGG,
as appropriate. If a copyright is indicated on a photo, graphic, or any other material,
permission to copy and use these materials must be obtained from the original source.
The Ateneo School of Government, a unit of the Ateneo de Manila University (Philippines),
operationalizes and oversees the development of ANSA-EAP, with support from The World
Bank’s Development Grant Facility. ANSA-EAP is an independent project of the Ateneo
School of Government under the Ateneo de Manila University, which is the executing agency
of the project. As a project of the Ateneo, it falls under the legal governance of the Ateneo
Board of Trustees and President.
A - Earthwork 25
* Clearing & Grubbing (Item 100) 25
* Removal of Structures and Obstructions (Item 101) 25
* Excavation (Item 102) 27
* Structure Excavation (Item 103) 29
* Embankment/Backfill (Item 104) 30
B - Subbase and Base Course (Preparation for Concrete Pavement)
* Subgrade Preparation (Item 105) 31
* Aggregate Subbase Course (Item 200) 32
* Aggregate Base Course (Item 201) . 32
* Placing of Forms 35
* Erroneous Practices in Subbase & Base Preparation 36
* Erroneous Practices in Placing of Forms 37
C - Surface Courses
* Portland Cement Concrete Pavement (Item 311) 38
* Process of Concrete Production 40
* How to Assess Item 311, Placing of Forms 44
* Erroneous Practices in Concrete Works 50
* Common/Major Defects in Concrete Pavement 53
Preface
INTRODUCTION
1. NEDA will train CCAGG on the In the course of their monitoring, CCAGG
mechanics of monitoring; read a full page report of the DPWH Abra
6 Laymanized Manual on Monitoring Infrastructure Projects by a Practitioner
published in a regional newspaper which This project was meant to enhance public
said that twenty of the projects they were accountabiolity of COA and was funded by
monitoring were already reported finished. the United Nations Development Program
They themselves asked how this could be (UNDP). A Memorandum of Agreement
when some of these projects were not yet was signed by the COA and CCAGG to
started, or have just begun or were but formalize their engagement. COA then
midway in implementation. They reported was headed by Chairman Celso Gangan.
the matter to NEDA. They also sought an Twenty-three road projects of the Dept. of
audience with the DPWH secretary and Public Works and Highways (DPWH) and
requested him to send an incorruptible community-based projects of the Dept.
audit team to verify their complaints. of Environment and Natural Resources
The audit team found their complaints (DENR) implemented in 1999 and 2000
meritorious. They also unearthed The joint venture was adjudged a success
certificates of project completion signed and was replicated in Samar, Camarines
by section chiefs and “turned over” to the Norte, and Mt. Province. This experience
end-users. An administrative case was proved that public accountability can be
filed against the eleven erring engineers enhanced transparent and accountable
which found them guilty. Eleven engineers governance through citizens’ participation.
were suspended from office for a period of
time without pay, commensurate to their The good that citizens’ monitoring
guilt. could give in attaining transparency
and accountability in the prosecution of
For pursuing the case unrelentingly, government projects has reached many
President Cory Aquino cited the CCAGG in places in the Philippines. Many civil
a fitting ceremony in Malacañang Palace. society organizations sought the CCAGG to
The DPWH Director for Region-I also replicate its activities with them. To date,
directed their district office that no projects there is now a Nothern Luzon Coalition
will be paid without the monitoring report for Good Governance (NLCGG) composed
of the CCAGG.. of twenty-one civil society organizations,
academe and Church-based social action
The successful initiation of the CCAGG into centers in the Cordilleras, Region I and
monitoring emboldened them all the more Region II. Many of them have started to
to go into project monitoring. In 2000, flex their muscles in exacting honesty and
Transparency International gave CCAGG its accountability in governance in their areas
first Integrity Award for its exemplary fight of operation.
against graft and corruption at the local
level. In the same year, the Commission
on Audit (COA) and the CCAGG signed a
Memorandum of Agreement to pilot test
Participatory Audit in Abra. This was the
first ever experience of COA in involving a
civil society organization in its audit works.
Independent Monitoring Described 7
followed up in subsequent meetings and pour cement to a muddy road?” “Why was
project visits. A copy of these corrections the mixture of cement and aggregates
and other recommendations are furnished watery?” Children also report anomalous
to the Commission on Audit (COA). transaction like “Why did the barangay
captain brought home bags of cement and
Public Participation in Project Monitoring steel bars after a drinking spree with the
and Evaluation as a Right project supervisor?” “The contractor used
Pozzoland not Portland cement.” These
Over the years, CCAGG encountered and many more are some of the indirect
communities who wanted to plunge interventions of woman and children in
into monitoring work but were deterred the field of monitoring.
by fear of meeting detractors who ask
questions like “Where did you get your Good Governance Result From Monitoring
authority to intervene in a purely technical
endeavor?” The CCAGG stands firm Experiences have shown fruitful
on the principle of two basic collective participation in Monitoring trickled down
rights of every citizen such as the right to to greater benefits of having a well-
participate in governance and the right to implemented project. Mothers who are
information which promotes transparency. household managers are relieved from
Communities, endowed with these rights worry if they have need to rush their
are free to intervene and to express their daughters to a hospital in an unholy hour
will for the improvement of their life. knowing that the road is safe to travel.
She will not feel hesitant to send her
Government institutions and child to a school knowing that is it well-
instrumentalities, as duty holders, are built. If her family lives in a farm, she has
compelled to respond to the rightful assurance that they can transport their
and appropriate demands of the people. goods to the market through a farm-to-
Monitoring findings will serve as valuable market road. And most health workers,
inputs to government on how to manage school supervisor and even by their local
public resources efficiently. executives. Mobility is enhanced as there
are more vehicles plying the route and
Gender Perspective of Monitoring transportation cost is cheaper because of
lesser wear and tear of vehicles. All these
Monitoring was and will never be a job are indicators of improved living condition
for men. Women and children who are to the advantage of children, women
often left at home are the innocent but and elderly as end result of citizens’
mindful witness whenever there are new participation in monitoring.
government projects in an area. These
women and children provide feedback
based on what they saw and heard. At
times, they ask good questions on the
process of construction work “Why do you
Independent Monitoring Described 9
Process of Monitoring
Monitoring
Stages of Documents Framework of
Process/
monitoring Gathered Analysis
Activities
- Periodic status
- Monitoring
report, POW/
- Reporting/ Deviations are
Project Plans,
Feedbacking brought to the
designs
- Problem solving attention of the
- Tender
session higher ups for
documents
- Follow up of proper action.
