Developing A Framework For Renegotiation of PPP Contracts
Developing A Framework For Renegotiation of PPP Contracts
DEVELOPING A FRAMEWORK
FOR RENEGOTIATION
OF PPP CONTRACTS
FINAL REPORT
5 DECEMBER 2014
Disclaimers
This report on Developing a Framework for Renegotiation of PPP Contracts has been com-
missioned by the Department of Economic Affairs, Ministry of Finance, Government of India
(DEA). UK Government’s Department for International Development (DFID) has provided
the funding support for commissioning the study, while, the World Bank has facilitated the
advisory work.
The contents of this report should not be construed to be the opinion of the DEA, DFID or
the World Bank. DEA is not liable for any direct, indirect, incidental or consequential dam-
ages of any kind whatsoever to the users, transmitters or distributors of this report.
The findings, interpretations and conclusions expressed herein are those of the authors and
should not be attributed in any manner to DEA, DFID and / or the World Bank, its affili-
ated organizations, or to the members of its Board of Executive Directors or the countries
they represent.
Acknowledgements
This report on Developing a Framework for Renegotiation of PPP Contracts has been put
together under a technical assistance facility provided through DFID – World Bank India
Trust Fund.
The report is an output in response to Department of Economic Affairs, Ministry of Finance’s
request to assist in developing a framework for renegotiation or amendment of PPP Agree-
ments, with particular focus on the National Highway and Major Port Concessions. The
report has been prepared by William Dachs. The advisory work has been facilitated by the
World Bank.
The author would like to express special thanks to Ms. Sharmila Chavaly, Joint Secretary
(Infrastructure), Ms. Abhilasha Mahapatra, Director (PPP Cell) and the rest of the staff of the
PPP Cell, Department of Economic Affairs (DEA), Government of India, for their input and
support in developing this Report as well as to the Review Group established by the DEA.
The author would also like to thank the Word Bank team consisting of the Task Team Leader
Mr. Sri Kumar Tadimalla and Ms. Carylann Lobo.
Cover photo: Jaipur- Kishangarh Section of NH-8, National Highways Authority of India
2. Introduction
In its Annual Report for 2012/13, the Ministry of Finance reported that the “Government of
India is promoting Public Private Partnerships (PPPs) as an effective tool for bringing private sector
efficiencies in creation of economic and social infrastructure assets and for delivery of quality public
services.” It went on to note that India has emerged as one of the “leading PPP markets in the
world, due to several policy and institutional initiatives taken by the Central government.” It notes
that over 900 PPP projects with a Total Project Cost (TPC) of Rs543,045 crore were approved
in the period 2010 to 2013 and are at different stages of implementation, i.e. under bidding,
construction and operational stages. Prior to this, some 600 projects with a TPC of Rs333,083
crore had been approved, demonstrating a marked acceleration in the rate of projects being
approved for procurement. This makes the Indian PPP programme one of, if not the, largest
in the world in terms of the number of projects approved for implementation as PPPs.
India has also developed a strong framework for the approval of projects at a central gov-
ernment level with appropriate oversight exercised by objective bodies aware of the fiscal
implications of PPPs. This oversight is exercised by the Public Private Partnership Appraisal
Committee (PPPAC), which was established in January 2006. PPPAC has approved 276
central project proposals with a TPC of Rs277,338.30 crore.
The table below shows these approvals by sector, number and TPC.
However, as shown in this report, various challenges have arisen along with the acceleration
in pace of the roll out of PPPs. In the Highways sector, the number of projects actually reach-
ing operations decreased to a handful in the past year. A blockage in the bidding process has
developed with private sector developers and financiers stating that they will not participate
3. Limitations
In terms of the limitations on scope of the report, the sectors are limited to the National
Highways and Major Ports. A further limitation is that the report does not focus on resolu-
tions specific to particular projects that are currently in distress but rather on a way forward
in refining and improving the PPP programme in terms of adjustments to the risk profile
adopted for the two sectors.
In addition, the limited available data on projects and their performance means that the report
is not empirical in nature. As such more reliance is placed on the feedback from stakeholders
than on empirical data for the conclusions reached.
It is noted that PPPs are complex contracts and their planning and implementation are among
the most complex forms of public planning and procurement. There is thus no single solution
to increasing the deal flow or reducing the distress currently experienced in the sectors and in
the projects. A chain of activities make up a PPP implementation process, starting with project
selection and ending with the expiry of the PPP Agreement some 25 to 30 years later. The
influence on value, risk and cost is greatest at the early stages of this process in the selection of
the projects and the work that government does in preparing them. Then, in implementation
of the PPP Agreement, the risk positions set out in contracts are only as good as the manage-
ment thereof by the two parties but in particular the contracting authority.
4. Context of Renegotiation
PPP Agreements or Concession Agreements differ from agreements for the provision of com-
mercial goods or services between two private sector entities in several ways. These include:
• PPPs relate to public services/goods awarded through a competitive bidding process;
• PPPs are typically very high value contracts, often with capital costs of hundreds of mil-
lions of dollars and ongoing operating costs and revenues of tens of millions of dollars per
year, which makes it difficult for a party to such agreement to tolerate any losses to capital
invested or revenue forgone;
• PPPs are usually long-term arrangements spanning 10-30 years and, hence, are not ame-
nable for writing “perfect” contracts covering all the situations and developments during
the course of their lifetime; and
• PPPs are often intended to provide essential facilities that may often not have substitutes
and can be neither paused nor disrupted while the contracting parties resolve the differences
that may arise during the course of implementation.
Given the characteristics set out above and the fact that PPPs have been used in great numbers
in many jurisdictions around the world, it is no surprise that a number of such projects have
become distressed in terms of the emergence of risks that may not have been contemplated
at the time of signing. As Guasch2 identifies, many such projects have been renegotiated over
time. The forms of distress may vary but factors that lead to such distress could include any
or a combination of the following:
• Lower than expected revenue;
• Higher than expected costs;
• Delays;
• Variations in contractual specifications and;
• Disagreements between the parties as to cause and effect of actions/inactions.
Any of these could give rise to a call for amending the terms of the Concession Agreement to
better reflect the project realities.
However, it is observable that such calls typically (but not always) originate from the private
party to the Concession Agreement and, since the objectives behind such a call will be biased
towards maintaining a required return on investment, or preventing a default under financing
agreements undertaken by the private party or avoiding a risk or set of risks, the amending
of the Concession Agreement may not be in the best interests of the public concessioning
authority (acting on behalf of the Government).
7. Sector Information
7.1. Highways
The National Highways Authority of India (NHAI) has provided data for the highways PPP
programme as well as data on a sample of 15 projects with detail around the shareholding
and financing arrangements for each project. This is attached as Annexure C. Although pre-
cise information on the number of projects in distress is not provided or indeed the causes of
distress it is possible to extract the following in an analysis of the data:
• There are 15 projects in the sample.
• Six are in the operations phase (of which 3 have partial CoDs).
• Seven are in the construction phase.
• Two are in some form of pre-CoD distress with construction either stopped or not com-
menced (Aligarh to Kanpur section of NH-91 and Gwalior-Jhansi section of NH-75).
• Four in the construction phase have received or are approved to receive Viability Gap Fund
(VGF) grants totaling some Rs1,625 crore.
• Three are annuity-type contracts (Rs2,147 crore TPC, excluding an NHAI amount of
Rs625 crore on the Hazaribag-Ranchi Concession), the rest are concessions of the DBFOT
type.
• The average contract duration is 24 years; the earliest COD is given as January 2008.
The Total Project Cost of all 15 projects is Rs17,200 crore; the TPC of the projects in distress
is Rs1,579 crore. The remainder is split between the Operational Concessions (Rs6,316 crore)
and those in construction (Rs9,143 crore).
The average D/E ratio is 74/26 while the average for the three annuity-type projects is 84/16
(all excluding VGF). This higher leverage is to be expected as annuity-type projects are much
lower risk, especially in the operations phase.
The government’s maximum contingent liability for these 15 sample projects, based on 90%
of debt due at financial close and assuming no insurance proceeds, is measured at Rs11,112
crore or some 65% of TPC, assuming that the TPC has not increased and been funded from
sponsor equity after financial close.
7.2. Ports
The Ministry of Shipping (MoS) has provided a set of data for all PPPs in the Major Ports
with detailed timing and investment values for each project. In addition, five sample projects
have data related to performance and tariffs. This is attached as Annexure D.
Since 1995, a total of 74 Major Port concessions have been implemented with a total maxi-
mum freight capacity of some 570MMTPA. The Total Project Cost (TPC) at time of signature
was Rs49,879 crore.
Of these 74 projects, nine were implanted before any form of Model Concession Agreement
was used (i.e. pre-2001); 16 were done between 2001 and 2006 under the standard agreement
developed by the IDFC and 49 under the MoS Model Concession Agreement.
8. Identified Issues
In feedback from stakeholders, several issues were raised that were general in nature and did
not relate to specific sectors.
