Coating Systems For Various Structures
Coating Systems For Various Structures
From the visit to certain structures and factory visit it has been
observed that the methods adopted earlier to prevent the structures from
corrosion was not scientific and adequate, it was trial & error techniques
only. Also it has been seen that method adopted was not effective to
prevent the corrosion for important structures. Study has been made to
find out the method adopted earlier and why it was not effective. And what
should be the proper methods to arrest or minimize the corrosion ^form
existing system.
Before studying the high performance coating, it is necessary to
know the methods used earlier. Following methods of painting or coating
Vwas adopted for the steel structures. Also it was observed that in earlier
Structural steel:
Earlier method for coating the structural steel, -
as finish paint).
oxide on it directly. But mill scale appears adherent, which needs not to be
138
completely adherent, and it is a temporary barrier on the surface. If such
steel exposed to weather, mill scale will (starts rusting, If this mill-scale
embedded in the coating. Coating tends to fail because red oxide primer is
not impervious and is not arresting vapour transfer, resulting into rusting of
mill-scale & eventually failure of coating. Hence require frequent
Conclusion:- {(
In all cases, even though the mild exposure pr dry weather, it is
always recommended to remove all mill scale by mechanical means or
grinding for better performance of any painting to reduce the maintenance
cost. But other than the mild exposure, exposure conditions as explained
earlier, this system is not adequate to sustain tee structures in aggressive
environment. For this, ‘High Performance Coating’ is tee only solution.
various temperatures & weather conditions). It was found that tee coating
systems adopted was satisfactory.
, / f
139
THE DIFFERENT STRUCTURES STUDIED ALONG WITH THE EARUER
METHODS OF COATINGS ARE,-
A) STEEL STRUCTURES:
1. Storage Tanks
I. Water storage tanks
II. Add & Alkali storage tanks
lil.Naphtha & Distillate Storage Tank
2. Chimney (Stacks)
I. Dual wall (Insulated)
3. Pipelines
I. Water supply line
II. Heat resistance pipes
B) CONCRETE STRUCTURES:
1. RCC Cooling Tower: Following are the sections of Cooling
tower, -
I. Hot water basin (Part of cooling tower situated at top),
II. Circulating water (C. W.) channel (Area between Cold
water basin and Circulating water pump house.),
III.Cooling water pump sump
IV. Cooling tower Super structure
A) STEEL STRUCTURES:
1. STORAGE TANKS
I) Water Storage Tank:
• Purpose of tank:
Storage of raw water before treatment.
140
• Material used for fabrication:
Structural steel i.e. MS plates, angles, channels, pipes
for connections.
• Dimensions:
Internal diameter 24.4 m I / D
Height: 16.2 m
• Type of roof:
Cone Roof Tank
• Atom covered under coating including supporting
structure:
External surfaces:
Tank Shell, Cone Roof, Curb Angles, Hand Rails,
Outside pipes, staircase.
Internal Surfaces:
Tank Shell, Bottom, Cone Roof, Roof Structure, Inside
Pipe Connections.
• Type of Exposure:
External surfaces exposed to salty weather due to
coastal area.
Internal Surfaces: Under Immersion services, water
pH between 6 to 7 (Potable water)
• Earlier methods of coating on such type of tank:
Internal surfaces:
In earlier method it was found that no coating was
applied.
External surfaces
External surfaces were found painted with Red oxide
as a primer, it was applied without any surface
preparation and synthetic enamel as a finish paint.
• Observation:
141
i-\i : £
142
System Suggested are:
System D - Aluminium Epoxy Mastic + Aluminium
Epoxy Mastic
System J - Epoxy Mastic + Epoxy Mastic
System L - Epoxy + Epoxy (Potable Water)
System L - Epoxy + Epoxy
Features-
Offers two coat, high build protection with ease of
application. We suggest the use of the same product
for both coats. Corrosion inhibitors are not necessary
in immersion service. A third coat may be added for
additional protection.
System-
For Potable Water 2 coat Super Hi-Gard 891 Epoxy
@ 4-6 mils daft (100-150microns)
Surface Preparation-SSPC-SP 5- White Metal Blast.
