Bill No. 2 - Roadworks Bill 2.2 Drainage and Erosion Protection
Bill No. 2 - Roadworks Bill 2.2 Drainage and Erosion Protection
Bill No. 2 - Roadworks Bill 2.2 Drainage and Erosion Protection
2 Page 6
Contract C - Civil Work
Vol. 5 Schedule 1 Bill of Quantities
Bill 2.2 includes also permanent drainage and erosion protection at spoil areas.
3.1.01.0 EARTHWORKS
3.1.01.01 Remove usable timber no 10.00 105.23 1,052.30
3.1.01.02 Clearing and grubbing ha 3.00 9,990.00 29,970.00
3.1.01.03 Topsoil excavation m3 100.00 3.34 334.00
3.1.01.04 Soil excavation
a) Bulk excavation, to spoil deposit m3 12,000.00 5.62 67,440.00
b) Excavation to stock pile (gravel, boulders) m3 500.00 6.35 3,175.00
c) Excavations for footings m3 500.00 6.52 3,260.00
3.1.01.05 Preparation of rock foundation for concreting m2 800.00 3.59 2,872.00
3.1.01.06 Fill and backfill
a) Embankment fill
i) Gravel m3 750.00 22.43 16,822.50
ii) Rock m3 750.00 17.21 12,907.50
b) Structural backfill m3 3,500.00 15.92 55,720.00
c) High quality rockfill m3 400.00 23.68 9,472.00
d) Backfill of trenches m3 400.00 14.89 5,956.00
e) Low permeability fill m3 400.00 16.76 6,704.00
f) Filter material, 0 - 60 mm m3 500.00 25.96 12,980.00
g) Drainage material , 50 - 100 mm m3 250.00 26.49 6,622.50
3.1.01.07 Placing of topsoil m2 500.00 0.32 160.00
3.1.01.08 Turfing (optional) m2 250.00 0.32 80.00
3.1.03.04 Water pressure testing, per packer setting, single packer, depth 0 - 20 m no 20.00 119.42 2,388.40
3.1.03.05 Cement pressure grouting, per packer setting, depth 0-20 m no 60.00 129.12 7,747.20
3.1.03.06 Cement grouting: Cement consumption per packer setting, Type A
a) 0 - 100 kg kg 9,000.00 0.88 7,920.00
b) 0 - 200 kg kg 6,000.00 1.05 6,300.00
c) 0 - 300 kg kg 4,000.00 1.27 5,080.00
d) 0 - 500 kg kg 3,000.00 1.63 4,890.00
e) More than 500 kg kg 3,000.00 2.61 7,830.00
Chemical grouting.
3.1.03.07 kg 100.00 23.71 2,371.00
Type of grout: Epoxy
3.1.03.08 Fully cement-grouted rock bolts. D=32mm
a) Length 2.0 m no 80.00 56.90 4,552.00
b) Length 3.0 m no 40.00 68.24 2,729.60
c) Length 4.0 m no 30.00 79.57 2,387.10
d) Length 6.0 m no 20.00 102.26 2,045.20
e) Length 8.0 m no 10.00 129.48 1,294.80