The first related to an overall focus on investment sources as alternatives to the public fiscus
rather than on efficiency gains that might arise from different forms of contracting. This
resulted in a preference for concessions over annuity-type payments in general and in particular
for bidders offering the largest concession fee (sometimes called a “negative” concession) pay-
able for the right to operate the infrastructure asset rather than the one most likely to operate
in a sustainable manner over a 5–30 year concession period.
The second related to project preparation, where time spent is often rushed resulting in inad-
equate identification of scope, cost and risk issues on projects.
The third related to optimistic bidding from the private sector where winning the bid was seen
as more important than being able to make a sustainable return on investment. The extent of
over-estimation of traffic demand in highways is a good example of this but the issue extends
to other sectors.
The fourth is the use of financing structures that minimize genuine equity and promote the
use of proxies such as shareholder loans that has concentrated risk in the banking sector.
Finally, poor contract management coupled with a very tight Model Concession Agreement
has limited the ability of concessioning authorities to identify distress, to mitigate the causes of
such distress and to implement changes to agreements to minimize the harm of such distress.
In order to categorize and commence a systematic process of addressing identified issues, an
exercise was undertaken in creating a list of specific issues in categories ranging from physical
to financial, economic, commercial and processes. The list is not exhaustive but does cover
Having identified, categorized and listed the issues it is now possible to examine them in the
context of international experience.
9. International Experience
A very detailed report on international experience, legal frameworks and case studies is attached
as Annexure B. The comparator countries are Australia, South Africa, the United Kingdom
and Chile and provide a rich source of data. Readers of this main report are encouraged to
read the international comparator report as the section below only highlights the experience
in dealing with the issues identified.
In preparing the international comparator report, interviews were conducted with senior
officials in each of the jurisdictions and their personal experiences and views on the matter of
renegotiation and amendment of concession agreements was recorded.
Each country examined has struggled with exactly the same issues that India has in terms of
mounting and sustaining a PPP programme that achieves a roll-out of infrastructure with
private capital. Each has struggled to maintain the position of significant risk transfer to the
private sector. Each has made significant changes to its PPP policy, frameworks and contractual
arrangements as part of the evolution of the PPP programme.
Each of these four countries permits amendments to their PPP Agreements and to varying
degrees has a regulatory framework that specifies how this should be done. These range from
the UK, which is the most flexible and has the highest delegation to the concessioning author-
ity, to Chile, which prescribes a 20% of approved capital value limit in its concession law.
South Africa requires approval of “material” amendments by the National Treasury.
All the countries have cases of changes and renegotiation and the case studies highlight the cir-
cumstances of each. Australia has a mix of cases ranging from a completely non-interventionist
government to active renegotiation. The “let the market work” approach in the Sydney Harbor
Tunnel and the Lane Cove Tunnel saw lenders step in and sell the concession in a competitive
bidding. The original equity was wiped out and the new owners obtained the asset (being the
concession and all its rights) at a deep discount. In Reliance Rail and Southern Cross Terminal
Stations, government was much more active in negotiating amended agreements to stave off
termination and provide a public service or save dispute costs.
Notes:
In India the cap on amendments relate to changes in traffic demand only
Chile permits special case amendments above 25% subject to approval
Chile requires that above 5% of TPC the variation must go to public tender
The mapping of issues identified to the international experience and case studies for each is set
out in the tables that follow in this section. Given that, even in the same jurisdiction, different
solutions were applied it is necessary to record different options for some issues.
Work was then undertaken in examining the MCA’s for National Highways and Major Ports
as well as some actual concession agreements to contrast Indian practice with international
practice on each issue. It is important to note that many of the differences are much nuanced
and, while it may appear that an issue is addressed in a MCA, it is actually not. This may
be because the commercial reality that flows from the contractual wording differs from the
intention of the drafters of the MCA or because of actual practice on the ground does not
follow the contractual requirements.
In illustration of this, two examples can be made. The first in the highways projects is how
the concession period is varied depending on the traffic volumes. The commercial reality is
that reduced traffic demand results in reduced revenue and an immediate cashflow problem
for the concessionaire. Adding on a period of time at the end of the concession period will
positively impact on a return on equity but will not ease the cash crisis of the concessionaire.
A second example is the matter of land or enabling services provision by the public sector
entity. There is no sense of the materiality of the land or service provision (or lack thereof ) in
a project because it is largely percentage based in the MCA obligations. A failure to provide
or enable a piece of land may render the whole project financially unviable or it may have no
effect at all. The difference is found in the details of each project.
As such readers of this report are urged not to simply say that an issue is addressed in the
MCA, but rather to think through the commercial and practical implications of the issue in
the context of the international comparator.
5 Contractual
1) If public party then
compensation for delay If site-related then
Compensation
to place private party Lane Cove Tunnel completion date 12
Event
in no-better-no-worse postponed
position
If Force Majeure then
Delay to 2) If no fault then relief on
5.1 Lane Cove Tunnel Relief Event completion date –
completion completion date granted
extended
3) If private party fault
then relief on completion Private party If private party then
granted relief and Lane Cove Tunnel risk – no liquidated damages –
liquidated damages change payable (15.4)
payable
Long stop date leading to Terminate and 12 month long stop
5.2 Non-completion All –
termination Retender date (15.5)
Private party bears
Factors outside Not covered unless
financial risks but relieved UK
5.3 Concessionaire’s Relief Event political or indirect
from completion and Standardisation
control political event
liquidated damages
1) Public party ordered
Variations with Change in Scope within
5.4 then costs as per schedule M7 Freeway Variation 2
cost increases 5% of TPC (17.1)
or no-better-no-worse
Variations with 2) Private party then cost
5.5 M7 Freeway Variation Not covered 2
cost savings saving shared
1) Can be made by Up to 50% of
Change in scope within
public party and paid Value without
Renegotiation 5% of TPC (17.1) or 13
for to leave private party retendering in EU
change in law
no-better-no-worse Directives
5.6 Amendments
2) Can be in settlement
Melbourne
of a dispute then in
Southern Cross Dispute Not covered
accordance with order or
Station
settlement agreement
Compensation
Compensation on basis of Compensation Recovery of direct
5.7 for Public Party Lane Cove Tunnel 13
no-better-no-worse Event additional costs
Breach
Suspension of obligations Chapman’s Peak Political events, non-
5.8 Force Majeure and termination on force Drive/ Lane Cove Force Majeure political events and 13
majeure compensation Tunnel indirect political events
No trigger unless Amendment and
discriminates, then Lane Cove Tunnel/ Compensation Compensation on
5.9 Change in Law 13
compensation on Chapman’s Peak Event no-better-no-worse
no-better-no-worse basis basis
Compensation by public
party on no-better-no- Melbourne
Uninsurable Compensation
5.10 worse basis measured Southern Cross Not covered 14
Events Event
against base case financial Station
model
Settlement agreements
Disputes and Settlement agreements to Melbourne
to avoid dispute,
5.11 Settlement avoid dispute, amend the Southern Cross Renegotiation 15
amend the Concession
Agreements Concession Agreement Station
Agreement
Assessed or Tendered
Termination
Market Value or x% of Chapman’s Peak 90% of Debt Due
Payments on Terminate and
5.12 Debt outstanding at time Drive/Lane Cove (based on TPC) less 16
Private Party Retender
of termination depending Tunnel claims outstanding
Default
on jurisdiction
6 Other
Project screening by
Sydney Harbour
Unbankable Treasury includes Not likely to receive
6.1 Tunnel and Lane
Projects commercial bankability approval or VGF
Cove Tunnel
test
Project breaches loan
Reckless
covenants leading to
Bidding on Limited ability to
6.2 step-in by lenders and Lane Cove Tunnel
forecast exclude reckless bids
substitution/ sale of
revenue
concessionaire
Lenders bear loss on sale Limited ability to
6.3 Naïve Lending of concessionaire so due Lane Cove Tunnel exclude bids with high
diligence thorough risk for lenders
Influenced by debt
Sydney Harbour
Financial underpin. Debt/ equity Limited commercial
6.4 Tunnel and Lane
Structure ratios assessed by Treasury viability testing
Cove Tunnel
commercial viability tests
Audited accounts,
inspections and audits,
Sydney Harbour
financial statements on Independent
Tunnel and Lane
Accurate 6 months’ and year’s Consultant (20); Right
6.5 Cove Tunnel and
Reporting performance; daily, to Inspect Records,
Chapman’s Peak
monthly annual reports Traffic sampling (21)
Drive
on traffic volumes and toll
revenues.
The reader will have noted the use of the term “material” in the context of a change or impact
to the concession agreement. There is no precise internationally applicable guidance on this.
However, all the jurisdictions and the EU Directives have a common approach that material-
ity is that that renders the concession materially different in character from the one initially
concluded and would have affected the decision to grant the concession if known at the time.
Chile and the EU directives have, as discussed above, set some quantitative benchmarks as a
percentage of total project cost.
