INFINITY - PMP 11 - Integration
INFINITY - PMP 11 - Integration
INFINITY - PMP 11 - Integration
PROJECT
INTEGRATION
MANAGEMENT
PROJECT INTEGRATION
MANAGEMENT
• Includes the processes and activities needed to identify,
define, combine, unify, and coordinate the various
processes and project management activities with the
Project Management Process Groups
• Making choices about where to concentrate resources and
effort
• Involves making tradeoffs among competing objectives
and alternatives
• Primarily concerned with effectively integrating the
processes among the Project Management Process
Groups
1
12/2/2014
PROCESSES MAP
INITIATING PROCESS
GROUP
2
12/2/2014
PLANNING PROCESS
GROUP
EXECUTION PROCESS
GROUP
3
12/2/2014
CLOSING PROCESS
GROUP
4
12/2/2014
BUSINESS CASE
This document provides the necessary information from a
business standpoint to determine whether or not the project
is worth the required investment.
• Market demand
• Organizational need
• Customer request
• Technological advance
• Legal requirement
• Social need
PROJECT STATEMENT OF
WORK (SOW)
The SOW is a narrative description of products or services to
be delivered by the project.
• Business need
• Product scope description
• Strategic plan
5
12/2/2014
PROJECT CHARTER
• The project charter documents the business needs, current understanding of the
customer’s needs and the new product, service, or result that it is intended to satisfy,
such as:
• Project purpose or justification
• Measurable project objectives and related success criteria
• High-level requirements
• High-level project description
• High-level risks
• Summary milestone schedule
• Summary budget
• Project approval requirements
• Assigned project manager
• Name and authority of the sponsor
PROJECT MANAGEMENT
PLAN
The project management plan integrates and consolidates all of the
subsidiary management plans and baselines from the planning processes
and includes but not limited to:
• The life cycle selected for the project and the processes that will be
applied to each phase.
• Results of the tailoring by the project management team as follows:
A. project management processes selected by the project
management team.
B. level of implementation of each selected process.
C. descriptions of the tools & techniques to be used for
accomplishing those processes.
D. how the selected processes will be used to manage the specific
project, including the dependencies and interactions among those
processes, and the essential inputs & outputs.
6
12/2/2014
PROJECT MANAGEMENT
PLAN
E) How work will be executed to accomplish the project objectives.
ENTERPRISE
ENVIRONMENTAL FACTORS
Any and all of the enterprise environmental factors and
systems of an organization that surround and influence the
success of the project must be considered; includes items
such as:
• Organizational culture and structure
• Governmental or industry standards
• Infrastructure
• Stakeholder risk tolerances
• Project management information systems
7
12/2/2014
ORGANIZATIONAL
PROCESS ASSETS
• Any or all process-related assets, from any or all of the
organizations involved in the project that are or can be used
to influence the project's success
• These process assets include formal and informal plans,
policies, procedures, and guidelines
• The process assets also represent the organization's
learning and knowledge from previous projects
• Could be grouped into two categories:
• Organization's processes and procedures for conducting work
• Organizational corporate knowledge base for storing and
retrieving information
CONFIGURATION
MANAGEMENT SYSTEM
A subsystem of the overall project management system; it is a collection of
formal documented procedures used to apply technical and of formal
documented procedures used to apply technical and administrative
direction and surveillance to:
• Identify and document the functional and physical characteristics of a
product, service, result, or component
• Control any changes to such characteristics
• Record and report the change and its implementation status
• Support the audit of the products, services, results, or components to
verify conformance to requirements
• It includes the documentation, tracking systems, and defined approval
levels necessary for authorizing and controlling changes
• In most application areas, the configuration management system
includes the Change Control System
8
12/2/2014
CHANGE CONTROL
SYSTEM
Collection of formal, documented procedures that define how
project deliverables and documentation are controlled,
changed and approved; specialized change control systems
exist for:
• Project Scope change control
• Schedule change control
• Cost change control
• Contract change control
• Subset of the configuration management system
INTEGRATED CHANGE
CONTROL
• Process of reviewing all change requests, approving
changes and controlling changes to deliverables and
organizational process assets.
• The configuration management system with change control
provides a standardized, effective, and efficient process to
centrally manage changes with the project.
• Every documented requested change must be either
accepted or rejected by some authority within the project
management team or an external organization representing
the initiator, sponsor, or customer.
• May include a Change Control Board (CCB) which is
responsible for approving or rejecting change requests.
