10.
14 MVA TRANSFORMER FOUNDATION
INPUT DATA
Depth of foundation 1.7 REBAR WORK
Footing size Footing Rebar
Length 3 Spacing x-direction
Width 3.75 Bottom 0.15
Wall height 1.475 Top 0.15
Footing thickness 0.35
C.C Thickness 0.075 Spacing y-direction
Footing sectional area(X-DIRECTION) 2.23
Top platform sectional area Bottom 0.15
A1 0.188 Top 0.15
A2 0.134
A3 0.118 0.44 Vertical Wall rebar
Spacing
SECTIONAL AREA (Y-DIRECTION) 0.09 Horizontal Rebar
DB10 0.2
DB12
Vertical Rebar
DB10
C.C SECTIONAL AREA(X-direction) 0.237 DB12 0.15
length 3.15
EARTH WORK
Earth cutting 22.7205
Rate of cutting 6
Earth filling 22.7205
Rate of filling 4
COST 227.205
R.C.C CASTING
VOLUME OF CONCRETE
MAIN BODY V1 6.69
V2 1.32
V3 0.3375
Total volume of concrete 8.3475
Rate 12000
Cost for main casting(TK) 100170
C.C WORK
Volume Of C.C work 0.74655
COST 8958.6
REINFORCEMENT WORK
Rebar along X-direction
BOTTOM X Unit wt RATE T.Weight
length of rebar 3.3
No of Rebar 26
DB10 0.666
DB12 0.888 76.1904
DB16 1.456
DB20 2.466 78
COST 5942.851
BOTTOM Y
Length of Rebar 4.05
No of Rebar 21
DB10
DB12 75.5244
DB16
DB20
COST 5890.903
Top X
Length of rebar 3.3
No of rebar 26
DB10
DB12 76.1904
DB16
DB20
COST 5942.851
Top Y-direction
Length of Rebar unit wt 4.05
No of rabar 21
DB10
DB12 75.5244
DB16
DB20
COST 5890.903
REBAR FOR VERTICAL WALL
No of rod Rod length WT
Horizontal rebar
DB10 33.5 3.3 73.6263
DB12
DB16 535.5639
DB20
COST 5742.851
No of rod Rod length WT
Vertical Rebar
DB10
DB12 21 2.125 158.508
DB16
DB20
COST 12363.62
Total Cost for rebar 41773.98
TOTAL COST FOR TRANSFORMER FOUNDATION 151130