Precommissioning General Safety
Precommissioning General Safety
Precommissioning General Safety
Print Name
Signature
Date
PM/FW Shell Corrib Project Team Dublin Ireland T +353 1 404 0700
F +353 1 459 9785, E [email protected]
/conversion/tmp/scratch/481919196.doc Page 1 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
CONTENTS
1. PURPOSE 4
2. SCOPE 4
3. REFERENCES 4
4. RESPONSIBILITIES 5
4.1 Construction Manager 5
4.2 HSE Manager 5
4.3 Pre-Commissioning Superintendent 5
5. HAZARDS IN PRE-COMMISSIONING 5
5.1 General Conduct of Work 5
5.2 Safe Conduct of Specific Types of Work 7
/conversion/tmp/scratch/481919196.doc Page 2 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
/conversion/tmp/scratch/481919196.doc Page 3 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
1. PURPOSE
The aim of the Pre-commissioning General Safety Procedure is to familiarise
and guide CMC and Contractor personnel in the safety requirements for carrying
out pre-commissioning activities on the Corrib Project Onshore Gas Terminal.
2. SCOPE
This document describes good working practice, general safety guidance, and
defined requirements for carrying out pre-commissioning activities on the CMC
pre-commissioning site for Corrib Project Onshore Gas Terminal. These
principles or their practical equivalents will be applied during offsite module
precommissioning activities.
When instructed, safety control methods will be amended to comply with the
stipulations of SEPIL for any work to be carried out within the Corrib Project
boundary fence.
3. REFERENCES
Work Site HSE Plan
/conversion/tmp/scratch/481919196.doc Page 4 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
4. RESPONSIBILITIES
5. HAZARDS IN PRE-COMMISSIONING
The management of the hazards associated with the above philosophy of works
will recognize the possibility of either construction or pre-commissioning
personnel being exposed to the hazards associated with the activities of the
other. The potential for exposure to hazardous situations is further increased by
the high site population and overlapping but independent multiple workfaces.
/conversion/tmp/scratch/481919196.doc Page 5 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
Internal preservation
/conversion/tmp/scratch/481919196.doc Page 6 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
Effects on those not carrying out the work, but working locally under
different supervision and work permit requirements. A worksite that was
safe for all site personnel to work in and pass through in the morning
may not be so in the afternoon. The hazards in any part of the
construction site working environment are continuously changing,
especially during the pre-commissioning period.
/conversion/tmp/scratch/481919196.doc Page 7 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
Projectiles are a risk when air blowing sections of pipeline for cleaning.
Large debris exiting form a blow exhaust point is a significant hazard
and can cause personnel injury and plant damage. Suitable cages or
muzzles are an effective precaution.
Low pressure leak testing can dislodge and accelerate small fittings or
tubing and cause injury. Ensure temporary fittings are properly attached
before applying the test. Some items of plant may not be suitably
pressure rated and to avoid damage they must be temporarily protected
from over pressure for pre-commissioning work.
Live utility systems may cause hazards to the uninitiated. When piping
is live it needs to be adequately identified. Certain personnel may need
to be trained to recognise these internal hazards.
/conversion/tmp/scratch/481919196.doc Page 8 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
/conversion/tmp/scratch/481919196.doc Page 9 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
Planning will be interfaced with area construction work and the sanction to
perform the work will be overseen by a single area authority.
Generic procedures and checklists will be employed for repeat activities. Parcels
of work will be described in a work pack and specific points for safe work and its
monitoring will be indicated on marked up PEFS and other job specific drawings.
Specific step by step method statements will be prepared for the safe control
activities such as HP tightness testing, ESD/EDP system tests, use of nitrogen
or chemicals.
Additional site training for the Contractors discipline personnel assigned to pre-
commissioning work will be given to emphasise the differences between
construction and pre-commissioning activities. To meet this requirement COMT
personnel will contribute and provide appropriate training material in conjunction
with site HSE personnel.
/conversion/tmp/scratch/481919196.doc Page 10 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
Routine weekly safety meetings will be held for pre-commissioning teams, and
led by the responsible CMC area pre-commissioning engineer. The safety
meetings will be used to highlight any significant upcoming activities and provide
two way feedback to the regular site-wide safety meetings.
Site circulars will be issued to publicise relevant activities and inform of any site
constraints or safety control implications. These will be advised to pre-
commissioning and construction personnel for use in the job site safety briefings.