9
12/2/2014
CHANGE CONTROL
BOARD
• Change Control Board (CCB) which is responsible for
reviewing and approving or rejecting change requests
• Chaired by the project manager (or designee)
• Powers and responsibilities must be well defined
• Agreed upon and approved by key stakeholders
PERFORM INTEGRATED
CHANGE CONTROL
Before push or ask the management for approval:
• Do you know if there’s another alternative?
• Did you evaluate/investigate the effect/impact of each of
the options (on time and cost for example)?
• What’s the best option?
• Do you have the authority to change or do you have to go
to CCB?
10
12/2/2014
DEVELOP PROJECT
CHARTER
The process of developing a document that formally
authorizes the existence of a project and provides the project
manager with the authority to apply organizational resources
to project activities.
DEVELOP PROJECT
CHARTER
INPUTS
1. Expert judgment
2. Facilitation techniques
OUTPUTS
1. Project charter
11
12/2/2014
DEVELOP PROJECT
MANAGEMENT PLAN
• Develop Project Management Plan is the process of defining,
preparing, and coordinating all subsidiary plans and
integrating them into a comprehensive project management
plan.
• The project management plan defines how the project is
executed, monitored & controlled and closed.
• The project management plan content will vary depending
upon the application area and complexity of the project.
• This process results in a project management plan that is
progressively elaborated by updates and controlled and
approved through the perform integrated change control
process.
DEVELOP PROJECT
MANAGEMENT PLAN
INPUTS
1. Project charter
2. Outputs from other processes
3. Enterprise environmental factors
4. Organizational process assets
1. Expert judgment
2. Facilitation techniques
OUTPUTS
12
12/2/2014
INPUTS
1. Project management plan
TOOLS & TECHNIQUES
2. Approved change requests
3. Enterprise environmental Factors 1. Expert judgment
4. Organizational process assets 2. Project information management
System
3. Meetings
OUTPUTS
1. Deliverables
2. Work performance data
3. Change requests
4. Project management plan updates
5. Project documents updates
13
12/2/2014
INPUTS
1. Project management plan
2. Schedule forecasts
3. Cost forecasts
TOOLS & TECHNIQUES
4. Validated changes 1. Expert judgment
5. Work performance information 2. Analytical techniques
6. Enterprise environmental Factors 3. Project management information
7. Organizational process assets System
4. Meetings
OUTPUTS
1. Change requests
2. Work performance reports
3. Project management plan updates
4. Project documents updates
14
12/2/2014
PERFORM INTEGRATED
CHANGE CONTROL
The process of reviewing all change requests, approving
changes and managing changes to the deliverables
organizational process the deliverables, organizational
process assets, project documents and the project
management plan; and communicating their disposition.
PERFORM INTEGRATED
CHANGE CONTROL
INPUTS
1. Project management plan
2. Work performance reports
TOOLS & TECHNIQUES
3. Change requests
4. Enterprise environmental Factors 1. Expert judgment
5. Organizational process assets 2. Meetings
3. Change control tools
OUTPUTS
1. Approved change requests
2. Change log
3. Project management plan updates
4. Project documents updates
15
12/2/2014
CLOSE PROJECT OR
PHASE
The process of finalizing all activities across all of the project
management process groups to formally complete the
project or phase.
CLOSE PROJECT OR
PHASE
INPUTS
1. Project management plan
2. Accepted deliverables
3. Organizational process assets
1. Expert judgment
2. Analytical techniques
3. Meetings
OUTPUTS
1. Final product, service, or result
transition
2. Organizational process assets
updates
16
12/2/2014
QUESTIONS
17
12/2/2014
18
12/2/2014
19
12/2/2014
20
12/2/2014
21
12/2/2014
GENERAL
PRINCIPLES
22
12/2/2014
PROFESSIONAL AND
SOCIAL RESPONSIBILITY
PMBOK® GUIDE NO REFERENCE
GENERAL PRINCIPLES
AND GUIDELINES
• Do the right thing!
• Behave in an honest, open manner
• Solve problems, do not hide them
• Do not violate local laws
• Do not accept bribes or favors
• Disclose potential conflicts of interest
23
12/2/2014
GENERAL PRINCIPLES
AND GUIDELINES
• Keep people informed
• Do not change standards or requirements after the fact
• Attempt to resolve problems at the level they occur, i.e. do
not immediately escalate!
• Make accurate, honest reports
• Make decisions on the basis of facts; not hearsay,
assumptions, or opinions
24