MQ SP M 4013 PDF
MQ SP M 4013 PDF
This specification has been revised as indicated below and described in the revision record on the
following page. Please destroy all previous revisions.
Lead Engineer
Engineering Manager:
Client Approval:
Record of Revisions
Revision Date Description
No.
1.0 SCOPE...........................................................................................................................................................4
8.0 IDENTIFICATION.......................................................................................................................................15
1.0 SCOPE
1.1 This specification defines the Positive Material Identification (PMI) program. The
requirements include qualification of procedures and personnel, extent of verification, and
verification marking and reporting.
1.2 “Positive Material Identification” (PMI) is a procedure used to ensure that specified alloy
materials are properly identified as to their alloy type, are marked according to the
Contractor’s requirements, and are installed as intended.
1.3 This Specification applies to “alloy material” as defined in paragraph 2.2.1 of this
Specification. All alloy materials purchased and/or used in fabrication by the Supplier
and any Sub-Suppliers and included in the scope of supply as defined in the Contractor’s
P.O. shall be covered by these requirements.
2.1 References
API RP578 Material Verification Program for New and Existing Alloy Piping Systems
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4013
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 01 Mar 2011
Contract Number: A5MU Page 5 of 18
Revision 1
2.2 Definitions
A. Alloy Materials in this specification are defined as all materials having a "P" number
greater than 1, as defined in ASME Section IX, QW-422. Aluminum (P-21 through P-
25) is exempt from the requirements of this specification.
B. The Contractor is the party which carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a project or operation
of a facility. The Principal may undertake all or part of the duties of the Contractor.
D. The Principal is the party which initiates the Project and ultimately pays for its design
and construction. The Principal will generally specify the technical requirement. The
Principal may also include an agent “Third Party Inspection Agency (TPIA)” or
consultant to act for, and on behalf of, the Principal.
E. With the exception of fasteners, an “inspection lot” is a group of components from the
same heat number or heat treatment batch from which a sample is drawn. For
fasteners, a lot is a group of similar components in terms of alloy type and size.
J. Bulks include flanges, fittings, valves, pipe, tubing fasteners and instrumentation
components.
L. “PMI” stamping on an item indicates PMI Verification has been performed on at least
one other item from the representative sample (i.e., the item stamped “PMI” is one on
which PMI Verification has not been performed).
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4013
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 01 Mar 2011
Contract Number: A5MU Page 6 of 18
Revision 1
3.0 GENERAL
3.1 PMI required by this specification is the responsibility of the Supplier and the Contractor
as described in Section 4.0 and shall be carried out in the presence of the Principal's
representative at his discretion. Contractor shall develop Project PMI Program based on
but not limited to this Specification.
3.2 For items requiring PMI by destructive tests, it is the Supplier's responsibility to provide
samples for checking the chemistry as outlined in this specification. The Supplier shall
have samples removed in the presence of the Contractor’s representative unless this
requirement is waived by the Principal on a case-by-case basis.
3.3 This Specification requires PMI to be carried out at a time which ensures that proper
materials are being used in the fabrication of an identifiable assembly (e.g. a pipe length
welded into a spool, or a nozzle welded into a vessel, etc.). All PMI records are to be
traceable to a material source and heat number. The Supplier shall demonstrate
traceability at anytime. This will require the results to be incorporated into fabrication
logs.
3.4 When traceability of a lot cannot be established back to a heat number, mill certification
or other positive means of identification, then that lot of items, regardless of quantity,
shall be examined 100%.
A. One hundred percent (100%) for a lot of five (5) pieces or less;
B. The greater of five (5) pieces or 5% for a lot of five (5) to two hundred (200) pieces;
and
C. The greater of ten (10) pieces or 3% for a lot greater than two hundred (200) pieces.
If any piece from a representative sample is found to be unacceptable, each piece of that
lot shall be examined.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4013
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 01 Mar 2011
Contract Number: A5MU Page 7 of 18
Revision 1
3.6 When a lot is found to contain unacceptable pieces, 100% of the next two lots from the
same Supplier and/or Sub-Supplier shall be examined. If both lots are acceptable, or
when two successive lots are acceptable, the representative sampling frequency given in
paragraph 3.5 of this Specification may be resumed.
3.7 Materials with no alloy type identification (i.e., permanent marking) cannot be PMI tested
on a representative basis, rather, shall be tested 100%.
3.8 Where items are rejected after verification, all remaining pieces of the same item from a
particular Supplier shall be verified. Rejected items shall be returned to the original
source of supply at no cost to the Contractor or Principal.