External Surfaces:
Exposure needs to be analyzed, here with consider the
case of resistance to salty weather & Fresh Water
Spray,-
Frequently wet by fresh water, involves condensation,
splash or spray. This would include interior or exterior
areas that experience frequent cleaning or washing
including stem cleaning.
This group of systems includes the use of inorganic
zinc as a primer. It is generally recognized that
inorganic zinc is the best coating that can be applied
to steel and that it offers the longest term of protection.
Systems using inorganic zinc have been known to last
for over 20 years. In some cases you may need to
substitute organic zinc. This will affect the overall
143
protection quality of the system but only by a small
amount.
System Suggested are:
System B - Inorganic Zinc + Epoxy Primer +
Polyurethane Finish
System C - Inorganic Zinc + Acrylic Latex Finish
System E - Aluminum Epoxy Mastic + Polyurethane
Finish
System G - Aluminum Epoxy Mastic + Acrylic Latex
Finish
System R - Acrylic Latex Primer + Acrylic Latex
intermediate + Acrylic Latex Finish
144
1 coat Carbothane 134 HS Polyurethane @ 2-4 mils
DFT (50-100 microns) or equivalent other make i.e.
Berger, Amron, etc.
Surface preparation: For both the surfaces: Surface
Preparation-SSPC-SP 10 Near White Blast.
Monitoring of Environmental parameters
Monitored the environmental parameters as explained
in earlier chapter i.e. Dew Point temp., surfaces Temp
of substrate, Relative Humidify.
Application methods
Application done by Spray Method & for touch up
Brush application.
Curing / overcoat Interval:
As per data given by the manufacturer.
Performance Test Conducted:
Internal surfaces: X
Visual Inspection is theNmandatory for every course of
action (as, per guidelines explained in earlier chapters)
for visual defects.
Surface profile after surface preparation by replica tape
method and by Comparator, Wet film thickness during
the application of coating, DFT after completion of
coating, adhesion test of finish paint by Knife test,
holiday test.
External surfaces
Visual Inspection is the mandatory for every course of
action (as per guidelines explained in earlier chapters)
for visual defects.
Surface profile after surface preparation by replica tape
method and by Comparator, Wet film thickness during
the application of coating, DFT after completion of
coating, adhesion test of finish paint by Knife test
145
• Review of performance test after one year:
External Surfaces:
Reviewed the same for complete performance through
out the period more than one year but did not find any
defects, which can be concluded that system applied
was OK
Internal Surfaces:
Reviewed the same for complete performance during
the period of shutdown till completion of one year but
did not find any defects, which can be concluded that
system applied was OK
146
Internal Surfaces: Under Immersion services, Acid &
Alkali.
• Earlier methods of coating on such type of tank:
Internal surfaces:
In a earlier method it was found that Acid or alkali
----- "s
147
System I - Epoxy Phenolic Primer + Epoxy Phenolic
Lining + Epoxy Phenolic Lining
System P - Epoxy Novalac + Epoxy Novalac
System U - Solventless Elastomeric Polyurethane
System suggested is System P>
System P - Epoxy Novalac + Epoxy Novalac
Features-
Outstanding chemical and physical abuse resistance.
One of the finest industrial coatings for a wide range
chemical resistance.
Higher temperature resistance than a standard J400
°F continuous).
System-
1 coat Thermaline 450 Epoxy Novalac @ 6-8 mils DFT
(150-200 microns)
1 coat Thermaline 450 Epoxy Novalac @ 6-8 mils DFT
(150-200 microns)
Surfaces-
Normally Steel or Concrete.
Surface Preparation-
White Metal Blast -SSPC-SP 5
148
• External Surfaces:
Coating system for external surfaces is same as Water
Storage Tank, External Surface, since exposure
conditions are the same.
• Monitoring of Environmental parameters
Monitor the environmental parameters as per chapter
i.e. Dew Point temp., surfaces Temp of substrate,
Humidity.
• Application methods
Application done by Bruch) roller & Trowel method.
• Curing / overcoat Interval:
As per data given by the manufacturer.
• Performance Test Conducted:
Internal surfaces: ^
Visual Inspection is! the mandatory for every course of
action (as per guidelines explained in earlier chapters)
for visual defects.
