Cadastral Report PDF
Cadastral Report PDF
Diploma
June 2018
UNIVERSITI TEKNOLOGI MARA
June 2018
CONFIRMATION BY PANEL OF EXAMINERS
I certify that a Panel of Examiners has met on 3 July 2018 to conduct the final
examination of Nurzaitie Aflah Binti Abdullah in her Industrial Training Report entitled
“Surrender and Re-Alienation for Subdivision on Lot 13506 (PT 1416) and Lot 13512
(PT1417), Mukim of Bukit Raja, District of Petaling, Selangor Darul Ehsan” in
accordance with Universiti Teknologi MARA Act 1976 (Akta 173). The Panel of
Examiner recommends that the student be awarded the relevant diploma. The Panel of
Examiners was as follows:
ii
AUTHOR’S DECLARATION
I declare that the work in this Industrial Training Report was carried out in accordance
with the regulations of Universiti Teknologi MARA. It is original and is the results of
my own work, unless otherwise indicated or acknowledged as referenced work. This
thesis has not been submitted to any other academic institution or non-academic
institution for any diploma or qualification.
I, hereby, acknowledge that I have been supplied with the Academic Rules and
Regulations for Post Graduate, Universiti Teknologi MARA, regulating the conduct of
my study and research
iii
SUPERVISOR’S DECLARATION
“I hereby declare that I have read this industrial training report and in my opinion this
report is sufficient in terms of scope and quality for the award of the Diploma in
Geomatic Science
Signature : ……………………………………
Name of Supervisor : Mohamad Azril Bin Che Azril
Date : June 2018
iv
ABSTRACT
In cadastral survey, there are a few survey that relate to this work which are include
subdivision, surrender and re-alienation, amalgamation, partition and other cases.
Regarding the issue of this project is the client want to do Surrender and Re-Alienation
for Subdivision on Lot 13506 (PT 1416) and Lot 13512 (PT1417), Mukim of Bukit Raja,
District of Petaling, Selangor Darul Ehsan. Solar observation has been made as a datum
for this project. However, the aim of this project is to subdivide 2 pieces of land into 8
portion and prepare the road reserve in the lot. Then produce the final plan of each lot.
v
ACKNOWLEDGEMENT
I would like to express my very great appreciation to Encik Mohamad Azril Bin Che
Aziz, the main supervisor for cadastral survey. For their patient guidance, enthusiastic
encouragement and constructive suggestions during planning and development of this
project. He also giving a lot of idea for me to generate creative ideas then build and
motivate for me to be more encourage. Also not forget to give me moral support to
complete the entire report within the time given.
Special thanks to Encik Abdul Muiz Bin Yazid as my supervisor at Jurukur Zenith
because always share and give any his own experience and knowledge for me. Without
his commitment to give some advice and supportive, I would not finished and less
confident to handle this project.
Lastly, huge appreciation to my beloved parents Abdullah Zakaria and Mahani Japar
who always give me very valuable advice for to make sure not to give up and by my
side. Thanks to all my friend for sharing and giving me their information and own
experience. Last but not least, I would like to thank the millions of thanks to god for
giving me chance to complete this project without any doubt.
vi
TABLE OF CONTENTS
CONTENT PAGE
DECLARATION OF INDUSTRIAL TRAINING REPORT i
CONFIRMATION BY PANEL OF EXAMINERS ii
AUTHOR’S DECLARATION iii
SUPERVISOR’S DECLARATION iv
ABSTRACT v
ACKNOWLEDGEMENT vi
TABLE OF CONTENT vii
LIST OF TABLES x
LIST OF FIGURES xi
LIST OF A:BBREVIATIONS xii
vii
2.2 Types of Control 15
2.2.1 Horizontal Control 15
2.2.1.1 Datum 15
2.2.1.2 Types of Traversing 17
2.3 Method of Adjustments 18
2.3.1 ‘C’ Correction 18
2.3.2 ‘M’ Correction 19
2.4 Calculation volume 20
2.5 Refixation 21
2.5.1 Baseline 21
2.5.2 Thirdmark 22
2.5.3 Refixation 23
2.6 Boundary Mark 24
2.6.1 Types of Boundary Mark 24
2.6.2 Distance Between Boundary Mark 24
2.6.3 Symbols Used in Cadastral Survey 25
2.7 Plan Processing 26
2.7.1 Preparing The Certified Plan 26
viii
4.4 Data Processing 44
4.5 Final Product 45
REFERENCE 74
APPENDIX 75
ix
LIST OF TABLES
x
LIST OF FIGURES
xi
LIST OF ABBREVIATIONS
Abbreviation
PT Pejabat Tanah
PU Permohonan Ukur
CP Certified Plan
RS Requisition Survey
PTD Pejabat Tanah Daerah
PKUP Pekeliling Ketua Pengarah Ukur & Pemetaan
NDCDB National Digital Cadastral Database
GNSS Global Navigation Satellite System
BKL Batu Konkrit Lama
CRM Cadastral Reference Mark
DSMM Director Survey and Mapping Malaysia
CV Calculation Volume
JUPEM Jabatan Ukur Pemetaaan Malaysia
PA Pelan akui
ASCII American Standard Code for Information Interchange
LLS Licensed Land Surveyor
LO Land Office
EDM Electronic Distance Measurement
GDM Geocentric Datum of Malaysia
xii
CHAPTER ONE
INTRODUCTION
In this chapter, there are a few explanation about the historical of the company, the
management, scope of work and organization structure of the company.
Jurukur Zenith is a licensed land surveying that registered under Land Surveyors
Board of Peninsular Malaysia and the only one company who conduct the land survey
services in Kota Kemuning, Shah Alam since 2011 until now. The company was
managed by Chinese surveyor Mr Heng Wei Kaiy Licenced Land Surveyor that
registered under act 458 (revised 1991).