Additional detail on the major issues and options is set out in the tables below.
The same delegation of powers as currently allocated between the line Ministry, the Standing
Finance Committee and the PPPAC would be used to determine the Approving Authority.
Key components of this process would be:
12.1. Objectivity
It is likely that the public concessioning authority is as interested in the outcomes of the Con-
cession Agreement renegotiation as the private party and may also have played a role (active
or passive) in the events leading to the project distress. As such it is unsuited to decide on the
necessity of renegotiation or to oversee the renegotiation or to approve its outcomes.
Renegotiation can have significant financial (explicit and contingent) outcomes. Some form
of fiscal oversight similar to that used in the original approval mechanism is required.
In addition to the use of the existing approval mechanisms for considering amendments to con-
cession agreements, there is also merit in considering the establishment of independent techni-
cal panels for each sector with a mandate to consider disagreements related to the valuation
of amendments A well-resourced panel with appointed members known to be independent
and capable of assessing the merits of a disagreement on amendments will signal government
commitment to a structured process that will improve market certainty and reduce spurious
calls for renegotiation.
Such panels would have good precedent in the current Indian Telecoms and power sectors
where the Telecom Regulatory Authority of India (TRAI) and the Central and State Electric-
ity Regulatory Commissions (CERCs and SERCs) play valuable roles as independent arbiters
with non-binding dispute resolution powers.
There would be costs associated with such a body, however these would be outweighed by the
benefits accruing to India’s massive PPP sector programmes.
13. Conclusions
The following conclusions can be drawn from this report:
13.1. India has emerged as one of the leading Public Private Partnership (PPP) markets
in the world, due to several policy and institutional initiatives taken by the central
government and a sustained effort in various sectors to accelerate the implementation
of PPP projects and programmes.
13.2. India has also developed a strong framework for the approval of PPP projects at a
central government level with appropriate oversight exercised by bodies independent
of the particular projects and aware of the fiscal implications of PPPs.
13.3. Various challenges have arisen along with the acceleration in pace of the roll out of
PPPs. A blockage in the bidding process of some PPP programmes has developed
with private sector developers and financiers stating that they will not participate in
any project bidding given the perception that participation has become too risky and
because their exposure to projects in implementation that may be in some distress is
too high.
13.4. The common themes that emerge across sectors are that risk allocation is viewed as
one-sided; several sovereign obligations are not being met, especially with regard to
land and right-of-way provisions in many highway PPPs.
14. Recommendations
It is recommended that, in conjunction with other reforms around project selection and con-
tract management currently underway in the DEA:
14.1. The Model Concession Agreements in National Highways and Major Ports be revisited
and amended to explicitly permit amendments of concession agreements;
14.2. Such amendments, to the extent that they are material in the context of the original
concession agreement, be approved by the same approving authority that approved
the entering into of the original concession agreement;
14.3. Such approval be based on an objective assessment of causation and fault; materiality;
risk; financial cost; adverse consequences and public benefit;
14.4. In the absence of other value-for-money criteria, 90% of debt due should be used
as the absolute limit of any payment by the State in any amendment or termination
and retendering that requires payment. This is in return for full access to revenue less
operating costs and in any lesser payment the proportion is maintained;
14.5. In a consultative way with a panel of legal experts and PPP practitioners the MCAs
be examined and amended to bring them into closer alignment with international
practice on other matters identified in this report, including variations, land provi-
sions, compensation events, refinancing, changes in traffic and revenue and economic
and financial changes;
14.6. The process of reaching settlements before formal dispute resolution processes be re-
examined and the possibility of using sector specific independent technical panels to
assess disputes with a view to settlement assessed; and
14.7. The bid evaluation process be amended to require more firmly underwritten bids
showing higher levels of involvement of lenders and to eliminate bids that are demon-
strably out of line with realistic commercial (cost and revenue) projections.
B. Meeting Notes
These Notes are those taken by the Author and do not purport to be complete and detailed
minutes of the meetings. Their purpose is to provide context to the various reports to be pre-
pared as part of this assignment. They have not been verified by the persons who participated
in the meetings.
1. IDFC
1.1. Date of Meeting: 5 May 2014
1.2. Organisations represented
1.3. IDFC Ltd
1.3.1. IDFC Project Finance
1.3.2. IDFC Foundation
1.4. Individuals
1.4.1. Cherian Thomas CEO IDFC Foundation
1. Purpose
The purpose of this report is to provide a brief review of current international practice
associated with the renegotiation of Concession Agreements, with a view to supporting the
establishment of an objective, fact-based approach to amending the terms of Concession
Agreements based on ascertainable cost, risk and social benefit and neutrality or benefit for
the Government of India.
The report is presented in two parts. The first deals with current documented principles and
practice in PPP contract amendments and the second is a comparison of four countries with
substantive and successful track records of PPPs, namely Australia, South Africa, the United
Kingdom and Chile, with a particular focus on national road networks
3. International Experience
This section presents findings from international practice as to the drivers for renegotiations
and implications thereof.
A number of concessions have been renegotiated across the globe and one of the biggest chal-
lenges is that the renegotiations are pervasive. Guasch (2004) examined close to 1,000 Latin
American Concession Contracts awarded between 1980 and 2000 and found that 30% of
all contracts were renegotiated.4 Different sectors show different propensity for renegotiation
with 54.4% in the transportation sector (roads, ports, tunnels and airports) and 74.4% in the
water sector. Renegotiations often favor the concessionaire, where 62% of the cases led to tariff
increases, 38% to extensions of the concession term and 62% to reductions in investment
obligations. This pattern is said to be similarly evident in developed countries (Gomez-Ibanez
and Meyer, 1993).
Between 1990 and 2003, only 3% of PPPs worldwide were cancelled (Thomsen, 2005). It is
more common for renegotiations to take place than for PPPs to be cancelled. Government is
typically much more likely to initiate renegotiations due to contract vagueness, lack of public
sector lending and absence of independent regulators (Bracey, 2013). PPPs are a useful mecha-
nism for procuring much needed public services but it is worth noting that an estimated 50%
7. Risk Considerations
All risks in PPPs need to be identified, allocated and managed. It is imperative that at the earli-
est stage all parties ensure debt sustainability as part of the risk assessment, as well as quantify
the cost associated with bearing such risks. The most suitable risk-sharing mechanism is the
one that optimally maximizes benefits and minimizes losses to both parties.
If the appropriate risks are not mitigated by the public sector, the investment and business
community may lose confidence in the process and government. This in turn could lead to the
government suffering a loss equal to the dollar equivalent of the total value of the economic
benefits and public goods delivered by the anticipated project if the private sector decides to
withdraw (Bracey, 2013).
It should also be noted that international donors/multilaterals assuming certain of the political
or commercial risks does not necessarily guarantee project success or that renegotiations will
not be necessary. This was recently seen in the M1 motorway extension in Hungary (Bracey,
2013, PPIAF Case Study, 2009).
M1 – HUNGARY
In this case study of a project renegotiation, considerable over-estimation of traffic demand
resulted in the EBRD, as security agent, realizing that the financial case for this project as a
private venture no longer existed and strongly encouraging the Ministry of Transport to rene-
gotiate the deal. The Ministry argued that the project was a private undertaking that needed
to be resolved privately. It became clear that only under strong pressure would the Ministry
eventually agree to support the project for an interim period by issuing a letter of credit (the
investors also provided a letter of credit) in July 1997. The renegotiated concession and its
consequences are:
• The outstanding debt of the Concessionaire, ELKMA, was transformed into a sovereign
debt under more favorable terms and conditions than those of the original debt (which
was not guaranteed);
• ELMKA was substituted by a newly established, fully state-owned special purpose company
(NyuMA);
• The shareholders of ELMKA lost their participation in equity without compensation; and
• The toll rates were reduced by nearly 50% in August 1999.
Empirical evidence does suggest that economic efficiency concerns should be addressed in the
design of toll concessions (Athias, 2007) where uncertainty and renegotiation issues have to
be considered. The world has increasingly seen a movement away from the concession model
(with a transfer of demand risk) towards the adoption of availability contracts (where the road
8. Other Considerations
Frequent negotiations are motivated by claims of changing situations over the lifespan of the
contract, as well as the long-term and incomplete nature of PPP contracts. However, renego-
tiations often occur during the construction phase, shortly after the contract award. Guasch
(2004) reports an average of 2.2 years between concession award and the first renegotiation.
Due to the medium to long-term nature of PPPs, many jurisdictions allow for a renegotia-
tion clause in the initial agreement. This specifies under what conditions the renegotiations
could be initiated, what the process would be and whether or not assistance could be used if
agreement cannot be reached. A possible challenge to this approach is that it allows too much
flexibility for either party to raise an issue where there is no compelling reason to do so, lead-
ing to costly delays and/or contestations.