Surface profile after surface preparation by replica tape
method and by Comparator, Wet film thickness during
the application of coating, DFT after completion of
coating, adhesion test of finish paint by Knife test,
holiday test.
External surfaces ^
Visual Inspection is the)nandatory for every course of
—__
149
Reviewed the same for complete performance through
out the period more than one year but did not find any
defects, which can be concluded that system applied
was OK.
Internal Surfaces:
Reviewed the same for complete performance during
the period of shutdown till completion of one year but
did not find any defects, which can be concluded that
system applied was OK
150
Tank Shell including supporting structure, which will
include channels stiffeners etc., roof top and top
ladder, Girder, stairway, outside pipes etc.
Internal Surfaces:
Tank Bottom, one meter of shell above tank bottom,
and 2 meter of shell from top, inside pipe connection,
* Type of Exposure:
External surfaces:
Exposed to salty weather due to coastal area.
Internal Surfaces:
Under Immersion services, coated only, Tank top 2
meter and bottom 1 meter. Because when distillate /
Naphtha comes in^raw tt contains the some amount of
water. Due to it’s heavier than fuel it settles down at
bottom and tends to corrosion of plates.
- SUGGESTED EFFECTIVE COATING FOR
DISTILLATE & NAPHTHA STORAGE TANK:
High performance coating is the best solution to
protect the structure from its aggressive environment,-
Following are the systems for better performance, -
INTERNAL SURFACES:
The systems suggested, two coats of epoxy (System
L) is frequently used for this service, make sure the
material selected meets the necessary standards and
V*'
Mastic
System J - Epoxy Mastic + Epoxy Mastic
System L - Epoxy + Epoxy (Potable Water)
System L - Epoxy + Epoxy
Features-
151
Offers two coat, high build protection with ease of
application^ We suggest the use of the same product
for both coats. Corrosion inhibitors are not necessary
in immersion service. A third coat may be added for
additional protection.
System-
2 coats of Berger Epilux 610 @ 30 microns per coat
i.e. 60 microns as a primer.
2 coats of Berger Epilux 78 HB @ 100 microns per
coat i.e. 200 microns.
Surface Preparation -
SSPC-SP 5-White Metal Blast.
EXTERNAL SURFACES:
Exposure needs to be analyzed, here with consider the
case of resistance to salty weather & Fresh Water
Spray,-
Frequently wet by fresh water, involves condensation,
splash or spray. This would include interior or exterior
areas that experience frequent cleaning or washing
including stem cleaning.
This group of systems indudes the use of inorganic
zinc as a primer. It is generally recognized that
inorganic zinc is the best coating that can be applied
to steel and that it offers the longest term of protection.
Systems using inorganic zinc have been known to last
for over 20 years. In some cases you may need to
substitute organic zinc. This will affect the overall
protection quality of the system but only by a small
amount.
System Suggested are:
System B - Inorganic Zinc + Epoxy Primer +
Polyurethane Finish
152
System C - Inorganic Zinc + Acrylic Latex Finish
System E - Aluminum Epoxy Mastic + Polyurethane
Finish
System G - Aluminum Epoxy Mastic + Acrylic Latex
Finish
System R - Acrylic Latex Primer + Acrylic Latex
intermediate + Acrylic Latex Finish
It was proved that the following systemjs worked very
effectively,-
System B - Inorganic Zinc + Epoxy Primer +
Polyurethane Finish
Features-
Outstanding corrosion resistance and undercutting
resistance afforded by the primer.
The intermediate epoxy coat forms a barrier protect the
primer.
The polyurethane finish gives excellent colour gloss
retention.
System-
1. 1 coat of Carboline Make-Carbo Zinc 11 HS
Inorganic Zinc @ 2-3 mils DFT (50-75 microns) or
equivalent appoved of other make i.e. Berger, Amron,
etc.
1 coat Carboline 893 Epoxy Primer @ 4-6 mils DFT
(100-150microns) or equivalent other make i.e. Berger,
Amron, etc.
1 coat Carbothane 134 HS Polyurethane @ 2-4 mils
DFT (50-100 microns) or equivalent other make i.e.
Berger, Amron, etc.