3.9 Dye check cleaner (or similar cleaner) should be used in cleaning of tools and sample
surfaces prior to obtaining samples for destructive testing.
3.10 Test locations for non-destructive PMI testing shall be ground or otherwise prepared to
the proper surface finish as specified by the analyzer devise manufacturer.
4.1 The state-of-the-art PMI machines can detect carbon plus elements in the periodic table
from atomic number 12 (carbon) through atomic number 92 (uranium); low
concentrations of certain elements are not detectable. Consequently, there are alloy
materials which require destructive laboratory analysis and they are identified in Table 1 -
Alloy Material PMI Requirements. All PMI equipment to be used on the Project shall be
calibrated in accordance to the requirements of API RP578, paragraph.5.3.
B. For destructive testing, a sample from each heat of material shall be forwarded to a
laboratory. The name of the laboratory must be submitted to the Contractor for
approval prior to forwarding the samples.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4013
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 01 Mar 2011
Contract Number: A5MU Page 8 of 18
Revision 1
In addition to any unique identification, the sample shall be tagged with the
Contractor’s purchase order number and item tag number. Upon receipt, the
Supplier shall submit the results of the analysis to the Contractor for review.
A. The Supplier shall provide for review and comment a PMI Program that complies with
the requirements of this Specification, and as specified by the Contractor. The PMI
Program shall consist of two basic elements:
1. A PMI Execution Plan, which shall include the following minimum definitions
and details.
C. The Supplier may not proceed with any PMI activities prior to receiving the
Contractor’s comments to the Supplier’s PMI Program.
D. Where accessible, welds shall be examined on both the inside and outside surfaces,
based on the sampling frequencies shown in paragraph 5.2 of this Specification.
Where applicable, base metal welds shall be examined prior to the application of
weld overlay or back cladding. The Supplier shall map all PMI tests of welds and
weld repairs and include the PMI mapping in the final documentation.
4.4 Shop and Field Fabricated Alloy Pipe, Plate, Weld Consumables
During fabrication, vessels, heat exchangers, rotating equipment and shop/field fabricated piping
including weld overlaid surfaces (stainless steel or other alloys) shall be subjected to PMI in
accordance with the following schedule. Sampling is to be representative of each welding
process used, for example, if GTAW is used for the root pass, SMAW for the hot pass(es) and
SAW for the fill and cap passes, in addition to PMI testing the root and cap surfaces, as required
per paragraph 4.3.4 of this specification, PMI must also be performed on the SMAW deposit prior
to covering it with SAW.
Automatic welding: one sample per seam for seams less than 15 m (49 ft 2 in.) in
length; two samples per seam for seams greater than 15 m (49 ft 2 in.) in length.
Manual welding: two samples per seam for seams less than 15 m (49 ft 2 in.) in
length; four samples per seam for seams greater than 15 m (49 ft 2 in.) in length.
C. Weld Repairs –
One sample for every 600 mm (24 in.) of repair length, minimum 1 sample per
repair.
A. Weld overlay
Sample frequency below shall be per each WPS and each heat of filler material used.
1. One sample for each ten square feet, or portion thereof, throughout the entire
overlayed section of each component.
2. One sample per 5% of accessible nozzle bores, with a minimum of one test
per equipment tag item.
3. One sample per 5% of nozzle faces, with a minimum of one test per
equipment tag item.
Note: PMI testing of weld overlay material shall be waived when production weld
chemical analysis is required.
B. Clad restoration
Sample frequency below shall be per each WPS and each heat of filler material used.
1. One sample for each ten linear feet, or portion thereof, of each category A, B,
C and D weld seams.
Note: PMI testing of clad restoration material shall be waived when production weld
chemical analysis is required.
C. Clad plate
Sample frequency below shall be per each heat of cladding material used.
1. One sample per clad plate less than ten linear feet in the major dimension.
2. Two samples, one each from opposite corners, per plate longer than ten
linear feet in the major dimension.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4013
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 01 Mar 2011
Contract Number: A5MU Page 12 of 18
Revision 1
5.4 Any other components or materials specifically designated for 100% PMI testing in the
Contractor’s P.O.
Prior to use in fabrication, all alloy consumables (including those for both pressure
containing and non-pressure containing welds) shall be PMI examined at the following
frequency.
A. Each heat of bare wire (for GMAW and GTAW);
5.6 Alloy stud fasteners shall be examined per paragraph 3.5 of this Specification.
5.7 The following items are exempt from PMI testing unless otherwise specified in the
Contractor’s Purchase Order.