- Exception
recommendations
reports
- Final /
completion report
- Statistical data - Assessment on
- Beneficiary socio-economic
Post Evaluation/ - Bench Marking
survey result and political
Impact - Actual Project
- Interview, impact.
Assessment functionality
feedbacking - Follow up
results recommendations
- Community
beneficiary profile
10 Laymanized Manual on Monitoring Infrastructure Projects by a Practitioner
shall not be abridged. The State shall by that oversee the operation of RPMES were
law, facilitate the establishment of adequate established in each region through EO 376
consultation mechanism.” and in each LGU levels through MO 176. At
the National level, the NPMC is composed
b) Executive Order No. 175 of NEDA, DBM, OP-PMS and DILG with
Signed on May 23, 1988 by President NEDA as the secretariat. At the regional
Corazon Aquino, this Executive Order level, RPMC is composed of NEDA, DBM,
provided guidelines for the implementation DILG, OP-PMS and NGO representatives.
of local government projects funded from While at the LGU level, PPMC composition
National Funds. These guidelines include is subject tot he discretion of the Local
the following: development council subject to the
inclusion of DILG, NGO representatives
a) The creation of Pre-qualification, and nominees of the development council.
Bids and Awards Committee (PBAC) in
each province and municipality shall The deputized NGO monitors are tasked
be responsible for the conduct of pre- to:
qualification of contractors, bidding,
evaluation and bids and recommending a) Assist the PMC or development council
awards to contracts; in the monitoring and evaluation of projects
b) The creation of Project Monitoring by identifying implementation problems or
Committee (PMC) that will monitor the outstanding performance through project
implementation of projects. exception reports;
b) Ensure effective/efficient
There is a provision in the PBAC where an implementation of projects through
NGO sits as an observer but in the PMC, an vigilance; and
NGO is a regular member. c) Act as government partners in ensuring
transparency in project implementation
c) Executive Order No. 376
d) “Republic Act 9184 otherwise known
The President, Mrs. Corazon Aquino signed as the Government Procurement Reform
Executive Order # 376 on November 2, Act (GPRA)”
1989. It established the Regional Project
Monitoring and Evaluation System (RPMES) It provides a mandatory venue for people’s
which envisions to monitor and evaluate all participation through the Bids and Awards
development projects (economic, social, Committee (BAC). The law requires that
physical, infrastructure development in all stages of the procurement process,
projects) at the regional, provincial and the Bids and Awards Committee shall
municipal levels funded from national and invite two observers. One coming from
locally generated resources. The RPMES duly recognized private sector association
shall be implemented by development and the other from a Non-Government
councils at various levels. Organization (NGO) duly registered with
The project monitoring committees (PMCs) the Securities and Exchange Commission
CCAGG Tools in Monitoring 15
(SEC). Another feature of the law is the playing field through the availment of a
inclusion of the Government Electronic greater number of potential bidders.
Procurement System (GEPS). This will
bring the procurement to a more level
Section 62.2.4
In case of structural defects/failure occurring during the applicable warranty period
provided in section 62.2.2 hereof, the Government shall undertake the necessary restoration
or reconstruction works and shall be entitled to full reimbursement by the parties found to be
liable, offenses incurred therein upon demand, without prejudice to the filing of appropriate
administrative, civil, and/or criminal charges against responsible persons as well as the
forfeiture of warranty securities posted in favor of the Government.
Based from the aforementioned rules the The performance of a completed project
Government, representing the citizenry, should therefore be monitored and
will be able to castigate and dispense evaluated until the warranty period lapses.
punishment due to negligent persons/ Our role as independent monitoring bodies
parties, maybe the contractor, consultants, and observant stakeholders is much needed
procuring entity’s representative/project in this stage – as Government partners – to
managers and supervisors, third parties or take full advantage of not so many project
the end users for the failure of the project. implementations in our areas.
CCAGG Tools in Monitoring 17
Area = 1 bh
2
CCAGG Tools in Monitoring 19
5. Trapezoid: Solution:
b2
1. Convert the given unit of measurements
h into meter.
2. Volume = L x W x t
= 1000m x 4.0m x 0.15m
= 600 cu.m.
Contributory to the quality and speed of concrete, etc. These excuses should not
work are the following: be allowed especially when the use of
these tools and equipment are specified in
Experience and Skill of the Workers in the contract. It would not be there without
their Field. a purpose
I. ROAD CONSTRUCTION /
REHABILITATION
Project Billboard
Billboard
2. Backhoe - It is used to
dig trenches for structure
excavation such as protection
walls, culverts, etc. Also used
in trimming uphill slope road
boundaries.
A. Earthwork
Clearing and grubbing Removal of Structures
(Item 100) and Obstruction (Item 101)
It should consist of clearing all vegetation
and debris as designated in the contract.
The work should also include the preser-
vation of all objects designated to remain.
3. Individual Unit Basis (Selective Clearing). Bridges, culverts, and other drainage
Cleared trees of 1.4m in height will be structures in use by traffic should not be
paid. Trees less than 150mm in diameter removed until satisfactory arrangements
will not be measured for payment. When have been made to accomodate traffic.
the measurement of cleared trees is by
piece, it will be done in accordance with Blasting or other operations necessary
the following schedule of sizes. for the removal of an existing structure
or obstruction, which may damage new
construction should be completed prior to
Diameter of Payment Item the start of the new work, unless otherwise
height of 1.4 m. designation provided in the special provision.
over 150 to
Small
900mm
Roadway Excavation
Construction Requirement/
Process
1. The trenches or foundation pits for 1. Look for the established vertical control
structures should be excavated to the point. This will be used for the computation
designed width, length and depth. of the actual volume of embankment.