Surface preparation:
Internal Surface: SSPC SP10 -Near White Metal Blast
Cleaning
153
External Surfaces: SSPC SP 10 - Near White Metal
Blast Cleaning
" Monitoring of Environmental parameters
Monitor the environmental parameters as per chapter
i.e. Dew Point temp., surfaces Temp of substrate,
Humidity.
• Application methods ^y
Application can be doneany of the methods explained
earlier; small portion can applied by brush or roller
(preferably Roller) and large portion by spray method.
• Curing / overcoat Interval:
As per data given by the manufacturer.
• Performance Test Conducted:
Internal surfaces:
Visual Inspection is the mandatory for every course of
action (as per guidelines explained in earlier chapters)
for visual defects.
Surface profile after surface preparation by replica tape
method and by Comparator, Wet film thickness during
the application of coating, DFT after completion of
coating, adhesion test of finish paint by Knife test,
holiday test.
External surfaces
Visual Inspection isthe mandatory for every course of
action (as per guidelines explained in earlier chapters)
for visual defects.
Surface profile after surface preparation by replica tape
method and by Comparator, Wet film thickness during
the application of coating, DFT after completion of
coating, adhesion test of finish paint by Knife test
• Review of performance test after one year:
External Surfaces:
154
Reviewed the same for complete performance through
out the period more than one year but did not find any
defects, which can be concluded that system applied
was OK
Internal Surfaces:
Reviewed the same for complete performance during
the period of shutdown till completion of one year but
did not find any defects, which can be concluded that
system applied was OK
2) STACK (CHIMNEY):
* Purpose of Stack:
Coating system for 98.17 m height steel stack, which
will be constructed for 1552MW, combined cycle power
plant
* Type:
Self-supporting type duel wall insulated steel stack.
■ Material used for fabrication:
Structural steel i.e. MS plates, angles, channels, pipes
for hand rails gratings.
■ Dimensions:
Internal diameter 6.5 m I ID
Height: 98.17 m (From Ground)
■ Thickness of plate Used:
22 mm thk, 16 mm thk, 12 mm thk, 8 mm thk MS plate
varying form TOP (8 mm tfik) to BOTTOM (22 mm
thk).
■ Areas covered under coating including supporting
structure:
External surfaces:
Stack Shell, Supporting channels, Curb Angles, Hand
Rails, ladders with cage.
155
Internal Surfaces:
No coating done on internal surface.
* Type of Exposure:
External surfaces exposed to salty weather due to
coastal area. Due to emission of heat temp of shell rise
up to <300 degree centigrade.
Internal Surfaces: Due to continuous emission of heat
no coating is required.
■ Earlier methods of coating on such type of tank:
In earlier method it was found that Chimneys were
constructed of RCC with no coating. And steel without
adequate coating techniques because found lots of
rusting on it and increased maintenance cost.
■ Observation:
' r-
resistance coating.
Suggested Coating system:
Primer - Inorganic Zinc Silicate + Finish coat- Hi.
Temp. Silicone Finish
Primer:
156
1 coat of Carboline Make-Carbo Zinc 11 HS Inorganic
Zinc @ 2-3 mils DFT (50-75 microns) or equivalent
approved of other make i.e. Berger, Amron, etc.
Finish Coat:
Hi. Temp. Silicone with or without Aluminum finish
Silicone aluminum top coat with a total Vol. Solids
content of not less than 35 Vol.%@ 1-1.5 mils DFT (25
- 35 microns)
Surface preparation:
External surface: SSPC SP 10-Near to white Metal
• Monitoring of Environmental parameters
Monitor the environmental parameters as explained in
earlier chapter i.e. Dew Point temp, surfaces Temp of
substrate, Humidity.
• Application methods
Application done by Spray & Roller.
* Curing / overcoat interval:
As per data given by the manufacturer.
* Performance Test Conducted:
External surfaces
Visual Inspection is the mandatary fa* every course of
action (as per guidelines explained in earlier chapters)
for visual defects.