Because of the establishment of the company has been long, their
professionalism in do the survey has been trusted. Its provide and carry out all the survey
work such as Consultant in Land and Property Development, Survey Services in Strata
Titles, Cadastral, Engineering, Topographical and GPS surveying and figure 1.1 below
show the logo of Jurukur Zenith’s Company.
1
1.1.1 Office Location And Contact
There are a few information about location and contact of the company as a
guideline for client to find the office. Figure 1.2 below show the office location for
Jurukur Zenith.
2
1.1.2 Organizational chart
This is the organization chart of Jurukur Zenith that handle and manage the job
and work of the survey. There are 14 workers including the owner of the company and
management team. 1.3 below show the organization chat of Jurukur Zenith Company.
PROJECT MANAGER
Sr HENG WEI KAIY
Figure 1.3 The Organization Chart Of The Company (Jurukur Zenith, 2018)
3
1.1.3 Technical And Administrative Staff
Technical staff
Administrative staff
4
1.1.4 List of Equipment Owner
There are a few equipment that the company provide in order to carry out the
survey work required. Table 1.0 below show the list of equipment that belongs to the
company to use in the survey work.
Table 1.1
List of Equipment Owner
Instruments Quantity
1x Total Station
(Topcon)
2x Tripod
3xPrism
5
1x Mini Pole
Mini Prism
1x GPS Handheld
(Garmin)
1x Sunglass Solar
6
1x A3 plotter
( brother MFC)
1x A2 plotter
1x A1 Plotter
1x Distometer
7
1.2 Executive Summary
The "Surrender and Re-Alienation for Subdivision on Lot 13506 (PT 1416) and
Lot 13512 (PT1417), Mukim of Bukit Raja, District of Petaling, Selangor Darul Ehsan"
project was accepted n surveyed by Jurukur Zenith. The PU was requested by client
which owner of the land. The project consist of 2 lot that need to be amalgamated into
1 single lot before it can be subdivide into 8 different lot. The lot should be surrender
to PT and re-alienated before it can proceed to next step which is subdivision. The area
of the alienated lot should be less than specified in the title as PT need to prepare some
road reserve.
The project was requested by the client in early year 2017 but Jurukur Zenith
was just recently conduct the project due to late approval by PT. I joined this project
halfway through since it started before my internship. Thanks to the surveyor guidance,
I get to understand the work flow from the beginning, covered what I was missing in
the early half, and stick till the completion of the project.
The cost of this project was estimated to be around RM 7000. The survey
quotation can be referred to the table 1.2. The project was handled and monitored by
Abdul Muiz Bin Yazid who is the project manager for Jurukur Zenith while the surveyor
in charge are Foo Chee Yong and Ng Yoon Fai.
Surrender and Re-Alienation for Subdivision on Lot 13506 (PT 1416) and Lot
13512 (PT1417), Mukim of Bukit Raja, District of Petaling, Selangor Darul Ehsan.
8
1.2.2 Site Location
The project was located at lot 13506 and lot 13512 Kayangan Height, Shah
Alam, Selangor by referring the coordinate of WGS 84. Figure 1.4 below show the
image of site location with the red line on the lot.
Y
LOT 31506
LOT 31512
9
1.2.3 Aim & Objective
Every project must have their own aim and objective to make sure the job will
be completed within the prescribed time.
Aim
- The aim of this project is to surrender and re-alienation lot 13506 and lot 13512
before proceed to subdivision into 8 different portion of lot with new CP for
each lot
Objective
- To be able to amalgamate 2 lot into 1 lot for subdivision under surrender and
re-alienation
- To be able to subdivide into 8 portions with difference certified plan as client
requested.
- To be able to prepare road reserve for the subdivided lot.
10
1.2.4 Scope of Work
There are a few stages need to be followed when doing this project on Lot
13506 and 13512 at Kayangan Height, Mukim Bukit Raja, Selangor.
b) Survey field
- Establishment of vertical control point using nearest benchmark
- Site reconnaissance n planning work
- Resurvey the lot
- Computation of solar observation to get true bearing
- Mark the boundary using Pipe
- Refix the new boundary mark for the new 8 plots
11
1.2.5 Quotation
Table 1.2 show all cost regards the survey work from the beginning until the last
out of final plan. It must calculate all the cost before the survey is carry out and need to
give to the client. All the fees are fixed and follow the Lembaga Jurukur Tanah Malaysia
Table 1.2
Quotation for the Survey
No Detail Quantity Unit Rate @ Total
RM (RM)
1 Land office cost
- Official land title search 2 Lot 50 100
- Application of “Hakmilik” 2 Lot 100 200
- FApplication Fees 2 Lot 50 100
2 Registration of “Majlis Daerah”
- Process 50
- Registration of Lot 2 Lot 30 60
- “Sijil merancang majlis 50
daerah”
3 Land Survey Board Cost
- basic charge 1000
- Pre – computation 1 350
- Survey (0.5 – 2.5 ha) Lot 1650
- line for azimuth 71.638 M 2.00 143.76
- line connection of control 364.114 M 2.00 728.23
survey
- Refixation boundary mark 10 170 1700
- Digital data 914.40
- Reimbursement software 1 30
packages
- GST (6%) 424.58
TOTAL (RM) 7500.970
12
CHAPTER TWO
THEORY
The theory of work that used during the work of surrender & re-alienation project is
explained briefly in this chapter. This chapter intends to help understand the importance
of applying such theory on survey work, also based on PKUP 2002 and PKUP 2009.