The choice of contract, whether to be flexible or rigid, depends partly on the country’s insti-
tutional framework. If the institutional framework is such that the reliability of enforcement
is weak, a flexible contract is more likely to be adopted.8
Toll road concessions deserve a special mention. They are normally long-term contracts involv-
ing large upfront investments. Traffic forecasts are notoriously imprecise, making toll road
concessions very risky. This fact, together with asymmetric information and overly optimistic
bidders’ proposals on contract value, make toll roads more prone to opportunism and rene-
gotiations (Athias, 2007).
10.1. Background
Australia’s PPP programme has been through several discernible phases in the past 25 years.
The first phase from 1987 to the mid-1990s was one of very large projects carried out at state
level, such as the Sydney Harbor Tunnel which reached financial close in 1987 and commenced
operations in 1992, the M5 Toll Road in 1991 and the M2 Toll Road in 1994. The state of
New South Wales was the public sponsor of these early projects acting through its public
agency, the Roads and Traffic Authority of New South Wales (RTA).
In the 10 years to 2005, the emphasis shifted to projects in various sectors including schools
and hospitals. The lead state was Victoria, which established a team within the state treasury
known as Partnerships Victoria that was set up in 2002 based on a state policy framework of
2000.
The third phase from around 2007 has seen the establishment of a national policy framework
for PPPs that is consolidated across all states and also broader than PPPs in its approach to
infrastructure finance. In addition, a national statutory body, Infrastructure Australia, was
established to institutionalize this national framework.
In total, since 1990, some 66,3 Australian dollars (equivalent to around Rs3,8 lakh crore) of
capital investment has been made into infrastructure and service PPPs.
In New South Wales the Infrastructure Financing Unit of NSW Treasury is responsible for
ensuring that agencies adhere to the processes set out in the NSW Guidelines and the National
Guidelines, and is the first point of contact in NSW for PPPs. Treasury assists agencies with
commercial/financing advice on PPPs through the preparation of required documents, the
Public Sector Comparator (PSC) and participating in the tender and negotiation process. An
experienced member of the Infrastructure Financing Unit will also be a member of the steering
committee for each project. The level of assistance provided by Treasury will vary according
to the procuring agency’s level of relevant experience.
National Guidelines
In addition to the various approvals prior to contract signature, additional approvals are
required in certain situations such as:
• Where there is a material change to the project including an amendment to the key project
objectives, scope of services or where the conclusions or major assumptions of the business
case (including the economic and financial appraisals) change significantly;
• If there is any material change in the risk allocation from that which was last approved by
government;
• If an amendment to the budget funding is required; and
• Where issues relating to the public interest arise.
Furthermore, if the procuring agency wishes to renegotiate any area of a PPP contract after it
has been approved and signed by government, the agency must obtain approval prior to com-
mencing renegotiations from the relevant PPP authority.10 Renegotiation of any significant
areas of a PPP contract after it has been approved and signed by government will require the
agency to obtain cabinet approval prior to commencing negotiations.
In cases where the agency wishes to renegotiate or amend any element of a previously-signed
PPP, the agency is required to consult with NSW Treasury prior to commencing negotiations.
Treasury will determine whether it would be appropriate to seek the approval of the treasurer
or cabinet.11
A senior official responsible for PPPs in NSW said the following:
“One of the problems with PPP contracts, is that they only deal with the situation/problem/issue that
they were initially set up for. The contract can assume that a range of other events or contingencies
may occur and prescribe paths that are to be followed if they do occur, but no person has the capac-
ity to foresee everything that may occur. Additionally interpretation of what is meant in a contract
can vary widely among readers, even though the contract drafter thought that there was no room
for ambiguity. Also performance by each side of their obligations to a contract is often less than the
willing compliance by each side assumed in the contract. Often, however, the lawyers handle this
by stating in the contract that only certain terms are essential elements and only breach of these
would lead to termination.
Problems often occur in contracts that I have knowledge of and in the absence of a clearly specified
treatment in the contract, the way they are handled is something like this:
1. Good knowledge is needed of the negotiating strengths each side has in the contract, and in other
issues in the relationship between the parties.
2. The parties to the contract may have a reasonable and honest understanding of how the current
problem has been arrived at, are able to discuss the situation in a non-emotional way, and have
a desire to continue the relationship because it is giving benefits to each (Situation A) – or the
parties are strongly arguing, shouting and blaming each other and making threats about what
they will do to each other (Situation B)
3. An amendment to the contract drafted by lawyers will be the solution in each case, but getting
to that amendment will be done differently in situations A or B.
4. In situation A, given that the contract sides are being honest and reasonable with each other,
commercial meetings should be held to scope out a way to go forward. Point number 1 is very
important and the Government negotiator must be a strong and experienced negotiator.
5. In situation B, the end solution will also be a negotiated amendment to the contract, but prefer-
ably a means will be found to be able to discuss the situation calmly.
6. Usually a solution will be negotiated between the parties – as it takes a very long and expensive
time to ‘solve’ a commercial dispute through the courts.”
The Cross City Tunnel PPP is the financing, design, construction, operation and maintenance
of two east–west toll road tunnels under the Sydney Central Business District. The project
has been funded, designed and built by the private sector, at an estimated development,
design, construction, fit out and commissioning cost of more than $700 million. The tunnel
components of the project must be operated, maintained and repaired by the private sector
participants until 18 December 2035 or any earlier termination of the project’s main contracts,
and will then be handed over to the public sector.
The tunnel opened for traffic in August 2005 (two months ahead of schedule). The traffic
forecasts were around 86,000-87,000 vpd in 2006 but actual traffic in that year was around
30,000 vpd.
10.9.1.1. Changes
On 23 December 2004, the RTA and the principal CrossCity Motorway consortium parties
to the project’s contracts executed an amendment contract under which the CrossCity Motor-
way parties undertook to fund up to $35 million of changes to the project’s works directed by
the RTA, in return for specified increases in the maximum permissible tolls on tunnel users.
On 27 December 2006, receivers and managers were appointed to the CrossCity Motorway
parties to the project’s main contracts. Following a competitive tender process, ownership
of the principal private sector parties to the project contracts was subsequently transferred
from the CrossCity Motorway consortium to a new consortium formed by ABN AMRO and
Leighton Contractors, under sale contracts that were executed on 19 June 2007 and completed
on 27 September 2007.
10.9.1.2. Triggers
There were two distinct changes. The first was for additional scope changes and the conces-
sionaire carried out $35 million of work on these changes for the RTA. The RTA compensated
CCM by allowing an increase of 15 cents in the base toll of $2.50 (1999 prices). This trigger
was thus an authority scope change.
The second change was the sale of the concession, which was done by the receivers appointed
by the financiers. This was triggered by the insolvency of the concessionaire.
10.9.1.3. Process
The first change was a negotiated scope change done in the context of the Concession Agree-
ments where RTA could require a change provided that the change would not adversely affect
the use, patronage or capacity of the Cross City Tunnel or the ability to levy or collect tolls,
and the change would not cause the company to breach any agreement with a third party.
Within 25 business days of receiving a change order from the RTA, the trustee or the company
(as relevant) had to give the RTA detailed estimates of the likely costs and the implications of
the proposed change for the functional integrity of the works, performance standards, quality
standards, the date of completion of the works and any other obligations adversely affected
by the change.
The RTA then had 15 business days to advise the trustee or the company whether it wished
to proceed with the proposed change. If it decided to proceed, and the RTA agreed with the
costings and advice of the trustee or the company, the RTA could notify the trustee or the
company and the change would be effected. The parties agreed to the costs and the method
of payment was by increasing the toll.
The second change was one initiated as a lender step-in on the concessionaire being placed in
receivership. The concession was sold in competitive bidding.
Receivers and managers were appointed in December 2006 and in the competitive tender
for sale, eight bids were received and five parties were shortlisted. The concession was sold to
ABN AMRO (RBS) / Leighton Contractors for $695 million in September 2007. The new
business and finance model was based on downward revision of traffic forecasts taking into
account actual traffic flows.
The sale was effected through a sale of shares and units.
The scope change was authorized by the RTA itself but there was not proper disclosure to the
parliament.
The RTA and treasury’s role in the sale was to observe and undertake the due diligence of the
proposed owners. The RTA and the treasurer needed to approve the amendment deed, which
effected the sale.
A subsequent requirement was for government approval if the conclusions/assumptions of the
business case change significantly due to development approval conditions, changes in costs or
revenues or changes in user charges and a decision was taken extending the life of the steering
committee to the initial delivery phase of all PPPs and requiring government approval prior
to commencing renegotiations on any signed PPP contract.
10.9.1.5. Outcomes
Under the sale, the concession agreement stayed in place and there was no change in risk
allocation or in pricing formula. All private sector obligations were transferred to the new
owners of Cross City Motorway.