2. The depth of excavation though 2. Verify the actual source of embankment
appoximated on the plans canl be materials and compare it with the approved
adjusted in order to secure a satisfactory quarry site.
foundation. 3. Any approved change in the quarry
site/borrow pit location should bear
a corresponding adjustment on the
Embankment (Item 104) computation of cost.
4. Make sure that the materials used
Description is granular such as sand and gravel or
selected borrow.
Embankment or backfill of holes, pits with 5. The embankment should be compacted.
the roadway is compacted using approved 6. The embankment should be completed
materials. as planned and programmed.
Construction Requirements
Construction Requirements
Material Requirements/Process
Construction Requirements
How to do FDT?
When to do FDT?
Placing of Forms
C. Surface Course
1. Measuring ingredients/Batching
The ingredients to be measured are
a. Cement
b. Fine aggregate
c. Coarse aggregate
d. Water
e. Mixtures
AGGREGATES are riverbed materials such a. Fine—natural sand or crushed stone with
as sand, gravel or crushed stones which most particles passing through a 3/8 inch
must be clean, hard, strong, and durable. (9.5mm) sieve.
Old concrete which has been crushed is a b. Coarse—are any particles greater than
feasible source of aggregate. 0.19 inch (4.75mm) but generally range
between 3/8 and 1.5 inches (9.5mm to
The aggregates should be free of absorbed 37.5mm) in diameter.
chemicals, coatings of clay, and other fine
materials.
Almost any natural water that is drinkable A. Cement: the most common used cement
and has no pronounced taste or odor can be is Portland. It should be dry, powdery and
used in mixing water for making concrete. free of lumps. Store cement away from
Water suitable for making concrete, damp floors. Stack the bags close together
however may not be fit for drinking. to reduce air circulation.
2. Mixing
3. Pouring
1. Expansion Joints - The adjoining slabs permit the concrete to expand as the temperature
increases. This is provided at right angles to the centerline of the road and should extend
to the full width and depth of slab at a distance, which varies from 18-27 meters.
Method of Measurement
The area to be paid for under this item is according to the length measured horizontally
along the centerline of each roadway.
46 Laymanized Manual on Monitoring Infrastructure Projects by a Practitioner
C. Post Construction
After placing the pavement forms, compaction work at the road base shall only be done
for correction purposes.
48 Laymanized Manual on Monitoring Infrastructure Projects by a Practitioner
Filling of aggregates
in the measuring box
should be levelled in
order to attain the exact
proportion of concrete
mixture.
Shear key
1. The surface must be free from cracks or A prime coat is applied to the prepared
shrinkage. untreated base or in the case of previously
2. It must withstand weather condition constructed asphalt or cement surface,
brought about by water, heat, cold, and tack coat is applied to improve the adhesion
oxidation. between the base and the surface course).
3. It must be resistant to internal moisture
such as water vapor. When new aggregate is to be used for the
4. It must possess a tight surface road to mix surface course, the existing
5. It must be smooth riding with skid free surface have scarified lightly and bladed to
surface. uniform grade and to cross section shown
on plans and then rolled or watered as
The durability of an asphalt pavement lies directed.
or depends much upon the construction of
the subgrade and the base course. Surface Treatment
A prime coat is applied over untreated and Overlay is a layer of asphalt laid on an
treated base before asphalt concrete is laid. existing pavement. The purpose is to
The purpose is to bind any loose particles of straighten out a distorted surface or to
the base and likewise act as a bond between cover cracks and joints of the pavements.
the base and the pavement to deter rising Overlay thickness could be from 50mm to
moisture from penetrating the pavement. 150mm.
Dust Palliatives for Dust Control is a Slurry Seals is an effective solution for
surface treatment of asphalt to control dust filling cracks and rejuvenating the road
and fine sand along the highways. surface. Slurry seal is a combination of
sand, crushed stone, emulsified asphalt
Prime Coat or Tack Coat. The purpose of and water.
the prime coat is to plug capillary voids
in the pavement to stop the movement What to Inspect?
of mixture and to improve the adhesion
between the base and surface course. 1. Proper placement of asphalt binders has
to be checked to avoid surface failure.
2. Proper compaction to avoid sagging of
Armor Coat is a treatment using a thin the surface and base.
bituminous binder covered by mineral 3. The sinking or sagging of the surface
aggregate applied to an earth gravel may be caused by the soft subbase.
or water bound macadam surface or to 4. Check that there is no pool of water
stabilized base. For limited funds, armor along this pavement type as it will soften
coat is used as temporary pavement and the surface causing it to be scoured.
protection for the base materials.
General Asphalt Road Irregularities
Seal Coat is the application of asphalt
binder to pavement surfaces covered with Improper construction, insufficient road
aggregate. Seal coat serves: a) to provide thickness and poor mixture ratio will
an abrasion and water resistant surface; only result to expensive patching or
and b) improve skid resistance of bleeding surface repair. The inefficiency of the
bituminous surface. construction can be either an act of
omission or commission.
Sheet Asphalt is a mixture of sand, fillers
and asphalt cement. Sheet asphalt is The absence of poor drainage design will
commonly about 1 ½ “ thick over asphalt mean erosion or deposition of materials
concrete or PCCP. Its surface is easily requiring costly clean-up operations.
cleaned and is extensively used as surface
course on urban streets.
B. Bedding E. Backfilling
The conduit bedding shoud conform to one Materials for backfill on each side and
of the classes specified below... top of the conduit shall be of fine, readily
compactible soil or granular material
Class A bedding should consists of a selected from excavation sites. No stones
continuous concrete cradle conforming to beyond 50 mm, chunks, plastic clay or
the plan details. other objectionable material should be
used.