2.1 Definition
2.1.1 Demarcation
13
2.1.2 Reconnaissance
14
2.2 Types of Control
2.2.1.1 Datum
15
After it was observed, a computation for po-new was done. This is to check the
difference and to make sure that it is within tolerance so that it is acceptable. For BKL
with less than 40m, the bearing should not exceed 1' while the distance should be within
± 0.0015. If the distance of BKL is more than 40m, the tolerance for the bearing should
not exceed 30" while the distance tolerance is 0.0015 and +0.006 for additional 20m.
Table 2.1 showed the datum condition according circular 2002:-
Table 2.1
Datum Determination
A line Tolerance
Bearing Distance
< 40 meter ≤ 1’ ± 0.0015
>40 meter ≥ 30” Each additional 20
meters add +0.006m
The interior angle between of two boundary mark should not exceed
10” or if it the previous survey which second class survey, the interior angle
must not exceed 20”
16
2.2.1.2 Type of traversing
Open Traverse
Open traverse means that the traverse start at known point and closed at
unknown point. This type of survey is usually used on a narrow path to pick up details.
It has less accuracy thus cannot be checked its tolerance and adjusted. Establishing new
boundary mark or refixation is prohibited from using this type of traverse.
Closed Traverse
Closed traverse is a traverse that start from a known point and end at known
point too. This type of traverse has high accuracy and suitable to conduct precise survey
such as establishing new boundary mark or refix. This type of traverse allow us to check
its accuracy thus applying correction to adjust it. There are 2 type of closed traverse
which is polygon and link traverse.
Polygon - It is a survey that start from known point and end at the same known point.
The line of the traverse will connect which each other thus shows a polygon shaped
diagram.
Link – Link traverse is a survey that start at known point and closed at another known
point. The first line and last line of the traverse does not connect with each other thus
showing a diagram of a link traverse
17
2.3 Method of Adjustments
Basically, surveyor will apply the adjustment for the data that had been collected
at the fieldwork by applying related correction before it can be used to the next of
refixation to find the thirdmark and baseline of the lot. Adjustment is compulsory before
refixation is proceed
Table 2.2
Formula of C Correction
Bearing Misclosure:
= (𝑀𝑒𝑎𝑠𝑢𝑟𝑒𝑑 𝑏𝑒𝑎𝑟𝑖𝑛𝑔 𝑓𝑟𝑜𝑚 𝑐𝑙𝑜𝑠𝑒𝑑 𝑏𝑒𝑎𝑟𝑖𝑛𝑔
− 𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝑏𝑒𝑎𝑟𝑖𝑛𝑔)
C Correction:
−(𝐵𝑒𝑎𝑟𝑖𝑛𝑔 𝑀𝑖𝑠𝑐𝑙𝑜𝑠𝑢𝑟𝑒)
𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑆𝑡𝑎𝑡𝑖𝑜𝑛𝑠
18
2.3.2 ‘M’ Correction
Source of M Correction:-
Solar observation
3 old boundary mark (proved)
3 old or new CRM (proved)
3 old Station from previous project
Table 2.3
Formula of M Correction
M Correction:
= [𝑇𝑟𝑢𝑒 𝑏𝑒𝑎𝑟𝑖𝑛𝑔 𝑓𝑟𝑜𝑚 𝑠𝑜𝑙𝑎𝑟 𝑜𝑟 𝑎𝑑𝑜𝑝𝑡𝑒𝑑 𝑏𝑒𝑎𝑟𝑖𝑛𝑔]
− [𝑀𝑒𝑎𝑛 𝑏𝑒𝑎𝑟𝑖𝑛𝑔 𝑜𝑓 𝐹𝐵](+𝑜𝑟 −)[𝑐 − 𝑐𝑜𝑟𝑟𝑒𝑐𝑡𝑖𝑜𝑛)
19
2.4 Calculation Volume
20
2.5 Refixation
2.5.1 Baseline
Baseline is a line that consist of 2 boundary mark that covered the surveyed site.
The boundary mark is chosen through computation of PO and NEW. It is better if the
line of the baseline is the longest and had least error in comparison. The pair that has
the least error is acceptable as the baseline. Baseline shall be longer than the boundary
line where its mark to be refixed. Table 2.4 showed the formula of the baseline is as
follow:-
Table 2.4
Formula of the Baseline
𝐵𝑎𝑠𝑒𝑙𝑖𝑛𝑒 = 𝑁𝑒𝑤 𝐵𝑒𝑎𝑟𝑖𝑛𝑔 − 𝑃𝑂 𝐵𝑒𝑎𝑟𝑖𝑛𝑔
21
2.5.2 Thirdmark
Purpose of baseline
2.5.3 Refixation
22
2.6 Boundary Mark
Boundary mark acts to show the owner of its lot boundary. It is planted after
being approval by DSMM. The drawing of the lot, its location, number of boundary
mark, and area of lot should be check before being approved. Any illegal removal of
boundary mark may cause a fine being implied to the doer.
There are a few type of boundary mark that used in the cadastral survey. Every
boundary mark has their own function and purpose to make sure we can recognize it
during the survey work.
Concrete - The concrete stone used for boundary mark is usually has 600mm with
a diameter of 75mm. It usually has punctured mark on its top as a reference for a
station. There also a sign at the boundary mark to differentiate who planted it. JUP
means that the boundary mark was planted by JUPEM. If it was planted by LLS,
there should be serial number of the stone which can be purchased from the state
JUPEM.
Granit - Granite stone is square with a size of 80 mm wide, 120 mm long and
600 mm high and has a punch mark for the station.
Iron Pipe - Iron pipe length is not less than 900 mm with diameter between 25
mm to 50 mm. it should be adorned with stainless steel and the top of the pipe
opening shall be sealed with concrete having a mark on the station point. If the
soil is sandy, muddy and swampy conditions, it is allowed to fall out 6 inches
from the ground.