In a subsequent event in 2013, Cross City Motorway was placed in voluntary administration
in 2013 after failing to refinance a $70 million debt. The refinancing was apparently hampered
by a state action to recover $64 million in stamp duty. It appears that another private sec-
tor company, Transurban, has offered to acquire $475 million of head debt (at a discount of
21% on the actual $600 million owed by principal investor RBS), plus a further $27 million
dependent on traffic volumes. This values the asset at just $500 million - half of its original
construction cost. It is not known if the offer was accepted.
The NSW auditor general examined the scope change and concluded that it was correctly
handled procedurally and that it was valued appropriately but queried whether imposing the
costs as an additional toll was appropriate.
The sale of the concession was not audited.
10.9.2.1. Changes
While the tunnel and ramps were successfully completed and opened to traffic in 2007, traffic
was much lower than predicted (in 2009 there was 50,000 AADT vs a forecast of 120,000).
Cash flow problems due to high operating costs occurred when revenue was low.
The 2008-2009 global financial crisis occurred in the period when the road might have been
expected to recover from low opening figures. Gross State Product growth stalled. Suburbs at
either end of the tunnel, with significant numbers of businesses in the financial services sector,
were particularly affected. Employment reduction led to commuter and business trip reduc-
tions. Planned office and residential developments, which would have brought more people
to tollway catchment, did not go ahead. Connector Motorways went into a receivership in
January 2010 after experiencing a string of losses. An administrator, PPB, and a receiver, Korda
Mentha, were appointed in January 2010. Korda Mentha appointed Goldman Sachs to run
a competitive process to sell Connector Motorways.
Connector Motorways was sold to Transurban in May 2010 for $630.5 million. Transurban
financed the acquisition with $372.5 million of equity and $258 million of debt.
Transurban is currently operating until concession expires in 2037. It cited that “it worked to
maximize the ‘Day 1’ EBITDA margin on the Lane Cove Tunnel, primarily by eliminating costs”.
10.9.2.2. Triggers
The trigger for the change was the concessionaire passing into receivership.
10.9.2.3. Process
The security trustee stepped in under the Concession Agreement and exercised its rights to
“assign, novate or otherwise dispose of any or all of the rights and obligations of the Trustee
and/or the Company under the agreements, or permitting a receiver to do so”.
The RTA had to grant the security trustee all necessary access to the relevant sites or land and
give the security trustee all relevant information in its possession.
The security trustee had to obtain the RTA’s consent before transferring or otherwise disposing
of the rights and obligations of the concessionaire under the project contracts, or disposing of
all the shares in the concession company.
10.9.2.5. Outcomes
Equity was written off completely. MBIA as guarantor of the bonds was faced with the major
loss associated with the debt and had sought to offset the cost of the debt write-down by
buying bonds in the secondary market at a significant discount to face value, and so a large
part of the debt write-down was passed to original bondholders. MBIA had suffered a credit
downgrade after the global financial crisis. Lane Cove Tunnel’s Moody’s bond rating had fallen
from Baa1 to B3.
The NSW government did not pay any compensation as a result of the failure. Transurban
acquired the assets of Connector Motorway, including its rights under the Concession Deed.
The terms of the Concession Deed were largely unchanged but there would have been an
issue in terms of the resetting of the project financial model given the potential carve-out of
refinancing gains and upside revenue sharing.
This was a private-party solution whereby a bankrupt concession company was sold in an open
competition where the bidding was on the value of the concession going forward. The bidding
value of $630 million was less than the estimated value of equity and debt of $1,6billion. These
losses would have wiped out the equity of $540 million and part of the $1,14 billion debt. It
is not known to what extent the monoline insurance covered these losses.
In 2013, Transurban announced that it had successfully refinanced $260 million of debt that
was due to mature in August 2013. It disclosed that it had an EBITDA of $35,4 million.
There was no audit of the changes. However, Infrastructure Australia commissioned a study
on improvements in toll revenue forecasting.
10.9.3.1. Changes
Under the original SDA signed in 2002, the state was not required to make any payment to
the concessionaire until completion of construction and handover of operations. At this point,
the 30-year concession period would begin and the SCSA would commence quarterly core
service payments (CSPs) to the concessionaire. The concessionaire subcontracted the design
and construction of the station to a developer (Leightons Contractors). Delays were encoun-
tered by the developer and the agreed construction milestones were not met. This resulted
in a global settlement agreement worth $32.25 million between the state, the concessionaire
and the developer.
The final global settlement agreement between the state and the private parties dealt with the
15-month delay in the project and, while there were some costs incurred by the state in the
settlement, the benefits outweighed the potential costs.
The agreement resulted in some risks being allocated to the state that were not consistent with
the desired risk allocation, namely:
• Payment of $8.5 million for settlement of non-contractual claims by the developer for
which it did not admit liability;
• Relieving the concessionaire from paying damages for not meeting construction milestones;
and
• Provision of a $20 million non-cash benefit to the concessionaire resulting from the SCSA
agreeing to pay the capital core service payment component backdated from the original
scheduled completion date, rather than from the date works were actually completed.
However, these measures were considered necessary to settle the developer’s claims and ensure
that the additional costs to the state were minimized. In addition, at least some of the delays
encountered by the developer were, in part, a result of site contamination (for which the SCSA
was liable) and some state-initiated modifications.
10.9.3.2. Triggers
The trigger was the lodging of a dispute under the Concession Agreement dispute resolution
procedures. This permits “that senior representatives of the parties must meet and use their reason-
able endeavors, acting in good faith, to resolve the dispute by joint discussions”.
The global settlement agreement was negotiated to minimize adverse impacts on the state’s
original cost expectations for the redevelopment. This was achieved by:
• A rigorous and structured negotiation process overseen by an interdepartmental committee;
• Use of independent experts to assist in legal, commercial and financial risk assessments to
determine the state’s actual liability and potential risk exposure, persuading the conces-
sionaire to contribute a fair and significant cash payment to the settlement;
• Avoiding lengthy litigation and legal costs estimated by the SCSA’s legal advisers to poten-
tially exceed $200 million; and
• Appointing a high-level negotiating team to conduct negotiations.
10.9.3.4. Approvals
Government was kept informed on the progress of negotiations and ensured that negotiations
were conducted within the set parameters.
Prior to finalizing the agreement, the SCSA appointed an independent commercial mediator
to assess the proposed settlement and certify whether:
• The process to negotiate a settlement was properly informed and rigorous; and
• The analysis of the proposed settlement and the amount to be contributed by the state was
consistent with the SCSA’s assessment of the state’s potential commercial and legal risk,
and adequately addressed that risk.
The SCSA engaged a Queen’s Counsel (QC) experienced in the construction industry and
dispute resolution to provide certification on the settlement. The QC concluded that: “The
settlement agreement was the best possible commercial settlement that was able to be negotiated
following a lengthy and vigorous process of commercial negotiations.”
10.9.3.5. Outcomes
There was an agreement to extend the practical completion date for principal works by 15
months from April 2005 to the end of July 2006 and relieve the concessionaire and the devel-
oper of their obligation to pay liquidated damages for not meeting the original scheduled
completion dates.
Under the terms of the global settlement, the concession period (originally scheduled to be the
30-year period commencing 27 April 2005) was effectively split into two concession periods:
• The 30-year operating concession period that commenced upon handover of operations
to the concessionaire on 1 August 2006 was 15 months later than agreed in the original
SDA.
• The 30-year capital concession period remained the original 30-year planned period com-
mencing 27 April 2005.
10.9.4.1. Changes
The venture was very highly geared with some $2,2 billion of debt and only $137 million of
equity. The debt was largely in the form of bonds wrapped by two monoline insurers. The
insurers were liquidated in the global financial crisis and the bonds were reduced to junk
status. When the time came to draw down on a senior debt facility provided by a consortium
of international banks, the lenders refused under a provision of the loan documents forcing
the concession company into a funding crisis when only seven trains had been delivered. This
opt out also reflected the underlying mispricing of the debt at pre-financial crisis levels rela-
tive to those post-crisis.
The NSW government agreed to provide $175 million deferred equity in order to prevent
a default of the concession company under its financing agreements. Rather than guarantee
the full amount of senior debt ($357million) or provide state funding, the state government
offered the deferred equity to be callable in six years conditional on delivery of the trains and
the provision of the full amount of senior debt. At the time that the equity is payable it is
expected that the annuity payments will be providing a revenue stream such that the conces-
sion company can refinance the project and not call on the state equity.
10.9.4.2. Triggers
The trigger was failure of the monoline insurers leading to a refused drawdown by the senior
debt lenders.
10.9.4.3. Process
The financing terms of the concession agreement were amended in negotiations between NSW
Treasury, NSW RailCorp, the concession company shareholders and the lenders.
10.9.4.4. Approvals
10.9.4.5. Outcomes
The NSW government cited the renegotiations as a major success given that a collapse of the
contract would have meant that the people of NSW would have been waiting up to seven
years for replacement trains. It said that the restructuring agreement provided all involved
parties with the confidence to fulfill their contractual obligations without major exposure of
the state balance sheet. By the end of 2013, 51 of the 78 air-conditioned trains were in service.
