Resolution No. R2020-12: Proposed Action
Resolution No. R2020-12: Proposed Action
Resolution No. R2020-12: Proposed Action
R2020-12
Amend Baseline Budget for the Hilltop Tacoma Link Extension
System Expansion Committee 06/11/2020 Recommend to Board Ron Lewis, DECM Executive
Board 06/25/2020 Final action Director
Madeleine Greathouse, Project
Director – Hilltop Tacoma Link
Extension
Proposed action
Amends the Adopted 2020 Budget by increasing the Hilltop Tacoma Link Extension baseline budget by
$35,400,000 from $217,346,000 to $252,746,000 to provide funding required to complete the project to
meet the planned revenue service date.
Project status
Conceptual Preliminary
Project Alternatives
Engineering/ Engineering/ Final Design Construction
Identification Identification
Draft EIS Final EIS
Fiscal information
This action increases the baseline budget without adding scope or schedule.
The current financial plan can accommodate the increased project cost. Current economic conditions,
however, will likely result in a significant loss in revenue and changes to long term projected financial
capacity.
Public involvement
Not applicable to this action.
Time constraints
A one-month delay would impact the construction phase of the project by limiting ongoing construction
contract administration efforts.
Kent Keel
Board Chair
Attest:
Kathryn Flores
Board Administrator