Iron spikes - Nail length of not less than 55 mm and 8 mm in diameter. The nail
head should be 15 mm in diameter and have a diameter of 46mm and mark at
point of the station.
23
2.6.2 Distance Between Boundary Mark
According PKUP 2009, each boundary mark should be planted before or during
the measurements carried out by using the requirement set by the Department Survey
DSMM.
Any boundary marks on a straight line shall be planted at intervals not exceeding
300 meters if the signs are visible or at intervals not exceeding 200 meters if they
are not visible at all.
Any boundary lines that follow the curve should be marked at the end of the cords
so that the normal distance from the curve to the crossover line does not exceed 0.2
meters.
A minimum distance of boundary mark is 0.1 meter.
24
2.6.3 Symbols Used in Cadastral Survey
Each type of boundary mark has its own symbol. This is to help the user to
recognize the types of boundary mark that is used at fieldwork. Table 2.4 shows the
types of boundary mark commonly used in fieldwork.
Table 2.5
Symbol Used In Cadastral Survey
Name Symbol
Pepaku Besi Baru PpBB
Pepaku Besi Lama PpBL
Batu Konkrit Baru BKB
Batu Konkrit Lama BKL
Batu Lama BL
Paip Baru PB
Paip Lama PL
Paku Baru (Berkonkrit) pkB
Paku Lama (Berkonkrit) pkL
Tanda Atas Batu TAB
Tiada Tanda TT
Piket Pkt
Tanam Pastian TP
Tanda Terabas Piawai Baru TTPB
Tanda Terabas Piawai Lama TTPL
Paip Terabas Piawai Baru PTB
Paip Terabas Piawai Lama PTL
Tugu System Penentu Dudukan GPS
Global
Tanda Aras Dengan Ketinggian ●← 119.21
Stesen Trigonometri TS
Tanda Kawalan Ukur Kadaster CRM
25
2.7 Plan Processing
Plan processing is the last stage to complete all the requirement needs to finish
the project and it is also final output for the client. It can be produce when all the data
already process and had been approve by authority.
CP is the short form of the Certified Plan. It is the last output for cadastral work
either in subdivision, partition or amalgamation. The purpose of the CP is to show the
real position of the boundary mark after it had been done the survey. By preparing the
Certified Plan, it can be issued the final title to the land owner. Figure 2.3 below shows
the example certified plan regarding this project. All the information in Certified Plan
are followed the DSMM:-
To complete the plan, side information of lot need to put on the left hand side to make
easy for the audience to understand the plan:-
Lot number
Scale
North arrow
Title
Name of state, district and mukim
History of the lot (if necessary)
PA number
26
Standard sheet number
No of old CP (if necessary)
Signed from DSMM
27
CHAPTER THREE
PERSONNEL AND EQUIPMENT
In this chapter, it will explain about the personnel who leading the survey work,
equipment used at the site and level of involvement in this project.
3.1 Personnel
i. Surveyor
- Foo Chee Yong
- Ng Yoon Fai
ii. Chainman
- Rasyid Ahmad
- Mustapar
- Awang Sulong
- Che Ngah
28
3.2 Equipment
There are a few instruments that used in this project to make sure the project can
be done completely. Table 3.1 below show the equipment that used are shown along
with its usage and accuracy at site in the project.
Table 3.1
Equipment Used In the Project
Instruments Function
TOPCON Total Station GTS – 235N
C/W
Used to measure the distance and bearing
between two points.
The data being display include the
horizontal bearing and distance, vertical
bearing and distance, and slope distance.
The instrument is available in 5” angle
accuracy, can be used to measure
distance up to millimetre and long-
lasting batteries
TRIPOD
PRISM
29
3.3 Level of Involvement
For level of involvement in this project, there are 3 step that practical student
will involve which are office work for documentation, fieldwork and data processing.
Practical student will be go through this step to make sure can learn all the procedure in
this project.
During documentation which 5%, I just get the certified plan from the staff and
prepare the document for subdivide since this project already began in late 2017. At the
field work, 44% I was involved as a chainman and help the surveyor in charge the
instrument but at the same time learn how to conduct the survey. Another 52% are data
processing, all the data are key in into the software. So it will be transfer to the
AutoCAD to produce the plan and drafter will generate ASCII file to the JUPEM by
using Jupem2u. Table 3.2 below shows briefly level of involvement and Figure 3.1
below shows the involvement in the project in the percentages.
Table
3.2 Level of Involvement
Type of Works List of Task
Office Work (4%) Prepare the document for
application of surrender and re-
alienation and number of PT
Official search of land lot
Buy PA from Geoportal server
Field Work (44%) Do the re-survey by our surveyor
Do the solar observation and
Complete the traverse around the
lot and pick up the boundary
Record all the data of the
observation in the Toughbook
and field book
Data Processing (52%) Transfer all the data to the
software
30
Draw the lot and the traverse in
AutoCAD
Perform the calculation of
refixation including calculation
volume of the traverse.
Prepare certified plan
PERCENTAGE OF INVOLEVEMENT
4%
31
CHAPTER FOUR
PROCEDURE OF WORK
In this chapter, there will be an explanation about procedure of work from the beginning
until it done and the method that has been applied in the fieldwork.
4.1 Planning
As usual before start the project, it must have the proper planning to make sure
the project run smoothly without any problem and can obtained good quality result.
Figure 4.1 below shows the flow chart of planning regarding the project that has been
done during the project is running and will briefly explain the step that has been.