Surface profile after surface preparation by replica tape
method and by Comparator, Wet film thickness during
the application of coating, DFT after completion of
coating, adhesion test of finish paint by Knife test
■ Review of performance test after one year:
External Surfaces:
Reviewed the same for complete performance through
out the period more than one year but did not find any
157
defects, which can be concluded that system applied
was OK
3. PIPE UNES:
I) WATER SUPPLY UNES:
• Type of Exposure:
Internal Surface:
Coating Not required
External surface:
For Exposure of resistance to salty weather & Fresh
Water Spray,-
• System Recommended is:
Inorganic Zinc silicate + 2 coate of High Build
Epoxy
• Type of Exposure:
Internal Surface: Not required
External surface:
For Exposure of Heat resistance up to 300 degree
centigrade
• System Recommended is:
Inorganic Zinc silicate + 2 coats of high temp
Silicone of DFT 25-35 microns.
158
1 coat of In-organic Zinc silicate Zinc Anode 304 of
Berger Make of DFT 50-100 microns.
2 coats of High Temp Silicone of Carboline make of
DFT 25 - 35 microns for each coat.
Other parameters are same as Stacks.
159
• Type of Exposure:
External surfaces:
Exposed to salty weather due to coastal area.
• Suggested effective coating for General type of
equipment:
High performance coating is the best solution to
protect the structure from its aggressive environment
also given the repair & touch up coating system.
Following are the systems for better performance,-
External Surfaces & Internal surfaces:
Exposure needs to be analyzed, here with consider the
case of resistance to salty weather & Fresh Water
Spray,-
Most of the cases it is recommended not use abrasive
blasting. Normally surface of sheet is smooth
therefore for better adhesion primer should be such
that which will adhere to plate and same time it should
be compatible to finish paint.
• System Suggested are:
System U: wash primer + polyurethane finish.
Features-
Outstanding adhesion on smooth surface & The
polyurethane finish gives excellent colour gloss
retention & corrosion resistance.
System-
2 coats of Bison wash primer of Berger make @ DFT
10 to 15 microns or equivalent approved of other make
i.e. Carboline, Amron, etc.
2 coat Carbothane 134 HS Polyurethane @ 2-4 mils
DFT (50-100 microns) or equivalent other make i.e.
Berger, Amron, etc.
Surface preparation:
160
External Surfaces & External surfaces:-Solvent
cleaning SSPC-SP-1
• Monitoring of Environmental parameters
Monitor the environmental parameters as per chapter
i.e. Dew Point temp., surfaces Temp of substrate,
Humidity.
• Application methods
Application of primer shall be possible by brush only
since very fast drying of primer. Finish paint applied by
spray for uniform finish.
• Curing / overcoat Interval:
As per data given by the manufacturer.
• Performance Test Conducted:
External surfaces / Internal surfaces:
Visual Inspection is done as per guidelines explained
in earlier chapters for visual defects.
DFT after completion of coating, adhesion test of finish
paint by Knife test
• Review of performance test after one yean
Reviewed the same for complete performance through
out the period more than one year but did not find any
defects, which can be concluded that system applied
was OK.
\ • For Touch up and repair method of coating:
Initially: tails advised to collect the data of exiting the
1r V. -'
161
Rust tolerant self priming epoxy mastic Berger make
protestomastic of DFT 60 to 100 microns. + Bison
wash primer of Berger make DFT 10 to 15 microns.
Finish paint-
Polyurethane of any standard brand.
Surface preparation:
SSPC-SP 1-Solvent cleaning, SSPC-SP 2-Hand tool
cleaning.
Control of all other parameters will be the same as
above.
B) CONCRETE STRUCTURES:
Concrete structures are more durable than Structural steel work, but in
some 'Ip aggressive environment like where continuous flash of salty
162
I. TO IV.rCOATING SYSTEMS FOR ABOVE STRUCTURES:
• Purpose of coating System:
To ensure the proper and complete installation of the
specified polyurethane lining systems on the specified
concrete surfaces.
Hie application procedure is based upon the specification
and technical information provided in the material
manufacturer’s technical data for the specific material.
• UNING SYSTEM -COATING MATERIALS
Geothane-520, consisting of Surfacer + Sealer-Futura-Bond-
320 Gel-(For filling of bug-holes and other concrete surface
defects)
Primer + Sealer- Futura - Bond 415 (over all surfaces at 3-5
DFT (75-125 microns)
Elastomer caulk- Future - Caulk 5705 (Filling of cracks.)
Elastomer lining - Geothane 520 (over all surfaces at 50-60
mils DFT (1.26-1.50mm)
• SURFACE PREPARATION FOR CONCRETE:
Note: New concrete shall be cured minimum of 28 days prior
to coating.