10.9.5. M7 Motorway
The M7 Motorway is a 40-kilometre dual carriageway motorway in Sydney developed as a
PPP with the RTA as the public authority. West Link Motorway Limited is the concessionaire.
Major construction started on the M7 Motorway in July 2003.
The project was opened to traffic in December 2005, eight months ahead of schedule.
The federal government contributed $360 million towards this motorway with the remainder
of the estimated $1.54 billion capital cost being met by the private sector.
10.9.5.1. Changes
A number of change orders were utilized by the RTA to make changes to the design and con-
struction of the project in accordance with relevant provisions in the project deed.
10.9.5.2. Triggers
10.9.5.3. Process
10.9.5.4. Approvals
The project has a steering committee and approval of the state treasury for any renegotiation
would be required. Scope changes are approved within the RTA.
10.9.5.5. Outcomes
An Infrastructure Partnerships Australia Case Study had this to say on the project:
“The road has been comprehensively hailed by all stakeholders as a great achievement that delivers
significant benefits to the community. The Australian, NSW and local governments have all praised
the contribution that Westlink M7 has made to improving transport across and through Sydney.
Business leaders have applauded Westlink M7 as a significant driver of investment and employment
growth in Sydney. Media attention has also been overwhelmingly positive.”
11.1. Background
The South African PPP Framework has borrowed heavily from practice and experience in the
United Kingdom (UK) where a form of contracting known as the Private Finance Initiative
(PFI) was a common source of the social and economic infrastructure developed in the 1990s
in the UK.
This form of contracting consists of the public sector, through a public agent, granting the
rights to design, build, finance and operate for a specified period of time some publicly-owned
infrastructure to a private party with substantial risk transfer to the private party. Because this
form of contracting was known to impose significant financial obligations and forms of risk on
the sovereign fiscus, responsibility for approval of projects implemented under such contracts
was given to Her Majesty’s Treasury (UK Treasury).
The South African framework for PPPs dates back to 1999 when the national Government
approved a framework for PPPs in terms of which the Minister of Finance and the Treasury
would be responsible for the oversight and fiscal management of PPPs. As a result, Treasury
Regulations (TRs) were subsequently made and promulgated in terms of section 76 of the
Public Finance Management Act, Act No 1 of 1999 (PFMA). Regulation 16 (TR 16) of the
TRs falls under Part 6 thereof – which Part is captioned “Frameworks” – and is pivotal to
the regulation of PPPs in the South African context. The TRs have been revised and reissued
a number of times, but TR 16 has remained substantially the same since the first version of
the TRs was made early in the second quarter of 2001 and it has not changed at all since the
revised TRs were made in March 2005.
TR 16 sets out a formal process by which an institution must obtain various approvals from
the relevant treasury for any project that meets the definition of a PPP. TR 16 also provides
for the requirements that have to be met for, among other things, a given project to be classi-
fied as a PPP and therefore to bring it within the ambit of TR 16 and for the various treasury
approvals that need to be granted to authorize the implementation thereof.
Pioneering PPP projects were undertaken between 1997 and 2000 by the SA National Roads
Agency for the N3 and N4 toll roads; by the Departments of Public Works and Correctional
Services for two maximum security prisons; by two municipalities for water services; and by
SA National Parks for tourism concessions.
11.9.1. Gautrain
The Gautrain is an 80km rapid rail system that links Johannesburg with Pretoria, South Africa’s
capital, and OR Tambo International Airport. The Gautrain PPP is between the Gauteng Pro-
vincial Government (GPG) and Bombela Concession Company (the concessionaire). It was
signed in September 2006 with a 19-year concession period. The project cost is USD2,5 billion
with approximately USD2 billion in government capital grants paid against milestones in the
pre-COD development phase. The remainder was in private sector debt and equity (85/15).
The government grant is linked to CPI and indexed annually so inflation risk is shared in the
same proportion as the grant / private finance.
The project financial structure is based on a base case financial model, which is a schedule
to the Concession Agreement. In it the base case return on equity is 18%. In return for a
minimum revenue guarantee, the GPG receives 50% of any revenue earned above this base
case return. Any changes to the concession from variations, change in law or project events
is measured against the base case financial model to determine a no-better-no-worse position
for the concessionaire.
The project stretches over some 80 kilometers for which the site had to be secured via expro-
priation or acquisition of servitude by the GPG. This could not be done before financial close
so a project management plan was developed for handover of different parts of the site over
time. Some parcels of land were handed over late to the concessionaire, giving rise to a claim
for compensation.
The extended site in an urban area also meant that there was a strong likelihood of unknown
utilities (water mains, power cables and the like). Flexibility was built into the Concession
Agreement by specifying a lump sum to cover all such utilities and then setting out how any
savings or additional costs above this base amount would be shared so as to incentivize both
parties to efficiently and cost effectively identify and move such utilities.
The ongoing insurance requirements for such a large project were identified but costing them
was difficult for bidders to do for the full concession period. It was deemed to be good value
for money to also use a reference benchmark amount to be used in the Concession Agreement
with savings shared between the parties on a bi-annual basis.
11.9.1.1. Changes
There have been a number of variations in the concession to date. Some of these have been
initiated by the GPG and a smaller number by the concessionaire to reflect scope changes
generating cost savings. In total the variations have been less than 1% of capital cost.
In 2011, the contractual date for operating commencement date was missed. In order to
commence a partial service, an interim operating period was agreed as an amendment to the
Concession Agreement. In terms of this, the parties accepted the reduced revenues from a
partial service and the concessionaire was made good by the civil contractor for delays.
In 2012, an agreement varying the Concession Agreement was entered into to regulate the
savings to be shared between the parties for unknown utilities in the rail reserve and to carry
out additional protection works to utilities outside the rail reserve.
In 2014, an ancillary revenue agreement regulating the additional revenue from sources such
as advertising and ICT services was negotiated.
11.9.1.2. Triggers
The triggers depend on the cause, be it a contractual target date being missed or an opportunity
to increase the revenue within the system.
11.9.1.3. Process
The Gauteng Provincial Government has created an agency known as the Gautrain Manage-
ment Agency (GMA) to manage its affairs with regard to the Concession Agreement and to
undertake the obligations and exercise the rights of the Province in this regard.
The GMA is the accounting authority for the government and exercises delegated powers in
making amendments to the Concession Agreement.
The provincial treasury is informed and consulted and is represented on the GMA Board.
11.9.1.5. Outcomes
All the amendments and variations to date have been voluntary amendments with the objec-
tive of preempting project distress in a structured manner based on the no-better-no-worse
principle. The project is performing well with demand and revenue performing in line with
forecasts. A beneficial refinancing is underway as is a variation to acquire additional rolling
stock.
In such a complex arrangement, the concession agreement variation and amendment procedure
is essential to managing the project effectively and in line with the National Treasury guidance
on contract management.
The GMA is audited annually on its performance of managing the concession. To date it has
received clean audits in all aspects including the variations and amendments.
11.9.2.1. Changes
Because of a single outstanding environmental approval for the toll plazas, the concessionaire
was unable to complete the toll plazas and for five years the concessionaire claimed payment
to the extent that revenue was below forecast because such circumstances were classified as a
“designated event” under the Concession Agreement. Between 2005 and 2008, the situation
was exacerbated by a road closure due to what the concessionaire cited as dangerous road
conditions. Given the lack of revenue incentive to keep the road open, this was contested by
the Province and a public outcry raised political tempers.
The Minister of Transport in the Province appointed a joint task team of treasury and transport
department officials assisted by financial, legal and technical advisors to investigate the matter.
The task team’s terms of reference may be summarized as:
• Establishing what happened to give rise to the current circumstances;
• Establishing whether there was any financial impropriety in any of the events;
• Establishing why things went wrong; and
• Providing options and recommendations as to what the Province should do in response to
the circumstances.
The task team carried out a detailed financial and non-financial systems analysis to identify
any fraudulent or financially inappropriate behavior by the concessionaire and the adequacy
of the systems.
Compliance with technical and operational specifications was also analyzed.
The task team analyzed:
• The key, high impact causes of Project distress;
• The cost of termination of the concession under any of its provisions;
• The cost benefit analysis of the Project;
• The likely future financial outcomes for the Project; and
• Future scenarios on traffic volumes and revenues.
The task team concluded that based on affordability (cost), risk transfer and value for money
it would be best to:
• Amend the Concession Agreement to provide more comprehensive definitions of the Clo-
sure Event and Damage Events and to prevent the concessionaire from unilaterally closing
the road; and
11.9.2.2. Triggers
The trigger was the closure of the drive for an extended period of time under the designated
event regime caused by the delayed regulatory approvals for the project.
11.9.2.3. Process
11.9.2.4. Approvals
The National Treasury approval in terms of TR16.8 as well as the support approval of the
Provincial Treasury.
The approval of the lenders was obtained by the concessionaire.