LLS registered
surrender and re- Drafter sent 16
Data processing
alienation for ASCII files to JUPEM
subdivision
LLS/JUPEM Produce
Apply to Land
Survey at fieldwork CP and signatured
Office Petalling
by Director
LLS apply PT
number to LO with PT number and QT Final Title is Issued
the document issued by LO to Land owner
needed
Figure 4.1 Flow Chart of Planning (Jurukur Zenith, 2018)
32
4.2 Preparation of Document
Based on the flow chart above, there are a few procedure and preparation that
involved for documentation regarding the project of surrender and re-alienation. It
starting from Land office Petalling from that district for application of subdivision and
JUPEM Selangor to get the final title for owner. The document that need to be prepared
are:-
After the application for subdivision is approved. The owner/surveyor need to prepare
the following doc:-
When the application had been approved PT number already issued by Land
Office, LLS will apply lot number from JUPEM before surveyor can proceed survey
work at site then produce 16 ASCII file that need to submit to Unit E-QC in JUPEM to
do some checking. Finally stages is will get the Certified Plan for the lot.
33
4.2.1 Documentation
In this stage, the office should be preparing the documents needed for surveyor
to do their job. The document mention included layout plan for area of the lot and pre-
computation plan for subdivision.
Layout plan
Before pre-computation plan made, layout plan should be done to show all the
information around the lot to make it easy for surveyor as a guidance to do the survey
work and can help the surveyor to know where the location of the adjacent boundary,
road reserve of the lot and lot number. Figure 4.2 below showed the example layout
plan from the project.
34
Pre-computation plan
Pre-comp was made to show the proposed line of subdivision for the lot so that
surveyor can do their job at ease and plan their route, after layout plan already signed
by LLS,. This plan should be show to land owner to make the land owner agree with
the subdivision. In the plan, agreement from Majlis Bandaraya Shah Alam, Lembaga
Perancang Bandar Malaysia & land owner should be included so the surveyor can
proceed with the survey work. Figure 4.3 below shows the pre-computation plan for
subdivision.
35
4.3 Fieldwork
As mentioned in chapter one, this project will be doing the surrender and re-
alienation for subdivision of two lot and divide it into 8 portions asking by the client as
a land owner of this parcel on Lot 13506 and Lot 13512 at Kayangan Height, Shah
Alam, Selangor.
This survey must be carried out follow the requirement that already fixed in
PKUP 2009 from JUPEM. There are a few parties that involved during running this
project such as Jurukur Zenith as a responsible to make sure the project is done, Land
Surveyor Board (LJT), Land Office (LO) and JUPEM.
All instruments used must be calibrate to make sure all data were recorded
correctly and there is no error during the survey before start the survey,. In this project,
we did two calibration that follow the requirement such as EDM calibration and
Differential Field Test but EDM calibration already did before I enter in this project.
DFT is the differential field test that should be carried out at the start of every
day job. It can be done in the traverse line which is on the first line or any longest line
of the traverse. Figure 4.4 below showed the diagram of DFT of the traverse and table
4.1 shows the booking of DFT. There are a few criteria that need to follow to make sure
can be acceptable. If the difference exceeding 0.020 m. The action following must be
taken if:-
a) DFT not exceed 0.010 meters. Determination CRM must be done again
b) DFT exceeds the limit. The total station should make calibration
36
Procedure of DFT:-
i. Set up total station at Station A and prism at station B at the first station with
the distance 71.641 m. Observe and record it.
ii. Move the total station at Station C which the middle of the line and prism at
station A and B.
iii. Calculate the tolerance for the observation to know the result.
Figure 4.4 Differential Field Test of the Project (AutoCAD 2007, 2018)
Table 4.1
Booking of DFT from the Project
Stn Bearing mean Fr Line to Distance Final
Face left Face right distance
Final
bearing
DFT A B 71.641 71.641
(71.641)
37
4.3.2 Horizontal Control
In horizontal control, there are a few procedure before start the traversing to
make sure it can complete without dropping anything important data in the survey work.
In figure 4.5 below showed the overall diagram of traverse with the radiation of BKL
and where it start.
i. Set up the first station either on BKL or establish new point outside the lot.
The point is establish and marked by using pegs to show that it is the point of
the traverse.
ii. The station of the traverse was established with 7 points around the lot and
near the BKL to make the radiation.
iii. When all the station was done marked, we start with solar observation with the
assumed bearing 185 00 00 to find the datum to make the traverse in correct
orientation. It was done on station 2 -1
iv. After the adjustment was applied as M-correction, we proceed for the next
station it complete to the last station as closed traverse.
v. After the traverse was done, C correction need to calculate to know the bearing
misclosure from initial bearing and last bearing which station 2-1
vi. All the data was recorded by face left and face right and the traverse was run in
clockwise direction.
38
Figure 4.5 Traverse Network of the Lot (AutoCAD 2007, 2018)
39
4.3.3 Adjustment
For the adjustment of the traverse, there are two conventional method of
adjustment that we applied in this project to make sure the orientation is in correct
position:-
M – Correction
In order to make sure the orientation of the traverse is correct, we do the solar
observation since we only found 2 old boundary mark at the site and we just assumed
the value of the bearing. The value of the observation must be compared to assumed
value to know the true value of the bearing.
C – Correction
40
4.3.4 Refixation
Based on calculation that has been made, a total of 9 BKL has been found to be
out of position and need to be refix. By using calculation of comparing PO and new, a
baseline and thirdmark has been concluded in order to do refixation. By using line 14-
20 as baseline, the refixation offset for the lot boundary has been computed through
reference of PKUP 2002. Line 14-22 act as third mark for baseline independent
checking and prevent any needless shifting. The offset for refixation was done from the
station nearest to the point of refixation. Figure 4.6 below showed the procedure and
step that need to follow in refixation:-
Calculate displacement
(comparison new - PO)
Perform adjustment to PO
values
41
Selection of baseline and thirdmark were based on the lowest tolerance After
the calculation of NEW and PO has been done,. Figure 4.7 below shows which one is
the baseline and thirdmark and figure 4.8 shows the enlargement of the line in detail.