Class B bedding should have a depth of not
less than 30 per cent of the vertical outside
diameter of the conduit. The minimum
thickness of bedding material beneath the
pipe be 100 mm.
C. Laying Conduit
Conduit laying begins at the down stream
end . Its lower segment should be
in contact with the shaped bedding
throughout its full length.
D. Jointing Conduit
The method of connecting conduit sections
should be such that the ends are fully
inserted and the inner and outer surfaces Check the size of the Reinforced Concrete Pipe
are reasonably sealed. (RCP) by measuring its diameter. The size to be
used should be the size as indicated in the Plan
and Program of Works (POWs) to avoid water
overspilling.
Road Construction / Rehabilitation 59
Head wall
Cross drainage
Head wall and concrete apron are constructed at the installed cross
drainage. The apron protects the foundation from scouring due to
the unrush of rain water.
Curing:
The structure shall be kept wet for a period
of at least three days after completion.
Road Construction / Rehabilitation 63
Protection Walls
Material Requirements
The boulders in these stone masonry structures are easily removed due to insuficient
grout applied. This can be a cause for easy collapse.
Road Construction / Rehabilitation 71
2. Embankment is a raised structure along the river bank made of materials like sand,
stones and soil.
3. Revetment is a flood control structure along the river banks for slope protection.
Revetments maybe a stone masonry, concrete blocks or walls.
78 Laymanized Manual on Monitoring Infrastructure Projects by a Practitioner
4. Spurdikes are used to deflect the flow of waters to prevent scouring of major structures.
5. Channels are conduits to divert flood flows. These structures could be open channels
or closed conduits.
Flood Control Structures 79
Bridges consist of two major breakdown: 3. Bored Pile. A drilling machine bores
the substructure and superstructure. the ground of about 1.50 meters
diameter until it reaches the hardest
A. The bridge substructure is composed strata of the soil. A steel reinforcement
of pier and abutment including the will be placed at the bored hole
foundation. followed by the pouring of concrete
The pier footing is constructed over the
There are three types of foundation for pier bored pile.
and abutment. These are:
B. Bridge Superstructure is composed of
1. Spread Footing. This is designed for beams, girders, trusses, deck and any part
abutment / pier which is constructed of the bridge which an abutment and pier
over solid rock. carries.
Main cables
Tower
Hangers
Railings
Steel matting
k
Dec
l
tee Protection wall
S
Steel panel
Bridge Components
Concrete railings
Protection wall
Column / Piers
Concrete girders
Side walk
Concrete deck/slab
84 Laymanized Manual on Monitoring Infrastructure Projects by a Practitioner
Types of Bridges
Types of Bridges
Types of Bridge
Box culve
rts
Diesel Hammer
Bar Cages
First Stage
A. A backhoe excavating
the foundation of the
bridge abutment.
B. Preparation for
the installation of the
footing reinforcement
Abutment post
Second Stage
B. Laying of steel
or concrete beams
and girders follows
after constructing the
abutment and pier.
Third Stage
Superstructure of the
bridge laid.
Bridge Construction 97
H-piles
Vertical bar
Footing bars
Shear studs
Bolts
Installation/construction of
girders and beams for the
superstructure of either a
Girders steel or concrete bridge.
The sequence may vary depending upon the walls and top slabs which are allowed
working condition in the jobsite, provided to set before the top of slab is placed and
that a special detail ( shear transfer appropriate keys are placed in the sidewall
mechanism) be adopted to eliminate weak for anchoring the top slab.
joints.
3. Consolidation are made with the aid no voids are left within the rubble masonry.
of mechanical vibrating equipment and
supplemented by hand and spacing and 4. The preparation and handling of the
tamping. concrete binder should be the same as that
of the concrete. In general, one cubic meter
4. Construction joints should be provided of rubble masonry will require one-half
where succeeding concrete are to be cubic meter (0.5 cu.m.) of concrete binder.
placed.
5. In case reinforcements are placed, no
5. Curing should be done for a period of stone should be closer than 10 cm to the
not less than 14 days. Form and support nearest reinforcing bars.
shall be removed only after the concrete 6. Rubble masonry should be cured for 5
as attained sufficient strength to support days.
its own weight.
For Support Structure
Reinforcement
A. Ungrouted Riprap
1. Reinforcement is laid, anchored and
embedded in the concrete. 1. Boulders should be placed immediately
following completion of the embankment,
2. Spacing of bars is measured along the channel or section of the structure.
center line of the bars.
2. On the prepared gravel blanket or
3. Reinforcing bars is accurately placed sub-grade, the boulders should be laid
and secured in position so as to avoid and arranged properly to offer maximum
displacement during the pouring of the resistance to displacement due to high
concrete. water velocity.
4. Splicing of bars is as shown in the plans. 3. Spalls of appropriate size filler stones
should be placed to fill spaces between the
5. Welding of bars is performed only where boulders.
shown in the drawings.
B. Grouted Riprap
For Rubble Masonry Structure
1. The bed for grouted riprap should be
1. The stones should be thoroughly wet excavated to the required elevation and
before they are installed in place. then properly tamped and trimmed.
2. The entire surfaces of every stone shouldl 2. The stone should be laid with close joints
be thoroughly covered with concrete binder. by hard.
3. The concrete binder should be placed 3. The stones should be moistures and then
into the spaces between the stones so that grouted with mortar.
106 Laymanized Manual on Monitoring Infrastructure Projects by a Practitioner
4. All spaces between the stones should be 2. The POW- It should be studied by the
completely filled with mortar from bottom team to familiarize the quantity and class
to top. of materials to be used in the project.
(The sizes and quality of materials to be
5. The grouted riprap should be cured with installed).
water for a minimum period of 3 days.
