PROGRESS REPORT FOR Corrotech J (436) December 1-2011: Description of Work Progress

The progress report summarizes work done from December 1-2011 for Project Corrotech J (436). 11 workers erected the main frame from grid lines 8 to 12 and completed decking and bolt tightening for the mezzanine area. Equipment on site included 1 crane, 1 forklift, and 2 man lifts.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
64 views7 pages

PROGRESS REPORT FOR Corrotech J (436) December 1-2011: Description of Work Progress

The progress report summarizes work done from December 1-2011 for Project Corrotech J (436). 11 workers erected the main frame from grid lines 8 to 12 and completed decking and bolt tightening for the mezzanine area. Equipment on site included 1 crane, 1 forklift, and 2 man lifts.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

PROGRESS REPORT FOR Corrotech J (436) December 1- 2011

PROJECT PROGRESS STATUS


         
are
a Description of Work Progress   REMARKS
A   Erection of main frame from grid line 8 to 12 @ grid J to A  
A   Mezzanine area decking sheet & Bolt tightening  
 
     
     
     
     
     
Man power and equipment
Mito
mia crane 1
Forman
Equipment on site

Erector 10 fork lift


Man power

man lift 2

total: 11
Main frame erection progress
Decking sheet progress
Mezzanine area Tightening bolt