Thoroughly clean all surfaces to be primed and coated,
effectively removing all traces of contamination, i.e: oil,
grease, release, agents, surfaces, dirt, etc.
Wash at high pressure water jetting (1500 psi or greater) with
10% TSP (Tri Sodium Phosphate ) in hot water solution.
Immediately rinse washed areas with clean water removing
all traces of detergent and contaminants.
Repeat the cleaning procedures as required to ensure
complete removal of all contamination. Remove all standing
or ponding water from horizontal surfaces.
163
Grind ail surface irregularities flush with surrounding surface
areas removing all ridges, spurs protrusions, etc.
Prepare all cracks which have opened to width of 1/6 inch
(1.6 mm) or greater (if required).
Open all cracks to a width of 34 inch(6.35) and depth of 34
inch (12.7 mm) using diamond tipped router bits or circular
saw blades or grinders.
Abrasives grit blast ail surfaces to the coated, effectively
removing all surfaces laitance, old coatings and loose spalled
surfaces, and providing a surfaces, and providing a surfaces
texture similar to medium-coarse sand paper approximate
surface profile of 3.0-6.0 mils (75-125 microns).
Required Operation ConcNtions:-
The compressed air supply shall be completely free of oil,
water and jprticuls^contaminants, and provide the required
volume of air at 100 psi or greater pressure.
The abrasive grit or steel shot shall be a clean, uniform grade
of appropriate size particles to obtain the specified surface
finish and profile. Do not use contaminated grit or hot.
Direct the abrasive grit blast onto the concrete surfaces at a
45 degree angle for best results. Move the blast nozzle with
rapid sweeping motions (“brush - blast*) and uniformly strip -
away the surface laitance, old coatings and spalled surfaces
to a clean profiled appearance.
Thoroughly clean all blasted surfaces to remove all dust and
debris after dry blasting.
(Dry) Sweep -down and./or blow-down all surfaces and
remove excess dust and debris.
(Wet) High pressure wash-down all surfaces and remove
excess dust debris and standing water. Thoroughly dry all
surfaces prior to final dealing procedures with vacuum-clean
164
all surfaces to be coated, effectively removing all remaining
dust.
LINING APPLICATION
system.
FLOOR TO WALL JOINT IN C.W. BASIN,
PUMPSUMP:-
MIXING
Thoroughly mix components A and B together utilizing
165
Maximum Recoat: 72 hours at 70 °F (21 °C)
166
FUTURA-CAULK K 5705* POLYURETHANE ELASTOMER
CAULK
This product used to fill up cracks more than 3mm
width:
Application Temperature Range:
Minimum: 45°F(7°C)
Maximum: 110 °F (44 °C)
Thoroughly mix components A and B together utilizing
an air powered mixer with impeller.
Mix Ratio : 9:1 A:B components
Mixed Pot Life: 30-45 minutes at 75 °F (24 °C)
Allow the applied Futura-Caulk 5705 to cure to a dry-
to-touch condition before over-coating with the
polyurethane coating.
Minimum cure : 1 -2 hours at 70-90 °F (21 -32 °C)
GEOTHANE 520:
Elastomer lining - Geothane 520 (over all surfaces as
finish coat.
These are 100% solids, zero V. O. C. polyurethane
elastomeric linings. Hie Geothane 520 must be batch
mixed, and requires airless spray equipment.
Application Temp. Range :
Minimum 45 °F (5 °C)
Maximum 120 F (49 °C )
Relative Humidity Conditions: Maximum 85%
Thoroughly mix components A and B together utilizing
an air powered mixer with impeller.
Mix Ratio : 1:1 A:B components
Mix Pot Life: 40 minutes at 75 0 (24 0C)
167
(Minimum thickness 50 Mils in two coats of 25-30 Mils
each)
Coat 1 of Geothane 520 - The gap between
successive applications of different material / coats
shall be maintained as shown in sketch no. 3 in
enclosed annexure.
Ambient temperature records have to be maintained
during application of each and every coat of Primer,
surfacer / Geothane 520 to determine minimum cure
time and maximum cure time.