C. All gaskets.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4013
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 01 Mar 2011
Contract Number: A5MU Page 13 of 18
Revision 1
6.2 The Principal reserves the right to establish an Inspection Hold Point for each fabricated
item just prior to surface preparation and painting. The Hold Point shall be used to verify
that the correct materials, including deposited weld metal, and color coding were used
prior to the loss of material identity marking during surface preparation.
6.3 The Hold Point verification shall also include a review of the PMI Analysis Reports and a
random spot check performed by the Supplier and witnessed by a Third Party Inspection
Agency (TPIA), Consultant or Contractor to act for and on behalf of the Principal.
6.4 The Contractor shall be contacted prior to performing PMI on any dissimilar / bimetallic
joints. The Supplier shall test the base metal on both sides of the dissimilar joint and the
center of the weld as separate samples. The Supplier shall demonstrate sufficient control
of consumables and meet the ASME Section II, Part C deposition requirements.
7.2 The results of weld metal PMI shall meet the requirements of ASME Section II, Part C for
the weld metal used. Analysis need only be performed for those elements specified in
Table 1 for comparable base materials.
7.3 If the PMI test results fall outside of the acceptable ranges, the item will be rejected.
7.4 This specification does not allow for percentage non-conformance. If any piece from a
random sample is found to be unacceptable, then the remainder of that lot shall be
verified by performing a 100% examination. If incorrect materials are shipped to the job-
site, backcharge procedures will be initiated against the Supplier.
7.5 All rejected materials shall be isolated in a "HOLD" area, tagged "REJECTED", and a
Non-conformance Report initiated by the Supplier.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4013
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 01 Mar 2011
Contract Number: A5MU Page 14 of 18
Revision 1
8.0 IDENTIFICATION
8.1 After PMI has been successfully completed, each piece shall be marked to identify the
alloy type (i.e., “PMIV 1¼ Cr” or “PMIV 316”) adjacent to the PMI test sight. The
preferred marking methods are low stress stamps or vibra-etch. Other marking methods
require the Principal’s agreement and authorization. If color coding is proposed, all
practices should be in accordance with Pipe Fabrication Institute Standard ES-22. Cut
lengths of pipe from PMI examined material are to have the PMI markings transferred to
all pieces. This marking is in addition to those normally required by applicable codes(s)
or other job specifications.
8.2 Items which cannot accommodate this identification shall be individually tagged with the
above 8.1 identification placed on tags.
8.3 Ink or paint shall be of a type whose chemistry will not be detrimental to the material
being identified and of an "indelible" type or other which is not easily removed
B. Where representative sampling is allowed, pieces may be PMI tested upon receipt
and those pieces tested shall be marked per 8.1 above. Items from the same lot that
are not tested shall be marked “PMI.”
C. Weld marks shall be placed adjacent to the welder’s mark, directly on the weld.
8.5 Other items shall have each piece identified a sufficient number of times and at different
locations to ensure visibility of identification during the fabrication or erection cycle.
8.6 When heat treatment is performed after material verification, the identification markings
shall be recognizable after the heat treatment.
8.7 The Supplier shall provide a “Quality Assurance Warehousing Procedure” for review by
Contractor and Principle. The Procedure shall address controls established to prevent
the inadvertent use of materials failing to pass examinations or those incorrectly identified
(see paragraph 7.5).
8.8 As outlined in this specification, the Contractor will witness at his discretion the required
examinations and application of the identification marks. This is not to be treated as an
Inspection Hold Point by the Supplier. This will assure the Contractor that alloy materials
have already received the necessary examinations and are acceptable.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4013
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 01 Mar 2011
Contract Number: A5MU Page 17 of 18
Revision 1
9.1 The party performing PMI shall submit a written procedure conforming to this
specification for the Contractor review and written approval.
9.2 The written procedure shall include complete description(s) of methods and equipment to
be used, the time in fabrication cycle when PMI will be carried out and the working
method used to identify that PMI has been carried out.
9.3 It shall also include qualifications of personnel (in accordance to API RP578, paragraph
5.5 and this specification), who will be responsible for performing PMI examinations.
10.1 The Quality Records and other forms and reports identified in and required by this
specification shall be maintained by the Supplier and copies made available to the
Contractor and Principal upon request.
11.1 The Seller shall report destructive and non-destructive PMI analysis results to the
Contractor and include PMI test reports in the final Code Data Package. See Table 2 for
the PMI report form.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4013
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 01 Mar 2011
Contract Number: A5MU Page 18 of 18
Revision 1
Examination Results
Additional Information
Manhours And Loss Incurred From Rejections, Etc.