/conversion/tmp/scratch/481919196.doc Page 11 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
6.6 Housekeeping
Good Housekeeping is a prerequisite of safe working with the objective of
accident prevention by reducing combustible materials to a minimum and
avoiding the creation of tripping hazards and obstructions in the working area.
At the end of the working day, each area will be cleared of all rubbish and
maintenance materials and tools must be neatly stowed.
Loose materials etc. will be removed from platforms/railings where they could
create a tripping hazard or be knocked off causing a hazard to those working
below.
Access to ladders, stairways, emergency routes and fire escapes will be kept
clear at all times. Waste materials and refuse will be placed in properly
designated locations to prevent fire or tripping hazards.
A Hazcon type hazard assessment may also be required where the activity
involves control of hazards which might have serious impact on adjacent
construction activities. Safety checklists and hazard assessments will also
involve CMC Site HSE personnel.
/conversion/tmp/scratch/481919196.doc Page 12 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
LOCATION ........................................................................................................
/conversion/tmp/scratch/481919196.doc Page 13 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
/conversion/tmp/scratch/481919196.doc Page 14 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
NOTES:
.......................................................................................................................
.......................................................................................................................
Above actions are in place and precautions reviewed with the team prior to implementation of
work.
PRE-COMMISSIONING ENGINEER
/conversion/tmp/scratch/481919196.doc Page 15 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
CMC pre-commissioning interface work with existing operating plant and with the
pre commissioning work will be covered by the normal Corrib operational permit
system.
CMC’s pre-commissioning work in the pig receiver, slug catcher and incinerator
areas will also be covered by the normal permit to work System.
This may take the form of a standardised document for repeat activities.
The hazard assessment and appropriate safety checklists will be reviewed at the
toolbox talk before commencing the activity.
Risk assessment involves rigid analysis of the existent hazards for each activity
by considering:
a. Hazards to Personnel (general public, adjacent operations, all site
personnel)
Fire or ignition source
Impacts or collisions
/conversion/tmp/scratch/481919196.doc Page 16 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
Check if existing standard controls are adequate to cover risks - i.e. Permit
authorities, standard PPE, site warning signs & barriers, etc.
/conversion/tmp/scratch/481919196.doc Page 17 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
Barriers
Warning claxons.
Safety Tagging
In addition notices will be posted at the normal entrance to the site or at the
permit control facility to provide information to all site personnel on the safety
significant pre-commissioning activities to be carried out that day, and any area
exclusions or limitations to be enforced.
/conversion/tmp/scratch/481919196.doc Page 18 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
Warning signs will be attached to ‘live lines’ at intervals of not more than
5 metres and additionally identified with a special tape.
Signs must denote state of line i.e. ‘HOT’, ‘UNDER AIR PRESSURE’
etc.
When the motor solo run is in progress the authorised electrical person will
assign a qualified competent electrical person to monitor the duration of the
running.
All electrical motors not on test or in use will be electrically isolated and locked
off in the substation.
Ensure there is a valid and recent gas test for the vessel internal logged in the
permit system.
To confirm all isolation blinds are in place and no temporary hoses are
attached to vessel connections.
/conversion/tmp/scratch/481919196.doc Page 19 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
Minimise the number of loose items taken into the vessel. Prior to entry inside
vessel, ensure all items that can fall from pockets while inside are removed and
stored outside the vessel i.e. coins, pens, pocket-knives etc. Ensure flashlights
and other items are not left inside on exiting the vessel.
For large vessels and multiple work faces a tally system may be operated. Prior
to entering vessel/confined space, individuals entering the vessel should hand
over their identification tag to the standby man. This is to enable rapid head
count if required. On leaving the vessel/confined space the standby man will
return the ID tags.
Permit Approval
Permits for the flushing and blowing will generally be issued as a continuation of
the hydrotest work.
Site Preparation
Where the line flushing is to take place, the area must be cordoned off and
warning signs “Line Flushing in Progress” placed in the surrounding area.
Drain facilities must be made available for the efficient disposal of water from the
area to the Open Drain system to prevent the area from flooding and possible
subsequent freeze over.
The surrounding area where the flushing is to take place must be prepared to
ensure that equipment within that area is adequately protected from water spray
and any debris that might be present inside the piping.
/conversion/tmp/scratch/481919196.doc Page 20 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
Before flushing is to take place the area must be thoroughly checked to ensure
that the water and eventually air is not going to interfere with any on going work
in that area or cause sudden distractions to the surrounding workforce.
