Method Statement For The Laying of Dense Bitumnous Macadam Binder Course

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

PROGRESSIVE PROGRESSIVE CONSTRUCTIONS LTD.

~
SUNWAY CONSTRUCTION BERHAD
JOINT VENTURE

FOUR LANING AND STRE NGTHENING OF


THE EXISTING TWO LAN E HIGHWAY
SECTION FROM KM 32.0 0 TO KM 398.75 ON
NH – 2 IN BIHAR (INDIA)
(CONSTRUCTION PACKAG E V-C)

METHOD STATEMENT
FOR THE LAYING OF
DENSE BITUMNOUS
MACADAM BINDER
COURSE

CLIENT: NATIONAL HIGHWAY AUT HORITY


OF INDIA

CONSULTANT: SNOWY MOUNTAIN ENGINEERING


CONSULTANT
METHOD STATEMENT FOR DENSE BITUMINOUS
MACADAM BINDER WORKS

1 GENERAL

The works generally consist of laying, spreading and compacting of dense bituminous
macadam material on prepared road base (WMM) which primed previously with prime coat
and in accordance to the requirement and specification given (Clause 507).

2 MATERIALS

Approved source of crushed stone, aggregates or combination of these depending on grading


(see figure 1) and passing of these materials in accordance to the specification (507.2.5) and
the binder content of 4.5% by the weight of total mix (Clause 507.3).

IS Sieve Per cent by weight passing the IS sieve

Designation
37.50 mm 100

26.50 mm 90 - 100

13.20 mm 56 – 80

4.75 mm 29 - 59

2.36 mm 19 – 45

300 micron 5 -17

75 micron 1-7

Figure 1

3 MACHINERY & EQUIPMENT

The equipment to be used for laying and spreading of sub base shall be by using mechanical
pavers, vibration tandem roller, pneumatic tyre roller and water truck as and when necessary.
4 METHOD FOR LAYING

SEQUENCE OF WORK

SPREADING

COMPACTION

4.1 SPREADING

Immediately upon receiving of the mixed DBM material, the mix shall be spread
uniformly on the prepared road base (WMM) according to the thickness specified
by using self propelled mechanical paver with suitable screeds capable of
spreading, tamping and finishing the mix to specified grades, lines and cross
section as shown in drawings.

4.2 COMPACTION

Thereafter, rolling shall be carried out by using with a set of rollers consist of
vibration tandem roller and pneumatic tyre roller. minimum of 100Kn static weight
and rolling will be carried out starting from lower edge towards upper edge
longitudinally.

5 AREA OF CONCERN
6 OBSTRUCTION
7 SITE RECORDS
8 METHOD OF MEASUREMENT