Figure 4.7 Diagram of Baseline and Thirdmark with Connection from Traverse
42
Figure 4.8 Enlargement Diagram of Baseline and Thirdmark (AutoCAD 2007,
2018)
43
4.4 Data Processing
All the data that recorded in Toughbook will be bring back to the office to give
to drafter for processing it after the survey at field work has been done,. The surveyor
will calculate the adjustment and manually write the booking of the traverse in the field
book as a hardcopy. The drafter will then process the data given and double check the
surveyor data and calculation. Using the AutoCAD software, the drafter will be able to
show the diagram of the traverse and lot. The drafter then will compare the drawing of
the fieldwork and the pre-computation plan to confirm the refixation.
return to office
with the data
Perform
calcualtion the
bowditch and area
computation
identify the
baseline and
thirdmark by
calculation
Calculate the
adjustment of
boundary mark for
refixation
Calculate the
offset to plant
new boundary
marks
44
4.5 Final Product
The final product in this project is certified plan where must be approved and
got signature from director of survey and mapping besides certified by Licensed Land
Surveyor who has conducted the survey on the fieldwork. This plan will be produced
by using the AutoCAD software and submit it to JUPEM to provide the frame of
certified plan. It used GDM 2000 Cassini-Soldner as coordinate system for this plan.
Figure 4.10 below shows the certified plan that need to produce.
45
CHAPTER FIVE
RESULT AND ANALYSIS
This chapter provides the result and analysis of the undertaken project. The final
product is briefly explained through analysis.
The result of EDM Baseline test that we did at Seksyen 6, Shah Alam, Selangor
by using ES105 model of Topcon. Based on the table 5.1 below showed the result of
the equipment that already been calibrate between observation of total station and
distance of base pillar from JUPEM and it is in good condition and the accuracy of the
equipment are in acceptable tolerance with the value 0.001m.
Table 5.1
Information of Instrument Calibration
No of pillar Distance been Fixed distance Different
From pillar To pillar observed (m) (m) (A-B)
1 2 5.016 5.013 0.003
1 3 9.997 9.995 0.002
1 4 49.006 49.001 0.005
1 5 86.994 86.998 -0.004
1 6 125.008 125.009 -0.001
1 7 163.005 163.003 0.002
1 8 201.012 201.012 0.000
1 9 251.009 251.007 0.002
46
1 10 300.028 300.034 -0.006
2 3 4.986 4.982 0.004
2 4 43.993 43.988 0.005
2 5 81.982 81.985 -0.003
2 6 119.993 119.996 -0.003
2 7 157.983 157.989 -0.006
2 8 195.998 195.999 -0.001
2 9 245.989 245.994 -0.005
2 10 295.018 295.021 -0.003
Total -0.009
N = Number of Observation 17
C = Total |A-B|/n 0.001
Before starting the project, a DFT was conducted to check the instrument. 3
point was established with the distance measured by tape. Total station n prism was
setup to measure the distance using EDM. Below is the data booking for the DFT that
was conducted.
Station Distance
A to B 71.641
C to A 31.600
C to B 40.043
47
5.2 Horizontal Control
Horizontal Control is essential in doing a survey work. In this project, the solar
observation was used as a horizontal control.
Solar observation was done in order to get the value for m-corr. It was done at
line 2-1 which traverse line. The observation was done with help of sunglasses. The
data was booking into the solar observation field book and then computed to get the
value of true bearing. After that, the value for m correction can be obtained thru true
bearing-observation bearing. The m correction was then applied to all line of
observation so that the orientation is corrected. Figure 5.1 and figure 5.2 below shows
the calculation of solar observation and the diagram of where solar observation has been
made.
48
Figure 5.2 Solar Observation with Traverse Connection
49
5.2.2 Datum
Calculation need to be made to make sure that the boundary mark is in good
position and to make sure the old boundary can be as the reference. The interior angle
was compared to determine whether it is within tolerance or not. Figure 5.3 below
showed the diagram of the line 26-16-11 which selected for datum proved.
Bearing PO – NEW = 89 50 00 − 89 50 38
= 00 00 38”
50
Distance different (PO – NEW):-
The datum used for this project is 1 solar observation and 2 proven BKL as
stated in PKUP 2009. The solar observation was done on line 2-1 which connect with
BKL 16 and BKL 26. The value of m correction which is 01’56’48” is applied to the
traverse to get the correct orientation. The 2 BKL was also proved to be in good
condition thus means that the datum used is acceptable.
51
5.2.3 Traversing
The traverse was start at line 2-1 with assumed bearing and continued on clockwise rotation. The last line of the traverse is closed at the
first station of the traverse. The solar observation was done at line 2-1 to get the correct orientation. Adjustment was apply to the traverse to reduce
the error such as c correction.