Barriers and warning notices will be placed to control access to the flush exhaust
area. During the flushing of lines the area will be kept under observation by pre-
commissioning or the assigned Subcontractor until all flushing has been
completed.
During flushing and blowing of lines, the quantity of water drained down will not
be allowed to exceed the maximum run off water allowable by the Corrib Project
requirements. For high capacity flushing operations, pre-commissioning
personnel will liaise with SEPIL operations and environmental personnel on a
daily basis to ensure planned flushing work does not contribute any constraint to
Corrib Project operations.
During the LP leak test, access to the area should be controlled and warning
signs posted.
Sections undergoing LP leak tests will remain under close supervision and will
be depressurised as soon as practicable after the test is complete.
At the end of the low-pressure leak test, the air will be de-pressured to
atmosphere, through drains/vents at safe locations.
The test envelope will remain boxed in under a slight positive pressure of dry oil
free air. This will serve as preservation until commissioning commences.
The general area of the air discharge points will be taped off with Marker Tape,
approximately thirty meters from the blow out point.
/conversion/tmp/scratch/481919196.doc Page 21 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
The blow out point will be surrounded with scaffold barrier structure, and a
diffuser or muzzle fixed approximately one or two meters away from the open
end to restrain any solid projectiles. (Alternatively the blow out point must be
directed to a secured and evacuated location)
Covering the whole barrier structure will be a tarpaulin securely fastened to the
scaffold frame. This will be a loosely lashed overlapped arrangement which will
assist in the containment of dust.
Suitable warning notices indicating "No Entry Air Blowing in Progress" or similar
will be positioned to cover all points of access.
Personnel not directly involved in the air blowing will be removed from the area
when the air horn is sounded.
All personnel in the noise-affected areas during the blowing activities will be
required to wear ear protection.
The blow out area will be checked thoroughly and patrolled to ensure that there
are no unauthorised personnel above ground or inside the Taped Off area. The
discharge area will be evacuated of all personnel well before the blowing is to
commence.
Air horns or alternative audible alarm will be sounded 5 minutes before the
intended air blow and again just prior to impending blowing
A specific permit to work and procedure will be required for assurance air
blowing of large systems.
For details of the Generic Procedure for air blowing refer to the Plant and
C01 Equipment Generic Pre-commissioning Procedures.
/conversion/tmp/scratch/481919196.doc Page 22 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
Before nitrogen is allowed on to the plant, CMC HSE will issue Safety Warning
Notices on site notice boards informing all personnel that nitrogen will be
introduced to the plant in the near future.
Nitrogen purging is carried out under strict control and only when vessels and
equipment have been finally closed and permission has been obtained from the
pre-commissioning superintendent.
Ensure any temporary hoses and fittings are in good condition and
rated for nitrogen pressure.
For a large volume pressure purge allow the system to stand at purge
pressure for a few minutes to allow mixing.
Maintain under a slight positive pressure and retest for oxygen if the
subsequent start-up operations do not follow on immediately.
/conversion/tmp/scratch/481919196.doc Page 23 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
The hazards associated with high pressure compressible gas testing relate to
the release of the stored pressure energy and the consequence of high pressure
leaks. Note that all components will have previously been individually strength
tested prior to the HP tightness test. The HP N2/He tightness test concentrates
on the leak tightness and containment capability of the final and permanent
integration of these components.
Preparation:
Initial preparation for the system envelope to be tested will include reviewing and
identifying all flanges and confirming that no temporary gaskets or temporary
closures exist.
The test may include the combination of several adjacent systems provided that
the test/design pressure is consistent across the defined system limits.
The test envelope will be defined on the PEFS and a step by step procedure
developed.
Isolations for the test envelope will be determined and the envelope
defined on a marked up PEFS
The tests will normally be carried out against normal process isolation
valves rather than temporary blinds.
/conversion/tmp/scratch/481919196.doc Page 24 of 25
Shell E & P Ireland Ltd 011142-71-RP-0016 Issue A
Corrib Project Onshore Gas Terminal 6 July 2005
The test sequence will be planned and defined such that permanent
flanges are not to be disturbed after the test.
The leak tightness of any closed valves forming the limits of the
envelope will be confirmed by monitoring the pressure frequently in any
downstream equipment.
Any isolation blinds used will be rated for line pressure rating and test
pressure.
During the test, access to the area will be restricted by placing barrier tape
completely around the test area. Warning signs will be posted every 15 meters.
Safety observers will patrol the area to enforce the restrictions in force.
/conversion/tmp/scratch/481919196.doc Page 25 of 25