3. The feasibility study- must be received.
6. Mortar for grouted riprap should consist This is where important information about
of one part cement to three parts of sand the project are indicated like the proponent,
by volume and water to produce a thick and target beneficiaries/ organization, target
creamy mixture. area, project cost, and sustainability plan
Manhole
Types of DWS Services:
b. Deep well can serve about 40-100
1. Level I - Point Source households and shallow well around
5-40 households depending on the yield/
a. It can be any of the following: shallow discharge.
or deep well, a developed spring, rain
2. Level II - Public Stand Post
water collected and infiltration galleries
with no distribution system. a. This is a communal faucet system
intended for rural areas. A simple pipe
disribution system with strategically
located faucets are provided where
houses are densely clustered.
4. Cased Well/Drilled Well is an open hole must be covered with contamination proof
normally constructed by jetting or drilling closure at the top.
using either rotary or percussion drilling
equipment. 3. Shallow Bored Well
Metal casings should be the same as for
5. Gravel Posted Well is a bored hole to deep wells. Concrete on tile casings should
accommodate casing/screen surrounded reach at least 10 feet below the ground.
by gravel is constructed by either rotary
or jetting method. 4. Driven or Jetted Well
Utilize the steel or wrought iron well pipe
Common Items of Work in Water Supply as the well’s own casing.
Project:
5. Deep Well
1. WELL DEVELOPMENT AND Wrought iron or heavy steel casing should
CONSTRUCTION be used.
a. Screens – Copper alloy, corrosion-
The elements of well completion are the resistant steels, or equally corrosion
following: resistant materials are used.
b. Length should not be less than the
a. Installing the well screen in sand and thickness of the water bearing formation
gravel foundation (aquifer). Partial penetration may be used.
b. Developing the water bearing formation
c. Cementing or grouting the well casing Gravel Packaging:
in the drilled hole
d. Sterilizing the well 1. Shallow Dug Wells
e. Providing other sanitary protection Gravel should be backfilled around the
casing and at the bottom, but this should
Well Construction not go higher than 10 feet recond from the
surface.
Criteria:
2. Drilled and Large Bored Wells
1. Casing – for all types of well, double case
or single case and grout the top 10 feet as At least 2 inches of gravel packing should
minimum. be provided around the screen sufficient
to allow losses during the development of
2. Shallow Dug Well the well.
Upper casings should be concreted or 6
inches minimum thickness to a depth of at Surging:
least 10 feet below the ground, however,
1. Pump Surging
casings should be perforated and should
This method involves repeated pumping
contain openings for the entry of water and
from the minimum to a higher rate until
must firmly be seated at the bottom. Well
the capacity of the well is reached.
Domestic Water Supply 115
Pipe Laying and Jointing c. Concrete pipe- galvanized steel ring bell
and spigot type joints or their variation with
a. The full length of each section of pipe rubber gaskets and cement linings should
should rest solidly on the pipe bedding. be used.
b. Any pipe that has its grade, alignment or
joint disturbed after laying should be lifted d. Steel pipe joints
up and re-laid after concreting the bedding. 1. Mechanical type couplings - Use
c. Pipe should not be laid in water or when on pipes 24 inches inside diameter or
weather conditions are not suitable for smaller.
work. 2. Welded joints- Used on pipes which
116 Laymanized Manual on Monitoring Infrastructure Projects by a Practitioner
have no inside and for pipes 24 inches The following are factors to consider in the
diameter and over. construction of surface reservior:
3. Flanged Joints- These are used
when valves or special fittings are to be Piping arrangement: For Large Tank
attached to the pipe.
4. Expansion Joints- Used at appropriate 1. Place inlet and outlet pipes at the
in terrals on pipe with welded joints to opposite ends or sides to provide circulation
relieve strains especially for exposed with the outlet pipe near the bottom.
pipes. 2. Provide overflow and drain pipe.
5. Packing- Rubber should be used on all 3. Provide valves on all pipes except the
except joints. overflow.
Intake Box
Transmission Pipe
Storage tank
or reservoir
Transmission pipe
Transmission Pipe is used to convey water from the spring source to the storage tank.
Transmission pipe at the intake box should be located at least 10 cm. from the bottom
of the box and/or at least 10 cm. from the top of the storage tank. The transmission line
should have the following appurtenance or fittings:
1. Union de patente for G.I. pipes should be spaced every 10 pipes or 60 meters.
2. A blow-off-valve should be provided at the lowest part of the transmission line. This will
be used for discharging impurities or solid particles that will be accumulated in the system.
3. Air relief valve should be provided at the highest point of the transmission line to release
trapped air for smooth flow in the system.
Distribution Pipe is used to convey
water from the storage tank to the
community. It should be provided with
the same fittings like the transmission
pipe.
Storage Tank
2. Setting Out
It is a process of using the surveying
instrument and appropriate technique to
transfer information from a plan to the
ground, in order to establish the building
line location.
3. Excavation
Excavation depth indicated in the drawings
shall be followed. If the required safe
bearing power of the soil is not obtained
at the excavation depth indicated, the
Building Construction 121
Important notes to consider: surface has not absorbed moisture and has
1. All steel reinforcing bars shall be not splintered, deformed or peeled, subject
accurately placed and secured against to the approval of the supervising Engineer.
displacement by tying them together at It is generally advantageous to leave form
each bar intersection with gauge No. 16 GI in place as long as possible to continue
wire. the curing period. However, there are
2. No metal reinforcements shall be times when it is necessary to remove them
installed in place unless it is free from rust, as soon as possible. In any case, forms
scale, mud, oil or other coatings, which will should not be removed until the concrete
destroy or reduce the bonding capability is strong enough to satisfactorily carry
with concrete. the stresses from both the dead load and
3. Lap splices in bars shall be avoided as any construction loads shall be supported
far as possible and shall be staggered in on, nor any shoring removed from, any
any one structural member. part of the structure under construction
except when that portion of the structure
Concrete Protection (ACI 318-71). Unless in combination with remaining forming
otherwise specified, the thickness of and shoring system has sufficient strength
concrete over reinforcement shall be as to support safely its weight and loads
follows: placed thereon. Sufficient strength should
1. Where concrete is deposited against be demonstrated by structural analysis
ground without use of forms, not less than considering proposed loads, strength of
3” forming and shoring system, and concrete
2. Where concrete may be exposed to strength data. Concrete strength data
ground but is placed in forms, not less than should be based on strength of field-cured
2” cylinders.