11.9.2.5. Outcomes
The outcome has been a very stable project with steady traffic growth to over 90% of the
forecast levels. Road closures have been minimized. The Province expects to make an overall
saving in the concession period given the post debt service period revenue sharing.
12.1. Background
Since 1992, the United Kingdom has used a form of public private partnership for the delivery
of public services that is known as the Private Finance Initiative (PFI). The UK placed great
emphasis on the concept of value for money in justifying the decision to procure infrastructure
and the services coming from this infrastructure (for example, health, transport, education
or custodial services) rather than by conventional procurement. By using the concept of PFI
credits to supplement the existing budgetary allocations, HM Treasury was able to support a
massive series of investments into infrastructure ranging from hospitals and schools to munici-
pal infrastructure and roads in the period 1992 to 2010.
Under a typical PFI deal, the public sector enters into a long-term contractual arrangement
with private sector companies, which undertake to design, build and operate an asset. There
are around 700 PFI contracts in the UK. Over 500 of these are in England, with a combined
capital value of almost GBP50 billion. The forecast PFI payment for these projects for 2010-
2011 was estimated at GBP8 billion. They are usually long-term arrangements typically
spanning 25 to 30 years. HM Treasury (the Treasury) estimates that the total commitments
on current PFI contracts for the next 25 years for the UK are approximately GBP200 billion.
The United Kingdom thus provides one of the most interesting studies of a PPP program.
Over the years this has been cited as the most successful PPP programme in terms of output
of infrastructure and the achievement of value for money. It also yielded one of the most
interesting forms of PPP unit in the world – a private company with a shareholding by the
UK government as well as private sector companies by the name of Partnerships UK, or PUK.
It not only assisted in the delivery of roads, schools and hospitals, prisons and government
buildings but also ventured into social housing, defense facilities, IT, minor ports and air-
port, rail and the like. For the period 1995 to 2007, the PFI was the world’s most active PPP
program.
It did, however, attract serious criticism, mostly because of the use of so-called PFI credits
whereby public authorities could be granted budget for payments to the private sector for the
delivery of services and infrastructure in the future (often up to 25 or even more years into
the future). These PFI credits created a massive future liability for government and during
the financial crisis and subsequent change in government in 2010 the PFI programme was
reviewed and substantially cut. PUK was dissolved and re-integrated into the Treasury.
13.1. Background
According to Engel,12 Chile has one of the most successful PPP programs among developing
countries. Some USD11 billion investments in public infrastructure have been made and these
investments have substantially improved the infrastructure and reduced transport costs. The
private pension funds and the life insurance companies, with their large pools of long-term
savings, have been active investors in bonds issued by large PPP projects.
On the down side, Chile also has a history of widespread renegotiations (both in terms of
numbers and prevalence in all sectors). It stands out in sharp contradistinction with the other
International Comparator Countries in the number of formal renegotiations. It is also the
only country in the four that has a formal part of PPP legislation dealing with renegotiation.
13.8. Examples
The following two examples (Engel, 2009) demonstrate how government used renegotiations
to bypass congressional approval for increased expenditure.
• The rainwater collectors. Santiago was prone to flooding and in 2001 the government,
under political pressure, decided to construct new main rainwater collectors. As further
indebtedness or limited budgetary resources were the constraints, government decided to
renegotiate the contracts of urban highways. Hundreds of millions of dollars were renegoti-
ated to form part of the construction of the highways, which would be paid for some time
in the future.
• The San Antonio Bypass. To access the main port of Chile, trucks had to travel through the
city of San Antonio. A special access route to bypass the city was designed. There were three
options to finance the route: (i) fund it from the fiscus (ii) independent self-financed tolled
concession or (iii) non-tolled extension to an existing Route 78. The President promised
the public that he would not toll the route, so it was decided to renegotiate the contract,
valuing the 8km at around USD45 million. An increase in tolls in the existing contract
together with a further tariff increase was the result.
110 Developing
Report on Developing
a Framework
a Framework
for Renegotiation
for Renegotiation
of PPP Contracts
of PPP Contracts
Annexure B1: EU Directive on Concessions
Article 43
Developing
Department
a Framework
of Economic
for Renegotiation
Affairs: Ministry
of PPPof
Contracts
Finance 111
d. where a new concessionaire replaces the one to which the contracting authority or the
contracting entity had initially awarded the concession as a consequence of either:
i. an unequivocal review clause or option in conformity with point (a);
ii. universal or partial succession into the position of the initial concessionaire, follow-
ing corporate restructuring, including takeover, merger, acquisition or insolvency, of
another economic operator that fulfils the criteria for qualitative selection initially
established provided that this does not entail other substantial modifications to the
contract and is not aimed at circumventing the application of this Directive; or
iii. in the event that the contracting authority or contracting entity itself assumes the
main concessionaire’s obligations towards its subcontractors where this possibility
is provided for under national legislation;
e. where the modifications, irrespective of their value, are not substantial within the mean-
ing of paragraph 4.
Contracting authorities or contracting entities having modified a concession in the cases set out
under points (b) and (c) of this paragraph shall publish a notice to that effect in the Official
Journal of the European Union. Such notice shall contain the information set out in Annex
XI and shall be published in accordance with Article 33.
2. Furthermore, and without any need to verify whether the conditions set out under points
(a) to (d) of paragraph 4 are met, concessions may equally be modified without a new
concession award procedure in accordance with this Directive being necessary where the
value of the modification is below both of the following values:
i. the threshold set out in Article 8;16 and
ii. 10% of the value of the initial concession.
However, the modification may not alter the overall nature of the concession. Where several
successive modifications are made, the value shall be assessed on the basis of the net cumula-
tive value of the successive modifications.
3. For the purpose of the calculation of the value referred to in paragraph 2 and points (b)
and (c) of paragraph 1, the updated value shall be the reference value when the concession
includes an indexation clause. If the concession does not include an indexation clause, the
updated value shall be calculated taking into account the average inflation in the Member
State of the contracting authority or of the contracting entity.
4. A modification of a concession during its term shall be considered to be substantial within
the meaning of point (e) of paragraph 1, where it renders the concession materially dif-
ferent in character from the one initially concluded. In any event, without prejudice to
paragraphs 1 and 2, a modification shall be considered to be substantial where one or more
of the following conditions is met:
a. the modification introduces conditions which, had they been part of the initial concession
award procedure, would have allowed for the admission of applicants other than those
initially selected or for the acceptance of a tender other than that originally accepted or
would have attracted additional participants in the concession award procedure;
112 Developing
Report on Developing
a Framework
a Framework
for Renegotiation
for Renegotiation
of PPP Contracts
of PPP Contracts
b. the modification changes the economic balance of the concession in favour of the conces-
sionaire in a manner which was not provided for in the initial concession;
c. the modification extends the scope of the concession considerably;
d. where a new concessionaire replaces the one to which the contracting authority or con-
tracting entity had initially awarded the concession in other cases than those provided
for under point (d) of paragraph 1.
5. A new concession award procedure in accordance with this Directive shall be required for
other modifications of the provisions of a concession during its term than those provided
for under paragraphs 1 and 2.
114
Length (BOT/ Equity Debt
Sl. Name of project Project IRR (as per Concession VGF (if any) Status of the
of the DBFOT/ Name of SPV Name of promoter COD component component
No. (stretch) cost (Rs.) submitted period Cr. project
stretch Annuity/ (Cr.) (Cr.)
cashflow)
OMT/
EPC)
Four laning
of Godhra to
Gujarat/Madhya
Pradesh Border
Section of 1. Isolux Corsan
Soma Isolux
NH-59, from km Concessions S.A, 2. Isolux
Varanasi 27 years incl. Under
129.300 to km 87.102 Corsan Concessions PCOD
DBFOT 750 Cr. Aurangabad 18.86% construction Rs. 225 Cr. Rs. 525 Cr. Nil Operation &
215.900 in the km India (P) Ltd, 3. Soma – 02.11.2013
Tollway (P) period Maintenance
state of Gujarat Enterprises Ltd , 4. Soma
Ltd
on Design, Build, Tollways (P) Ltd
Finance, Operate
and transfer
(“DBFOT”) basis
under NHDP III”
Six laning of M/s Reliance
Pune Satara Infrastructure Ltd. JV
M/s PS Toll Under
Annexure C: NHAI Data
115
Rs. Expressways Under
Highway - NH8, Not
8 27.7 km BOT 5,550.00 Private NA NA 20 years 23-01-2008 NA 1146 Operation &
Km. 14.3 to Applicable
million Limited Maintenance
Km. 42.0 (Delhi
(w.e.f.
Gurgaon)
19.05.2014)
Nature of
contract
Project
Length (BOT/ Equity Debt
Sl. Name of project Project IRR (as per Concession VGF (if any) Status of the
116
of the DBFOT/ Name of SPV Name of promoter COD component component
No. (stretch) cost (Rs.) submitted period Cr. project
stretch Annuity/ (Cr.) (Cr.)
cashflow)
OMT/
EPC)
Rs.