Table 5.2
Booking of the Traverse (Jurukur Zenith, 2018)
Bearing Line Final
Stn mean fro to Distance distance
Face left Face right m Final bearing
DFT A B 71.641 71.641
(71.641)
C A 31.600 31.600
(31.599)
C B 40.042 40.043
(40.043)
C A 31.600
A B 71.643
Assumed Datum 185 00 00 2 183 03 12 1 71.641
M – 01 56 48 PKT PKT
52
1 183 0312 03 03 13 150 55 02 2 150 55 02 8 13.161 13.161
2 PKT BKL (13.160)
8 150 55 02 330 55 02
1 SA 95 53 17 2 95 53 17 10 24.851 24.851
2 PKT BKL (24.851)
10 95 53 17 275 53 17
1 SA 93 39 43 2 93 39 43 11 39.086 39.086
2 PKT BKL (39.086)
11 93 39 43 273 39 43
53
2 C + 07” PKT PKT (68.508)
3 88 24 35 268 24 40
54
18 111 11 01 291 11 03
5 SA 23 46 54 6 23 47 21 21 10.589 10.589
6 M + 27” PKT BKL (10.589)
21 23 46 54 203 46 54
55
6 SA 154 03 33 7 154 04 07 24 9.031 9.031
7 M + 34” PKT BKL (9.030)
24 154 03 33 334 51 44
6 SA 11 25 20 7 11 25 54 25 17.842 17.843
7 M + 34” PKT BKL (17.843)
25 11 25 20 191 25 20
7 SA 03 02 25 1 03 03 12 2 71.638 71.638
1 C + 47 PKT Bg Terikat BKL (71.637)
2 03 02 22 183 02 28
56
5.3 Adjustment
Line 2 – 1 = 03 03 12
Should be read = 03 02 25
Different = -47” each 7 station (1, 2, 3, 4, 5, 6, 7)
C – Correction = +6.71” for each station
In the traverse, adjustment of the line is very important to make sure the error
can be reduce and being the true path by apply M and C-correction of each line.
According PKUP 2002, C-correction of the traverse cannot be exceed the maximum of
bearing misclosure which 1’15” and based on the result, it shows that the value of C-
Correction is 47” which is under 1’15”.
57
Linear Misclosure:-
Table 5.3
Calculation Volume of the Traverse
Line Bearing Distance Latid Depart Adjusted Coordinate
Latid Depart S W
2 -3049.800 -20661.000
3 88 24 45 68.507 1.898 68.481 1.899 68.482 -3047.901 -20592.518
4 179 53 03 46.969 -46.969 0.095 -46.968 0.096 -3094.869 -20592.423
5 182 53 46 27.484 -27.449 -.1389 -27.448 -1.388 -3122.318 -20593.811
6 183 28 57 50.444 -50.351 -3.064 -50.350 -.3.063 -3172.668 -20596.874
7 284 03 07 61.943 15.040 -60.089 15.041 -60.089 -3157.627 -20656.963
1 347 47 14 37.129 36.289 -7.854 36.289 -7.854 -3121.337 -20664.817
2 03 03 12 71.638 71.536 3.816 71.537 7.854 -3049.8000 -20661.000
Total = 364.114 -0.006 -0.006 0.000 0.000
58
1
Traverse Accuracy =
√∆𝐿𝑎𝑡𝑖𝑡𝑢𝑑𝑒2 + ∆𝐷𝑒𝑝𝑎𝑟𝑡𝑢𝑟𝑒²
∑𝐷𝑖𝑠𝑡𝑎𝑛𝑐𝑒
1
=
√(0.006)2 +(0.006)2
364.114
= 1 : 46825
Based on table 5.3 which showed the calculation to get linear misclosure by
follow PKUP 2002 to know the acceptable misclosure for the distance of first and last
line of the traverse. It shows that the result is under 1:8000 which 1:46825 and it is
acceptable to use for survey.
59
5.4 Refixation
a. Baseline New
b. Baseline PO
In this survey work, line chosen to be baseline is line BKL 14-20. The line goes
through the lot n have the least error thus acceptable. The baseline is then supported by
thirdmark that is proved in good condition. This prevent for any unnecessary swing of
the survey data. Below are the result of the baseline n thirdmark:-
60
5.4.2 Calculation for third mark
a. Thirdmark New
a. Thirdmark PO
= -14”
Distance thirdmark new – PO = 125.937 – 125.950
= -0.012
61
5.4.3 Interior Angle between Baseline and Thirdmark
Line PO New
Baseline (BKL 14 – BKL 20) 184 24 50 184 20 34
Thirdmark ( BKL 14 – BKL 02 54 37 02 54 23
22)
Different 181 26 11 181 26 13
Based on the result above, the value comparison of interior angle between New
and PO is 00 00 02. It can be acceptable because the tolerance are not more than ± 10”
such as stated in PKUP 2002.