3. Where concrete may be exposed to
weather, not less than 1 ½” In any case, the minimum requirements on
4. In slabs and walls not exposed to the the following prevail on normal condition
ground or to the weather, not less than ¾” of loading.
5. In beams, girders and columns, not less
than 1 ½”. CONCRETE WORKS
SAND GRAVEL
CLASS MIXTURE CEMENT
cu.m. cu.m.
40kg/bag 50kg/bag
The measuring box used to measure sand Specifications usually require a minimum
and gravel for the values above for 40kg/ of one minute mixing for stationary mixers
bag cement has a dimension of 0.30m x of up to one cubic meter capacity with an
0.30m x 0.30m. increase of 15 seconds for each additional
one cubic meter or fraction thereof. The
Unless otherwise indicated on the project mixing period should be measured from
Plan or in the Specifications, the following the time all cement and aggregate are
classes of concrete shall be adopted: already in the drum, provided that all of
Use Class A (fc’ = 3000 psi) for slabs, beams, the water is added before one-fourth of
girders, arches,columns, wall spanning the mixing time has elapsed. Under usual
openings and acting as beams, baffles or conditions, up to about 10% of the mixing
pins at windows and concrte of 0.10m or water should be placed in the drum before
less in thickness. the solid materials are added. Water then
Use Class B (fc’ = 2500 psi) for walls thicker should be added uniformly with the solid
than 0.10m, footings, piers and reinforced materials; leaving about 10% to be added
concrete steps and slabs on fill. after all other materials are in the drum.
Use Class C (fc’ = 2000 psi) for all plain
concrete work on fill Ready Mixed Concrete
Concrete should not be moved horizontally methods because the concrete is likely to
over too long a distance as it is being placed segregate under this intense action when
in forms or slabs. When the distance is consolidation guidelines are not met.
too long, excess water and mortar are
forced ahead of the moving concrete. This Proper mechanical consolidation makes
produces a non-uniform, poor quality possible the placement of stiff mixes with
concrete when an increased water-cement low water-cement ratios and high coarse
ration finally occurs. aggregate contents associated with high
quality concrete. Vibration, either internal
In walls, beams, and girders, the first or external, is the most widely used method
batches in each lift should be placed at for consolidating concrete. When concrete
each end of the section, with subsequent is vibrated, the internal friction between
placement progressing toward the center. coarse aggregate particles is temporarily
The height of free fall of concrete need not destroyed and the concrete behaves
be limited unless a separation of particles like a liquid; it settles in the form under
occurs, in which case a limit of 0.9 to 1.2 the action of gravity and the entrapped
meters may be adequate. large air bubbles rise more easily to the
surface. Friction is reestablished as soon
To avoid cracking due to settlement, as vibration stops. Internal or immersion-
concrete in columns and walls should be type vibrators, often-called spud or poker
allowed to stand for at least two hours, and vibrators are commonly used to consolidate
preferably overnight, before concrete is concrete in walls, columns, beams, and
placed in any slab, beam, or girder framing slabs. Proper use of internal vibrators
onto them. Haunches and column capitals is important for best result. Whenever
are considered part of the floor or roof and possible, the vibrator should be lowered
should be placed integrally with them. vertically into the concrete at regular
intervals and allowed to descend by gravity.
3. Consolidating Concrete It should penetrate quickly to the bottom of
Consolidation is the process of compacting the layer being placed and at least 150mm
fresh concrete and to mold it within the into any preceding layer. The vibrator
forms and around embedded parts and should be held stationary for 5-15 seconds
reinforcement and to eliminate stone until adequate consolidation is attained,
pockets and entrapped air. and then slowly withdrawn. Vibrators
should not be used to move concrete
Plastic, flowing mixes can be consolidated horizontally since this causes segregation.
by hand rodding, which is, thrusting a
tamping rod or other suitable tool into 4. Construction Joint
the concrete. The rod should be long Construction joints occur when fresh plastic
enough to reach the bottom of the form concrete is placed in contact with existing,
or lift, and thin enough to pass between hardened concrete and a high quality bond
the reinforcing steel and the forms. A and water-tightness is needed between the
mix that can be consolidated by hand two concrete placements.
should not be consolidated by mechanical
Building Construction 127
The concrete near the top surface of a lift should be offset at a minimum distance of
is often of inferior quality to the concrete two times the width of intersecting beams.
below. This is due to the used of badly e. Beams, girders, or slabs supported
proportioned or high-slump mixtures that by columns or walls should not be cast
cause excessive laitance, bleeding, and or erected until concrete in the vertical
segregation. support members is no longer plastic.
in accordance with ASTM C42 (Method of position while the mortar is still soft and
Obtaining and Testing Drilled Cores and plastic, and shall be extended and anchored
Sawed Beams of Concrete) In such case, to concrete slab or beam.
three cores should be taken for each
strength test more than 3.5 Mpa below Surfaces for plastering works shall be
specified value of fc’. cleaned of all projections, dust, loose
c. If concrete, the structure will be dry particles, grease and other foreign matter.
under service conditions, cores should be Before plastering it shall be wetted
air dried for seven days before test and thoroughly with fog spray of clean water
should be tested dry. If concrete in the to produce a uniformly moist condition.
structure is more than superficially wet
under service conditions, cores should be Plaster works shall be finished level,
immersed in water for at least 40 hours and plumbed, square and true without
be tested wet. waves, creeks, blisters, pits, crazing,
d. Concrete in an area represented by core discolorations, projections and other
tests is considered structurally adequate imperfections.
if the average of three cores is equal to at
least 85% of fc’ and if no single core is less CARPENTRY AND JOINERY WORKS
than 75% of fc’. Additional testing of cores All lumber shall have four (4) sides.
extracted from locations represented by Lumber shall be of approved quality, well
erratic core strength results should be seasoned, thoroughly dry and free from
permitted. loose or unsound knots, sap, shakes or
e. If the above criteria are not met, and other imperfections, impairing strength,
if structural adequacy remains in doubt, durability and appearance.
the responsible authority may order load
tests for the questionable portion of the Framing lumber and other rough carpentry
structure, or take other appropriate action. shall be fitted closely, set accurately to the
required lines and levels.