Maximum re-coat time exceeded by less than 24
hours: The surface reactivation will be done by
spraying MEK.
The each coat of Geothane 520 shall be applied by
uniform multiple pass spray. This shall be performed
in 3-4 passes, with each pass applied using a 50%
overlap of the previous pass aid applied in a cross-
hatch pattern to provide the most uniform and
consistent thickness.
Allow tie first coat of Geothane 520 to cure to a dry-
to-touch condition before over coating with the second
coat. Do not exceed the maximum recoat time.
Minimum cure : 3-4 hours at 70-90 °F (21-32 °C)
Maximum Recoat: 72 hours at 70 °F (21 °C)
Preferable Recoat: 4-24 hours at 70 °F (21 °C)
use.
168
Random Elcometer Adhesion Tests will be performed
by representatives of the owners to verify compliance
to: (a) lining thickness specification (b) lining adhesion
specification.
• ACCEPTANCE CRITERIA
Inspected for following Defects, -
BLISTERS- All blisters greater than 3/8 inch diameter (
9.53 mm) shall be cut out and repaired. Groups of
blisters of any size shall be repaired
PINHOLES- No pinhole will be permitted. The pinhole
area shall be identified and shall be cut out and
repaired as blistered area.
DELAMINATIONS- Any delaminations of the lining
shall be removed and repaired.
ADHESION- 0-99 psi adhesion will be considered
unacceptable and 100 psi or greater will be
considered acceptable. Areas showing adhesion
below 100 psi may require removal and replacement of
coating.
• DRY FILM THICKNESS -
The polyurethane lining exclusive of the surfacer and
primer, shall be no less than 50 mils DFT (1.25 mm),
nor greater than 60 mils DFT (1.50mm).
169
• COATING MATERIAL:
170
6 to7 mils in a coat. Before applying on clear areas,
the comers and edges shall be smoothen.
vi. The mixed paint will be used within its pot-life, i.e., only
the quantity of paint, which can be spread within pot-
life only, be mixed.
vii. The thickness of paint applied will be checked with
WETFILM THICKNESS GAUGE along with application
of paint.
• COATING INSPECTION:
i. Surface temperature and humidity readings shall be
taken prior to application of each coat.
ii. The Dry Film thickness shall be measured with an
ELCOMETER. The testing method shall be in
accordance with SSPC PA - 2.
iii. Defective or damaged coating that have been repaired
and replaced shall be reinserted to the original
requirements.
iv. The coatings applied over concrete surfaces will be
visually inspected to ensure they are free of pinholes /
voids.
v. The Moisture Content of surfaces shall be determined
using an electronic moisture meter or acceptable
equivalent method. We will not apply paint when
moisture content of concrete is above 12%.
vi. Ensure that cementations surfaces are prepared as
specified, void & rock pockets are filled flush with
compatible patching /filler materials, and incompatible
liquid airing membrane is removed.
vii. The coating shall be visually inspected for application
defects such as over spray, runs, sags etc.
viii. /Ml Inspection gauges / Instruments shall be
calibrated.
171
REVIEW OF PERFORMANCE, TOUCH-UP AND
REPAIR:
While inspection shut down, it was observed that the
coating in the basin was in good condition with few
exceptions of application related defects (such as bug
holes, pinholes between coats, runs, missed / skips,
etc. which could account for 2-4 percent of coated wall
surface area in the applied coating). There was no
indication provide continued acceptable service for the
design life of the coating system. How long a coating
will last depend on the user’s approach to and
philosophy of maintenance coating program: Proactive
approach or deferred maintenance. First maintenance
painting should take place wAien initial breakdown of
the coating occurs or is detected. Once significant
coating break down occurs, it is more costly to repair
and the effectiveness of the protection is greatly
reduced.
172
These include exposed rebar or tie wire, exposed
nails, cracked grout, exposed concrete surfaces,
damaged concrete surfaces, rough areas with
inadequate coating, etc.
173
essentially restrict the entry of saline water in to
concrete.
Fill bug holes, blowouts, voids, etc. with the paste with
putty knife or other suitable means. Wipe excess putty
from the coated surface, if required. Allow the fill coat
to dry for a minimum recoat period as specified on the
service.
The conclusions based on the present study are given in the next Chapter.
174