M/s
625.07 Cr
Hazaribag
BOT (NHAI), M/s IL&FS & M/s Punj Partial COD: Rs. 738.18 Not Under
9 Hazaribag-Ranchi 73.799 Ranchi 18 years Rs. 131 Cr.
(Annuity) 869.18 Lloyd Limited 15.09.2012 Cr. Applicable Construction
Expressways
(Concess-
Ltd
ionaire)
Four laning of Under
Gwalior-Jhansi Construction
80.127
section of NH-75 M/s Gwalior- (work
km
from km 16.00 to BOT Rs. 604 Jhansi M/s D.S. Construction Ltd, Not Not has been
10 (68.627 11.94% 20 years 216.40 Cr. 504.92 Cr.
km 96.127 in the (Annuity) Cr. Expressway M/s Apollo Enterpises Ltd. achieved Applicable stopped by
km in
State of Madhya Limited concession-
MP)
Pradesh & Uttar aire since
Pradesh March, 2012)
Improvement,
Operation and
Maintenance
including
strengthening
and widening of
Existing 2 lane
road to 4 lane 20 years (3
M/s Oriental M/s Oriental Structural
dual carriageway years for Under
Rs. 472 Pathways Engg. Pvt. Ltd., M/s Delhi
11 from km 12.600 77.55 km BOT construction 20.08.2009 Rs. 130 Cr. Rs. 520 Cr. Nil Operation &
Cr. (Indore) Pvt. Brass & Metal works
to km 84.700 of and 17 years Maintenance
Ltd Pvt. Ltd
NH-3 (Indore- for O&M)
Khalghat
Section) in the
State of Madhya
Number
Type and Average
of
estimated Form of Total debt/
projects Number Number
max Model project Tariff equity Number
by year Number actually in distress
freight Concess- cost at regime ratio at CA termin-
since awarded imple- (see d
capacity ion Agree- signature applied signing ated
comm- mented above)
at time of ment used date date (if
ence-
signing known)
ment
1995-96 2 2 5 * 61.77 RoC N.A.
1996-97 1 1 13.2 * 750.00 RoC N.A.
1997-98 3 3 24.5 * 1130.00 RoC N.A.
1998-99 2 2 10.5 * 300.00 RoC N.A. 1
1999-00 0 0 0 * 0.00 RoC N.A.
2000-01 1 1 1.5 * 27.00 RoC N.A.
2001-02 4 4 19.62 IDFC 1152.03 RoC N.A. 1
2002-03 2 2 5.88 IDFC 198.35 RoC N.A.
2003-04 1 1 13.5 IDFC 703.34 RoC N.A.
2004-05 3 3 54.6 IDFC 3445.50 2005 G N.A.
2005-06 1 1 3.5 IDFC 20.00 2005 G N.A.
2006-07 6 5 42.8 IDFC 2118.00 2005 G N.A. 1
2007-08 3 3 20.6 MCA 1613.00 2005 G N.A.
2008-09 4 4 14.4 MCA 4442.45 2008 G N.A. 2
2009-10 11 8 61.37 MCA 2744.95 2008 G N.A. 2
2010-11 9 7 58.92 MCA 3817.46 2008 G N.A. 1
2011-12 3 2 79.32 MCA 7735.74 2008 G N.A. 1
2012-13 11 11 39.2 MCA 1780.50 2008 G N.A. 2
2013-14 14 14 101.52 MCA 17839.83 2008 G N.A.
Total 81 74 569.93 49879.92 6 5
Notes:
1) (*) indicates agreements not based on any model agreement.
2) (IDFC) : indicates agreements based on Standard Agreement drafted by IDFC
3) (MCA): indicates Agreements based on Model Concession Agreement of the Ministry
4) (RoC) : indicates tariff was prescribed on return on capital employed basis. However there were no general tariff guidelines issued
by ministry
5) 2005G : indicates tariff was prescribed as per 2005 Tariff Guidelines issued by Ministry
6) 2008G : indicates tariff was prescribed as per 2008 Tariff Guidelines issued by Ministry
Type and
estimated Form of
Debt/equity % Debt to
max freight Project cost Actual Model Tariff Volumes % Application
Project Date CA ratio at CA be paid on
handling at signature project cost Concession regime of forecast for revised
Name signed signing concession-
capacity date (if known) Agreement applied (latest) tariff regime
date aire default
at time of used
signing
Creation of
Port related
SOR is
facilities by The
M/s. ESSAR revised
M/s. ESSAR agreement As per SOR
has been based
OIL LTD. signed in approved
handling on the
At OOT 1997 is by TAMP
cargo to clauses of
Department 8/10/1997 7.5 MMTPA Rs. 750 Cr. Not known not as per and terms & NA NA
the tune of Agreement.
Vadinar, the form conditions
more than Accordingly,
KPT for their of Model of the
300% of the revised
9 MMTPA Concession Agreement.
capacity tariff is
Oil refinery Agreement.
applicable.
off Vadinar
Village
Ministry of Shipping
Data required by World Bank Consultants for Contract Renegotiation (PPP Projects)
Data for Sample of Projects
(Kolkata Port: Supply, Operation & Maintenance of cargo handling equipment at
Berth Nos.2 & 8 Haldia)
Type and
Debt/
estimated Form of
Project Actual equity % Debt to Volumes Application
max freight Model
Date CA cost at project Tariff regime ratio be paid on % of for revised
Project Name handling Concession
signed signature cost (if applied at CA concession- forecast tariff
capacity Agreement
date known) signing aire default (latest) regime
at time of used
date
signing
This was a
Supply, contracting
Operation & model where
Contracting
Maintenance port paid to
model.
of different contractor on
Terms &
cargo per tonne basis
October 8.0 million Rs.150 Rs.140 conditions Not
handling finalised through N/A N/A N/A
2009 tons crore crore * were known
equipment tender, KoPT
approved
at Berth realised tariff
by Board of
Nos.2 & 8 of from the users as
Trustees.
Haldia Dock per its Scale of
Complex Rates approved
by TAMP.
Type and
estimated Form of
Debt/equity % Debt to
max freight Project cost Actual Model Tariff Volumes % Application
Project Date CA ratio at CA be paid on
handling at signature project cost Concession regime of forecast for revised
Name signed signing concession-
capacity date (if known) Agreement applied (latest) tariff regime
date aire default
at time of used
signing
Develop- Model
ment of Concession
Yes, TAMP
Barge The project Agreement
notified Operation
handling 30.03.2013 1.35MTPA Rs.27.29 Cr. is yet to issued by * ** no
tariff on yet to start
facility at start Ministry of
17.08.12
Bharathi Shipping ,
Dock Ports wing
*EAC recommended for the project and formal letter from MoEF is awaited. Financial Closure yet to be achieved .
** If the termination is after the date of Commercial operation, due to a concessionaire Event of Default, the compensation payable by the Concessioning Authority to the
Concessionaire shall be the lowest of ,
i. Book value
ii. 90%(ninety percent) of debt due
iii. The actual project cost
Ministry of Shipping
Data required by World Bank Consultants for Contract Renegotiation (PPP Projects)
Data for Sample of Projects
(Chennai Port: Chennai Container Terminal - CCTPL)
Type and
estimated Form of
Debt/equity % Debt to
max freight Project cost Actual Model Tariff Volumes % Application
Project Date CA ratio at CA be paid on
handling at signature project cost Concession regime of forecast for revised
Name signed signing concession-
capacity date (if known) Agreement applied (latest) tariff regime
date aire default
at time of used
signing
Model
Chennai Revision
Concession
Container Yes, TAMP of Tariff
150 million Rs.778.03 Agreement
terminal 09/08/2001 1.26 MTEU notified Not known * About 60% by TAMP
USD Cr. based
Pvt. Ltd. tariff is under
on IDFC
(CCTPL) litigation
agreement
* If the termination is after the date of Commercial operation, due to a concessionaire Event of Default, the compensation payable by the Concessioning Authority to the
Concessionaire shall be the lowest of,
i. Book value
ii. 90% (ninety percent) of debt due
iii. The actual project cost
Type and
estimated Form of
Debt/equity % Debt to
max freight Project cost Actual Model Tariff Volumes % Application
Project Date CA ratio at CA be paid on
handling at signature project cost Concession regime of forecast for revised
Name signed signing concession-
capacity date (if known) Agreement applied (latest) tariff regime
date aire default
at time of used
signing
Redevelop-
ment
Model Yes, TAMP
of BT to
10/08/2004 15.60 MTPA Rs.900 Cr. Rs.1078 Cr. Concession notified Not known * About 150% no
Container
Agreement tariff
Terminal
(APMT)
* If the termination is after the date of Commercial operation, due to a concessionaire Event of Default, the compensation payable by the Concessioning Authority to the
Concessionaire shall be the lowest of,
i. Book value
ii. 90%(ninety percent) of debt due
iii. The actual project cost