CONCRETE HOLLOW BLOCKS
A concrete hollow block (CHB) shall have No structural member shall be cut, bored
fine and even texture and well defined or notched for the passage of pipes or
edges. It shall be true to size, without conduits without the approval of the Project
cracks, chips, splits and other defects Engineer. All members damaged by such
which may weaken the units. cutting or boring shall be reinforced by
means of specially formed and approved
Masonry units shall be wetted before it sheet metal or bar steel shapes, or removed
is laid plumbed, leveled and accurately and replaced new, as directed by the project
spaced. Full mortar bedding must be engineer.
provided in such a way that no gap is formed
between the blocks and the mortar. To Spikes, nails and bolts shall be of the proper
ensure a good bond, it is best to alter the size as indicated in the drawing and in the
location of a block and fitted to its proper Specifications. Members shall be drilled
Building Construction 133
accurately for bolting, and care should be DOORS AND DOOR FRAMES
observed so as not to split the members. Doors and doorframes shall conform to the
sizes, designs and kind of materials shown
ELECTRICAL WORKS in the details of doors or as per the bill of
The electrical installation shall be done in materials.
accordance with the approved plans and
under the direct supervision and control of STEEL WINDOWS
a licensed Professional Electrical Engineer Steel windows ton be used in this project
or Master Electrician. shall conform to the size and designs shown
in the detail drawings or schedule of steel
All electric works and materials shall windows, or as per the bill of materials.
conform to the provisions of the latest
edition of the Philippine or National Electric VARNISHING AND PAINTING
Code. Paints and varnish materials of the brands
specified shall be delivered to the building
PLUMBING WORKS site with labels intact, unbroken packages
All plumbing works shall be done in and seals. Color shall be in accordance
accordance with the approved plans and with what is specified on the plans or as
under the direct supervision and control directed.
of a licensed Sanitary Engineer or Master
Plumber. Areas to be treated with paint or varnish
must be clean, dry, smooth and free from
The plumbing installation shall conform dust, rust, and grease oil. Nail holes and
to the provisions of the National Plumbing cracks shall be puttied, caulked or grouted
Code and the rules and regulations enforced and thoroughly sandpapered before any
in the locality. paint or varnish is applied.
134 Laymanized Manual on Monitoring Infrastructure Projects by a Practitioner
All concrete and masonry surfaces must be After which, check whether soil is hard
thoroughly neutralized either by brush or enough conforming to specified soil bearing
spray with a solution of 4 lbs. zinc sulfate pressure.
to each gallon of water. Ascertain that
alkalinity is removed; otherwise, a second Foundation
treatment with the same solution shall be 1. Verify if there is gravel bedding requirement
applied. The surface must be dried within prior to putting of reinforcement. Also
24 hours before the application of paint or verify the thickness of gravel bedding vis-
varnish. à-vis the specified thickness.
2. Check for the dimension of the footing if
The directions printed on the label of the it is conforming to the planned dimension.
approved paint and varnish shall be strictly 3. Check the reinforcement if it is provided
followed. with minimum concrete cover of 3 inches
as shown by its distance from the soil or
It shall be the contractor’s responsibility gravel bedding below and the side forms
to protect his painting works during 4. C h e c k w h e t h e r t h e n u m b e r o f
the time his work is underway. He reinforcement and diameter is actually
shall be accountable for any kind of provided as per specifications. And also
damages to the work or property of others note for the grade of the reinforcement.
caused by his employees or by himself.
Concrete Works
Upon completion of the painting works, the
contractor shall eliminate all paint spots Reinforcement
from all finished work, his equipment, and 1. Check the number and size of reinforcing
shall leave the entire premises free from steel bar used.
rubbish caused by his work. 2. Check for the location of splices vis-à-vis
the specified location.
3. Check for the overlap length provided for
Additional Points to Consider in Assessing every splices.
Buildings: 4. Check for the provision of standard hooks
on every specified regions of structural
Staking & Survey of Site elements such as beams, columns and
1. Check actual dimension of building line shear walls if they conform to specified
vis-à-vis plan. bending schedules
2. Check for the presence of vertical natural
grade line. This will determine the actual Concrete
amount of cut or fill. 1. Check for the brand of cement used
which should conform to the specified type
and brand.
Excavation 2. Check for the size of aggregates which
1. Verify the depth of excavation for individual should conform to the maximum size
footings vis-à-vis the construction plan. specified.
Building Construction 135
8. Chutes For conveying concrete to Low cost and easy to Slope range between
lower level, usually below maneuver. No power 1 to 2 and 1 to 3
ground level on all types required, gravity does and chutes must be
of concrete construction. most of the work. adequately supported in
all positions. Arrange
for discharge at end
(downpipe) to prevent
segregation. Long
chutes over 6 meters,
or those not meeting
slope standards must
discharge into a hopper
before distribution to
point of need.
Building Construction 139
11. Concrete Use to convey concrete Pipelines take up little Constant supply of
pumps direct from central space and can be readily fresh, plastic concrete
discharge point to extended. Deliver is needed with average
formwork or to secondary concrete in continuous consistency and
discharge point. stream. Mobile-boom without any tendency to
pump can move concrete segregate. Care must
both vertically and be taken in operating
horizontally. pipeline to ensure an
even flow and to clean
out at conclusion of each
operation. Pumping
vertically around bends
and through flexible hose
will considerably reduce
the maximum pumping
distance.