62
5.4.4 Adjustment Bearing and Distance Factor
a. bearing factor
63
b. distance factor
64
5.4.5 Vector Displacement
4 -3089.062 -20603.262
16 266 15 13 29.506 -1.928 -29.442 -3090.99 -20632.704
4 -3089.062 -20603.262
17 169 02 13 21.109 -20.724 4.014 -3109.786 -20599.158
5 -3116.510 -20604.651
19 152 03 21 19.970 -17.642 9.358 -3134.152 -20595.293
6 -3166.860 -20607.714
21 23 47 21 10.589 9.689 4.271 -3157.171 -20603.443
65
7 -3151.819 -20667.803
23 172 52 18 20.703 -20.543 2.569 -3172.362 -20665.234
7 -3151.819 -20667.803
24 154 04 07 9.031 -8.122 3.949 -3159.941 -20663.854
7 -3151.819 -20667.803
25 11 25 54 17.843 17.489 3.536 -3134.330 -20664.267
1 -3115.530 -20675.656
26 23 45 59 26.723 24.457 10.770 -3091.073 -20664.886
66
NDCDB Measure
BKL N/S E/W N/S E/W ∆ Latid ∆ Depart Vector Displacement Status
17 -3109.717 -20599.195 -3109.786 -20599.158 0.069 -0.037 √(0.069)² +(-0.037)² = 0.078 Refix
19 -3134.090 -20595.269 -3134.152 -20595.293 0.062 0.024 √(0.062)² +(0.024)² = 0.066 Refix
21 -3157.163 -20603.442 -3157.171 -20603.443 0.008 0.001 √(0.008)² +(0.001)² = 0.008 OK
22 -3172.159 -20608.753 -3172.159 -20608.753 0.000 0.000 √(0.000)² +(0.000)² = 0.000 Fixed
23 -3172.319 -20665.213 -3172.362 -20665.234 -0.043 -0.021 √(-0.043)² +(-0.021)² =0.048 OK
24 -3159.900 -20663.855 -3159.941 -20663.854 -0.041 0.001 √(-0.041)² +(0.001)² = 0.041 OK
25 -3134.285 -20664.245 -3134.330 -20664.267 -0.045 -0.022 √(-0.045)² +(-0.022)² = 0.050 OK
26 -3091.049 -20664.905 -3091.073 -20664.886 -0.024 0.019 √(-0.024)² +(0.019)² = 0.031 OK
16 -3090.958 -20632.711 -3090.99 -20632.704 -0.032 0.007 √(-0.032)² +(0.007)² = 0.033 OK
15 -3090.872 -20602.231 -3090.925 -20602.230 -0.053 0.001 √(-0.053)² +(0.001)² = 0.053 Refix
67
5.4.6 Offset for Refixation
Line 4 – BKL 15
Line 4 – BKL 17
Line 5 – BKL 19
68
5.5 Area Comparison
Lot 13506
Coordinate
Line Bearing Distance S W
15 89 50 16 30.480 -3090.925 -20602.230
17 170 50 56 19.088 -3109.786 -20599.158
19 170 50 56 24.687 -3134.152 -20595.293
25 269 50 16 68.976 -3134.330 -20664.267
26 359 07 36 43.241 -3091.073 -20664.886
16 89 50 16 32.194 -3090.99 -20632.704
Total Distance = 218.666
Linear Misclosure = 1:237888 Area = 2846.091 m²
Lot 13512
Coordinate
Line Bearing Distance S W
19 89 50 16 68.976 -3134.152 -20595.293
21 199 30 16 24.478 -3157.171 -20603.443
22 199 30 16 15.908 -3172.159 -20608.753
23 269 50 16 56.460 -3172.362 -20665.234
24 06 14 36 12.493 -3159.941 -20663.854
25 359 07 36 25.618 -3134.330 -20664.267
Total Distance = 203.933
Linear Misclosure = 1:228637 Area = 2365 m²
Lot 13506
69
Lot 13512
Table 5.4
Result of Area Comparison
Lot Pre Comp New Different Percentages
1 2846.125 2846.091 0.034 Under 5%
2 2365.387 2365.349 0.038 Under 5%
Based on the result in the table 5.4 above the different between pre-comp and
NEW calculation are show a few different value. According to JUPEM, the different
between it should not be above 5%. If it not below 5%, it might be have error during
perform the calculation.
This plan was produced by the drafter before it can be submit to JUPEM together
with the 16 ASCII files. The final product is the certified plan that show the final lot of
the subdivision in A3 size. All information of the plan need to show such as title, scale,
area, new number of the lot , bearing and distance as a guideline and was follow the
requirement that need to do the subdivision on the lot 13506 and 13512. It was scale in
1:750 which is the suitable scale for the lot to make sure it clear to print. Figure 5.5
below shows the certified plan as a final product in this project.
70
Figure 5.5 Certified Plan (AutoCAD 2007, 2018)
71
CHAPTER SIX
CONCLUSION
This chapter explained conclusion about the project and a comment about this
industrial training. A suggestion was prepared to help improving the work.
6.1 Comment
6.2 Suggestion
Firstly, the student should be train more about fieldwork. The duration provided
by UiTM is not enough for the student to master the fieldwork. It should be extended
so that the student can master the fieldwork and put it for practice in the future. UiTM
also should provide more instrument that is in good condition so that the student can
avoid delay in their work and taking turns with other class. The student also should be
more creative in plotting the plan. Student also need to be disclosed more about modern
knowledge, technologies and techniques in surveying so that they can adapt themselves
at work.
72
6.3 Conclusion
In conclusion, Cadastral Survey work need good time management and high
commitment to achieve high accuracy. This project managed to achieve all of that with
the linear misclosure of 1:46825 using datum of 1 solar observation and 2 boundary
mark. After my involvement in this project, I can concluded that Cadastral Survey work
is complicated work as it requires high accuracy and precision that satisfied the DSMM.
The main purpose of this cadastral survey is to make sure all the boundary mark of
assigned lot is in the same position as in the title produced. Every error must be adjusted
by applying correction so that is does not overlap with other lot. High precision work
also help in keeping good relationship with the land lord. The surveyor and chainman
also teach us in applying some faster method in doing the survey work which is one of
the useful experience gained.
73
REFERENCES
Abdul Muiz Yazid. (2018). Personal Communication. Project Manager Jurukur Zenith.
Federal Register. (2018). Retrieved from palmettohistory: www.palmettohistory.org
Foo Chee Yong . (2018). Surveyor. Jurukur Zenith.
James Brooke. (2018). Retrieved from Engineering Training:
www.engineeringtraining.tpub.com
Ng Yoon Fai. (2018). Surveyor. Jurukur Zenith.
Sr Mohamad Azril Che Aziz. (2018). Personal Communication, Supervisor. Arau,
Perlis: Universiti Teknologi Mara.
Sr Mohd Adhar Abd Samad, Sr Mohamad Azril Che Aziz, Sr Hj Ahmad Nadzari
Yahaya. (2015). Introduction to Cadastral Survey. First Edition. Arau, Perlis:
Universiti Teknologi Mara.
74