140 Laymanized Manual on Monitoring Infrastructure Projects by a Practitioner
13. Tremies For placing concrete Can be used to funnel Precautions are needed
under water concrete down through to ensure that the
the water into the tremie discharge end is
foundation or other part of always buried n fresh
the structure being cast. concrete, so that a seal
is preserved between
water and concrete
mass. Diameter should
be 10-12 inches unless
pressure is available.
Concrete pumps can be
used. Concrete mixture
needs more cement.
14. Screw Use for spreading With a screw spreader Screws are usually used
spreaders concrete over flat areas a batch of concrete as part of a paving train.
as in pavements. discharged from bucket They should be used
or truck can be quickly for spreading before
spread over a wide area vibration is applied.
to a uniform depth. The
spread concrete has good
uniformity of compaction
before vibration is used
for final compaction.
Building Construction 141
Glossary of Terms
Admixture - a chemical added to the con- Extra Work - Labor and/or materials pro-
crete mix to enhance its workability. vided by the contractor which are not stip-
ulated in the contract but are essential to
Calendar Days - means a period of twen- the satisfactory completion of a project.
ty four hours extending from midnight to Feasibility Study - A preliminary study
midnight and shall include all days of the conducted before any project is started in
calendar. order to assess its engineering and eco-
nomic viability.
Change Order - A written order is-
sued by the implementing agency to the Final Estimate - is an estimate prepared
contractor containing revisions or unfore- by the government engineers after the
seen work resulting either in the increase project has been completed, for the pur-
in the original quantities of any or all pose of computing the final payment due
items of work or in the reclassification of the contractor and to tally exact work
an existing item to another item as those quantities done.
provided for in the original contract or de-
crease in the quantity of the work due to Force Majeure - An act of God, natural
under runs or deletion of portions or sec- calamity such as floods, lightning, earth-
tions of the project. quake, etc. which are beyond human con-
trol, therefore no person shall be held
Concrete - is an stonelike engineering legally accountable for the damages and
material made from a mixture of portland losses it may cause.
cement, water, fine and coarse aggre-
gates, and a small amount of air. It is the Garnishment - a legal order or warning
most widely used construction material in with reference to the recovery of costs or
the world. Is the only major building mate- debt from a debtor’s property or wages
rial that can be delivered to the job site in
a plastic state. This unique quality makes Honeycomb - in construction, it refers
concrete desirable as a building material to the cavities, voids or hollow spaces
because it can be molded to virtually any resembling a waxy hexagonal cells con-
form or shape. taining honey extracted from a bees’ hive.
These are formed at the sides of a finish
Contractor - A person or firm who has un- concrete structure due to insufficient con-
dertaken or contracted to execute work or solidation or water content.
to provide services.
144 Laymanized Manual on Monitoring Infrastructure Projects by a Practitioner
Infrastructure Projects - include the con- Procuring entity - refers to any branch,
struction, improvement, rehabilitation, department, office, agency, or instrumen-
demolition, repair, restoration or main- tality of the government, including state
tenance of public systems, services and universities and colleges, government-
facilities necessary for economic activity, owned and/or controlled corporations,
including power and water supplies, pub- government financial institutions, and lo-
lic transportation, telecommunications, cal government units procuring goods,
bridges, roads, schools and other related Consulting Services and Infrastructure
construction projects Projects.
Overhead Cost - The operating expenses Program of Work - This contains the
and other labor costs which are not con- complete information of the project like
sidered as direct labor on the job. Exam- name, location, project cost, implement-
ple of this are office rentals and telephone ing agency, project limits, source of fund,
bills, insurances, office equipment, inter- date started, date completion, work items
ests, legal expenses, expenses for plans and quantities, materials to be used and
and specifications, traveling expenses and approving officials.
miscellaneous expenses of the office. It is
usually programmed at 10% of the total Progress Estimate - A periodic estimate
project cost. prepared by the government engineers as
the work progresses in order to determine
Plan - A drawing or diagram showing the amount of partial payment due to the
the layout, arrangement, or structure of a contractor. Ten percent of the amount due
proposed project. Type and quality of the to the contractor every partial payment is
structure and materials are also indicated kept temporarily as a retention fund re-
herein. served to cover expenses for rectifying de-
fects and completion of the work if aban-
Portland Cement - Typical portland ce- doned by the contractor.
ments are mixtures of tricalcium silicate
(3CaO · SiO2), tricalcium aluminate (3CaO Slippage - The difference between Actu-
· Al2O3), and dicalcium silicate (2CaO · al and Target physical accomplishment.
SiO2), in varying proportions, together It may be positive, which means that the
with small amounts of magnesium and project is ahead of schedule, negative,
iron compounds. Gypsum is often added which means it is behind schedule, or
to slow the hardening process. zero, which means on-schedule.
Procurement - refers to the acquisition of Source of fund - This indicates who spon-
goods, consulting services, and the con- sored the project. Most of the special
tracting for infrastructure projects by the
procuring entity. It shall also include the
lease of goods and real estate
Building Construction 145
REFERENCES
Standard Specifications
for Public Works and Highways
Volume II, 1998
Social accountability is the process of constructive engagement between citizens and government
in monitoring how government agencies and their officials, politicians, and service providers use
public resources to deliver services, improve community welfare, and protect people’s rights.
The social accountability approach needs four basic conditions to work: a) organized, capable
citizen groups; b) responsive government; c) context and cultural appropriateness; and d) access
to information.
ANSA-EAP operates in a large and diverse region. It pursues a geographic strategy that currently
puts priority on support and technical assistance to social accountability activities in Cambodia,
Indonesia, Mongolia, and the Philippines. It also follows a thematic and sector strategy by supporting
mainly local social accountability efforts that deal with service delivery (education, health, local
infrastructure), procurement monitoring, the youth, extractive industries, and climate change.